EX-99.1 · Figure 21-7: High-level Implementation Schedule
Figure 21-7: High-level Implementation Schedule
Waterberg Technical Report
The development of the North Portal and the supporting infrastructure would be undertaken as a separate sustaining capital project commencing from 2053.
To facilitate the control of the Waterberg Project an execution WBS, aligned to the intended execution strategy, was developed that groups the Waterberg Project into the work packages described in Table 21-13.