EX-99.5 · Projects under development

Projects under development

Projects under development comprise (i) projects owned by the Company that have not yet achieved a Notice to Proceed (“NTP”), and (ii) projects that have been divested, but for which the Company has retained the engineering, procurement and construction (“EPC”) agreement and continues to perform development activities on behalf of the purchaser

NameLocationSize (MWDC)TimelineMilestoneExpected Cost (in Canadian dollar)Cost Incurred (in Canadian dollar)Sources of FundingCurrent Status
261 Township (Phase2)Alberta, Canada4.2Q3 FY2026NTP200,0005,500Equity financing, working capitalPhase 1 construction started in Q1 FY2025. Interconnection for Phase 2 is being prepared to submit after the interconnection agreement is executed for phase 1 with Fortis.
GainesvilleNew York, USA7Q3 FY2026NTP1,500,0001,127,144Development feeThe project has been sold to Qcells in Q2 FY2025. Construction expected to start in Q2 FY2026 subject to resolution of permitting issues. See “Legal Matters and Contingencies”.
Hwy 28New York, USA7Q2 FY2026NTP2,750,0002,529,861Development feeThe project has been sold to Qcells in December 2024. Construction expected to start in Q2 FY2026.
SUNYNew York, USA28Q4 FY2026Completion of interconnection studies, engineering and permitting, along with interconnection deposit, and procurement bid application fee2,900,000481,761Equity financing, working capitalThe interconnection application to New York Independent System Operator has been accepted into the new cluster study program. The project will move on to the customer engagement window, which will list any project physical infeasibility screens and a scooping meeting for the phase 1 study.
NS ProjectsNova Scotia, Canada31Q3 FY2026NTP900,00012,542Service feeThe Company will complete the interconnection project with Nova Scotia Power Inc., lead in-depth engineering studies, and complete the solar design. Construction is expected to begin in Q3 2026. Projects are owned by a third party.
Oak OrchardNew York, USA7Q3 FY2026NTP1,900,0001,151Equity financing, working capitalThe project is under interconnection study.
BoyleNew York, USA5.4Q3 FY2026NTP3,900,00023,792Equity financing, working capitalThe project has completed its interconnection approval and is now in the permitting stage.
Silver SpringsNew York, USA2.9Q3 FY2026NTP1,300,00070,335Equity financing, working capitalThe project has completed its interconnection approval and is now in the permitting stage.

Management’s Discussion and Analysis

GrandviewPennsylvania, USA13.8Q2 FY2027NTP1,200,000-Equity financing, working capitalThe project is under interconnection study.
StaufferPennsylvania, USA7Q3 FY2026NTP1,250,0002,115Equity financing, working capitalThe Company has secured a lease over the project site and will continue to work to complete the next steps in permitting, interconnection and securing the necessary financing for construction of the project.
North MainNew York, USA7.2Q3 FY2026NTP1,250,00022,714Equity financing, working capitalThe project is under interconnection study.
Skaneateles (Jordan Rd 1&2)New York, USA14.4Q2 FY2026NTP2,330,0002,014,150Equity financing, working capitalThe project received interconnection approval and is in the final stage of the permitting process.
Viridi Solar and BESSNew York, USA3.06 MW (Solar) 1.2 MWH (BESS)Q3 FY2026NTP1,300,0001,152,239Equity financing, working capitalThe Company has secured a lease over the project site and will continue to work to complete the next steps in permitting, interconnection and securing the necessary financing for construction of the project.
Jordan Rd, GainesvilleNew York, USA7.2Q4 FY2026NTP1,900,00068,186Equity financing, working capitalThe project is under interconnection study.
Glen RdNew York, USA4.3Q4 FY2026NTP1,500,00015,758Equity financing, working capitalThe project is under interconnection study.
Hoadley Hill RdNew York, USA7.2Q4 FY2026NTP1,900,00088,302Equity financing, working capitalThe project is under interconnection study.
Forest Hill RdNew York, USA4.584Q4 FY2026NTP1,500,00014,666Equity financing, working capitalThe project is under interconnection study.
Glor RdNew York, USA7.2Q4 FY2026NTP1,900,00026,946Equity financing, working capitalThe project is under interconnection study.
Day HollowNew York, USA2.8Q4 FY2026NTP700,00028,309Equity financing, working capitalThe project is under interconnection study.
903 (BESS)Ontario, CanadaDischarge: 4.74 Storage: 18.96Q1 FY2026NTP12,001,3828,917,359Equity financing, working capitalEPC project. EPC agreement entered Oct. 3, 2023. Debt financing has been secured through RBC. Commencement of construction remains subject to receipt of final permits. There is no certainty that final permits will be received.
OZ-1 (BESS)Ontario, CanadaDischarge: 4.74 Storage: 18.96Q1 FY2026NTP12,001,3829,323,959Equity financing, working capitalEPC project. EPC agreement entered Oct. 3, 2023. Commencement of construction remains subject to receipt of financing and final permits. There is no certainty that financing or final permits will be received. See “Legal Matters and Contingencies”.

Management’s Discussion and Analysis

During the current fiscal year certain projects that were previously disclosed were cancelled as follows:

●The site in Black Creek, NY representing 3.2 MW DC that was announced on May 6 2024. Development was discontinued due to high interconnection costs, which impacted the project’s overall financial viability.
●Projects in the Orleans County representing 30 MW that were announced on April 22, 2024. These projects were cancelled due to the costs associated with the Coordinated Electric System Interconnection Review (“CESIR”), which rendered these projects financially unsustainable.
●Project in Clay, New York, representing 7.00 MW DC that was announced on August 15, 2024. The project was cancelled because it was determined to not be financially viable.