Skip to main content

GoldMining Inc.

For the period ended Jul 31, 2026. Filed Jul 22, 2026.

View on SEC.gov

About this filing

What a company based outside the US has published at home or sent to its shareholders. It is how many foreign companies share results and news between annual reports.

Jul 31, 2026 · Filed Jul 22, 2026

Use the contents to explore the available documents and sections.

GLDG$0.78+4.1%Stored close · as of Nov 6, 2026
See the whole filing, with its images and exhibits
Contents

EX-99.2 · Table 16.21 - Basic Project Parameters

Table 16.21 - Basic Project Parameters

ItemUnitValue
1. Work Schedule
Mining and Crushing
Days per yearday365
Shifts per dayshifts3
Hours per shift (average)h /d8
Break time per day (meals/rest)h2.25
Number of crewsnº4
Absenteeism rate (including vacation)%16.5%
2. Material Densities and Moisture (in situ)
Average Density
Dry basis
Mineralized Materialt/m32.56
Wastet/m32.37
Fresh Rock Density
Dry basis
Mineralized Materialt/m32.70
Wastet/m32.70
Average Moisture
Mineralized Material%5%
Waste%5%
3. Swell, Spreading and Compaction
3.1 Swell
Mineralized Material and Waste%25%
3.2 Waste Compaction%10%
3.3 Material spread by dozer%75%
4. Pit Parameters
Bench height (blasting)
Mineralized Materialm10
Wastem10
Maximum road gradient%10%
5. Blasting
Explosive
Density (Emulsion)g/cm31.10
Stemming Mineralized Materialm1
Stemming Wastem1
Hole filling factor%100%
6. Main Equipment
Drill rig / air compressor
Hole diameter Mineralized Materialpol4.0
Hole diameter Wastepol4.0
Hole inclinationº0
Subdrilling%10%
Penetration ratem/h36
GoldMining Inc. NI 43-101 Report – São Jorge ProjectPage 208
ItemUnitValue
Vf/Vp factor%60%
Drill pattern
Burden Mineralized Materialm3.00
Spacing Mineralized Materialm5.00
Burden Wastem4.00
Spacing Wastem6.00
Hydraulic excavator - Mineralized Material
Bucket capacity Mineralized Materialm31.8
Bucket capacity Wastem33.6
Average cycle times30
Bucket fill factor%95%
Haul truck - Mineralized Material
Payload capacityt19
Body volumem312
Haul truck - waste
Payload capacityt40
Body volumem325
7. Equipment Performance Factors
Drill
Physical availability%80%
Utilization%65%
Hydraulic excavator
Physical availability%85%
Utilization%78%
Truck
Physical availability%85%
Utilization%80%
8. Operational Efficiency Factors
Hourly efficiency%90.0%
Overall operating efficiency%95%
Weather factor%100%
9. Truck Speeds
Truck - mine/plant and mine/waste dump
Loaded (haul)km/h25
Empty (return)km/h30
10. Fixed Truck Times
Spotting/loading manoeuvresmin1.00
Dumping including manoeuvremin1.25
Fleet rounding limit%3%
GoldMining Inc. NI 43-101 Report – São Jorge ProjectPage 209

16.13.4** Mining Fleet Sizing**

The sizing of the main mining equipment fleet was based on the operational parameters presented in the previous section. The equipment was sized to perform excavation, loading, and haulage of material from the mining faces to the primary crusher and waste rock dumps. The fleet sizing reflects average operating conditions and does not consider short-term operational variability.

The following tables present the calculation basis used for fleet sizing, as well as a summary of the resulting equipment fleet (Table 16.22 to Table 16.27).

GoldMining Inc. NI 43-101 Report – São Jorge ProjectPage 210