Operational efficiency
We take a portfolio view of our project
improvement activities at individual sites.
This allows us to prioritize the most
effective projects, supporting energy
efficiency, reduced carbon emissions, and
lower costs.
During 2025 we completed energy
efficiency reviews across four production
regions: the North Sea, Oman, Egypt and
Asia Pacific. Our refining business also
completed the energy efficiency
programme launch in 2024. Additional
reviews were carried out at the Cherry
Point (US), Castellón (Spain) and
Gelsenkirchen (Germany) refineries. The
opportunities identified through these
reviews will be progressed through our
established business processes and plans
that support our net zero ambition.
In 2025 a total of 14 new emissions
reduction projects and actions
contributed to reductions of 0.27 MtCO 2 e,
including low carbon energy consumption
projects. This is in addition to the 27
emissions reduction projects delivered in
2024, which achieved a reduction of
0.42MtCO 2 e. These projects are tracked
based on GHG reductions and include
energy efficiency improvements.
Archaea Energy purchased renewable
energy certificates (RECs) equivalent to
125ktCO 2 e in emissions savings on a
market basis.
A further 144ktCO 2 e of emissions
reductions were achieved through energy
efficiency improvements in production
processes and flaring optimization
projects during 2025. These included:
Three projects at our Tangguh facility
delivering 45ktCO 2 e in reductions,
including flare purge rate
rationalization and boil-off gas flaring
minimalization.
A power synchronization project
between two platforms in Trinidad and
Tobago which reduced spinning
reserve through an electrical tie-over
enabling load sharing, delivering
14ktCO 2 e reductions.
Ongoing programmes at bpx energy
including replacement of natural-gas
driven pneumatic controllers,
installation of solar air compressors,
electrification measures and
reductions in fugitive emissions,
delivering 80ktCO 2 e.
In addition, our Castellón, Rotterdam
(Netherlands), and Whiting (US) refineries
have implemented further actions to drive
energy efficiency and reduce carbon
emissions, including steam trap repair
and replacement programmes. At Cherry
Point the restoration of cooling water
infrastructure improved reliability in
meeting refinery needs and enhanced the
efficiency of compressor operations.
As part of managing energy efficiency, we
take a portfolio-wide approach to
assessing and prioritizing spinning
reserve reduction opportunities. Spinning
reserve involves running additional power
generation machines to provide an excess
of energy supply. This can help to protect
production from plant vulnerabilities,
including power generation reliability.
Reducing spinning reserve can increase
exposure to power fluctuations for
production. We take a risk-based
approach when considering reducing the
number of running machines. This
allows bp to realise emissions and
maintenance cost reductions from fewer
running machines, while managing the
associated production risk.
bp is involved in several external groups
working on energy efficiency, including
the Oil & Gas Climate Initiative (OGCI), the
International Association of Oil & Gas
Producers (IOGP) and Energy Star. We
continue to run an annual training course
for new chemical engineers, which
includes energy efficiency upskilling, and
we offer GHG emissions and energy
efficiency training for more experienced
engineers and practitioners.
The text of this filing, as the company filed it with the SEC, without its images or exhibits. This is not investment advice.