EX-99.1 · Work Programs and Project Documentation
Work Programs and Project Documentation
In addition to following its obligations under the RUC, JV Inkai, like all subsoil users, is required to abide by work programs, which is a mandatory part of the RUC, and which relate to its operations over the life of the mine.
Work programs must be developed in accordance with project documents. The Subsoil Code establishes three types of project documents for uranium production, depending on the type and stage of the work:
| • | Pilot production project: none for JV Inkai. |
| • | Mining project: JV Inkai’s PUDD. |
| • | Decommissioning project. |
The project documents are developed and undergo a review and approval process. All work must be in compliance with the project documents, and conducting any work without an approved project document, or innon-compliance with it, is not permitted. Since January 2015, subsoil users conducting production of hard materials, including uranium, are allowed to produce within 20% (above or below) of their approved project targets in a year without triggering a requirement to revise the approved project documents. Any changes to the project documents that affect investment project targets included in the work program require amendments to the work program. Thus, changes of types, methods, technologies, volumes and terms of uranium mining operations are only allowed after amendment of the relevant project documents. Any amendments to aspects of the work program that are an integral part of the RUC require an application to the Competent Authority for approval, signing and registering amendments to the RUC.
The Amendments stipulate that an increase in production, an increase in the reserves, or an extension of the mining period are only allowed upon introduction to the contract of one of the following obligations of a foreign participant in a subsoil user:
| • | to increase a national uranium company’s participation interest in a subsoil user to 90%; or |
| • | to enter into a separate agreement in the territory of Kazakhstan on transfer of technology for converting and enriching uranium to the form of uranium hexafluoride enriched up to 5% providing for (1) obligation to ensure localization of the technology by building a plant together with a national uranium company, (2) obligation to sign a long-term agreement on the purchase of the plant’s products to guarantee a market for not less than 50% of the plant’s products, and (3) penalties for breach of these obligations. |
If the subsoil user accepts one of these obligations but subsequently violates it, the Competent Authority may terminate the contract.
The Amendments have retroactive effect.