RIO TINTO LTD
For the period ended Dec 31, 2025. Filed Feb 19, 2026.
View on SEC.govAbout this filing
The yearly report of a company based outside the US. It covers much of what a 10-K does, and may follow accounting rules other than US ones.
FY2025 · Filed Feb 19, 2026
Contents
Environmentally committed
We recognise that our operations have an inherent impact on nature, both directly
and indirectly, and we are committed to contributing to the global shift toward a
nature positive future.
Achieving our mission to be the most valued metals and mining
business relies on the responsible stewardship of shared natural
resources. Sustainable success is driven by better decision-making,
fostering collaboration, maintaining transparency, and measuring
performance as we aim to minimise our impact on nature and
society.
Business decisions centred on strong sustainability and social
licence are imperative to creating long-term value. Our Executive
Committee and Board have overall responsibility for, and oversight
of, environmental management and performance through our Risk
Management and Sustainability Committees, including a principal
environment risk that we track at a Group level.
We have shared our support for the ICMM’s Nature Position
Statement, to align industry action on the Kunming-Montreal Global
Biodiversity Framework (GBF) and 2030 targets. Our nature
framework outlines the processes and actions that underpin our
contribution to a nature positive future, in line with increasing
societal expectations.
We take a long-term view of our responsibilities, managing the risks
and impacts of our activities from exploration and project inception
through closure and beyond. We are committed to refining our
systems and processes to ensure transparent, accountable
decision-making that strengthens environmental outcomes and
manages nature-related risks responsibly.
As stewards of natural resources, we recognise the trust placed in
us. We manage air, biodiversity, land, and water with care, along
with the material inputs and outputs of our operations and their full
life cycle footprint. This commitment ensures we operate responsibly
while supporting resilient ecosystems and sustainable communities.
Our nature frameworkAmbition: To meaningfully contribute to a nature positive future through integrated environmental management practices that support our operational excellence objective.Commitments: Deliver on our commitments for nature - including our Standards and the ICMM Nature Position Statement.Risk: Enhance our understanding and management of material business risks across our operations and value chain.Assurance Increase stakeholder confidence in performance and reporting through internal and external assurance activities for our assets and supply chains.Targets: Operational nature targets to focus our efforts on continuous improvement.Disclosures: Enhance transparency of environmental performance information and data over time.
Commitments
Our commitment to the ICMM Nature Position Statement informs
our actions and accountabilities to deliver the desired
environmental, social and economic outcomes for the business. This
includes the following clear commitments:
We contribute to the global nature positive goal of “halting and
reversing biodiversity loss by 2030 from a 2020 baseline, with a
full recovery by 2050”.
We do not explore or extract resources within the boundaries of
UNESCO World Heritage sites. All reasonable steps will be taken
to ensure future operations adjacent to World Heritage sites are
not incompatible with the outstanding universal value for which
these sites are listed and do not put the integrity of these sites at
risk.
We respect legally designated protected areas and ensure any
new operations or changes to existing operations are not
incompatible with the objectives for which the protected areas
were established.
We do not undertake deep-sea mining, and believe it should not
take place unless comprehensive scientific research refutes
currently held evidence that it will create significant environmental
and socioeconomic implications.
Performance and targets
Our nature target program is a core component of our nature
framework and one of the ways we plan to contribute to a nature
positive future. The program acknowledges the interconnectedness
of the realms of nature – air, land and water - and their ties to
biodiversity, climate and society. The nature targets program
includes a set of locally focused, site improvement plans, initiated in
- The program seeks to enhance the transparency of our nature
risks, challenges and performance. Progress on the nature targets
will be reported annually on our website.
Water
Water is essential to life. It is inherently linked to healthy, thriving
ecosystems and communities, and holds spiritual significance to
Indigenous and land-connected Peoples all over the world. It is also
an essential resource for our operations, enabling access to
orebodies and processing of ore to provide the materials the world
needs. As water is a finite shared resource, responsible water
stewardship is critical to our business’s success. Protecting water
ensures it remains available and clean for the ecosystems and
communities that depend on it, and for stable and sustainable
operations to continue for generations.
Our commitment to responsible water stewardship is reflected
through our business strategy, standards, policies and member
association commitments.
We have developed a water risk framework that we use to
consistently identify, assess, manage and communicate water risk
across our portfolio. The framework allows us to have relevant
conversations about water threats and opportunities, informing
decisions and strategic plans, for operational and catchment-level
decisions beyond an individual site. It covers four water risk
categories:
1)water resource (issues relating to water withdrawals for
supply purposes)
2)water quality and quantity (issues relating to excess surface
water management, discharges or seepage)
3)dewatering (issues relating to groundwater withdrawals to safely
depressurise and access below water table orebodies)
4)long-term obligations (consideration of items 1-3 over long
timescales, eg post mining).
Our 2025 water risk profile shows how our exposure varies across
the four risk categories. We manage all risks in accordance with our
company standards and applicable local regulations and guidelines.
We have a library of water management controls that promote
consistent operational risk management and assurance by our
frontline asset teams and supporting second-line functions. The
controls guide and organise how we monitor, plan, use infrastructure
and adaptively manage water. Our approach to water is integrated
with our approach to communities, climate change, tailings
management and closure.
Group water risk profile (percentage of managed operations 1)
Examples of ranking
Water resource
Is there enough water available for environment needs, community
needs and our operational use?
Our iron ore port operations in the Pilbara, Western Australia, are
supplied with water from the West Pilbara Water Supply Scheme.
The scheme is vulnerable to drought, and Traditional Owner groups
have raised concerns about environmental and cultural impacts. The
water resource risk for these operations is assessed as high. Rio
Tinto is committed to enhancing water security in this region.
Water quality and quantity
Does the way we manage water onsite, or discharge excess water,
cause environmental impacts or operational constraints?
Our ilmenite mine near Havre-Saint-Pierre (HSP) in Quebec,
Canada is surrounded by ecologically and socially significant lakes
and water features. The quality and quantity risk for HSP mine is
assessed as high and excess water from the mine needs to be
carefully managed. To ensure water is released to the environment
at a suitable quality, we are working on a multi-year water
management improvement project.
Dewatering
Does the removal of water from the operational areas of our sites
impact regional aquifers or our mine plans?
Impacts associated with dewatering and water supply activities in
the Pilbara, Western Australia are recognised as a very high risk for
our business. Returning water to the aquifers impacted by our
mining activities in a controlled manner is the focus of a number of
ongoing studies. We are also continuing to work with Traditional
Owners on water management.
Long-term obligations
Do our operational activities generate long-term or ongoing
obligations related to water?
We may sometimes generate impacts that we are required to
manage over the long term, such as post-closure pit lakes in the
Pilbara, or potential seepage from our waste rock or tailings facilities
in our aluminium and copper sites. Our systems and standards aim
to ensure that risks are identified early and managed appropriately
and responsibly throughout the asset life cycle, including legacy
issues.
| l Not applicable | l Low risk | l Moderate risk | l High risk | l Very high risk |
|---|
- Due to rounding, the sum may not total 100%. Ratings based on 2025 assessment, excluding projects and recent lithium acquisitions. Refer to Sustainability Fact Book for additional
information.
Our water balance
Our Group water balance outlines where water was withdrawn from,
discharged to, recycled, or reused and consumed at our operations.
The reported categories correlate with the requirements of ICMM
and the Global Reporting Initiative.
We also report on our aggregated water balance for sites in water-
stressed areas. We assess water stress using the World Resources
Institute’s Aqueduct Water Risk Atlas mapping tool.
For more information see our 2025 Sustainability Fact Book at riotinto.com/sustainabilityreporting
Our water performance
Our total operational withdrawals for 2025 were 1,147 gigalitres (GL)
(2024: 1,250 GL). Freshwater, or category 1 quality, withdrawals
accounted for 386 GL or 34% of this total (2024: 399 GL).
Freshwater is generally suitable for consumption with minimal
treatment required. Where possible, we aim to minimise our
extractions from water sources of this quality.
Total discharges for 2025 were 626 GL (2024: 641 GL). Total water
recycled or reused for 2025 was 374 GL (2024: 344 GL).
Our activity
We progressed several initiatives in 2025 that demonstrate our
ongoing recognition of the importance of respecting rights,
partnerships, innovation and transparency. These include:
Implementation of the QIT Madagascar Minerals water strategy,
with transparent reporting of water management and performance
data through the 2024 Water Report and monthly dashboard, in
parallel with community-focused programs.
Construction of Stage 1 (4 GL) Dampier desalination plant, which will
allow us to reduce our groundwater withdrawals from the Bungaroo
Aquifer in the Pilbara, Western Australia, and establishment of a
Memorandum of Understanding with the Western Australian
Government to assess feasibility for a Stage 2 plant expansion.
Management or involvement in regional water monitoring and
engagement programs, including initiatives in Gladstone Harbour
(Queensland, Australia), Nechako Valley (British Columbia, Canada),
and Saguenay–Lac-Saint-Jean (Quebec, Canada).
Piloting technologies for water treatment and metal recovery at
our Kennecott operation in the US, including use of plant-based
methods (phytoremediation).
Working collaboratively with stakeholders to improve our
understanding of the cultural value of water.
Entering a partnership with Skarn to develop an innovative water
intensity benchmarking dataset for the lithium sector.
Updating our Surface Water Allocation Disclosure Dashboard and
continued work on an expansion of the dashboard to include
groundwater information in 2026.
For more information see riotinto.com/water
Biodiversity
Biodiversity underpins the ecosystems that sustain life, livelihoods,
and economies. For Rio Tinto, healthy ecosystems are critical – not
only for supporting ecological communities but also for ensuring
operational resilience. Our mining activities often intersect with
areas of high ecological value, and the industry relies on ecosystem
services such as clean water and air, erosion control, and climate
stability.
We recognise the potential impacts of our activities on biodiversity
and are committed to achieving no net loss (NNL) or a net gain (Net
Positive Impact, NPI) to biodiversity, measured against a 2020
baseline, by the end of closure.
Rio Tinto’s approach to biodiversity management is embedded in
Environment Standards and aligned with global frameworks,
including the Global Reporting Initiative. We apply the mitigation
hierarchy - avoid, minimise, rehabilitate and offset - to prioritise
avoidance across all stages of the mining lifecycle, including
exploration, project development, operations and closure.
Where impacts cannot be avoided, we implement mitigation and
rehabilitation measures. Where applicable, offsets are initiated early
in the project life cycle and developed in consultation with
stakeholders to address residual impacts. Recent updates to our
exploration procedures have improved the capture and reporting of
avoidance actions as part of tenure management. Additionally,
enhancements to our Studies guidance will strengthen the
integration of mitigation, offsetting and avoidance measures during
project initiation.
We maintain asset-level biodiversity action plans, addressing priority
species – including those listed on the International Union for
Conservation of Nature (IUCN) Red List. These efforts are guided
by site-specific assessments and inclusive engagement with
stakeholders, particularly Indigenous and land-connected
communities.
Globally, one of the central challenges for business is establishing
scalable approaches to assess the condition of nature. We actively
participate in industry and cross-sectoral forums to advance our
methodologies to measure no net loss or net gain to biodiversity
across our operations; this includes the ICMM Nature Working
Group.
Our strategic partnerships with Proteus (UNEP-WCMC) and BirdLife
International continued, allowing us to contribute to, and benefit
from, global biodiversity expertise. We also had the opportunity to
sponsor the Western Australia Biodiversity Conference, and
participate in the UNEP-WCMC Nature Action Dialogues.
Through 2025, Rio Tinto continued to strengthen its biodiversity
management approach, translating our nature positive commitments
into tangible actions across our global operations. Guided by the
ICMM Nature Position Statement and aligned with emerging global
frameworks such as the Taskforce on Nature-related Financial
Disclosures (TNFD), we focused on building robust baselines,
piloting measurement methodologies, enhancing transparency and
investing in conservation partnerships that deliver ecological
benefits beyond our operational footprint.
We actively participated in the Nature Positive Initiative (NPI) Pilot
Program for our Pilbara Iron Ore and Oyu Tolgoi copper assets,
supported by our piloting partner BirdLife International. This initiative
tested draft global terrestrial biodiversity metrics using site-specific
and public data to assess the current and 2020 baseline state of
nature through real-world case studies. The results will contribute to
NPI’s further refinement of recommended metrics and guidance
material in 2026.
Environmental data collection at our assets continues to inform our
understanding of the ecological context within and surrounding our
operational footprint, and it is a critical step toward measuring
progress against no net loss. In alignment with our Environment
Standards, these monitoring activities are shaped by regulatory
requirements and host community engagement. In 2025, we
continued a portfolio-wide program to develop biodiversity baselines
and an NNL prioritisation framework aligned with global best
practice principles and ICMM commitments.
To further support our baselining and state-of-nature measurement
efforts, we conducted a comprehensive review of publicly available
data and tools. Using NNL/NPI calculation methodologies and a
suite of global guidance and reference documents, we derived
insights into the 2020 ecosystem extent, condition and species
presence across key assets in Australia, Asia, Africa and Canada.
This generated a detailed technical understanding of available tools
applicable to a global footprint that encompasses a wide range of
biomes.
Additional Conservation Actions (ACAs) play a complementary role
in strengthening our biodiversity management approach, particularly
where opportunities remain to uplift ecological outcomes after
applying mitigation processes. ACAs help deliver broader ecological
benefits beyond our operational footprint, be that supporting species
recovery, enhancing ecosystem resilience or enhancing
understanding of our natural environment. In 2025, we initiated and
continued several key projects, such as our Pilbara Conservation
Project, Founders Factory Start-up Partnerships for Sustainability
and the North Queensland Land and Sea Program. Visit our website
for more information.
For more information see riotinto.com/biodiversity
Land
Effective land management is essential to minimising environmental
impacts and supporting sustainable mining operations. Key activities
include planning and managing land use to reduce disturbance,
implementing progressive rehabilitation during the life of mine, and
restoring ecosystems post-closure. We focus on soil conservation,
erosion control, and revegetation practices, while engaging with
stakeholders to align land use with community and environmental
values. These efforts ensure responsible stewardship of land
resources and contribute tolong-term environmental resilience.
In 2025, we rehabilitated 26 km 2 of land, mostly at our Argyle
diamond mine in Australia, Simandou project in Guinea and iron ore
mines and exploration areas in the Pilbara.
In Mongolia, we rehabilitated another 6 km² of abandoned mine
workings outside our operational footprint, near the Tsagaan Zur
river in the Selenge province. This effort supports Oyu Tolgoi’s
commitment to the Government of Mongolia’s national initiative to
plant one billion trees by 2030. We established and handed over
another 3 tree nurseries in the South Gobi to the local community,
with a combined capacity to produce an additional one million
saplings annually. We planted 1.6 million trees and awarded 5 more
scholarships to students pursuing forestry studies.
Throughout the last year, we continued to transform commitments
into action. We developed a number of site improvement plans
focused on land stewardship for priority operations as part of the
implementation of our nature targets program.
At the end of the year, our land footprint – total disturbed area – was
1,818 km 2, an increase of 56 km 2 from 2024. This includes all
disturbances at our operating assets and activities, such as
exploration activities, smelters, mines and supporting infrastructure.
The majority of disturbance occurred at Weipa and Simandou as a
result of the establishment of new mining areas.
Our rehabilitation and closure teams continue to partner with
research centres to refine our approaches and improve outcomes.
At our bauxite mines and refineries, we have progressed trials
focusing on transforming stored tailings material into soils that will
support plant growth. To strengthen monitoring of rehabilitated
areas, we advanced trials of digital tools designed to complement
traditional on-ground data collection.
In addition, 14 of our operations completed rehabilitation
trials aimed at improving seed germination, reducing erosion
and enhancing topsoil quality – critical factors for
rehabilitation success.
For more information about our closure work see page 51.
Waste
As the global population continues to grow and industrialise,
effective management of waste materials is expected to become
increasingly important for people and nature. Rio Tinto produces
materials that play an important role in the economy while managing
mineral and non-mineral materials responsibly. We strive to enhance
our approach to materials management practices by designing out
waste where possible, keeping resources in use longer, and safely
and responsibly disposing of wastes across our business and value
chain.
Our mineral waste generation and disposal volumes have remained
similar over the past 5 years, however there is more annual
variability in non-mineral waste volumes and disposals, which is
largely driven by mine development and closure activities. Looking
ahead, we aim to maximise resource efficiency while eliminating
waste and recovering valuable materials. We will continue to explore
circular solutions and innovative ways to manage materials.
For more information about tailings see page 51.
Air quality
Clean air is essential for the health of ecosystems and host
communities that surround our operations. Emissions such as
particulates and gases have the potential to impact air quality and
the atmosphere, so we have a responsibility to ensure they are
managed in line with regulations and stakeholder expectations.
Some emissions can be hazardous and require careful monitoring
and management. The potentially hazardous emissions we monitor
at operations are:
sulphur oxides (SOx), mainly at our aluminium and copper smelters
nitrogen oxides (NOx), mainly from burning fossil fuels
gaseous fluoride emissions from aluminium smelters
respirable particulate emissions (PM 10 and PM 2.5) - very fine particles
from mining and processing operations and from burning fossil fuels.
We apply the mitigation hierarchy across all phases of the mining
life cycle to keep air emissions within acceptable limits. Our first
priority is to avoid generating emissions wherever possible.
Progress on decarbonisation initiatives has supported reductions in
air pollutants, including the installation of solar power, heat recovery
systems, and the use of renewable fuels.
Many of our hazardous emission levels have remained relatively
stable over the past 5 years (NOx, SOx, fluoride), though we have
seen a slight increase in PM 10 values over the past 3 years. We aim
to reduce point source emissions by upgrading equipment with best-
available technologies and incorporating control technology
evaluations into capital projects. Proper operation and maintenance
of assets is critical to minimising emissions, though some inevitably
leave our sites. We implement and expand air monitoring networks
inside and outside our site boundaries.
Operational environment overview
| 2025 | 2024 | 2023 | 2022 | 2021 | |
|---|---|---|---|---|---|
| Significant environmental incidents1 | 0 | 0 | 1 | 1 | 2 |
| Fines and prosecutions – environment ($’000)2 | 1,639.3 | 604.8 | 987.0 | 109.8 | 7.4 |
| Land footprint – disturbed (cumulative square kilometres)3 | 1,818 | 1,762 | 1,813 | 1,775 | 1,700 |
| Land footprint – rehabilitated (cumulative square kilometres) | 610 | 587 | 552 | 522 | 494 |
| Mineral waste disposed or stored (million tonnes) | 924 | 980 | 983 | 978 | 1,005 |
| Non-mineral waste disposed or stored (million tonnes) | 0.77 | 0.66 | 0.73 | 0.75 | 0.65 |
| SOx emissions (thousand tonnes) | 75.2 | 73.7 | 72.8 | 66.2 | 70.2 |
| NOx emissions (thousand tonnes) | 58.7 | 55.3 | 67.2 | 64.6 | 62.3 |
| Fluoride emissions (thousand tonnes) | 2.23 | 2.40 | 2.61 | 2.36 | 2.36 |
| Particulate (PM10) emissions (thousand tonnes) | 176.2 | 168.2 | 169.5 | 146.3 | 142.3 |
- Significant environmental incident is an incident with an actual consequence rating of high or very high. We measure and rate incidents according to their actual environmental and
compliance impacts using 5 severity categories: very low, low, moderate, high and very high. Very high and high environmental incidents are usually reported to the relevant product
group head and the Rio Tinto Chief Executive as soon as possible.
- In 2025, we received environmental fines and administrative penalties relating to contaminant releases, permitting non compliances, discharge exceedances and failures to meet
regulatory requirements across several operations. At Yarwun in Australia, regulators issued two penalty infringement notices for contaminant releases involving saline effluent from a
pipeline and the discharge of bauxite washwater slurry from a wharf. In Canada, the Vaudreuil plant received non compliances under the Environmental Quality Act and hazardous
materials regulations, the Roberval/Port Alfred site was cited for delayed incident reporting, and the Arvida plant exceeded discharge criteria for toxicity and hydrocarbons and received a
non compliance relating to environmental operating conditions. Further administrative penalties were issued at Havre Saint Pierre and Lac Tio for inadequate project construction
authorisations and containment infrastructure maintenance practices, delayed reporting of permit exceedances, and unauthorized disposal of residual materials, along with federal
penalties related to 2023 effluent exceedances and sampling errors during an unauthorized discharge. In the United States, enforcement actions continued under the Wilmington
operations consent decree. Following extensive investigations at Kennecott Copper, historical permitting non-compliances related to water containment failures and upset conditions was
resolved through a monetary penalty, with no detectable contamination identified. Separately, at Rotterdam operations in Europe, a transporter was fined for non compliant hazardous
goods labelling under EU ADR regulations during shipment of product in France.
- A reduction in cumulative disturbance from 2023-2024 is a result of the sale of Dampier Salt Limited’s Lake MacLeod operation.
Note: The numbers may change year to year and retrospectively due to reconciliations of data.
Tailings
We engage with stakeholders throughout the life cycle of our tailings
storage facilities (TSFs), from design to closure. We also collaborate
closely with external bodies to improve the way tailings are
managed across our industry.
We operate 111 TSFs across our global assets. Of the 111 TSFs, 40
are active, 24 are inactive and 47 are closed.
We work through technical committees and joint venture
relationships to support leading practice in tailings management.
Our full tailings disclosure is available on our website. We
periodically update the list of TSFs to reflect operational and
ownership changes. These include changes due to the transition to
closure or remediation obligations for legacy assets, and
reclassification of facilities.
Our facilities are regulated and permitted and have been managed
for many years to comply with local laws, regulations, permits,
licences and other requirements. Tailings management has been
included in the Group risk register since 2010, and our Group safety
standard for tailings and water storage facilities has been in place
since 2015. Our internal assurance processes verify that our
managed TSFs operate in accordance with this standard, which we
updated in 2021.
Our TSFs have emergency response plans – tested through training
exercises in collaboration with stakeholders such as local
emergency services – and follow strict business resilience and
communication protocols.
We have continued to progress our implementation of the Global
Industry Standard on Tailings Management (GISTM). This focuses
on preventing tailings facility failures, reducing the social and
environmental impacts of tailings facilities, and improving
engagement and transparency on tailings with local communities.
We have also assessed our progress on implementation through
self-assessment and independent audits, using ICMM’s GISTM
Conformance Protocols.
In 2025, we achieved full GISTM conformance for the “Very High”
and “Extreme” consequence classification tailings facilities, and for
the majority of the “Low”, “Significant” and “High” consequence
facilities.
Our product group and Closure teams will continue to work towards
full conformance and we will report our performance yearly in
accordance with the GISTM requirements.
In August 2025, in accordance with Principle 15 of the GISTM, we
updated our public tailings disclosures for the 14 “Very High” and
“Extreme” TSFs we operate and published new information on a
further 84 tailings facilities rated “Low”, “High” or “Significant”.
For more information see riotinto.com/tailings
We continued to regularly convene the Tailings Management
Committee with our designated Accountable Executives. This
provides coordinated governance of tailings management
practices across the Group.
We continued to play an active role in the ICMM tailings working
group, which provides guidance to support the safe, responsible
management of tailings with the goal of eliminating fatalities and
catastrophic events.
Closure
We are committed to being responsible operators throughout the
entire life of our assets, delivering value at every stage – from
discovery to closure.
Today, we plan for the end right from the beginning, incorporating
closure in each stage of the asset life cycle in the way we design,
build and operate.
We work with communities, governments and other stakeholders to
complete closure activities and repurpose and renew sites for their
next use.
At the end of 2025, closure provisions on our balance sheet totalled
$17.8 billion (2024:$15.7 billion).
In 2025, we continued to advance delivery of our major closure projects
in Australia and management of our global legacy portfolio.
Argyle diamond mine
We continue rehabilitating the former Argyle diamond mine on
Miriwoong and Gija country in Western Australia. We have made
significant progress on reprofiling the former processing plant area,
and waste rock dumps, and capping the tailings storage facility. We
have now passed beyond 85% overall project completion, and the
removal of the Argyle mine accommodation facilities, utilities
infrastructure and airport is nearly complete.
We are continuing to review our contracting strategy to focus on
work awarded to Traditional Owner businesses, spending
A$47.1 million in 2025 (2024: A$44.9 million).
Gove refinery and residue disposal areas
While bauxite mining operations continue until the end of the
decade, we are progressing demolition of the Gove alumina refinery
and rehabilitation work on the former bauxite residue disposal areas
(BRDA), a type of tailings storage facility, on the lands of the Yolŋu
peoples in the Northern Territory of Australia.
In 2025, we completed demolition of the remaining large structures
of the refinery. Working with Traditional Owners, and through careful
planning, we took measures to ensure the protection of an important
cultural heritage site during demolition activity, understanding its
importance to the Yolŋu. We have processed around 127,000
tonnes of scrap steel for recycling since 2023. We continue to
advance soil remediation of the refinery site as we work towards
final landform and revegetating the area.
We are progressing rehabilitation work of the former BRDAs,
completing civil works on Pond 5 to prepare for monitoring and
maintenance, and starting work on Pond 6 South, working with a
Traditional Owner business on enabling works.
We launched a pilot housing demolition program for properties
unsuitable to be retained, to create opportunities for local builders to
develop new and diverse housing on vacant, serviced lots. Work to
upgrade services such as sewer lines, power and water
is also underway.
We are developing programs that build local capability and
resilience, including partnering with schools to offer virtual work
experience opportunities for young people.
We continue to be an active member of the Gove Peninsula Future
Reference Group along with Traditional Owners, Northern Territory
and Commonwealth governments, and the Northern Land Council,
to support planning for the region’s future and helping transition to a
post-mining future.
Ranger Rehabilitation Project
We continue to operate under the Management Services Agreement
(MSA) with Energy Resources of Australia Ltd. (ERA) to manage the
Ranger Rehabilitation Project with oversight from the ERA board.
The former Ranger uranium mine is located on the traditional lands
of the Mirarr People in the Northern Territory. The MSA builds on
ERA’s existing rehabilitation efforts and enables us to share our
technical expertise in the design, planning and execution of closure
projects, including managing stakeholder engagement and delivery
partner relationships.
Rio Tinto holds approximately 98.43% of ERA’s shares and in April
2025, we began the compulsory acquisition process to acquire the
remaining shares in ERA. In May 2025, objections were lodged
during the objection period by the holders of at least 10% of the ERA
shares subject to the acquisition notice. We have applied for court
approval of the proposed compulsory acquisition of the remaining
shares in ERA, and the matter remains before the court.
In 2025, we progressed Pit 3 dry capping, installing geotextile
and beginning the initial dry capping layers. We continue to
face challenges in drying the tailings surface and are assessing
engineering options and solutions to continue the capping
works in 2026. Other aspects of the project are making good
progress including environmental management, regulatory
approvals, stakeholder engagement, land tenure negotiations
and technical studies.
We remain committed to the rehabilitation of the Ranger Project
Area to a standard that will establish an environment similar to the
adjacent Kakadu National Park, a World Heritage site. We continue
to work with all key stakeholders, including the Mirarr People, to
complete this important rehabilitation project.
Legacy assets
We manage over 90 legacy assets in 9 countries and 30 tailings
storage facilities (TSF) across our portfolio.
We have achieved safe closure status at Argyle TSFs ATD 1, ATD 2
and ATD 3 at the former Argyle Diamond Mine in Western Australia
and the Kelian in-pit TSF at Kelian in Indonesia. At Holden and
Ridgeway in the US, Kelian Namuk in Indonesia, and Segoussac in
France, TSF risks are considered as low as reasonably practicable,
demonstrating improvement in risk management.
For more information on tailings management, see page 51.
We continue to progress execution and enabling work across the
global legacy portfolio to meet our commitments. In 2025:
We started phase 2 of our rehabilitation work at Dammarie-lès-
Lys in France. Work includes removal of contaminated soil,
enabling the site for repurposing. To reduce impacts due to dust,
noise and traffic to the nearby community, work will be completed
under a tent.
We restarted rehabilitation work at Salindres in France. Work
includes land shaping, reinforcement of a dyke, capping and
improved water management.
We progressed regulatory approval for our remediation plan at
Beatson, a series of former copper mines in Alaska, US, which
enables us to prepare for execution.
We continued to review our portfolio for commercial opportunities,
completing the surrender of the lease of land at the Anglesey site
in Wales, UK. This site is a former aluminium smelter
decommissioned in 2013, with voluntary remediation works
completed from 2018 to 2024, enabling the area for
redevelopment.
Our approach
Where relevant, all of our operating sites have closure plans, and
we are developing closure plans for assets that have an indefinite
life, such as some port facilities. We review these plans regularly to
align with stakeholder expectations and to incorporate lessons
learned from other closure projects. At operations with joint
ownership structures, we endeavour to work in partnership with
other asset owners to ensure we consider closure through asset
design, planning and operations. Further review and update of
closure planning at Arcadium assets will be carried out to ensure
they are consistent with Rio Tinto requirements.
While planning for closure currently starts when we first design a
mine, we start more detailed planning at least a decade before we
expect an operation will close.
In 2025, we met our guidance provided to the market in 2024,
spending ~$1 billion on closure activities as we progressively
rehabilitate our operations and progress work at Argyle, Ranger, the
Gove alumina refinery and legacy sites.
For more information about our closure risks see page 96, and for more on closure provisions and financial statements, see page 163.
Partnering for the future
We work to solve the challenges of the future to reduce our liabilities
and create better outcomes.
We continued partnering with research and academic organisations,
start-ups and technology solutions providers to
find better ways to close and repurpose our assets. These include
opportunities to reprocess mineral and industrial residues,
selectively recover minerals from mine-influenced waters, augment
our knowledge base for closure, and improve execution and
monitoring of rehabilitation and revegetation.
We continued our partnership with SiTration, a Massachusetts
Institute of Technology mining start-up, to remediate and unlock
value from mine-influenced waters.
We have been collaborating with the Australian National
University to develop an advanced filtration system, inspired by
nature, that can recover critical resources such as copper and
lithium from mining wastewater, while simultaneously turning dirty
water into clean water.
We have been working with university partners in Europe to
recover critical minerals and remediate alkaline seepage from
bauxite residue deposit areas.
We have been trialling AI-driven workflows and remotely operated
platforms to help us track our progress and predict trajectories
towards rehabilitation and closure completion criteria on mine
sites, combining in situ and remote sensing.
The text of this filing, as the company filed it with the SEC, without its images or exhibits. This is not investment advice.