Greenidge Generation Holdings Inc.
For the period ended Dec 31, 2025. Filed Mar 31, 2026.
View on SEC.govAbout this filing
A company's yearly report to the SEC, with audited financial statements. It is the fullest account a company gives of its business, its finances and the risks it sees.
FY2025 · Filed Mar 31, 2026
What changed in Management’s Discussion and Analysis?
Read the current filingPrevious report: 10-K
Period ended 2024-12-31; filed 2025-03-31.
0001628280-25-015543
Item 7. Management’s Discussion and Analysis of Financial Condition and Results of OperationsCurrent report: 10-K
Period ended 2025-12-31; filed 2026-03-31.
0001844971-26-000011
Item 7. Management’s Discussion and Analysis of Financial Condition and Results of OperationsThe baseline is this issuer’s latest earlier reporting period of the same form that was filed before the current report. A previous 10-Q is a different quarter, not a year-over-year comparison. Amendments are excluded.
Compared 115 previous paragraphs and 119 current paragraphs.
53 unchanged; 32 reworded; 32 added; 28 removed; 2 previous and 2 current paragraphs rearranged.
Tables are not compared: 8 previous and 10 current tables excluded. Dates, whitespace, punctuation and numbering changes are ignored; changes to financial figures remain significant.
A changed paragraph is not evidence that risk increased or decreased. An unchanged paragraph does not establish that risk stayed the same.
Added paragraphs (32)
Current report
We are a developer and operator of datacenters and powered assets designed to support energy-intensive computing workloads. We currently build, maintain and operate datacenters focused on bitcoin mining, along with related power and electric infrastructure. We are increasingly focused on leveraging our power generation assets, grid interconnection rights and datacenter development expertise to support AI and HPC workloads, which we believe represent a significant long-term growth opportunity.
Current report
We own and operate a vertically integrated cryptocurrency datacenter and power generation facility in Torrey, New York, which includes a natural gas power generation plant with approximately 106 MW of nameplate capacity. We also own a 34-acre greenfield site in Columbus, Mississippi, which we expect will provide access to 40 MW of datacenter capacity by the first quarter of 2027. Additionally, we have 7.5 MW of self-mining capacity in North Dakota through a five-year lease which provides us with energy access to support our cryptocurrency mining operations. We operated 7 MW of self-mining capacity at the Mississippi Facility prior to the sale of the facility on September 16, 2025.
Current report
Results from Operations
Current report
Total cost of revenue, exclusive of depreciation, increased $8.7 million, or 21%, to $49.8 million during 2025 as compared to the prior year. We estimate the increase is composed of approximately 15% due to higher natural gas costs primarily due to a 47% increase in natural gas prices, as well as a 5% overall increase due to a 9% increase in average emissions cost compared to the prior period, as well as a 3% increase due to higher electricity costs compared to the prior period.
Current report
•Decrease of approximately $0.6 million in professional services and consulting expenses resulting from reduced discretionary spending;
Current report
•Decrease of approximately $0.3 million due to less environmental remediation expenses incurred during 2025 compared to the prior year period.
Current report
Loss (gain) on digital assets
Current report
We recognized a loss on digital assets of $21.0 thousand for the year ended December 31, 2025 as a result of a decrease in the price of bitcoin in the last quarter of 2025. The loss consisted of a $3.0 million unrealized loss on digital assets held in treasury, offset by a$3.0 million realized gain on sales of bitcoin during the year. There was a$1.4 million unrealized gain on digital assets and a$0.7 million realized gain on sales of bitcoin during the year ended December 31, 2024.
Current report
We recognized a gain on the sale of assets of $11.5 million during the year ended December 31, 2025, primarily due to a $10.5 million gain on sale of our 152-acre property in South Carolina and a $1.4 million gain on sale of assets from our
Current report
Mississippi plant, which comprised miner infrastructure, miners and land, as well as other long-lived assets during the year. During the year ended December 31, 2024, we recognized a $0.6 million loss on the sale of assets.
Current report
Depreciation decreased $1.7 million, or 12%, to $11.8 million for the year ended December 31, 2025 as compared to the prior year period due to a lower asset base.
Current report
Operating loss
Current report
Total other income (expense), net
Current report
During the year ended December 31, 2025, other expense, net decreased $17.0 million, or 202%, to other income, net of $8.6 million, primarily due to decreased interest expense and a gain on troubled debt restructuring as a result of the privately negotiated exchange agreements, the public tender/exchange offers and open market debt repurchases, as well as the absence of impairment of equity securities and changes in fair value of warrant asset that existed in the prior year.
Current report
Net income (loss)
Current report
EBITDA and Adjusted EBITDA (loss)
Current report
Adjusted Free Cash Flow
Current report
"Adjusted Free Cash Flow” is defined as net cash flow provided by (used for) operating activities less purchases of and deposits for property and equipment, which is then adjusted to add revenue from digital assets production and remove proceeds from the sale of digital assets already included in operating activities. Digital assets (i.e., bitcoin) generated from mining are treated as an adjustment to reconcile net income (loss) to cash used in operating activities in the GAAP financial statements. This Adjusted Free Cash Flow measure approximates the Company’s cash flow as if such digital assets, which are highly liquid, continued to be liquidated at the time of receipt, and presented within operating activities, instead of being presented within investing activities as a result of the Company’s bitcoin retention strategy. Adjusted Free Cash Flow is not intended to be a measure of residual cash available for management’s discretionary use since it omits significant sources and uses of cash flow, including, without limitation, mandatory debt repayments and realized and unrealized gains (losses) on digital assets.
Current report
Total Debt and Net Debt
Current report
“Total Debt” differs from the GAAP measure of total long-term debt as it represents the aggregate outstanding principal indebtedness under the Company’s 8.50% Senior Notes due 2026 and 10.00% Senior Notes due 2030, excluding adjustments for unamortized discounts, premiums, and issuance costs that are netted against the principal under GAAP to arrive at the carrying value. “Net Debt” is defined as Total Debt less cash and cash equivalents (including restricted cash)
Current report
and digital assets. The most directly comparable GAAP financial measure to Total Debt and Net Debt is total long-term debt (including the current portion), which is reported at amortized cost on the Company’s consolidated balance sheet in accordance with U.S. GAAP (ASC 470-60).
Current report
Management has taken certain actions since 2022 to improve our liquidity, including, among other things, the sale of assets, the proceeds of which were used to extinguish $80.3 million of long-term debt, and significant restructuring activities to materially reduce selling, general and administrative expenses. In addition to these actions taken in prior years, we completed the following transactions in 2025 to continue to improve our liquidity position:
Current report
•On December 11, 2025, we completed the sale of the 152 acres of the South Carolina Land we owned in Spartanburg, South Carolina and an assignment of our rights to 60 MW of electrical services, which is expected to be made available to the South Carolina Land by September 2026, to an affiliate of The Lightstone Group and Lighthouse Datacenters for $18.0 million in cash paid at closing and the right to receive up to $18.0 million in additional future contingent payments. Any future contingent payments are payable at $180,000 per MW of power capacity made available to the South Carolina Land before December 31, 2030, to the extent such capacity exceeds the Initial Load. We recognized a gain on the sale of $10.5 million and have not recognized any consideration related to the additional future contingent payments as they are not realizable as of December 31, 2025.
Current report
•On August 1, 2025, we entered into the APA and certain ancillary agreements to sell certain assets comprising the Mississippi Facility, other than the adjoining 5.6-acre tract of land with over 73,000 square feet of industrial warehouse space, for $4.2 million in cash, which closed on September 16, 2025 (see Note 4, “Property and Equipment”).
Current report
•During 2025, we completed a series of public tender/exchange offers, pursuant to which we repurchased $15.0 million in aggregate principal amount of the Senior Notes for a total of $5.7 million in cash and exchanged an additional $5.0 million in aggregate principal amount of the Senior Notes for $2.3 million in aggregate principal amount of the New Notes.
Current report
•During 2025, we paid $0.7 million in cash to repurchase an aggregate of $1.1 million principal amount of the Senior Notes in open market transactions. We recognized a gain on extinguishment of debt of $0.4 million as a result of such open market repurchases.
Current report
Following the conclusion of the privately negotiated exchanges, the public tender/exchange offers and open market debt repurchases, we had $36.7 million in aggregate principal amount of the Senior Notes outstanding, along with $3.1 million of capitalized contractual interest payments, and $2.3 million in aggregate principal amount of the New Notes outstanding, along with $1.0 million of capitalized contractual interest payments. The Senior Notes mature on October 31, 2026, at which time all outstanding principal, together with any accrued and unpaid interest thereon, will become due. The New Notes mature on June 30, 2030, at which time all outstanding principal, together with any accrued and unpaid interest thereon, will become due. See Note 5,“Debt” for additional information.
Current report
We are considering various alternatives to address our obligations under the Senior Notes, including:
Current report
•Issuances of new debt and/or equity to refinance, repay or otherwise satisfy the existing Senior Notes.
Current report
Additionally, our ability to achieve projected cash flows depends on our ability to obtain and comply with required permits and licenses, including the Title V Air Permit for our New York facility. While this permit is subject to the Stipulation, it may still face legal challenges from third-party environmental groups (see Note 10, “Commitments and Contingencies”), which may have an adverse impact on our operations and our ability to meet cash flow forecasts.
Current report
Given the uncertainty regarding our financial condition over the next 12 months from the date the consolidated financial statements contained in this Annual Report were issued, we have concluded that there is substantial doubt about our ability to continue as a going concern for a reasonable period of time.
Current report
Net cash used for financing activities was $10.6 million for the year ended December 31, 2025, as compared to $11.2 million provided by financing activities for the year ended December 31, 2024. The decrease is primarily related to the absence of activity under our equity financing agreements in 2025 and cash payments in connection with privately negotiated exchange agreements, public tender/exchange offers and open market repurchases of the Senior Notes.
Removed paragraphs (28)
Previous report
Discontinued Operations
Previous report
The contract with Support.com’s largest customer expired on December 31, 2022 and was not renewed and the business ceased operations in 2023. As a result, we have classified the Support.com business as held for sale and discontinued operations in these condensed consolidated financial statements as a result of management and the board of directors making a decision to pursue alternatives for the Support.com business and to strictly focus on its cryptocurrency mining, datacenter hosting and power generation operations. See Note 3, "Discontinued Operations" of our audited condensed consolidated financial statements for additional information.
Previous report
Results from Continuing Operations
Previous report
On January 30, 2023, upon entering into the NYDIG Hosting Agreement, we transitioned the majority of the capacity of our owned datacenter facilities to datacenter hosting operations. We entered into hosting arrangements at third party sites for the remaining owned miners in the first and second quarters of 2023 which were terminated in the second quarter of 2024.
Previous report
Total cost of revenue, exclusive of depreciation, decreased $9.9 million, or 19%, to $41.1 million during 2024 as compared to the prior year. We estimate the decrease is comprised of the following:
Previous report
•The South Carolina Facility contributed 24% of cost of revenue in 2023, as compared to no activity at the facility in 2024 following the sale in the fourth quarter of 2023.
Previous report
•The cancellation of third-party hosting contracts in the second quarter of 2024 resulted in an 8% reduction to cost of revenue due to lower hosting fees;
Previous report
•Natural gas costs increased year-over-year by 12% as a result of 5% higher volume usage by the New York Facility, as well as a 6% increase in natural gas prices year-over-year.
Previous report
•Total restructuring costs decreased approximately $4.1 million in 2024 compared to the prior year, mainly as a result of non-recurring restructuring costs incurred in the prior year;
Previous report
•Total stock compensation decreased approximately $0.5 million in 2024 compared to the prior year, as a result of a decline in amortized expense relating to RSUs with a higher grant date fair value, which was offset partially by an increase in amortized expense relating to options granted in prior periods.
Previous report
Gain on digital assets
Previous report
We recognized a gain on digital assets of $2.2 million for the year ended December 31, 2024 as a result of measuring digital assets at fair value due to our adopting ASU 2023-08, Accounting for Disclosure of Crypto Assets, on January 1, 2024. This is compared to a gain on sale of digital assets of $0.5 million recognized during the year ended December 31, 2023, which is presented in Other (expense) income. The increase in the gain was a result of our transition to a bitcoin self-mining retention strategy in the third quarter of 2024, as well as the increase in the price of bitcoin.
Previous report
We recognized a loss on the sale of assets of $0.6 million during the year ended December 31, 2024, as a result of selling long-lived assets, comprising primarily of excess mining infrastructure equipment. This is compared to a gain on sale of assets of $9.9 million recognized during the year ended December 31, 2023, which was primarily a result of the sale of the South Carolina Facility.
Previous report
Depreciation decreased $0.1 million, or 1%, to $13.5 million for the year ended December 31, 2024 as compared to the prior year period due to a lower asset base resulting from the sale of our South Carolina Facility during the fourth quarter of 2023, which was partially offset by the acquisition of miners and miner infrastructure during 2024.
Previous report
Operating loss from continuing operations
Previous report
Total other expense, net
Previous report
During the year ended December 31, 2024, other expense, net decreased $3.7 million, or 31%, to $8.4 million primarily due to decreased interest expense as a result of the NYDIG debt extinguishment. This was partially offset by an impairment of equity securities of $0.9 million and change in fair value of warrant asset of $0.5 million.
Previous report
Net Loss from continuing operations
Previous report
Loss from discontinued operations
Previous report
In conjunction with our decision to pursue alternatives, including a sale of Support.com, we have reported the Support.com business as discontinued operations in the consolidated financial statements. Loss from discontinued operations, net of tax was $0.0 for the year ended December 31, 2024, as compared to a loss of $0.5 million for the year ended December 31, 2023. See Note 3, "Discontinued Operations", in the Notes to Consolidated Financial Statements for a further breakdown.
Previous report
EBITDA from continuing operations and Adjusted EBITDA (loss) from continuing operations
Previous report
On November 27, 2024, we entered into a purchase and sale agreement to sell the remaining 152-acres to Data Journey for $12.1 million in cash and an 8% profit participation in the property's planned data center. We anticipate the closing of the sale of the land in 2025 to generate proceeds that will further improve our liquidity.
Previous report
We continued to improve our liquidity position in 2024. On February 12, 2024, we entered into a securities purchase agreement (the “Armistice SPA”) with Armistice Capital Master Fund Ltd. (“Armistice”). Pursuant to the Armistice SPA, Armistice purchased (i) 450,300 shares of Class A common stock (the “SPA Shares”), and (ii) a pre-funded warrant (the “Pre-Funded Warrant”) to purchase 810,205 shares of Class A common stock (the “Pre-Funded Warrant Shares”). The per share purchase price of the SPA Shares and the Pre-Funded Warrant Shares was $4.76, resulting in aggregate gross proceeds of $6.0 million, and after giving effect to the exercise price of $0.0001 per Pre-Funded Warrant Share, we received net proceeds of $6.0 million. In addition, we issued to Armistice a five-year warrant to purchase up to 1,260,505 shares of Class A common stock, exercisable commencing on August 14, 2024 at an exercise price of $5.25 per share.
Previous report
We believe our existing cash and cash equivalents, together with digital assets, cash generated from operations and the proceeds from the sale of the South Carolina Facility, will be sufficient to fund our operations and satisfy our current obligations through the next 12 months. However, our projected operating cash flows are not sufficient in the long term to meet our existing long-term debt obligations and will only be sufficient to fund operations and current operations if bitcoin mining economics remain at or above current levels.
Previous report
We may also raise additional funds through sales of equity under the Common Stock Purchase Agreement. For the year ended December 31, 2024, we issued 1,595,855 shares under the Common Stock Purchase Agreement for net proceeds of $4.3 million.
Previous report
While the Company believes it will be successful in its efforts to improve liquidity, which will allow it to meet its financial commitments for at least the next 12 months, there can be no assurance that these efforts will be successful.
Previous report
Net cash provided by financing activities from continuing operations was $11.2 million for the year ended December 31, 2024, as compared to $13.8 million for the year ended December 31, 2023. The decrease is primarily related to a $18.7 million reduction in sales of Class A common stock under our ATM Agreement. This was partially offset by a $6.0 million increase in proceeds from the issuance of common stock and pre-funded warrant under the Armistice SPA, a $6.8 million elimination of principal payments on debt in 2023 due to its restructuring, and a $3.3 million increase in proceeds from the issuance of common stock under the Equity Purchase Agreement.
Previous report
An impairment charge of $0.2 million was recorded for the year ended December 31, 2024, which was the remaining value of certain miners that were determined to be no longer recoverable.
Reworded paragraphs (32)
Previous wording
You should read the following discussion of our financial condition and results of operations in conjunction with our consolidated financial statements and related notes included herein. Among other things, those financial statements include more detailed information regarding the basis of presentation for the following information. The financial statements have been prepared in accordance with accounting principles generally accepted in the United States of America ("U.S. GAAP") and are presented in U.S. dollars. The following discussion contains forward-looking statements that involve risks and uncertainties. As a result of many factors, such as those set forth under "Risk Factors," "Cautionary Statement Regarding Forward-Looking Statements" and elsewhere in this Annual Report, our actual results may differ materially from those anticipated in these forward-looking statements. You should carefully review the sections titled "Cautionary Statement Regarding Forward-Looking Statements" and "Risk Factors" in this Annual Report.
Current wording
You should read the following discussion of our financial condition and results of operations in conjunction with our consolidated financial statements and related notes included herein. Among other things, those financial statements include more detailed information regarding the basis of presentation for the following information. The financial statements have been prepared in accordance with accounting principles generally accepted in the United States of America (“U.S. GAAP”) and are presented in U.S. dollars. The following discussion contains forward-looking statements that involve risks and uncertainties. As a result of many factors, such as those set forth under“Risk Factors,” “Cautionary Statement Regarding Forward-Looking Statements” and elsewhere in this Annual Report, our actual results may differ materially from those anticipated in these forward-looking statements and the going concern discussion in Note 2,“Significant Accounting Policies—Going Concern,” in the Notes to Consolidated Financial Statements. You should carefully review the sections titled“Cautionary Statement Regarding Forward-Looking Statements” and“Risk Factors” in this Annual Report.
Previous wording
We own cryptocurrency datacenter operations in Torrey, New York, Columbia, Mississippi, lease property for purposes of operating a cryptocurrency datacenter in Underwood, North Dakota and previously owned and operated a facility in Spartanburg, South Carolina (collectively, the "facilities"). The New York Facility is a vertically integrated cryptocurrency datacenter and power generation facility with an approximately 106 MW nameplate capacity, natural gas power generation facility. We generate revenue from four primary sources: (1) datacenter hosting, which we commenced on January 30, 2023, (2) cryptocurrency mining, and (3) power and capacity.
Current wording
We generate revenue from three primary sources: (1) datacenter hosting, (2) cryptocurrency mining, and (3) power and capacity.
Previous wording
We generate all the power we require for operations in the New York Facility, where we enjoy relatively lower market prices for natural gas due to our access to the Millennium Gas Pipeline price hub. We believe our competitive advantages include efficiently designed mining infrastructure and in-house operational expertise that we believe is capable of maintaining a higher operational uptime of miners. We are mining bitcoin and hosting bitcoin miners, which contributes to the security and transactability of the bitcoin ecosystem while concurrently supplying power to assist in meeting the power needs of homes and businesses in the region served by our New York Facility.
Current wording
We generate all the power we require for operations in the New York Facility, where we enjoy relatively lower market prices for natural gas due to our access to the Millennium Gas Pipeline price hub. We believe our competitive advantages include efficiently designed mining infrastructure and in-house operational expertise that we believe is capable of maintaining a higher operational uptime of miners. We are mining bitcoin and hosting bitcoin miners, which contributes to the security and transactability of the bitcoin ecosystem while concurrently supplying power to meet the increasingly growing power needs of homes and businesses in the region served by our New York Facility.
Previous wording
At December 31, 2024, Greenidge datacenter operations consisted of approximately 30,700 miners with approximately 3.3 EH/s of combined capacity for both datacenter hosting and cryptocurrency mining, of which 18,200 miners, or 1.8 EH/s, is associated with datacenter hosting and 12,500 miners, or 1.5 EH/s, is associated with Greenidge's cryptocurrency mining.
Current wording
Our datacenter operations consist of approximately 23,900 miners with approximately 2.7 EH/s of combined capacity for both datacenter hosting and cryptocurrency mining, of which 17,000 miners, or 1.7 EH/s, are associated with datacenter hosting and 6,900 miners, or 1 EH/s, are associated with our cryptocurrency mining.
Previous wording
The following table sets forth key components of our results from continuing operations during the years ended December 31, 2024 and 2023.
Current wording
The following table sets forth key components of our results from operations during the years ended December 31, 2025 and 2024.
Previous wording
For our cryptocurrency mining revenue, we generate revenue in the form of bitcoin by earning bitcoin as rewards and transaction fees for supporting the global bitcoin network with application-specific integrated circuit computers ("ASICs" or "miners") owned by us. Our cryptocurrency mining revenue decreased by $5.2 million, or 21%, to $19.1 million during the year ended December 31, 2024.
Current wording
For our cryptocurrency mining revenue, we generate revenue in the form of bitcoin by earning bitcoin as rewards and transaction fees for supporting the global bitcoin network with miners owned by us. Our cryptocurrency mining revenue decreased by $3.8 million, or 20%, to $15.2 million during the year ended December 31, 2025.
Previous wording
We estimate that the decrease was primarily driven by the 13% decrease in average hashrate for company owned miners. The decline in average hashrate is attributable to our focus on maximizing profitability by prioritizing operations of our most efficient miners and curtailing operations of less efficient miners during periods of decreased profitability. The 68% increase in the difficulty factor and the lower bitcoin rewards as a result of the halving was offset by the 129% increase in the average price of bitcoin year-over-year.
Current wording
We estimate that the decrease was primarily driven by the 47% increase in the difficulty factor and the lower bitcoin rewards as a result of the halving that occurred in April 2024, which was partially offset by the 54% increase in the average price of bitcoin year-over-year, as well as a 4% increase in average hashrate in company-owned miners compared to prior year.
Previous wording
As of December 31, 2024, our fleet of miners ranged in age from 0.2 to 3.3 years and had an average age of approximately 2.25 years. We do not have scheduled downtime for our miners. When we have unscheduled downtime, we may from time to time replace a miner with a substitute miner to minimize overall fleet downtime. As of December 31, 2024, our fleet of miners ranged in efficiency from approximately 15.0 to 34.0 joules per terahash (“J/TH”) and had an average efficiency of 27.4 J/TH.
Current wording
As of December 31, 2025, our fleet of miners ranged in age from 0.7 to 4.3 years and had an average age of approximately 2.3 years. We do not have scheduled downtime for our miners. When we have unscheduled downtime, we may from time to time replace a miner with a substitute miner to minimize overall fleet downtime. As of December 31, 2025, our fleet of miners ranged in efficiency from approximately 15.0 to 34.2 joules per terahash (“J/TH”) and had an average efficiency of 21.1 J/TH.
Previous wording
Under the NYDIG Hosting Agreement, we generate revenue from a reimbursement fee that covers the cost of power and direct costs associated with management of the mining facilities, a hosting fee and a gross profit-sharing arrangement. The arrangement covers substantially all of our current mining capacity at the New York Facility. The South Carolina Facility was dedicated to hosting from February 2023 through the date of the sale of such facility on November 15, 2023. We generated revenue of $29.8 million and $39.5 million in 2024 and 2023, respectively. This decrease of $9.6 million was mainly due to the sale of the South Carolina Facility in the fourth quarter of 2023, which accounted for a $12.4 million decrease in hosting revenue. The New York Facility hosting revenue increased by $2.4 million, primarily due to an additional month of hosting in 2024, as the contract commenced at the end of January 2023.
Current wording
Under the NYDIG Hosting Agreement, we generate revenue from a reimbursement fee that covers the cost of power and direct costs associated with management of the mining facilities, a hosting fee and a gross profit-sharing arrangement. The arrangement covers substantially all of our current mining capacity at the New York Facility. We generated revenue of $21.5 million and $29.8 million in 2025 and 2024, respectively. This decrease of $8.4 million was due to a 47% increase in average difficulty and a 25% decrease in hosting MWhs, partially offset by a 54% increase in the average price of bitcoin. We managed approximately 1.2 EH/s of average active hash rate in our hosting services, which produced approximately 221 bitcoins.
Previous wording
Our power and capacity revenue increased $4.0 million, or 59%, to $10.6 million in 2024. We estimate that higher power and capacity sales volume due to increased demand and higher average power and capacity prices caused revenue increases of approximately 23% and 36%, respectively.
Current wording
Our power and capacity revenue increased $11.4 million, or 108%, to $22.1 million in 2025. We estimate that higher power and capacity sales volume due to increased demand and higher average power and capacity prices caused revenue increases of approximately 36% and 72%, respectively.
Previous wording
Selling, general and administrative expenses decreased $8.9 million, or 34%, to $17.3 million during the year ended December 31, 2024 as compared to the prior year period. The main drivers of the decrease in selling, general and administrative expenses were:
Current wording
Selling, general and administrative expenses decreased $4.8 million, or 28%, to $12.5 million during the year ended December 31, 2025 as compared to the prior year period. The main drivers of the decrease in selling, general and administrative expenses were:
Previous wording
•Total payroll and benefits and other employee costs decreased approximately $1.2 million in 2024 compared to the prior year, as a result of declines in employee expenses including incentive compensation as result of the restructuring activities in the prior year to reduce our cost structure;
Current wording
•Total payroll and benefits and stock compensation decreased approximately $0.6 million and $1.1 million, respectively, in 2025 compared to the prior year, as a result of declines in employee expenses related to the corporate overhead cost, a decrease in incentive compensation and the forfeiture of unvested stock options;
Previous wording
•Total insurance expense decreased approximately $2.2 million in 2024 compared to the prior year, as a result of declines in coverage related to umbrella, property, and liability policies;
Current wording
•Total insurance expense decreased approximately $2 million in 2025 compared to the prior year, as a result of declines in coverage related to umbrella, property, and liability policies due to a lower asset base;
Previous wording
•Total legal costs decreased approximately $1.2 million in 2024 compared to the prior year, as a result of declines in attorney and legal counsel fees, primarily as a result of fewer significant transactions in 2024, as compared to 2023;
Current wording
•Total legal costs decreased approximately $0.3 million in 2025 compared to the prior year, as a result of declines in attorney and legal counsel fees, primarily as a result of fewer significant transactions in 2025 as compared to 2024; and
Previous wording
As a result of the impairment assessment conducted to evaluate future uses of the remaining real estate assets in South Carolina during the year ended December 31, 2023, we recognized impairment charges of $4.0 million associated with long- lived assets to reduce the net book value of our company to fair value. During the year ended December 31, 2024, we recognized impairment charges of $0.2 million related to damaged miners, which was equal to the remaining net book value of the miners. See Note 4, "Property and Equipment, Net", in the Notes to Consolidated Financial Statements for a further discussion of the impairment.
Current wording
As a result of the impairment assessments conducted during the years ended December 31, 2025 and 2024 we recognized impairment charges of nil and $0.2 million, respectively. The impairment charge recognized during the year ended December 31, 2024 was associated with long-lived assets to reduce the net book value of our company to fair value. See Note 4, “Property and Equipment, Net,” in the Notes to Consolidated Financial Statements for a further discussion of the impairment.
Previous wording
We recognize environmental liabilities in accordance with ASC 410-30, Asset Retirement and Environmental Obligations. As of December 31, 2024 we have recognized environmental liabilities for a coal-ash pond and landfill which were inherited due to the legacy coal operations at our property in Torrey, New York. These costs are considered to be both probable and estimable. We have recorded a total environmental liability of $30.7 million and $30.2 million as of December 31, 2024 and 2023, respectively, for the remediation of these sites. We recognized a charge of $0.5 million and $2.4 million during the years ended December 31, 2024 and 2023, respectively, for the remeasurement of environmental liabilities. The charges for the years ended December 31, 2024 and 2023 were as a result of an update in the cost estimates associated with the landfill post closure liabilities as part of our continuing evaluation of the site.
Current wording
We recognize environmental liabilities in accordance with ASC 410-30, Asset Retirement and Environmental Obligations. As of December 31, 2025 we have recognized environmental liabilities for a coal-ash pond and landfill which were inherited due to the legacy coal operations at our property in Torrey, New York. These costs are considered to be both probable and estimable. We have recorded a total environmental liability of $31.0 million and $30.7 million as of December 31, 2025 and 2024, respectively, for the remediation of these sites. We recognized a charge of $0.4 million and $0.5 million during the years ended December 31, 2025 and 2024, respectively, for the remeasurement of environmental liabilities. The charges for the years ended December 31, 2025 and 2024 were as a result of an update in the cost estimates associated with the landfill post closure liabilities as part of our continuing evaluation of the site.
Previous wording
As a result of the factors described above, operating loss from continuing operations was $11.4 million for the year ended December 31, 2024 as compared to $16.9 million for the year ended December 31, 2023.
Current wording
As a result of the factors described above, operating loss from operations was $3.8 million for the year ended December 31, 2025 as compared to $11.4 million for the year ended December 31, 2024.
Previous wording
Our effective tax rate for the year ended December 31, 2024 was 0.35%, which was lower than the statutory rate of 21% because we have a full valuation allowance on deferred tax assets. We recorded and will continue to carry a full valuation allowance against our gross deferred tax assets that will not reverse against deferred tax liabilities within the scheduled reversal period. Our effective tax rate for the year ended December 31, 2023 was 0.0%.
Current wording
Our effective tax rate for the year ended December 31, 2025 was (9.96)%, which was lower than the statutory rate of 21% because we have a full valuation allowance on deferred tax assets. We recorded and will continue to carry a full valuation allowance against our gross deferred tax assets that will not reverse against deferred tax liabilities within the scheduled reversal period. Our effective tax rate for the year ended December 31, 2024 was 0.35%.
Previous wording
As a result of the factors described above, net loss from continuing operations decreased to $19.8 million for the year ended December 31, 2024 as compared to $29.0 million for the year ended December 31, 2023.
Current wording
As a result of the factors described above, we recognized net income of $5.3 million for the year ended December 31, 2025 as compared to a net loss of $19.8 million for the year ended December 31, 2024.
Previous wording
The following non-GAAP measures are intended to supplement investors’ understanding of our financial information by providing measures which investors, financial analysts, and management use to help evaluate our operating performance. Items which we do not believe to be indicative of ongoing business trends are excluded from these calculations so that investors can better evaluate and analyze historical and future business trends on a consistent basis. Definitions of these non-GAAP measures may not be comparable to similar definitions used by other companies. These results should be considered in addition to, not as a substitute for, results reported in accordance with U.S. GAAP.
Current wording
The following non-GAAP measures are intended to supplement investors’ understanding of our financial information by providing measures which investors, financial analysts, and management use to help evaluate our operating performance. Items which we do not believe to be indicative of ongoing business trends are excluded from these calculations so that investors can better evaluate and analyze historical and future business trends on a consistent basis. Definitions of these non-GAAP measures may not be comparable to similar definitions used by other similarly titled measures computed by other companies, because all companies may not calculate these non-GAAP financial measures in the same fashion. These results should be considered in addition to, not as a substitute for, results reported in accordance with U.S. GAAP.
Previous wording
"EBITDA from continuing operations" is defined as loss from continuing operations before taxes, interest, and depreciation and amortization. "Adjusted EBITDA from continuing operations" is defined as EBITDA from continuing operations adjusted for stock-based compensation and other special items determined by management, including, but not limited to business expansion costs, impairments of long-lived assets, remeasurement of environmental liabilities and restructuring as they are not indicative of business operations. EBITDA from continuing operations and Adjusted EBITDA from continuing operations are intended as supplemental measure of our performance that is neither required by, nor presented in accordance with, U.S. GAAP. Management believes that the use of EBITDA from continuing operations and Adjusted EBITDA from continuing operations provides an additional tool for investors to use in evaluating ongoing operating results and trends and in comparing our financial measures with those of comparable companies, which may present similar non-GAAP financial measures to investors. However, you should be aware that when evaluating EBITDA from continuing operations and Adjusted EBITDA from continuing operations, we may incur future expenses similar to those excluded when calculating these measures. In addition, our presentation of these measures should not be construed as an inference that its future results will be unaffected by unusual or non-recurring items. Our computation of Adjusted EBITDA from continuing operations may not be comparable to other similarly titled measures computed by other companies, because not all companies may calculate Adjusted EBITDA from continuing operations in the same fashion.
Current wording
“EBITDA” is defined as earnings before taxes, interest, and depreciation and amortization. “Adjusted EBITDA” is defined as EBITDA adjusted for stock-based compensation and other special items determined by management, including, but not limited to business expansion costs, impairments of long-lived assets, remeasurement of environmental liabilities and restructuring as they are not indicative of business operations. EBITDA and Adjusted EBITDA are intended as supplemental measure of our performance that is neither required by, nor presented in accordance with, U.S. GAAP. Management believes that the use of EBITDA and Adjusted EBITDA provides an additional tool for investors to use in evaluating ongoing operating results and trends and in comparing our financial measures with those of comparable companies, which may present similar non-GAAP financial measures to investors. However, you should be aware that when evaluating EBITDA and Adjusted EBITDA, we may incur future expenses similar to those excluded when calculating these measures. In addition, our presentation of these measures should not be construed as an inference that its future results will be unaffected by unusual or non-recurring items.
Previous wording
Because of these limitations, EBITDA from continuing operations and Adjusted EBITDA from continuing operations should not be considered in isolation or as a substitute for performance measures calculated in accordance with U.S. GAAP. We compensate for these limitations by relying primarily on our U.S. GAAP results and using EBITDA from continuing operations and Adjusted EBITDA from continuing operations on a supplemental basis. You should review the reconciliations of Net loss from continuing operations to EBITDA from continuing operations and Adjusted EBITDA from continuing operations below and not rely on any single financial measure to evaluate our business. The reported amounts in the table below are from our Consolidated Statements of Operations and Comprehensive Loss in our Consolidated Financial Statements included in this Annual Report.
Current wording
Because of these limitations, EBITDA and Adjusted EBITDA should not be considered in isolation or as a substitute for performance measures calculated in accordance with U.S. GAAP. We compensate for these limitations by relying primarily on our U.S. GAAP results and using EBITDA and Adjusted EBITDA on a supplemental basis. You should review the reconciliations of Net income (loss) to EBITDA and Adjusted EBITDA below and not rely on any single financial measure to evaluate our business. The reported amounts in the table below are from our Consolidated Statements of Operations and Comprehensive Income (Loss) in our Consolidated Financial Statements included in this Annual Report.
Previous wording
On December 31, 2024, we had cash and cash equivalents of $8.6 million and digital assets of $7.0 million. To date, we have primarily relied on debt and equity financing to fund our operations, including meeting ongoing working capital needs. The Company has historically incurred operating losses and negative cash flows from operations.
Current wording
On December 31, 2025, we had cash and cash equivalents of $19.6 million and digital assets of $6.5 million. To date, we have primarily relied on debt and equity financing to fund our operations, including meeting ongoing working capital needs. We have historically incurred operating losses and negative cash flows from operations.
Previous wording
We are considering various items to address the long-term debt obligations, including the retirement or purchase of our outstanding debt through cash purchases and/or exchanges for equity or debt, in open-market purchases, privately negotiated transactions or otherwise. Such repurchases or exchanges, if any will be upon such terms and at such prices as we may determine, and will depend on prevailing market conditions, our liquidity requirements, contractual restrictions and other factors. The amounts involved may be material and to the extent equity is used, dilutive. During the year ended December 31, 2024, we entered into privately negotiated exchange agreements, pursuant to which we issued an aggregate of 692,433 shares of our Class A common stock, in exchange for $3.7 million aggregate principal amount of our 8.50% Senior Notes due October 2026.
Current wording
•The retirement or repurchase of our outstanding debt through cash purchases and/or exchanges for equity or other debt securities, which may be conducted in open market purchases, privately negotiated transactions or other transactions. Such repurchases or exchanges, if any, will be on terms and at prices determined by us, and will depend on prevailing market conditions, our liquidity requirements, contractual restrictions and other factors. The amounts involved may be material and, to the extent equity is used, may be dilutive to existing stockholders.
Previous wording
Our operating cash flows are highly dependent on bitcoin mining economics commonly measured by hashprice. Increases in the price of bitcoin benefit us by increasing the amount of revenue earned for each bitcoin earned. Increases in the difficulty to mine a bitcoin adversely affect us by decreasing the number of bitcoin earned. Increases in the costs of electricity, natural gas, and emissions credits adversely affect us by increasing operating costs. Depending on our assumptions regarding the bitcoin hashprice and energy price inputs, the estimates of the amounts of required liquidity vary significantly. There can be no assurances that these assumptions used to estimate liquidity requirements and future cash burn rates will be correct, and the ability to be predictive is uncertain due to the limited ability to predict future bitcoin and energy prices. The Company’s forecast also anticipates proceeds from the South Carolina Facility classified as held for sale and any inability to close on a sale of that facility will further adversely impact the Company’s liquidity projections. Additionally, the inability to procure and comply with the permits and licenses required to operate our facilities, including the Title V Air Permit for the New York Facility, which is subject to ongoing litigation (see Note 10, "Commitments and Contingencies"), may have an adverse impact on our ability to meet cash flow forecasts.
Current wording
Our cash flow projections indicate that we will have sufficient liquidity to meet our cash requirements through the third quarter of 2026 but will not be sufficient to satisfy the debt payments due in October 2026. Our operating cash flows are highly dependent on bitcoin mining economics commonly measured by hashprice. Increases in the price of bitcoin benefit us by increasing the amount of revenue earned for each bitcoin earned, while increases in the difficulty to mine a bitcoin adversely affect us by decreasing the number of bitcoin earned. In addition, increases in the costs of electricity, natural gas, and emissions credits adversely affect us by increasing operating costs. Depending on our assumptions regarding the bitcoin hashprice and energy price inputs, the estimates of the amounts of required liquidity vary significantly. There can be no assurance that our assumptions used to estimate liquidity requirements and future cash burn rates will be correct, and the ability to be predictive is uncertain due to the limited ability to predict future bitcoin and energy prices.
Previous wording
The debt payments included in the table above include the principal and interest amounts due. The lease payments include fixed monthly rental payments and exclude any variable payments. Environmental obligations are based on estimates subject to various assumptions including, but not limited to, closure and post-closure cost estimates, timing of expenditures, escalation factors, and requirements of granted permits. Additional adjustments to the environment liability may occur periodically due to potential changes in remediation requirements regarding coal combustion residuals which may lead to material changes in estimates and assumptions.
Current wording
The debt payments included in the table above include the principal and interest amounts due. The lease payments include fixed monthly rental payments and exclude any variable payments. Environmental obligations are based on estimates subject to various assumptions including, but not limited to, closure and post-closure cost estimates, timing of expenditures, escalation factors, and requirements of granted permits. Additional adjustments to the environment liability may occur periodically due to potential changes in remediation requirements regarding coal combustion residuals which may lead to material changes in estimates and assumptions. Self-mining capacity obligation payments are based on required minimum usage in connection to its capacity lease agreement. Natural gas transportation payments for the transportation of 15,000 dekatherms of natural gas per day by Empire Pipeline Incorporated.
Previous wording
Net cash used for operating activities from continuing operations was $12.0 million for the year ended December 31, 2024, as compared to cash used for operating activities from continuing operations of $12.2 million for the year ended December 31, 2023. The variance in operating cash flow during the year ended 2024 as compared to 2023 was driven by a decrease in prepaid expenses, increase in contract liabilities and an advantageous change in net loss, which was partially offset by the transition to bitcoin self-mining retention strategy, which enables the Company to accumulate bitcoin from its owned miners, the purchase of additional RGGI credits during 2024 and payment of accrued expenses.
Current wording
Net cash used for operating activities was $15.0 million for the year ended December 31, 2025, as compared to cash used for operating activities of $12.0 million for the year ended December 31, 2024. The variance in operating cash flow during the year ended 2025 as compared to 2024 was driven by a decrease in proceeds from the sale of digital assets due to our bitcoin retention strategy, a decrease in accounts payable, a decrease in contract liabilities and an increase in other operating assets due to the funding of a trust for environmental remediation costs, which was partially offset by an increase in accrued emissions expense and related party payables, a decrease in emissions and carbon offsets due to the surrender of credits for the current control period, and a decrease in revenues from digital assets production.
Previous wording
Net cash used for investing activities from continuing operations was $3.9 million for the year ended December 31, 2024, as compared to $6.0 million for the year ended December 31, 2023. The decrease is primarily related to $2.6 million of lower purchases of and deposits for property and equipment compared to the prior year due to the lower miner purchases and lower proceeds from the sale of assets of $3.9 million. This was partially offset by proceeds of $3.5 million from the sale of digital assets.
Current wording
Net cash provided by investing activities was $36.6 million for the year ended December 31, 2025, as compared to $3.9 million used for investing activities for the year ended December 31, 2024. The increase is primarily related to $8.0 million of lower purchases of and deposits for property and equipment compared to the prior year due to the lower miner purchases, an increase of proceeds from the sale of assets of $19.9 million and an increase of proceeds from the sale of digital assets of $12.2 million.
Previous wording
Our significant accounting policies are discussed in detail in Note 2, "Significant Accounting Policies", in the Notes to Consolidated Financial Statements for the year ended December 31, 2024; however, we consider our critical accounting policies to be those related to the valuation of long-lived assets and remeasurement of environmental obligations.
Current wording
Our significant accounting policies are discussed in detail in Note 2, “Significant Accounting Policies,” in the Notes to Consolidated Financial Statements for the year ended December 31, 2025; however, we consider our critical accounting policies and estimates to be those related to the valuation of long-lived assets and remeasurement of environmental obligations.
Previous wording
During 2024, we determined that a triggering event had occurred as of September 30, 2024 due to declines in hashprice, driven by lower bitcoin rewards for miners post-halving, increases in the difficulty factor due to increase in the overall hashrate as more efficient miners entered the market, and a lack of a corresponding increase in bitcoin price. For the purposes of performing the recoverability test we consider all of our long-lived assets to be a single asset group as we operate as an integrated power and crypto datacenter operations business and this grouping represents the lowest level of identifiable independent cash flows. We concluded that projected undiscounted cash flows were in excess of the carrying value of the asset group, and, therefore, the assets are considered to be recoverable and no determination of impairment was necessary.
Current wording
In accordance with ASC 360-10, we review our long-lived assets for impairment whenever events or changes in circumstances indicate that the carrying amount of the assets may not be fully recoverable. To determine recoverability of a long-lived asset, management evaluates whether the estimated future undiscounted net cash flows, based on prevailing market conditions, from the asset are less than its carrying amount. If impairment is indicated, the long-lived asset is written down to fair value. We determined that a triggering event had occurred as of December 31, 2025 due to declines in hashprice, driven by lower bitcoin rewards for miners post-halving, increases in the difficulty factor due to increase in the overall hashrate as more efficient miners entered the market, combined with a decline in bitcoin price in the fourth quarter of 2025. For the purposes of performing the recoverability test, we consider the New York Facility and North Dakota Facility to be separate asset groups representing the lowest level of identifiable independent cash flows. We concluded that projected undiscounted cash flows for the New York Facility were in excess of the carrying value of the asset group, and therefore, the assets are considered to be recoverable and no determination of impairment was necessary. For the North Dakota Facility, we determined that the projected undiscounted cash flows were below the carrying value of the asset group and performed the second step of the impairment test. We determined that no impairment was to be recorded as the fair value of the assets were in excess of the carrying value.
Previous wording
We recognize environmental liabilities in accordance with ASC 410-30, Asset Retirement and Environmental Obligations. As of December 31, 2024, we have recognized environmental liabilities for a coal-ash pond and landfill, which were inherited due to the legacy coal operations at our property in Torrey, New York. These costs are considered to be both probable and estimable. We have recorded a total environmental liability of $30.7 million and $30.2 million as of December 31, 2024 and 2023, respectively, for the remediation of these sites. We recognized a charge of $0.5 million and $2.4 million during the years ended December 31, 2024 and 2023, respectively, for the remeasurement of environmental liabilities. The charges were as a result of updates in the cost estimates associated with the landfill post-closure liabilities as part of our continuing evaluation of the site.
Current wording
We recognize environmental liabilities in accordance with ASC 410-30, Asset Retirement and Environmental Obligations. As of December 31, 2025, we have recognized environmental liabilities for a coal-ash pond and landfill, which were inherited due to the legacy coal operations at our property in Torrey, New York. These costs are considered to be both probable and estimable. We have recorded a total environmental liability of $31.0 million and $30.7 million as of December 31, 2025 and 2024, respectively, for the remediation of these sites. We recognized a charge of $0.4 million and $0.5 million during the years ended December 31, 2025 and 2024, respectively, for the remeasurement of environmental liabilities. The charges were as a result of updates in the cost estimates associated with the landfill post-closure liabilities as part of our continuing evaluation of the site.
Previous wording
We will remain an “emerging growth company” for up to five years from our first sale of common stock pursuant to an effective Securities Act registration statement in 2021, or until the earliest of (i) the last day of the first fiscal year in which our total annual gross revenues exceed $1.235 billion, (ii) the date that we become a “large accelerated filer” as defined in Rule 12b-2 under the Exchange Act, which would occur if the market value of our Class A common stock held by non-affiliates exceeds $700 million as of the last business day of our most recently completed second fiscal quarter, or (iii) the date on which we have issued more than $1 billion in non-convertible debt during the preceding three year period.
Current wording
We will remain an “emerging growth company” for up to five years from our first sale of common stock pursuant to an effective Securities Act registration statement in 2021 (or September 15, 2026), or until the earliest of (i) the last day of the first fiscal year in which our total annual gross revenues exceed $1.235 billion, (ii) the date that we become a “large accelerated filer” as defined in Rule 12b-2 under the Exchange Act, which would occur if the market value of our Class A common stock held by non-affiliates exceeds $700 million as of the last business day of our most recently completed second fiscal quarter, or (iii) the date on which we have issued more than $1 billion in non-convertible debt during the preceding three year period.
Rearranged current paragraphs (2)
Current report — wording carried from elsewhere
During the year ended December 31, 2025, Greenidge increased power and capacity MWhs due to favorable power and capacity economics, while reducing MWhs dedicated to hosting services. At December 31, 2025, Greenidge datacenter operations consisted of approximately 23,900 miners with approximately 2.7 EH/s of combined capacity for both datacenter hosting and cryptocurrency mining, of which 17,000 miners, or 1.7 EH/s, is associated with datacenter hosting and 6,900 miners, or 1.0 EH/s, is associated with Greenidge’s cryptocurrency mining.
Current report — wording carried from elsewhere
•During 2025 and 2024, we entered into privately negotiated exchange agreements, pursuant to which we issued an aggregate of 1,934,889 shares of our Class A common stock and paid an aggregate of $2.9 million in cash in exchange for $14.5 million in aggregate principal amount of the Senior Notes.
Rearranged previous paragraphs (2)
Previous report — wording carried elsewhere
Our datacenter operations consist of approximately 30,700 miners with approximately 3.3 EH/s of combined capacity for both datacenter hosting and cryptocurrency mining, of which 18,200 miners or 1.8 EH/s, are associated with datacenter hosting and 12,500 miners, or 1.5 EH/s are associated with our cryptocurrency mining. In 2023, prior to the South Carolina transaction, our datacenter operations consisted of approximately 42,300 miners with approximately 4.6 EH/s of combined capacity for both datacenter hosting and cryptocurrency mining, of which 32,100 miners, or 3.4 EH/s, were associated with datacenter hosting and 10,200 miners, or 1.2 EH/s, were associated with Greenidge’s cryptocurrency mining.
Previous report — wording carried elsewhere
In accordance with ASC 360-10, we review our long-lived assets for impairment whenever events or changes in circumstances indicate that the carrying amount of the assets may not be fully recoverable. To determine recoverability of a long-lived asset, management evaluates whether the estimated future undiscounted net cash flows, based on prevailing market conditions, from the asset are less than its carrying amount. If impairment is indicated, the long-lived asset is written down to fair value.