EX-99.5 · Existing projects
Existing projects
The Company classifies its existing projects as those that are currently in the construction phase.
| Name | Location | Size | Timeline | Milestone | Current Status |
|---|---|---|---|---|---|
| (MWdc/MWh) | |||||
| Geddes | New York, USA | 3.7 | Q1 FY2026 | Reach PTO (permission to operate) | The project has reached PTO in Q1 FY2026. |
| Settling Basins - 1 | New York, USA | 7 | Q2 FY2026 | Reach PTO (permission to operate) | EPC project. Construction started in Q2 FY2024. Owned by Honeywell. |
| Settling Basins - 2 | New York, USA | 7 | Q2 FY2026 | Reach PTO (permission to operate) | EPC project. Construction started in Q2 FY2024. Owned by Honeywell. |
| Settling Basins - 3 | New York, USA | 7 | Q2 FY2026 | Reach PTO (permission to operate) | EPC project. Construction started in Q2 FY2024. Owned by Honeywell. |
| Camillus | New York, USA | 3.1 | Q3 FY2026 | Reach PTO (permission to operate) | EPC project. Construction started in Q4 FY2025. Owned by Solar Advocate. |
| 261 Township (Phase1) | Alberta, Canada | 1.4 | Q2 FY2026 | Reach PTO (permission to operate) | It’s the first phase of a total 4.2MW project. The construction started in Q1 FY2025. |
| SFF06 (BESS) | Ontario, Cananda | Discharge: 4.74 Storage: 18.96 | Q3 FY2026 | Reach PTO (permission to operate) and secure financing for construction. | IPP project. Construction started in Q3 FY2025 |
| Hardie Rd | New York, USA | 7 | Q4 FY2026 | Reach PTO (permission to operate) | EPC project. Construction started in Q4 FY2025. Owned by Qcells. |
| Rice Road | New York, USA | 6.4 | Q4 FY2026 | Reach PTO (permission to operate) | EPC project. Construction started in Q4 FY2025. Owned by Qcells. |