Table 21‑3 Processing Plant Initial Capital
| Process Area | Initial Capital Cost (USD$ M) |
|---|---|
| Primary crushing and stockpile | 40.7 |
| Process plant general | 17.2 |
| Primary/secondary grinding | 51.1 |
| Regrind and flotation | 42.0 |
| Leach | 28.7 |
| Strip, regeneration, gold room | 11.7 |
| Detox, tailings dewatering | 9.3 |
| Reagents and services | 15.5 |
| Concentrate dewatering/handling | 2.2 |
| Tailings/water pumps and pipelines | 6.3 |
| Total directs | 224.7 |
| Indirects and Owner's costs | 44.9 |
| Total directs + indirects | 269.6 |
| 21.2 | SUSTAINING CAPITAL COST ESTIMATE |
Sustaining capital cost estimates include all capital costs that would be incurred years 1 through year 11, and mine closure in year 12. Total sustaining capital cost estimates are summarized in Table 21‑4.