Skip to main content

New Fortress Energy Inc

For the period ended Dec 31, 2024. Filed Mar 10, 2025.

View on SEC.gov

About this filing

A company's yearly report to the SEC, with audited financial statements. It is the fullest account a company gives of its business, its finances and the risks it sees.

FY2024 · Filed Mar 10, 2025

NFE$4.49+16.6%Stored close · as of Nov 6, 2026

What changed in Risk Factors?

Read the current filing

Previous report: 10-K

Period ended 2023-12-31; filed 2024-02-29.

0001749723-24-000011

Item 1A. Risk Factors

Current report: 10-K

Period ended 2024-12-31; filed 2025-03-10.

0001749723-25-000029

Item 1A. Risk Factors

The baseline is this issuer’s latest earlier reporting period of the same form that was filed before the current report. A previous 10-Q is a different quarter, not a year-over-year comparison. Amendments are excluded.

Compared 321 previous paragraphs and 317 current paragraphs.

236 unchanged; 60 reworded; 20 added; 7 removed; 18 previous and 1 current paragraphs rearranged.

Tables are not compared: 0 previous and 0 current tables excluded. Dates, whitespace, punctuation and numbering changes are ignored; changes to financial figures remain significant.

A changed paragraph is not evidence that risk increased or decreased. An unchanged paragraph does not establish that risk stayed the same.

Added paragraphs (20)

Current report

• Our data center infrastructure business has no operating history, and it may not be profitable;

Current report

Our ability to continue as a going concern is dependent upon our ability to complete certain transactions and delay capital expenditures

Current report

As discussed in note 2 to the financial statements, under ASC 205-40, when first assessing whether substantial doubt is raised about the entity’s ability to continue as a going concern, management cannot consider the potential mitigating effects of its plans that have not been fully implemented at the assessment date. Management has concluded that the Company’s current liquidity and forecasted cash flows (which exclude the effect of the Transactions as defined below), from operations are not sufficient to support, in full, obligations as they become due. Management has approved a plan to support its liquidity position by: (i) delaying certain discretionary payments, including planned capital expenditures and dividends, that are within management’s control, and (ii) continuously renewing the LNG cargo financing facility over the succeeding twelve months. Management’s plan also includes the availability of a backstop agreement that was executed in March 2025 and provides up to $100 million of availability. Management concluded that such plans are probable of being implemented and the Company will have sufficient liquidity to meet its obligations as they become due over the next twelve months from the date that the consolidated financial statements were issued. In addition to management’s plan outlined above, the Company continues to explore asset sales, settlement of claims and other strategic transactions (collectively, the “Transactions”) that seek to optimize the value of the Company’s portfolio while providing additional liquidity and cash flow to the Company. However, there are inherent uncertainties, as the execution of the Transactions are outside of management’s control and therefore there are no assurances that these transactions will be executed. Furthermore, there are inherent risks with the Company’s ability to continue to implement plans in future periods that will support its liquidity position, such as its ability to further extend the terms of vendor payments and other obligations.

Current report

In addition, these rules and regulations are assessed, managed, administered and enforced by various governmental agencies and bodies, whose actions and decisions could adversely affect our business or operations. In the United States and Puerto Rico, approvals of the DOE under Section 3 of the NGA, as well as several other material governmental and regulatory permits, approvals and authorizations, including under the CAA and the CWA and their state analogues, may be required in order to construct and operate an LNG facility and export LNG. Permits, approvals and authorizations obtained from the DOE and other federal and state regulatory agencies also contain ongoing conditions, and additional requirements may be imposed. On July 1, 2024, the Western District of Louisiana stayed the pause in its entirety, The Biden Administration appealed the ruling in August 2024 and litigation remains ongoing. On December 17, 2024, the DOE publicly released a multi-volume study of its view of the potential effects of U.S. LNG exports on the domestic economy; U.S. households and consumers; communities that live near locations where natural gas is produced or exported; domestic and international energy security, including effects of U.S. trading partners; and the environment and climate. The DOE stated that it intends to use this study to inform its public interest review of and future decisions regarding exports to non-FTA nations. The study is subject to a sixty-day public comment period and the finalization of the study and any application of it in future decision-making will be determined by the new presidential administration. Although President Trump oppose the DOE pause on export authorizations and advocated prompt of new authorizations during his presidential campaign, we expect that most DOE long-term, non-FTA authorizations will continue to experience delays. While the Trump Administration is widely expected to support LNG exports, there can be no assurance as to its views of the recently released DOE study or its future policies, or the impact of those policies on our existing and future projects.

Current report

Our data center infrastructure business has no operating history, and we may not recognize revenue or operating income in the future.

Current report

On July 2, 2024, we announced the launch of Klondike Digital Infrastructure, a power and data center infrastructure business. We are subject to a multitude of risks inherent in a recently established business venture in a rapidly developing and changing industry. We have no operating history in the data center infrastructure business and may not be able to achieve our business objectives. We cannot assure you that our past experience will be sufficient to allow us to successfully achieve our business objectives, and our past performance should not be used as an indicator of our likely performance. Our lack of operating history in the data center infrastructure business, particularly in the development and operation of data center infrastructure, also makes it difficult to evaluate the prospects of this business. We have not yet been able to confirm that our business model can or will be successful, and we may not ever recognize revenue or operating income from this business. Our expectations regarding the data center business may not prove to be accurate. Our operating results will likely fluctuate moving forward as we develop this business. In addition, we expect additional growth in this business, which could place significant demands on our management team and other resources and require us to continue developing and improving our operational, financial and other internal controls. We may not be able to address these challenges in a cost-effective manner or at all. If we do not effectively manage our growth, we may not be able to execute on our business plan, respond to competitive pressures or take advantage of market opportunities, and our business, financial condition and results of operations could be materially harmed.

Current report

We do not currently generate cash from operations from this new business line, so we will need additional funding from other sources to develop this business. There can be no assurance that we will be able to obtain financing on favorable terms or at all, or that we will have sufficient capital to fully implement our business plan, which could have a material adverse effect on this business, results of operations, financial condition and prospects. You should consider our data center business and prospects in light of these risks and the risks and difficulties that we will encounter as we continue to develop our business model. We may not be able to address these risks and difficulties successfully, which would materially harm our business and operating results.

Current report

Our data center business strategy depends on the successful development of our projects and any delays or unexpected costs associated with such projects may harm our growth prospects, future operating results and financial condition.

Current report

We intend to develop a geographically diverse portfolio of power and data center infrastructure and we have more than 1,000 acres of developable land across sites in Brazil, Ireland, and the United States that we are analyzing for potential use in the business. Our business strategy depends upon the successful acquisition, permitting, gas supply, transmission work and completion of the development of these sites and similar projects in the future. Current and future development projects and expansion into new markets will involve substantial planning, allocation of significant company resources and certain risks, including risks related to the acquisition of real property, financing, zoning, permits and other regulatory approvals, construction costs and delays.

Current report

These development projects will also require us to carefully select and rely on the experience of one or more general contractors and associated subcontractors during the construction process. Should a general contractor or significant subcontractor experience financial or other problems during the construction process, we could experience significant delays, increased costs to complete the project and other negative impacts to our expected financial returns. Site selection in current and expansion markets is also a critical factor in our expansion plans, and there may not be suitable properties available in our markets at a location that is attractive to our customers and has the necessary combination of other characteristics. Furthermore, while we may prefer to locate new data centers adjacent to or in close proximity to our existing data centers, we may be limited by the size and location of suitable properties. If we are unable to successfully develop and operate data center properties, our business, financial condition and results of operations will be significantly impaired.

Current report

Our data center business model depends upon the demand for data centers.

Current report

We intend to be in the business of developing infrastructure to serve data centers. A reduction in the demand for data center power or connectivity would have an adverse effect on our ability to develop our data center infrastructure business. We are susceptible to general economic slowdowns as well as adverse developments in the data center, internet and data communications and broader technology industries. Any such slowdown or adverse development could lead to reduced corporate information technology (“IT”) spending or reduced demand for data center space. Reduced demand could also result from business relocations, including to markets that we do not currently serve. Changes in industry practice or in technology could also reduce demand for the physical data center space we will provide. Our results of operations and financial condition could be materially adversely affected as a result of any or all of these factors.

Current report

We have incurred, and may in the future incur, a significant amount of debt. The agreements governing our significant indebtedness place restrictions on us and our subsidiaries, reducing operational and financing flexibility and creating default risks.

Current report

Our ability to service our existing and any future debt will depend on our performance and operations, which is subject to factors that are beyond our control and compliance with covenants in the agreements governing such debt. We may be unable to maintain a level of cash flows from operating activities sufficient to permit us to fund our day-to-day operations or to pay the principal, premium, if any, and interest on our indebtedness. If our cash flows and capital resources are insufficient to fund our debt service obligations and other cash requirements, we could face substantial liquidity problems and could be forced to reduce or delay investments and capital expenditures or to sell assets or operations, seek additional capital or restructure or refinance our operations or indebtedness. If we cannot make scheduled payments on our debt, we will be in default and, as a result, lenders under and holder of any of our existing and future indebtedness could declare all outstanding principal and interest to be due and payable, the lenders under our debt instruments could terminate their commitments to loan money, our secured lenders could foreclose against the assets securing such borrowings and we could be forced into bankruptcy or liquidation. We may also incur additional debt to fund our business and strategic initiatives. If we incur additional debt and other obligations, the risks associated with our substantial leverage and the ability to service such debt would increase, which could have a material adverse effect on our business, results of operation and financial condition.

Current report

Despite our substantial level of indebtedness, we and our subsidiaries will be permitted to incur additional indebtedness in the future. This could further exacerbate the risks associated with our substantial indebtedness.

Current report

In addition, as our existing indebtedness matures, we may need to refinance that indebtedness with new indebtedness that may have a higher interest rate, which will increase our fixed costs. Although the instruments governing our indebtedness contain restrictions on the incurrence of additional indebtedness, these restrictions are subject to a number of qualifications and exceptions and the indebtedness incurred in compliance with these restrictions could be substantial. If we incur additional debt and other obligations, the risks associated with our substantial leverage and the ability to service such debt would increase, which could have a material adverse effect on our business, results of operation and financial condition. For example, the New 2029 Notes issued pursuant to the New 2029 Indenture, issued in part to refinance our 2025 Notes, 2026 Notes and 2029 Notes in part to provide additional liquidity to the business, bear interest at a rate of 12.000% per annum, representing a signficiant increasing our annual interest expense, while also increasing our total aggregate principal amount of indebtedness outstanding. For additional detail, see “Management’s Discussion and Analysis of Financial Condition and Results of Operations—Recent Developments”- and "Liquidity and Capital Resources-Long Term Debt and Preferred Stock."

Current report

Our charterers may inadvertently violate applicable sanctions and/or call on ports located in, or engage in transactions with, countries that are subject to restrictions imposed by the U.S. or other governments, which could adversely affect their business.

Current report

In the past, securities class action litigation has often been brought against companies following periods of volatility in the market price of their securities. We are currently subject to a putative securities class action complaint relating to a drop in our share price and could become involved in additional litigation of this type in the future if our share price is volatile for any reason. This type of litigation could result in reputational damage, substantial costs and a diversion of management's attention and resources needed to successfully run our business.

Current report

Future sales and issuances of our Class A common stock, securities convertible or exchangeable into our Class A common stock or rights to purchase our Class A common stock could result in additional dilution of the percentage ownership of our shareholders and may cause our share price to fall.

Current report

To raise capital, we may sell substantial amounts of Class A common stock or securities convertible into our exchangeable for Class A common stock. These future issuances of Class A common stock or Class A common stock-related securities to purchase Class A common stock, together with the exercise of outstanding restricted stock units and any additional shares issued in connection with other transactions, if any, may result in material dilution to our investors. Such sales may also result in material dilution to our existing shareholders, and new investors could gain rights, preferences and privileges senior to those of holders of our Class A common stock. In particular, on October 1, 2024, we exchanged 96,746 shares of our Series A Convertible Preferred Stock for 96,746 shares of our Series B Convertible Preferred Stock. Such shares are convertible at the option of the holders thereof into shares of Class A common stock on the terms set forth in the certificate of designations governing the Series B Convertible Preferred Stock. Additionally, on December 6, 2024, we issued 15,700,998 shares of our Class A common stock in satisfaction of our commitment fee obligations under the Exchange and Subscription Agreement in connection with the issuance of the New 2029 Notes.
Removed paragraphs (7)

Previous report

•Our charterers may inadvertently violate applicable sanctions and/or call on ports located in, or engage in transactions with, countries that are subject to restrictions imposed by the U.S. or other governments, which could adversely affect its business;

Previous report

•We are a “controlled company” within the meaning of Nasdaq rules and, as a result, qualify for and intend to rely on exemptions from certain corporate governance requirements;

Previous report

Our charterers may inadvertently violate applicable sanctions and/or call on ports located in, or engage in transactions with, countries that are subject to restrictions imposed by the U.S. or other governments, which could adversely affect its business.

Previous report

We are a “controlled company” within the meaning of Nasdaq rules and, as a result, qualify for and intend to rely on exemptions from certain corporate governance requirements.

Previous report

Affiliates of certain entities controlled by Wesley R. Edens, Randal A. Nardone and affiliates of Fortress Investment Group LLC (“Founder Entities”), together with affiliates of Energy Transition Holdings LLC, hold a majority of the voting power of our stock. In addition, pursuant to the Shareholders’ Agreement, dated as of February 4, 2019, by and among the Company and the respective parties thereto (the “Shareholders’ Agreement”), the Founder Entities currently have the right to nominate a majority of the members of our Board of Directors. Furthermore, the Shareholders’ Agreement provides that the parties thereto will use their respective reasonable efforts (including voting or causing to be voted all of the Company’s voting shares beneficially owned by each) to cause to be elected to the Board, and to cause to continue to be in office the director nominees selected by the Founder Entities. Affiliates of Energy Transition Holdings LLC are parties to the Shareholders’ Agreement and as of December 31, 2023 hold approximately 12.5% of the voting power of our stock. As a result, we are a controlled company within the meaning of the Nasdaq corporate governance standards. Under Nasdaq rules, a company of which more than 50% of the voting power for the election of directors is held by an individual, a group or another company is a controlled company and may elect not to comply with certain Nasdaq corporate governance requirements, including the requirements that:

Previous report

•a majority of the board of directors consist of independent directors as defined under the rules of Nasdaq;

Previous report

These requirements will not apply to us as long as we remain a controlled company. A controlled company does not need its board of directors to have a majority of independent directors or to form independent compensation and nominating and governance committees. We intend to utilize some or all of these exemptions. Accordingly, our corporate governance may not afford the same protections as companies that are subject to all of the corporate governance requirements of Nasdaq.
Reworded paragraphs (60)

Previous wording

•LNG that is processed and/or stored on FSRUs and transported via pipeline is subject to risk of loss or damage;

Current wording

•LNG that is processed, transported and/or stored on FSRUs and transported via pipeline is subject to risk of loss or damage;

Previous wording

Our success depends on key members of our management, the loss of any of whom could disrupt our business operations.

Current wording

•Our success depends on key members of our management;

Previous wording

A small number of our original investors have the ability to direct the voting of a majority of our stock, and their interests may conflict with those of our other stockholders.

Current wording

•A small number of our original investors have the ability to direct a significant amount of our common stock, and their interests may conflict with those of our other stockholders;

Previous wording

•The declaration and payment of dividends to holders of our Class A common stock is at the discretion of our board of directors and there can be no assurance that we will continue to pay dividends in amounts or on a basis consistent with prior distributions to our investors, if at all;

Current wording

•The declaration and payment of dividends to holders of our Class A common stock is at the discretion of our board of directors and we do not expect to pay dividends for the foreseeable future;

Previous wording

A change in tax laws in any country in which we operate could adversely affect us.

Current wording

•A change in tax laws in any country in which we operate could adversely affect us; and

Previous wording

•construction accidents that could result in personal injury or loss of life;

Current wording

•construction, commissioning or operating accidents that could result in personal injury or loss of life;

Previous wording

The occurrence of any one of these factors, whatever the cause, could result in unforeseen delays or cost overruns to our projects. Delays in the development beyond our estimated timelines, or amendments or change orders to our construction contracts, could result in increases to our development costs beyond our original estimates, which could require us to obtain additional financing or funding and could make the project less profitable than originally estimated or possibly not profitable at all. Further, any such delays could cause a delay in our anticipated receipt of revenues, a loss of one or more customers, and our inability to meet milestones or conditions precedents in our customer contracts, which could lead to delay penalties and potentially a termination of agreements with our customers. We have experienced time delays and cost overruns in the construction and development of our projects as a result of the occurrence of various of the above factors, and no assurance can be given that we will not continue to experience in the future similar events, any of which could have a material adverse effect on our business, operating results, cash flows and liquidity.

Current wording

The occurrence of any one of these factors, whatever the cause, could result in unforeseen delays or cost overruns to our projects. Delays in the development beyond our estimated timelines, or amendments or change orders to our construction contracts, could result in increases to our development costs beyond our original estimates, which could require us to obtain additional financing or funding and could make the project less profitable than originally estimated or possibly not profitable at all. Further, any such delays could cause a delay in our anticipated receipt of revenues, a loss of one or more customers, and our inability to meet milestones or conditions precedents in our customer contracts, which could lead to delay penalties and potentially a termination of agreements with our customers. We have experienced time delays and cost overruns in the construction and development of our projects as a result of the occurrence of various of the above factors, including most recently with our First LNG project in Altamira, Mexico, and no assurance can be given that we will not continue to experience in the future similar events, any of which could have a material adverse effect on our business, operating results, cash flows and liquidity.

Previous wording

In particular, we are subject to risks related to the operation of power plants, liquefaction facilities, marine and other LNG operations with respect to our facilities, FSRU and LNG carriers, which operations are complex and technically challenging and subject to mechanical risks and problems. In particular, marine LNG operations are subject to a variety of risks, including, among others, marine disasters, piracy, bad weather, mechanical failures, environmental accidents, epidemics, grounding, fire, explosions and collisions, human error, and war and terrorism. An accident involving our cargos or any of our chartered vessels could result in death or injury to persons, loss of property or environmental damage; delays in the delivery of cargo; loss of revenues; termination of charter contracts; governmental fines, penalties or restrictions on conducting business; higher insurance rates; and damage to our reputation and customer relationships generally. Any of these circumstances or events could increase our costs or lower our revenues. If our chartered vessels suffer damage as a result of such an incident, they may need to be repaired. Repairs and maintenance costs for existing vessels are difficult to predict and may be substantially higher than for vessels we have operated since they were built and result in higher than anticipated operating expenses or require additional capital expenditures. The loss of earnings while these vessels are being repaired would decrease our results of operations. If a vessel we charter were involved in an accident with the potential risk of environmental impacts or contamination, the resulting media coverage could have a material adverse effect on our reputation, our business, our results of operations and cash flows and weaken our financial condition. Our offshore operating expenses depend on a variety of factors including crew costs, provisions, deck and engine stores and spares, lubricating oil, insurance, maintenance and repairs and shipyard costs, many of which are beyond our control, such as the overall economic impacts caused by the global COVID-19 outbreak. Other factors, such as increased cost of qualified and experienced seafaring crew and changes in regulatory requirements, could also increase operating expenditures. Future increases to operational costs are likely to occur. If costs rise, they could materially and adversely affect our results of operations. In addition, operational problems may lead to loss of revenue or higher than anticipated operating expenses or require additional capital expenditures. Any of these results could harm our business, financial condition and results of operations.

Current wording

In particular, we are subject to risks related to the operation of power plants, liquefaction facilities, marine and other LNG operations with respect to our facilities, FSRU and LNG carriers, which operations are complex and technically challenging and subject to mechanical risks and problems. In particular, marine LNG operations are subject to a variety of risks, including, among others, marine disasters, piracy, bad weather, mechanical failures, environmental accidents, epidemics, grounding, fire, explosions and collisions, human error, and war and terrorism. An accident involving our cargos or any of our chartered vessels could result in death or injury to persons, loss of property or environmental damage; delays in the delivery of cargo; loss of revenues; termination of charter contracts; governmental fines, penalties or restrictions on conducting business; higher insurance rates; and damage to our reputation and customer relationships generally. Any of these circumstances or events could increase our costs or lower our revenues. If our chartered vessels suffer damage as a result of such an incident, they may need to be repaired. Repairs and maintenance costs for existing vessels are difficult to predict and may be substantially higher than for vessels we have operated since they were built and result in higher than anticipated operating expenses or require additional capital expenditures. The loss of earnings while these vessels are being repaired would decrease our results of operations. If a vessel we charter were involved in an accident with the potential risk of environmental impacts or contamination, the resulting media coverage could have a material adverse effect on our reputation, our business, our results of operations and cash flows and weaken our financial condition. Our offshore operating expenses depend on a variety of factors including crew costs, provisions, deck and engine stores and spares, lubricating oil, insurance, maintenance and repairs and shipyard costs, many of which are beyond our control. Other factors, such as increased cost of qualified and experienced seafaring crew and changes in regulatory requirements, could also increase operating expenditures. Future increases to operational costs are likely to occur. If costs rise, they could materially and adversely affect our results of operations. In addition, operational problems may lead to loss of revenue or higher than anticipated operating expenses or require additional capital expenditures. Any of these results could harm our business, financial condition and results of operations.

Previous wording

Our operations are, and will be, dependent upon LNG being a competitive source of energy in the markets in which we operate. In the United States, due mainly to a historic abundant supply of natural gas and discoveries of substantial quantities of unconventional or shale natural gas, imported LNG has not developed into a significant energy source. The success of the domestic liquefaction component of our business plan is dependent, in part, on the extent to which natural gas can, for significant periods and in significant volumes, be produced in the United States at a lower cost than the cost to produce some domestic supplies of other alternative energy sources, and that it can be transported at reasonable rates through appropriately scaled infrastructure. LNG prices have increased materially in the past, including in August 2021 through the end of 2022, and global events, such as the COVID-19 pandemic, Russia’s invasion of Ukraine and global inflationary pressures, have generated further energy pricing volatility, which have had and may in the future have an adverse effect on market pricing of LNG and global demand for our products, as well as our ability to remain competitive in the markets in which we operate. Potential expansion in the Caribbean, Latin America and other parts of the world where we may operate is primarily dependent upon LNG being a competitive source of energy in those geographical locations. For example, in the Caribbean, due mainly to a lack of regasification infrastructure and an underdeveloped international market for natural gas, natural gas has not yet developed into a significant energy source. In Brazil, hydroelectric power generation is the predominant source of electricity and LNG is one of several other energy sources used to supplement hydroelectric generation. The success of our operations is dependent, in part, on the extent to which LNG can, for significant periods and in significant volumes, be produced internationally and delivered to our customers at a lower cost than the cost to deliver other alternative energy sources.

Current wording

Our operations are, and will be, dependent upon LNG being a competitive source of energy in the markets in which we operate. In the United States, due mainly to a historic abundant supply of natural gas and discoveries of substantial quantities of unconventional or shale natural gas, imported LNG has not developed into a significant energy source. The success of the domestic liquefaction component of our business plan is dependent, in part, on the extent to which natural gas can, for significant periods and in significant volumes, be produced in the United States at a lower cost than the cost to produce some domestic supplies of other alternative energy sources, and that it can be transported at reasonable rates through appropriately scaled infrastructure. LNG prices have increased materially in the past, including in August 2021 through the end of 2022, and global events, such as Russia’s invasion of Ukraine and global inflationary pressures, have generated further energy pricing volatility, which have had and may in the future have an adverse effect on market pricing of LNG and global demand for our products, as well as our ability to remain competitive in the markets in which we operate. Potential expansion in the Caribbean, Latin America and other parts of the world where we may operate is primarily dependent upon LNG being a competitive source of energy in those geographical locations. For example, in the Caribbean, due mainly to a lack of regasification infrastructure and an underdeveloped international market for natural gas, natural gas has not yet developed into a significant energy source. In Brazil, hydroelectric power generation is the predominant source of electricity and LNG is one of several other energy sources used to supplement hydroelectric generation. The success of our operations is dependent, in part, on the extent to which LNG can, for significant periods and in significant volumes, be produced internationally and delivered to our customers at a lower cost than the cost to deliver other alternative energy sources.

Previous wording

In addition, these rules and regulations are assessed, managed, administered and enforced by various governmental agencies and bodies, whose actions and decisions could adversely affect our business or operations. In the United States and Puerto Rico, approvals of the Department of Energy (“DOE”) under Section 3 of the NGA, as well as several other material governmental and regulatory permits, approvals and authorizations, including under the CAA and the CWA and their state analogues, may be required in order to construct and operate an LNG facility and export LNG. Permits, approvals and authorizations obtained from the DOE and other federal and state regulatory agencies also contain ongoing conditions, and additional requirements may be imposed. For example, in February 2024, the Biden Administration announced a temporary pause on pending approvals of LNG exports to non-FTA countries. While the duration of the pause remains unclear, any restrictions on or delays in approving natural gas exports could negatively impact our business in the future. Certain federal permitting processes may trigger the requirements of the National Environmental Policy Act (“NEPA”), which requires federal agencies to evaluate major agency actions that have the potential to significantly impact the environment. Compliance with NEPA may extend the time and/or increase the costs for obtaining necessary governmental approvals associated with our operations and create independent risk of legal challenges to the adequacy of the NEPA analysis, which could result in delays that may adversely affect our business, contracts, financial condition, operating results, cash flow, liquidity and profitability. On July 15, 2020, the White House Council on Environmental Quality issued a final rule revising its NEPA regulations. The Council on Environmental Quality has announced that it is engaged in an ongoing and comprehensive review of the revised regulations and is assessing whether and how the Council may ultimately undertake a new rulemaking to revise the regulations. The impacts of any such future revisions that may be adopted are uncertain and indeterminable for the foreseeable future. On June 18, 2020, we received an order from FERC, which asked us to explain why our San Juan Facility is not subject to FERC’s jurisdiction under section 3 of the NGA. On March 19, 2021, as upheld on rehearing on July 15, 2021, FERC determined that our San Juan Facility is subject to its jurisdiction and directed us to file an application for authorization to operate the San Juan Facility but also found that allowing operation of the San Juan Facility to continue during the pendency of an application is in the public interest. In order to comply with the FERC’s directive, on September 15, 2021, we filed an application for authorization to operate the San Juan Facility, which remains pending.

Current wording

Certain federal permitting processes may trigger the requirements of the National Environmental Policy Act (“NEPA”), which requires federal agencies to evaluate major agency actions that have the potential to significantly impact the environment. Compliance with NEPA may extend the time and/or increase the costs for obtaining necessary governmental approvals associated with our operations and create independent risk of legal challenges to the adequacy of the NEPA analysis, which could result in delays that may adversely affect our business, contracts, financial condition, operating results, cash flow, liquidity and profitability. On July 15, 2020, the White House Council on Environmental Quality issued a final rule revising its NEPA regulations. The Council on Environmental Quality has announced that it is engaged in an ongoing and comprehensive review of the revised regulations and is assessing whether and how the Council may ultimately undertake a new rulemaking to revise the regulations. The impacts of any such future revisions that may be adopted are uncertain and indeterminable for the foreseeable future. On June 18, 2020, we received an order from FERC, which asked us to explain why our San Juan Facility is not subject to FERC’s jurisdiction under section 3 of the NGA. On March 19, 2021, as upheld on rehearing on July 15, 2021, FERC determined that our San Juan Facility is subject to its jurisdiction and directed us to file an application for authorization to operate the San Juan Facility but also found that allowing operation of the San Juan Facility to continue during the pendency of an application is in the public interest. In order to comply with the FERC’s directive, on September 15, 2021, we filed an application for authorization to operate the San Juan Facility, which remains pending.

Previous wording

The design, construction and operation of our infrastructure, facilities and businesses, including our FSRUs, FLNG units and LNG carriers, the import and export of LNG, exploration and development activities, and the transportation of natural gas, among others, are highly regulated activities at the national, state and local levels and are subject to various approvals and permits. The process to obtain the permits, approvals and authorizations we need to conduct our business, and the interpretations of those rules, is complex, time-consuming, challenging and varies in each jurisdiction in which we operate. We may be unable to obtain such approvals on terms that are satisfactory for our operations and on a timeline that meets our commercial obligations. Many of these permits, approvals and authorizations require public notice and comment before they can be issued, which can lead to delays to respond to such comments, and even potentially to revise the permit application. Jurisdiction-specific employment, labor, and subcontracting laws may also affect contracting strategies and impact construction and operations. We may also be (and have been in select circumstances) subject to local opposition, including citizens groups or non-governmental organizations such as environmental groups, which may create delays and challenges in our permitting process and may attract negative publicity, which may create an adverse impact on our reputation. In addition, such rules change frequently and are often subject to discretionary interpretations, including administrative and judicial challenges by regulators, all of which may make compliance more difficult and may increase the length of time it takes to receive regulatory approval for our operations, particularly in countries where we operate, such as Mexico and Brazil. For example, in Mexico, we have obtained substantially all permits but are awaiting final approvals for our power plant and permits necessary to operate our terminal. In connection with our application to the U.S. Maritime Administration ("MARAD") related to our FLNG project off the coast of Louisiana (as discussed further below), MARAD announced it had initially paused the statutory 356-day application review timeline on August 16, 2022 pending receipt of additional information, and restarted the timeline on October 28, 2022. MARAD issued a second stop notice on November 23, 2022 and on December 22, 2022, MARAD issued a third data request for supplemental information. Following review of NFE's response to the December 2022 data requests, MARAD extended the stop-clock on February 21, 2023 pending clarification of responses and receipt of additional information. In addition, jurisdiction-specific employment, labor, and subcontracting laws may also affect contracting strategies and impact construction and operations. No assurance can be given that we will be able to obtain approval of this application and receive the required permits, approvals and …

Excerpt shortened here; the source contains the full paragraph.

Current wording

MARAD announced it had initially paused the statutory 356-day application review timeline on August 16, 2022 pending receipt of additional information, and restarted the timeline on October 28, 2022. MARAD issued a second stop notice on November 23, 2022 and on December 22, 2022, MARAD issued a third data request for supplemental information. Following review of NFE's response to the December 2022 data requests, MARAD extended the stop-clock on February 21, 2023 pending clarification of responses and receipt of additional information. In addition, jurisdiction-specific employment, labor, and subcontracting laws may also affect contracting strategies and impact construction and operations. No assurance can be given that we will be able to obtain approval of all applications or receive the required permits, approvals and authorizations from governmental and regulatory agencies related to our projects with favorable terms on a timely basis or at all. We intend to apply for updated permits for the Pennsylvania Facility with the aim of obtaining these permits to coincide with the commencement of construction activities. We cannot make any assurance as to if or when we will receive these permits, which are needed prior to commencing certain construction activities related to the facility. Any administrative and judicial challenges to our permits can delay and protract the process for obtaining and implementing permits and can also add significant costs and uncertainty. We cannot control the outcome of any review or approval process, including whether or when any such permits and authorizations will be obtained, the terms of their issuance, or possible appeals or other potential interventions by third parties that could interfere with our ability to obtain and maintain such permits and authorizations or the terms thereof. Furthermore, we are developing new technologies and operate in jurisdictions that may lack mature legal and regulatory systems and may experience legal instability, which may be subject to regulatory and legal challenges, instability or clarity of application of laws, rules and regulations to our business and new technology, which can result in difficulties and instability in obtaining or securing required permits or authorizations. In addition, our LNG transportation activities are subject to broad array of regulations, and our operations are dependent upon obtaining and maintaining required permits and authorizations,. For example, the United States Coast Guard ("USCG") regulates the navigable waterways through which vessels we own, lease or direct must traverse to supply LNG in Puerto Rico. Our business in Puerto Rico must comply with all applicable Coast Guard regulations. If we are incorrect in our interpretation of applicable requirements, of if there is a change in the interpretation or application of those requirements, the Coast Guard could determine that we have not compiled with applicable requirements, which could lead to f…

Excerpt shortened here; the source contains the full paragraph.

Previous wording

A key part of our business strategy is to attract new customers by agreeing to finance and develop new facilities, power plants, liquefaction facilities and related infrastructure in order to win new customer contracts for the supply of natural gas, LNG, steam or power. This strategy requires us to invest capital and time to develop a project in exchange for the ability to sell our products and generate fees from customers in the future. When we develop these projects, our required capital expenditure may be significant, and we typically do not generate meaningful fees from customers until the project has commenced commercial operations, which may take a year or more to achieve. If the project is not successfully developed for any reason, we face the risk of not recovering some or all of our invested capital, which may be significant. If the project is successfully developed, we face the risks that our customers may not fulfill their payment obligations or may not fulfill other performance obligations that impact our ability to collect payment. Our customer contracts and development agreements do not fully protect us against this risk and, in some instances, may not provide any meaningful protection from this risk. This risk is heightened in foreign jurisdictions, particularly if our counterparty is a government or government-related entity because any attempt to enforce our contractual or other rights may involve long and costly litigation where the ultimate outcome is uncertain. If we invest capital in a project where we do not receive the payments we expect, we will have less capital to invest in other projects, our liquidity, results of operations and financial condition could be materially and adversely affected, and we could face the inability to comply with the terms of our existing debt or other agreements, which would exacerbate these adverse effects.

Current wording

A key part of our business strategy is to attract new customers by agreeing to finance and develop new facilities, power plants, liquefaction facilities and related infrastructure in order to win new customer contracts for the supply of natural gas, LNG, steam or power. We intend to employ a similar strategy for our Klondike business. This strategy requires us to invest capital and time to develop a project in exchange for the ability to sell our products and generate fees from customers in the future. When we develop these projects, our required capital expenditure may be significant, and we typically do not generate meaningful fees from customers until the project has commenced commercial operations, which may take a year or more to achieve. If the project is not successfully developed for any reason, we face the risk of not recovering some or all of our invested capital, which may be significant. If the project is successfully developed, we face the risks that our customers may not fulfill their payment obligations or may not fulfill other performance obligations that impact our ability to collect payment. Our customer contracts and development agreements do not fully protect us against this risk and, in some instances, may not provide any meaningful protection from this risk. This risk is heightened in foreign jurisdictions, particularly if our counterparty is a government or government-related entity because any attempt to enforce our contractual or other rights may involve long and costly litigation where the ultimate outcome is uncertain. If we invest capital in a project where we do not receive the payments we expect, we will have less capital to invest in other projects, our liquidity, results of operations and financial condition could be materially and adversely affected, and we could face the inability to comply with the terms of our existing debt or other agreements, which would exacerbate these adverse effects.

Previous wording

Our business strategy relies upon our ability to successfully market our products to our existing and new customers and enter into or replace our long-term supply and services agreements for the sale of natural gas, LNG, steam and power. If we contract with our customers on short-term contracts, our pricing can be subject to more fluctuations and less favorable terms, and our earnings are likely to become more volatile. An increasing emphasis on the short-term or spot LNG market may in the future require us to enter into contracts based on variable market prices, as opposed to contracts based on a fixed rate, which could result in a decrease in our cash flow in periods when the market price for shipping LNG is depressed or insufficient funds are available to cover our financing costs for related vessels. Our ability to generate cash is dependent on these customers’ continued willingness and ability to continue purchasing our products and services and to perform their obligations under their respective contracts. Their obligations may include certain nomination or operational responsibilities, construction or maintenance of their own facilities which are necessary to enable us to deliver and sell natural gas or LNG, and compliance with certain contractual representations and warranties. Further, adverse economic conditions in our industry increase the risk of nonpayment and nonperformance by customers, particularly customers that have sub-investment grade credit ratings. The impact of a pandemic, such as COVID-19, including governmental and other third-party responses thereto, on our customers could enhance the risk of nonpayment by such customers under our contracts, which would negatively affect our business, results of operations and financial condition. In particular, JPS and SJPC, which are public utility companies in Jamaica, could be subject to austerity measures imposed on Jamaica by the International Monetary Fund (the “IMF”) and other international lending organizations. Jamaica is currently subject to certain public spending limitations imposed by agreements with the IMF, and any changes under these agreements could limit JPS’s and SJPC’s ability to make payments under their long-term GSAs and, in the case of JPS, its ability to make payments under its PPA, with us. In addition, PREPA is currently subject to bankruptcy proceedings pending in the U.S. District Court for the District of Puerto Rico. As a result, PREPA’s ability to meet its payment obligations under its contracts will be largely dependent upon funding from federal sources. Specifically, PREPA’s contracting practices in connection with restoration and repair of PREPA’s electrical grid in Puerto Rico, and the terms of certain of those contracts, have been subject to comment and are the subject of review and hearings by U.S. federal and Puerto Rican governmental entities. Certain of our subsidiaries are counterparties to contracts with governmental entities, including PREPA. …

Excerpt shortened here; the source contains the full paragraph.

Current wording

Our business strategy relies upon our ability to successfully market our products to our existing and new customers and enter into or replace our long-term supply and services agreements for the sale of natural gas, LNG, steam and power. If we contract with our customers on short-term contracts, our pricing can be subject to more fluctuations and less favorable terms, and our earnings are likely to become more volatile. An increasing emphasis on the short-term or spot LNG market may in the future require us to enter into contracts based on variable market prices, as opposed to contracts based on a fixed rate, which could result in a decrease in our cash flow in periods when the market price for shipping LNG is depressed or insufficient funds are available to cover our financing costs for related vessels. Our ability to generate cash is dependent on these customers’ continued willingness and ability to continue purchasing our products and services and to perform their obligations under their respective contracts. Their obligations may include certain nomination or operational responsibilities, construction or maintenance of their own facilities which are necessary to enable us to deliver and sell natural gas or LNG, and compliance with certain contractual representations and warranties. Further, adverse economic conditions in our industry increase the risk of nonpayment and nonperformance by customers, particularly customers that have sub-investment grade credit ratings. For example, JPS and SJPC, which are public utility companies in Jamaica, could be subject to austerity measures imposed on Jamaica by the International Monetary Fund (the “IMF”) and other international lending organizations. Jamaica is currently subject to certain public spending limitations imposed by agreements with the IMF, and any changes under these agreements could limit JPS’s and SJPC’s ability to make payments under their long-term GSAs and, in the case of JPS, its ability to make payments under its PPA, with us. In addition, PREPA is currently subject to bankruptcy proceedings pending in the U.S. District Court for the District of Puerto Rico. As a result, PREPA’s ability to meet its payment obligations under its contracts will be largely dependent upon funding from federal sources. Specifically, PREPA’s contracting practices in connection with restoration and repair of PREPA’s electrical grid in Puerto Rico, and the terms of certain of those contracts, have been subject to comment and are the subject of review and hearings by U.S. federal and Puerto Rican governmental entities. Certain of our subsidiaries are counterparties to contracts with governmental entities, including PREPA. Although these contracts require payment and performance of certain obligations, we remain subject to the statutory limitations on enforcement of those contractual provisions that protect these governmental entities. In the event that PREPA or any applicable governmental counterparty does not …

Excerpt shortened here; the source contains the full paragraph.

Previous wording

Our results of operations for the year ended December 31, 2023, include our Montego Bay Facility, Old Harbour Facility, San Juan Facility, certain industrial end-users and our Miami Facility. In addition, we placed a portion of our La Paz Facility into service in the fourth quarter of 2021, and our revenue and results of operations have begun to be impacted by operations in Mexico, including agreements with certain power generation facilities in Baja California Sur. Our results for 2023 exclude other developments, including our Puerto Sandino Facility, the Barcarena Facility, Santa Catarina Facility and Ireland Facility. Jamaica, Mexico and Puerto Rico have historically experienced economic volatility and the general condition and performance of their economies, over which we have no control, may affect our business, financial condition and results of operations. Jamaica, Mexico and Puerto Rico are subject to acts of terrorism or sabotage and natural disasters, in particular hurricanes, extreme weather conditions, crime and similar other risks which may negatively impact our operations in the region. See “—Risks Related to the Jurisdictions in Which We Operate—We are subject to the economic, political, social and other conditions in the jurisdictions in which we operate.” We may also be affected by trade restrictions, such as tariffs or other trade controls. Additionally, tourism is a significant driver of economic activity in these geographies and directly and indirectly affects local demand for our LNG and therefore our results of operations. Trends in tourism in these geographies are primarily driven by the economic condition of the tourists’ home country or territory, the condition of their destination, and the availability, affordability and desirability of air travel and cruises. Additionally, unexpected factors could reduce tourism at any time, including local or global economic recessions, terrorism, travel restrictions, pandemics, severe weather or natural disasters. Due to our current lack of asset and geographic diversification, an adverse development at our operating facilities, in the energy industry or in the economic conditions in these geographies, would have a significantly greater impact on our financial condition and operating results than if we maintained more diverse assets and operating areas.

Current wording

Our results of operations for the year ended December 31, 2024, include our Montego Bay Facility, Old Harbour Facility, San Juan Facility and certain industrial end-users. In addition, we placed a portion of our La Paz Facility into service in the fourth quarter of 2021, and our revenue and results of operations have begun to be impacted by operations in Mexico, including agreements with certain power generation facilities in Baja California Sur. Our results in 2024 exclude other developments, including our Puerto Sandino Facility, the Barcarena Facility, Santa Catarina Facility and Ireland Facility. Jamaica, Mexico and Puerto Rico have historically experienced economic volatility and the general condition and performance of their economies, over which we have no control, may affect our business, financial condition and results of operations. Jamaica, Mexico and Puerto Rico are subject to acts of terrorism or sabotage and natural disasters, in particular hurricanes, extreme weather conditions, crime and similar other risks which may negatively impact our operations in the region. See “—Risks Related to the Jurisdictions in Which We Operate—We are subject to the economic, political, social and other conditions in the jurisdictions in which we operate.” We may also be affected by trade restrictions, such as tariffs or other trade controls. Additionally, tourism is a significant driver of economic activity in these geographies and directly and indirectly affects local demand for our LNG and therefore our results of operations. Trends in tourism in these geographies are primarily driven by the economic condition of the tourists’ home country or territory, the condition of their destination, and the availability, affordability and desirability of air travel and cruises. Additionally, unexpected factors could reduce tourism at any time, including local or global economic recessions, terrorism, travel restrictions, pandemics, severe weather or natural disasters. Due to our current lack of asset and geographic diversification, an adverse development at our operating facilities, in the energy industry or in the economic conditions in these geographies, would have a significantly greater impact on our financial condition and operating results than if we maintained more diverse assets and operating areas.

Previous wording

Our current results of operations and liquidity are, and will continue to be in the near future, substantially dependent upon a limited number of customers, including JPS, SJPC, CFE and PREPA, which have each entered into long-term GSAs and, in the case of JPS, a PPA in relation to the power produced at the CHP Plant, with us, and Jamalco, which has entered into a long-term SSA with us, and which represent a substantial majority of our income. Our operating results are currently contingent on our ability to maintain LNG, natural gas, steam and power sales to these customers. Our near-term ability to generate cash is dependent on these customers’ continued willingness and ability to continue purchasing our products and services and to perform their obligations under their respective contracts. The loss of any of these customers could have an adverse effect on our revenues and we may not be able to enter into a replacement agreement on terms as favorable as the terminated agreement. We may be unable to accomplish our business plan to diversify and expand our customer base by attracting a broad array of customers, which could negatively affect our business, results of operations and financial condition.

Current wording

Our current results of operations and liquidity are, and will continue to be in the near future, substantially dependent upon a limited number of customers, including JPS, SJPC, CFE and PREPA, which have each entered into long-term GSAs and, in the case of JPS, a PPA in relation to the power produced at the CHP Plant, with us, and Jamalco, which has entered into a long-term SSA with us, and which represent a substantial majority of our income. Our operating results are currently contingent on our ability to maintain LNG, natural gas, steam and power sales to these customers. Our near-term ability to generate cash is dependent on these customers’ continued willingness and ability to continue purchasing our products and services and to perform their obligations under their respective contracts. The loss of any of these customers or the early termination of any of these contracts could have an adverse effect on our revenues and we may not be able to enter into a replacement agreement on terms as favorable as the terminated agreement. We may be unable to accomplish our business plan to diversify and expand our customer base by attracting a broad array of customers, which could negatively affect our business, results of operations and financial condition.

Previous wording

We are actively pursuing a significant number of new contracts for the sale of LNG, natural gas, steam, and power with multiple counterparties in multiple jurisdictions. Counterparties commemorate their purchasing commitments for these products in various degrees of formality ranging from traditional contracts to less formal arrangements, including non-binding letters of intent, non-binding memorandums of understanding, non-binding term sheets and responses to requests for proposals with potential customers. These agreements and any award following a request for proposals are subject to negotiating final definitive documents. The negotiation process may cause us or our potential counterparty to adjust the material terms of the agreement, including the price, term, schedule and any related development obligations. We cannot assure you if or when we will enter into binding definitive agreements for transactions initially described in non-binding agreements, and the terms of our binding agreements may differ materially from the terms of the related non-binding agreements. In addition, the effectiveness of our binding agreements can be subject to a number of conditions precedent that may not materialize, rendering such agreements non-effective. Moreover, while certain of our long-term contracts contain minimum volume commitments, our expected sales to customers under existing contracts may be substantially in excess of such minimum volume commitments. Our near-term ability to generate cash is dependent on these customers’ continued willingness and ability to nominate in excess of such minimum quantities and to perform their obligations under their respective contracts. Given the variety of sales processes and counterparty acknowledgements of the volumes they will purchase, we sometimes identify potential sales volumes as being either “Committed” or “In Discussion.” “Committed” volumes generally refer to the volumes that management expects to be sold under binding contracts or awards under requests for proposals. “In Discussion” volumes generally refer to volumes related to potential customers that management is actively negotiating, responding to a request for proposals, or with respect to which management anticipates a request for proposals or competitive bid process to be announced based on discussions with potential customers. Management’s estimations of “Committed” and “In Discussion” volumes may prove to be incorrect. Accordingly, we cannot assure you that “Committed” or “In Discussion” volumes will result in actual sales, and such volumes should not be used to predict the Company’s future results. We may never sign a binding agreement to sell our products to the counterparty, or we may sell much less volume than we estimate, which could result in our inability to generate the revenues and profits we anticipate, having a material adverse effect on our results of operations and financial condition.

Current wording

We are actively pursuing a significant number of new contracts for the sale of LNG, natural gas, steam, and power with multiple counterparties in multiple jurisdictions. Counterparties commemorate their purchasing commitments for these products in various degrees of formality ranging from traditional contracts to less formal arrangements, including non-binding letters of intent, non-binding memorandums of understanding, non-binding term sheets and responses to requests for proposals with potential customers. These agreements and any award following a request for proposals are subject to negotiating final definitive documents. The negotiation process may cause us or our potential counterparty to adjust the material terms of the agreement, including the price, term, schedule and any related development obligations. We cannot assure you if or when we will enter into binding definitive agreements for transactions initially described in non-binding agreements, and the terms of our binding agreements may differ materially from the terms of the related non-binding agreements. In addition, the effectiveness of our binding agreements can be subject to a number of conditions precedent that may not materialize, rendering such agreements non-effective. Moreover, while certain of our long-term contracts contain minimum volume commitments, our expected sales to customers under existing contracts may be substantially in excess of such minimum volume commitments. Our near-term ability to generate cash is dependent on these customers’ continued willingness and ability to nominate in excess of such minimum quantities and to perform their obligations under their respective contracts. Given the variety of sales processes and counterparty acknowledgments of the volumes they will purchase, we sometimes identify potential sales volumes as being either “Committed” or “In Discussion.” “Committed” volumes generally refer to the volumes that management expects to be sold under binding contracts or awards under requests for proposals. “In Discussion” volumes generally refer to volumes related to potential customers that management is actively negotiating, responding to a request for proposals, or with respect to which management anticipates a request for proposals or competitive bid process to be announced based on discussions with potential customers. Management’s estimations of “Committed” and “In Discussion” volumes may prove to be incorrect. Accordingly, we cannot assure you that “Committed” or “In Discussion” volumes will result in actual sales, and such volumes should not be used to predict the Company’s future results. We may never sign a binding agreement to sell our products to the counterparty, or we may sell much less volume than we estimate, which could result in our inability to generate the revenues and profits we anticipate, having a material adverse effect on our results of operations and financial condition.

Previous wording

We may not be able to replace these contracts on desirable terms, or at all, if they are terminated. Contracts that we enter into in the future may contain similar provisions. If any of our current or future contracts are terminated, such termination could have a material adverse effect on our business, contracts, financial condition, operating results, cash flows, liquidity and prospects.

Current wording

In addition, we have short-term customer contracts with renewal rights which the customer may choose not to renew. We may not be able to replace these contracts on desirable terms, or at all, if they are terminated. Contracts that we enter into in the future may contain similar provisions. If any of our current or future contracts are terminated, such termination could have a material adverse effect on our business, contracts, financial condition, operating results, cash flows, liquidity and prospects.

Previous wording

Under our GSAs, PPAs and SSAs, we are required to deliver to our customers specified amounts of LNG, natural gas, power and steam, respectively, at specified times and within certain specifications, all of which requires us to obtain sufficient amounts of LNG from third-party LNG suppliers or our own portfolio. We may not be able to purchase or receive physical delivery of sufficient quantities of LNG to satisfy those delivery obligations, which may provide a counterparty with the right to terminate its GSA, PPA or SSA, as applicable, or subject us to remedial obligations under those agreements. While we have entered into supply agreements for the purchase of LNG between 2024 and 2047, we may need to purchase significant additional LNG volumes to meet our delivery obligations to our downstream customers. Price fluctuations in natural gas and LNG may make it expensive or uneconomical for us to acquire adequate supply of these items or to sell our inventory of natural gas or LNG at attractive prices. Failure to secure contracts for the purchase of a sufficient amount of LNG or at favorable prices could materially and adversely affect our business, operating results, cash flows and liquidity.

Current wording

Under our GSAs, PPAs, capacity reservation agreements and SSAs, we are required to deliver to our customers specified amounts of LNG, natural gas, power and steam, respectively, at specified times and within certain specifications, all of which requires us to obtain sufficient amounts of LNG from third-party LNG suppliers or our own portfolio. We may not be able to purchase or receive physical delivery of sufficient quantities of LNG to satisfy those delivery obligations, which may provide a counterparty with the right to terminate its GSA, PPA, capacity reservation agreement or SSA, as applicable, or subject us to remedial obligations under those agreements. While we have entered into supply agreements for the purchase of LNG between 2024 and 2047, we may need to purchase significant additional LNG volumes to meet our delivery obligations to our downstream customers. Price fluctuations in natural gas and LNG may make it expensive or uneconomical for us to acquire adequate supply of these items or to sell our inventory of natural gas or LNG at attractive prices. Failure to secure contracts for the purchase of a sufficient amount of LNG or at favorable prices could materially and adversely affect our business, operating results, cash flows and liquidity.

Previous wording

Additionally, we are dependent upon third-party LNG suppliers and shippers and other tankers and facilities to provide delivery options to and from our tankers and energy-related infrastructure. If any third parties were to default on their obligations under our contracts or seek bankruptcy protection, we may not be able to replace such contracts or purchase LNG on the spot market or receive a sufficient quantity of LNG in order to satisfy our delivery obligations under our GSAs, PPAs and SSAs or at favorable terms. Under tanker charters, we are obligated to make payments for our chartered tankers regardless of use. We may not be able to enter into contracts with purchasers of LNG in quantities equivalent to or greater than the amount of tanker capacity we have purchased, as our vessels may be too small for those obligations. Any such failure to purchase or receive delivery of LNG or natural gas in sufficient quantities could result in our failure to satisfy our obligations to our customers, which could lead to losses, penalties, indemnification and potentially a termination of agreements with our customers. Furthermore, we may seek to litigate any such breaches by our third-party LNG suppliers and shippers. Such legal proceedings may involve claims for substantial amounts of money and we may not be successful in pursing such claims. Even if we are successful, any litigation may be costly and time-consuming. If any such proceedings were to result in an unfavorable outcome, we may not be able to recover our losses (including lost profits) or any damages sustained from our agreements with our customers. See “—General Risks—We are and may be involved in legal proceedings and may experience unfavorable outcomes.” These actions could also expose us to adverse publicity, which might adversely affect our reputation and therefore, our results of operations. Further, it could have an adverse effect on our business, operating results, cash flows and liquidity, which could in turn materially and adversely affect our liquidity to make payments on our debt or comply with our financial ratios and other covenants. See “—We have incurred, and may in the future incur, a significant amount of debt.”

Current wording

Additionally, we are dependent upon third-party LNG suppliers and shippers and other tankers and facilities to provide delivery options to and from our tankers and energy-related infrastructure. If any third parties were to default on their obligations under our contracts or seek bankruptcy protection, we may not be able to replace such contracts or purchase LNG on the spot market or receive a sufficient quantity of LNG in order to satisfy our delivery obligations under our GSAs, PPAs, capacity reservation agreements and SSAs or at favorable terms. Under tanker charters, we are obligated to make payments for our chartered tankers regardless of use. We may not be able to enter into contracts with purchasers of LNG in quantities equivalent to or greater than the amount of tanker capacity we have purchased, as our vessels may be too small for those obligations. Any such failure to purchase or receive delivery of LNG or natural gas in sufficient quantities could result in our failure to satisfy our obligations to our customers, which could lead to losses, penalties, indemnification and potentially a termination of agreements with our customers. Furthermore, we may seek to litigate any such breaches by our third-party LNG suppliers and shippers. Such legal proceedings may involve claims for substantial amounts of money and we may not be successful in pursing such claims. Even if we are successful, any litigation may be costly and time-consuming. If any such proceedings were to result in an unfavorable outcome, we may not be able to recover our losses (including lost profits) or any damages sustained from our agreements with our customers. See “—General Risks—We are and may be involved in legal proceedings and may experience unfavorable outcomes.” These actions could also expose us to adverse publicity, which might adversely affect our reputation and therefore, our results of operations. Further, it could have an adverse effect on our business, operating results, cash flows and liquidity, which could in turn materially and adversely affect our liquidity to make payments on our debt or comply with our financial ratios and other covenants. See “—We have incurred, and may in the future incur, a significant amount of debt.”

Previous wording

LNG that is processed and/or stored on FSRUs and transported via pipeline is subject to risk of loss or damage.

Current wording

LNG that is processed, transported and/or stored on FSRUs and transported via pipeline is subject to risk of loss or damage.

Previous wording

LNG processed and stored on FSRUs may be subject to loss or damage resulting from equipment malfunction, faulty handling, ageing or otherwise. Where we have chartered in, but subsequently not outchartered an FSRU, which in turn results in our being unable to transfer risk of loss or damage, we could bear the risk of loss or damage to all those volumes of LNG for the period of time during which those applicable volumes of LNG are stored on an FSRU or are dispatched to a pipeline. Any such disruption to the supply of LNG and natural gas may lead to delays, disruptions or curtailments in the production of power at our facilities, which could materially and adversely affect our revenues, financial condition and results of operations.

Current wording

LNG processed, transported and stored on FSRUs may be subject to loss or damage resulting from equipment malfunction, faulty handling, cargo ageing or otherwise. Where we have chartered in, but subsequently not outchartered an FSRU, which in turn results in our being unable to transfer risk of loss or damage, we could bear the risk of loss or damage to all those volumes of LNG for the period of time during which those applicable volumes of LNG are stored on an FSRU or are dispatched to a pipeline. Any such disruption to the supply of LNG and natural gas may lead to delays, disruptions or curtailments in the production of power at our facilities, which could materially and adversely affect our revenues, financial condition and results of operations.

Previous wording

In addition to our own fleet of vessels, we rely on third-party ocean-going tankers and freight carriers (for ISO containers) for the transportation of LNG and ship-to-ship kits to transfer LNG between ships. We may not be able to successfully enter into contracts or renew existing contracts to charter tankers on favorable terms or at all, which may result in us not being able to meet our obligations. Our ability to enter into contracts or renew existing contracts will depend on prevailing market conditions upon expiration of the contracts governing the leasing or charter of the applicable assets. Therefore, we may be exposed to increased volatility in terms of charter rates and contract provisions. Fluctuations in rates result from changes in the supply of and demand for capacity and changes in the demand for seaborne carriage of commodities. Because the factors affecting the supply and demand are outside of our control and are highly unpredictable, the nature, timing, direction and degree of changes in industry conditions are also unpredictable. Likewise, our counterparties may seek to terminate or renegotiate their charters or leases with us. If we are not able to renew or obtain new charters or leases in direct continuation, or if new charters or leases are entered into at rates substantially above the existing rates or on terms otherwise less favorable compared to existing contractual terms, our business, prospects, financial condition, results of operations and cash flows could be materially adversely affected.

Current wording

In addition to our own fleet of vessels, we rely on third-party ocean-going tankers and freight carriers (for ISO containers) for the transportation of LNG and use ship-to-ship kits to transfer LNG between ships. We may not be able to successfully enter into contracts or renew existing contracts to charter tankers on favorable terms or at all, which may result in us not being able to meet our obligations. Our ability to enter into contracts or renew existing contracts will depend on prevailing market conditions upon expiration of the contracts governing the leasing or charter of the applicable assets. Therefore, we may be exposed to increased volatility in terms of charter rates and contract provisions. Fluctuations in charter rates result from changes in the supply of LNG tankers and demand for capacity and changes in the demand for seaborne carriage of commodities. Because the factors affecting the supply and demand are outside of our control and are highly unpredictable, the nature, timing, direction and degree of changes in industry conditions are also unpredictable. Likewise, our counterparties may seek to terminate or renegotiate their charters or leases with us. If we are not able to renew or obtain new charters or leases in direct continuation, or if new charters or leases are entered into at rates substantially above the existing rates or on terms otherwise less favorable compared to existing contractual terms, our business, prospects, financial condition, results of operations and cash flows could be materially adversely affected.

Previous wording

Furthermore, our ability to provide services to our customers could be adversely impacted by shifts in tanker market dynamics, shortages in available cargo carrying capacity, changes in policies and practices such as scheduling, pricing, routes of service and frequency of service, or increases in the cost of fuel, taxes and labor, emissions standards, maritime regulatory changes and other factors not within our control. The availability of the tankers could be delayed to the detriment of our LNG business and our customers because the construction and delivery of LNG tankers require significant capital and long construction lead times. Changes in ocean freight capacity, which are outside our control, could negatively impact our ability to provide natural gas if LNG shipping capacity is adversely impacted and LNG transportation costs increase because we may bear the risk of such increases and may not be able to pass these increases on to our customers.

Current wording

Furthermore, our ability to provide services to our customers could be adversely impacted by shifts in tanker market dynamics, shortages in available cargo carrying capacity, changes in policies and practices such as scheduling, pricing, routes of service and frequency of service, or increases in the cost of fuel, taxes and labor, emissions standards, maritime regulatory changes, sanctions and other factors not within our control. The availability of the tankers could be delayed to the detriment of our LNG business and our customers because the construction and delivery of LNG tankers require significant capital and long construction lead times. Changes in ocean freight capacity, which are outside our control, could negatively impact our ability to provide natural gas if LNG shipping capacity is adversely impacted and LNG transportation costs increase because we may bear the risk of such increases and may not be able to pass these increases on to our customers.

Previous wording

Hire rates for FSRUs and LNG carriers fluctuate over time as a result of changes in the supply-demand balance relating to current and future FSRU and LNG carrier capacity. This supply-demand relationship largely depends on a number of factors outside of our control. For example, driven in part by an increase in LNG production capacity, the market supply particularly of LNG carriers has been increasing. We believe that this and any future expansion of the global LNG carrier fleet may have a negative impact on charter hire rates, vessel utilization and vessel values, the impact of which could be amplified if the expansion of LNG production capacity does not keep pace with fleet growth. The LNG market is also closely connected to world natural gas prices and energy markets, which it cannot predict. A substantial or extended decline in demand for natural gas or LNG could adversely affect our ability to charter or re-charter our vessels at acceptable rates or to acquire and profitably operate new vessels. Accordingly, this could have a material adverse effect on our earnings, financial condition, operating results and prospects.

Current wording

Hire rates for FSRUs and LNG carriers fluctuate over time as a result of changes in the supply-demand balance relating to the market requirements for FSRUs and LNG carries and future FSRU and LNG carrier capacity. This supply-demand relationship largely depends on a number of factors outside of our control. For example, driven in part by an increase in LNG production capacity, the market supply particularly of LNG carriers has been increasing. We believe that this and any future expansion of the global LNG carrier fleet may have a negative impact on charter hire rates, vessel utilization and vessel values, the impact of which could be amplified if the expansion of LNG production capacity does not keep pace with fleet growth. The LNG market is also closely connected to world natural gas and LNG prices and energy markets, which it cannot predict. A substantial or extended decline in demand for natural gas or LNG could adversely affect our ability to charter or re-charter our vessels at acceptable rates or to acquire and profitably operate new vessels. Accordingly, this could have a material adverse effect on our earnings, financial condition, operating results and prospects.

Previous wording

Our FSRU facilities have excess capacity that is currently not dedicated to a particular anchor customer. Part of our business strategy is to utilize undedicated excess capacity of our FSRU facilities to serve additional downstream customers in the regions in which we operate. However, we have not secured, and we may be unable to secure, commitments for all of our excess capacity. Factors which could cause us to contract less than full capacity include difficulties in negotiations with potential counterparties and factors outside of our control such as the price of and demand for LNG. Failure to secure commitments for less than full capacity could impact our future revenues and materially adversely affect our business, financial condition and operating results.

Current wording

Our FSRU facilities have excess capacity that is currently not dedicated to a particular anchor customer. Part of our business strategy is to utilize undedicated excess capacity of our FSRU facilities to serve additional downstream customers in the regions in which we operate. However, we have not secured, and we may be unable to secure, commitments for all of our excess capacity. Factors which could cause us to contract less than full capacity include difficulties in negotiations with potential counterparties, timing of start-up of new third party projects and factors outside of our control such as the price of and demand for LNG for a particular project. Failure to secure commitments for less than full capacity could impact our future revenues and materially adversely affect our business, financial condition and operating results.

Previous wording

Our principal strategy for our FSRU and LNG carriers is to provide steady and reliable shipping, regasification and offshore operations to NFE terminals and, to the extent favorable to our business, replace or enter into new long-term carrier time charters for our vessels. For new LNG projects continue to be provided on a long-term basis, though the level of spot voyages and short-term time charters of less than 12 months in duration together with medium term charters of up to five years has increased in recent years. This trend is expected to continue as the spot market for LNG expands. More frequent changes to vessel sizes, propulsion technology and emissions profile, together with an increasing desire by charterers to access modern tonnage could also reduce the appetite of charterers to commit to long-term charters that match their full requirement period. As a result, the duration of long-term charters could also decrease over time. We may also face increased difficulty entering into long-term time charters upon the expiration or early termination of our contracts. The process of obtaining long-term charters for FSRUs and LNG carriers is highly competitive and generally involves an intensive screening process and competitive bids, and often extends for several months. If we lose any of our charterers and are unable to re-deploy the related vessel to a NFE terminal or into a new replacement contract for an extended period of time, we will not receive any revenues from that vessel, but we will be required to pay expenses necessary to maintain the vessel in seaworthy operating condition and to service any associated debt.

Current wording

Our principal strategy for our FSRU and LNG carriers is to provide steady and reliable shipping, regasification and offshore operations to NFE terminals and, to the extent favorable to our business, replace or enter into new long-term carrier time charters for our vessels. For new LNG projects, LNG ships continue to be provided on a long-term basis, though the level of spot voyages and short-term time charters of less than 12 months in duration together with medium term charters of up to five years has increased in recent years. This trend is expected to continue as the spot market for LNG expands and becomes more liquid. More frequent changes to vessel sizes, propulsion technology and emissions profile, retirements of older vessels, together with an increasing desire by charterers to access modern tonnage could also reduce the appetite of charterers to commit to long-term charters that match their full requirement period. As a result, the duration of long-term charters could also decrease over time. We may also face increased difficulty entering into long-term time charters upon the expiration or early termination of our contracts. The process of obtaining long-term charters for FSRUs and LNG carriers is highly competitive and generally involves an intensive screening process and competitive bids, and often extends for several months. If we lose any of our charterers and are unable to re-deploy the related vessel to a NFE terminal or into a new replacement contract for an extended period of time, we will not receive any revenues from the deliveries from that vessel, but we will be required to pay expenses necessary to maintain the vessel in seaworthy operating condition.

Previous wording

•the size and age of a vessel; and

Current wording

•the size, tank type and age of a vessel; and

Previous wording

•the cost of retrofitting, steel or modifying existing vessels, as a result of technological advances in vessel design or equipment, changes in applicable environmental or other regulations or standards, customer requirements or otherwise.

Current wording

•the cost of retrofitting, steel prices or modifying existing vessels, as a result of technological advances in vessel design or equipment, changes in applicable environmental or other regulations or standards, customer requirements or otherwise.

Previous wording

As our vessels age, the expenses associated with maintaining and operating them are expected to increase, which could have an adverse effect on our business and operations if we do not maintain sufficient cash reserves for maintenance and replacement capital expenditures. Moreover, the cost of a replacement vessel would be significant.

Current wording

As our owned or chartered vessels age, the expenses associated with maintaining and operating them are expected to increase, which could have an adverse effect on our business and operations if we do not maintain sufficient cash reserves for maintenance and replacement capital expenditures. Moreover, the cost of a replacement vessel could be significant and subject to market pricing.

Previous wording

During the period a vessel is subject to a charter, we will not be permitted to sell it to take advantage of increases in vessel values without the charterers’ consent. If a charter terminates, we may be unable to re-deploy the affected vessels at attractive rates or for our operations and, rather than continue to incur costs to maintain and finance them, we may seek to dispose of them. When vessel values are low, we may not be able to dispose of vessels at a reasonable price when we wish to sell vessels, and conversely, when vessel values are elevated, we may not be able to acquire additional vessels at attractive prices when we wish to acquire additional vessels, which could adversely affect our business, results of operations, cash flow, and financial condition.

Current wording

During the period a vessel is subject to a charter, we will not be permitted to sell it to take advantage of increases in vessel values without the charterers’ consent. If a charter terminates, we may be unable to re-deploy the affected vessels at market rates or for our operations and, rather than continue to incur costs to maintain and finance them, we may seek to dispose of them. When vessel values are low, we may not be able to dispose of vessels at a reasonable price when we wish to sell vessels, and conversely, when vessel values are elevated, we may not be able to acquire additional vessels at attractive prices when we wish to acquire additional vessels, which could adversely affect our business, results of operations, cash flow, and financial condition.

Previous wording

The carrying values of our vessels may not represent their fair market value at any point in time because the market prices of secondhand vessels tend to fluctuate with changes in charter rates and the cost of new build vessels. Our vessels are reviewed for impairment whenever events or changes in circumstances indicate that the carrying amount may not be recoverable. We recognized an impairment charge on one of our vessels for the year ended December 31, 2023 and we cannot assure you that we will not recognize impairment losses on our vessels in future years. Any impairment charges incurred as a result of declines in charter rates could negatively affect our business, financial condition, or operating results.

Current wording

The carrying values of our vessels may not represent their fair market value at any point in time because the market prices of secondhand vessels tend to fluctuate with changes in charter rates, vessel availability and the cost of new build vessels, steel prices and foreign exchange rates. Our vessels are reviewed for impairment whenever events or changes in circumstances indicate that the carrying amount may not be recoverable. We recognized an impairment charge on one of our vessels for the year ended December 31, 2023 and we cannot assure you that we will not recognize impairment losses on our vessels in future years. Any impairment charges incurred as a result of declines in charter rates could negatively affect our business, financial condition, or operating results.

Previous wording

The success of our current operations and future projects will depend in part on our ability to create and maintain a competitive position in the natural gas liquefaction industry. In particular, although we plan to build out our delivery logistics chain in Northern Pennsylvania using proven technologies such as those currently in operation at our Miami Facility, we do not have any exclusive rights to any of these technologies. In addition, such technologies may be rendered obsolete or uneconomical by legal or regulatory requirements, technological advances, more efficient and cost-effective processes or entirely different approaches developed by one or more of our competitors or others, which could materially and adversely affect our business, ability to realize benefits from future projects, results of operations, financial condition, liquidity and prospects.

Current wording

The success of our current operations and future projects will depend in part on our ability to create and maintain a competitive position in the natural gas liquefaction industry. In particular, although we plan to build out our delivery logistics chain in Northern Pennsylvania using proven technologies, we do not have any exclusive rights to any of these technologies. In addition, such technologies may be rendered obsolete or uneconomical by legal or regulatory requirements, technological advances, more efficient and cost-effective processes or entirely different approaches developed by one or more of our competitors or others, which could materially and adversely affect our business, ability to realize benefits from future projects, results of operations, financial condition, liquidity and prospects.

Previous wording

We have developed our Fast LNG strategy to procure and deliver LNG to our customers more quickly and cost-effectively than traditional LNG procurement and delivery strategies used by other market participants. Our ability to create and maintain a competitive position in the natural gas liquefaction industry may be adversely affected by our inability to effectively implement our Fast LNG technology. We are about to finalize construction of our first Fast LNG solution, but we have not yet produced or supplied any LNG from that facility, and are therefore subject to construction risks, risks associated with third-party contracting and service providers, permitting and regulatory risks. We are also developing our first onshore LNG facility and are also therefore subject to construction risks, risks associated with third-party contracting and service providers, permitting and regulatory risks. See “—We are subject to various construction risks” and “—We depend on third-party contractors, operators and suppliers.” Because our Fast LNG technology has not been previously implemented, tested or proven, we are also exposed to unknown and unforeseen risks associated with the development of new technologies, including failure to meet design, engineering, or performance specifications, incompatibility of systems, inability to contract or employ third parties with sufficient experience in technologies used or inability by contractors to perform their work, delays and schedule changes, high costs and expenses that may be subject to increase or difficult to anticipate, regulatory and legal challenges, instability or clarity of application of laws, rules and regulations to the technology, and added difficulties in obtaining or securing required permits or authorizations, among others. See “—Failure to obtain and maintain permits, approvals and authorizations from governmental and regulatory agencies and third parties on favorable terms could impede operations and construction.” The success and profitability of our Fast LNG technology is also dependent on the volatility of the price of natural gas and LNG compared to the related levels of capital spending required to implement the technology. Natural gas and LNG prices have at various times been and may become volatile due to one or more factors. Volatility or weakness in natural gas or LNG prices could render our LNG procured through Fast LNG too expensive for our customers, and we may not be able to obtain our anticipated return on our investment or make our technology profitable. In addition, we may seek to construct and develop floating offshore liquefaction units as part of our Fast LNG in jurisdictions which could potentially expose us to increased political, economic, social and legal instability, a lack of regulatory clarity of application of laws, rules and regulations to our technology, or additional jurisdictional risks related to currency exchange, tariffs and other taxes, changes in laws, civil unrest…

Excerpt shortened here; the source contains the full paragraph.

Current wording

We have developed our Fast LNG strategy to procure and deliver LNG to our customers more quickly and cost-effectively than traditional LNG procurement and delivery strategies used by other market participants. Our ability to create and maintain a competitive position in the natural gas liquefaction industry may be adversely affected by our inability to effectively implement our Fast LNG technology. We have commenced operations at our first Fast LNG solution, but we have not yet supplied any LNG from that facility to customers, and are therefore subject to risks related to full commercial development of the facility. We are also developing our first onshore LNG facility and are therefore subject to construction risks, risks associated with third-party contracting (including the risk that we will not be able to execute contracts with third parties that are necessary to develop the project) and service providers, permitting and regulatory risks. See “—We are subject to various construction risks” and “—We depend on third-party contractors, operators and suppliers.” Because our Fast LNG technology has not been previously implemented, tested or proven, we are also exposed to unknown and unforeseen risks associated with the development of new technologies, including failure to meet design, engineering, or performance specifications, incompatibility of systems, inability to contract or employ third parties with sufficient experience in technologies used or inability by contractors to perform their work, delays and schedule changes, high costs and expenses that may be subject to increase or difficult to anticipate, regulatory and legal challenges, instability or clarity of application of laws, rules and regulations to the technology, and added difficulties in obtaining or securing required permits or authorizations, among others. For example, in April 2024, we experienced an incident involving equipment failure during the commissioning of our Fast LNG project in Altamira, Mexico, which delayed our commencement of operations and resulted in increased costs and delay of commencement of revenue generating activity. See “—Failure to obtain and maintain permits, approvals and authorizations from governmental and regulatory agencies and third parties on favorable terms could impede operations and construction.” The success and profitability of our Fast LNG technology is also dependent on the volatility of the price of natural gas and LNG compared to the related levels of capital spending required to implement the technology. Natural gas and LNG prices have at various times been and may become volatile due to one or more factors. Volatility or weakness in natural gas or LNG prices could render our LNG procured through Fast LNG too expensive for our customers, and we may not be able to obtain our anticipated return on our investment or make our technology profitable. In addition, we may seek to construct and develop floating offshore liquefaction units as part o…

Excerpt shortened here; the source contains the full paragraph.

Previous wording

On an ongoing basis, we engage with lenders and other financial institutions in an effort to improve our liquidity and capital resources. As of December 31, 2023, we had approximately $6,919.5 million aggregate principal amount of indebtedness outstanding on a consolidated basis. The terms and conditions of our indebtedness include restrictive covenants that may limit our ability to operate our business, to incur or refinance our debt, engage in certain transactions, and require us to maintain certain financial ratios, among others, any of which may limit our ability to finance future operations and capital needs, react to changes in our business and in the economy generally, and to pursue business opportunities and activities. If we fail to comply with any of these restrictions or are unable to pay our debt service when due, our debt could be accelerated or cross-accelerated, and we cannot assure you that we will have the ability to repay such accelerated debt. Any such default could also have adverse consequences to our status and reporting requirements, reducing our ability to quickly access the capital markets. Our ability to service our existing and any future debt will depend on our performance and operations, which is subject to factors that are beyond our control and compliance with covenants in the agreements governing such debt. We may incur additional debt to fund our business and strategic initiatives. If we incur additional debt and other obligations, the risks associated with our substantial leverage and the ability to service such debt would increase, which could have a material adverse effect on our business, results of operation and financial condition.

Current wording

On an ongoing basis, we engage with lenders and other financial institutions in an effort to improve our liquidity and capital resources. As of December 31, 2024, we had approximately $9,027.1 million aggregate principal amount of indebtedness outstanding on a consolidated basis (which does not include any unconsolidated debt). The terms and conditions of our indebtedness, including the2026 Notes Indenture, the 2029 Notes Indenture, the Intercompany Credit Agreements and the Existing Credit Agreements (each as defined in "Management's Discussion and Analysis of Financial Condition and Results of Operations-Recent Developments."), include restrictive covenants that may limit our ability to operate our business, to incur or refinance our debt, pay dividends or make distributions or make certain other restricted payments, create liens on our or our subsidiaries' assets, sell or otherwise dispose of assets, engage in certain transactions, and require us to maintain certain financial ratios, among others, any of which may limit our ability to finance future operations and capital needs, react to changes in our business and in the economy generally, and to pursue business opportunities and activities. If we fail to comply with any of these restrictions or are unable to pay our debt service when due, our debt could be accelerated or cross-accelerated, and we cannot assure you that we will have the ability to repay such accelerated debt. Any such default could also have adverse consequences to our status and reporting requirements, reducing our ability to quickly access the capital markets. Additionally, our Existing Credit Agreements and the intercompany loan agreements securing, directly or indirectly, the New 2029 Notes require proceeds of certain asset sales be used to pay down existing indebtedness, which may further limit our ability to operate our business and finance future operations and capital needs.

Previous wording

We believe we will have sufficient liquidity, cash flow from operations and access to additional capital sources to fund our capital expenditures and working capital needs for the next 12 months and the reasonably foreseeable future. In the future, we expect to incur additional indebtedness to assist us in developing our operations and we are considering alternative financing options, including in specific markets or the opportunistic sale of one of our non-core assets. We also historically have relied, and in the future will likely rely, on borrowings under term loans and other debt instruments to fund our capital expenditures. If any of the lenders in the syndicates backing these debt instruments were unable to perform on its commitments, we may need to seek replacement financing. We cannot assure you that such additional funding will be available on acceptable terms, or at all. Our ability to raise additional capital on acceptable terms will depend on financial, economic and market conditions, which have increased in volatility and at times have been negatively impacted due to our progress in executing our business strategy and other factors, many of which are beyond our control, including domestic or international economic conditions, increases in key benchmark interest rates and/or credit spreads, the adoption of new or amended banking or capital market laws or regulations, the re-pricing of market risks and volatility in capital and financial markets, risks relating to the credit risk of our customers and the jurisdictions in which we operate, as well as general risks applicable to the energy sector. Additional debt financing, if available, may subject us to increased restrictive covenants that could limit our flexibility in conducting future business activities and could result in us expending significant resources to service our obligations. Additionally, we may need to adjust the timing of our planned capital expenditures and facilities development depending on the requirements of our existing financing and availability of such additional funding. If we are unable to obtain additional funding, approvals or amendments to our financings outstanding from time to time, or if additional funding is only available on terms that we determine are not acceptable to us, we may be unable to fully execute our business plan, we may be unable to pay or refinance our indebtedness or to fund our other liquidity needs, and our financial condition or results of operations may be materially adversely affected.

Current wording

We believe we will have sufficient liquidity, cash flow from operations and access to additional capital sources to fund our capital expenditures and working capital needs for the next 12 months and the reasonably foreseeable future. In the future, we expect to incur additional indebtedness to assist us in developing our operations and we are considering alternative financing options, including in Brazil and other specific markets or the opportunistic sale of one of our non-core assets such as the sale of our assets in Jamaica. We also historically have relied, and in the future will likely rely, on borrowings under term loans and other debt instruments to fund our capital expenditures. If any of the lenders in the syndicates backing these debt instruments were unable to perform on its commitments, we may need to seek replacement financing. We cannot assure you that such additional funding will be available on acceptable terms, or at all. Our ability to raise additional capital on acceptable terms will depend on financial, economic and market conditions, which have increased in volatility and at times have been negatively impacted due to our progress in executing our business strategy and other factors, many of which are beyond our control, including domestic or international economic conditions, increases in key benchmark interest rates and/or credit spreads, the adoption of new or amended banking or capital market laws or regulations, the re-pricing of market risks and volatility in capital and financial markets, risks relating to the credit risk of our customers and the jurisdictions in which we operate, as well as general risks applicable to the energy sector. The terms of the Notes financing subjected us to, anda dditional debt financing, if available, may subject us to increased restrictive covenants that could limit, and in the case of the former, significantly limit, our flexibility to incur additional indebtedness and conduct future business activities and could result in us expending significant resources to service our obligations. Additionally, we may need to adjust the timing of our planned capital expenditures and facilities development depending on the requirements of our existing financing and availability of such additional funding. If we are unable to obtain additional funding, approvals or amendments to our financings outstanding from time to time, or if additional funding is only available on terms that we determine are not acceptable to us, we may be unable to fully execute our business plan, we may be unable to pay or refinance our indebtedness or to fund our other liquidity needs, and our financial condition or results of operations may be materially adversely affected.

Previous wording

We have entered into, and may in the future enter, into joint venture arrangements with third parties in respect of our projects and assets. For example, in August 2022, we established Energos, as a joint venture platform with certain funds or investment vehicles managed by Apollo, for the development of a global marine infrastructure platform, of which we owned 20% prior to our sale of our 20% stake in February 2024. As we do not operate the assets owned by these joint ventures, our control over their operations is limited by provisions of the agreements we have entered into with our joint venture partners and by our percentage ownership in such joint ventures. Because we do not control all of the decisions of our joint ventures, it may be difficult or impossible for us to cause the joint venture to take actions that we believe would be in its or the joint venture’s best interests. For example, we cannot unilaterally cause the distribution of cash by our joint ventures. Additionally, as the joint ventures are separate legal entities, any right we may have to receive assets of any joint venture or other payments upon their liquidation or reorganization will be effectively subordinated to the claims of the creditors of that joint venture (including tax authorities, trade creditors and any other third parties that require such subordination, such as lenders and other creditors). Moreover, joint venture arrangements involve various risks and uncertainties, such as our commitment to fund operating and/or capital expenditures, the timing and amount of which we may not control, and our joint venture partners may not satisfy their financial obligations to the joint venture. We have provided and may in the future provide guarantees or other forms of credit support to our joint ventures and/or affiliates. Failure by any of our joint ventures, equity method investees and/or affiliates to service their debt requirements and comply with any provisions contained in their commercial loan agreements, including paying scheduled installments and complying with certain covenants, may lead to an event of default under the related loan agreement. As a result, if our joint ventures, equity method investees and/or affiliates are unable to obtain a waiver or do not have enough cash on hand to repay the outstanding borrowings, the relevant lenders may foreclose their liens on the relevant assets or vessels securing the loans or seek repayment of the loan from us, or both. Either of these possibilities could have a material adverse effect on our business. Further, by virtue of our guarantees with respect to our joint ventures and/or affiliates, this may reduce our ability to gain future credit from certain lenders.

Current wording

We have entered into, and may in the future enter, into joint venture arrangements with third parties in respect of our projects and assets. For example, in August 2022, we established Energos, as a joint venture platform with certain funds or investment vehicles managed by Apollo, for the development of a global marine infrastructure platform, of which we owned 20% prior to our sale of approximately all of our 20% stake in February 2024. As we do not operate the assets owned by these joint ventures, our control over their operations is limited by provisions of the agreements we have entered into with our joint venture partners and by our percentage ownership in such joint ventures. Because we do not control all of the decisions of our joint ventures, it may be difficult or impossible for us to cause the joint venture to take actions that we believe would be in its or the joint venture’s best interests. For example, we cannot unilaterally cause the distribution of cash by our joint ventures. Additionally, as the joint ventures are separate legal entities, any right we may have to receive assets of any joint venture or other payments upon their liquidation or reorganization will be effectively subordinated to the claims of the creditors of that joint venture (including tax authorities, trade creditors and any other third parties that require such subordination, such as lenders and other creditors). Moreover, joint venture arrangements involve various risks and uncertainties, such as our commitment to fund operating and/or capital expenditures, the timing and amount of which we may not control, and our joint venture partners may not satisfy their financial obligations to the joint venture. We have provided and may in the future provide guarantees or other forms of credit support to our joint ventures and/or affiliates. Failure by any of our joint ventures, equity method investees and/or affiliates to service their debt requirements and comply with any provisions contained in their commercial loan agreements, including paying scheduled installments and complying with certain covenants, may lead to an event of default under the related loan agreement. As a result, if our joint ventures, equity method investees and/or affiliates are unable to obtain a waiver or do not have enough cash on hand to repay the outstanding borrowings, the relevant lenders may foreclose their liens on the relevant assets or vessels securing the loans or seek repayment of the loan from us, or both. Either of these possibilities could have a material adverse effect on our business. Further, by virtue of our guarantees with respect to our joint ventures and/or affiliates, this may reduce our ability to gain future credit from certain lenders.

Previous wording

Greenhouse Gases/Climate Change. The threat of climate change continues to attract considerable attention in the United States and around the world. Numerous proposals have been made and could continue to be made at the international, national, regional and state government levels to monitor and limit existing and future GHG emissions. As a result, our operations are subject to a series of risks associated with the processing, transportation, and use of fossil fuels and emission of GHGs. In the United States to date, no comprehensive climate change legislation has been implemented at the federal level, although various individual states and state coalitions have adopted or considered adopting legislation, regulations or other regulatory initiatives, including GHG cap and trade programs, carbon taxes, reporting and tracking programs, and emission restrictions, pollution reduction incentives, or renewable energy or low-carbon replacement fuel quotas. At the international level, the United Nations-sponsored “Paris Agreement” was signed by 197 countries who agreed to limit their GHG emissions through non-binding, individually-determined reduction goals every five years after 2020. The United States rejoined the Paris Agreement, effective in February 2021, and other countries where we operate or plan to operate, including Jamaica, Brazil, Ireland, Mexico, and Nicaragua, have signed or acceded to this agreement. However, the scope of future climate and GHG emissions-focused regulatory requirements, if any, remain uncertain. Governmental, scientific, and public concern over the threat of climate change arising from GHG emissions has resulted in increasing political uncertainty in the United States and worldwide. For example, based in part on the publicized climate plan and pledges by the U.S. government, there may be significant legislation, rulemaking, or executive orders that seek to address climate change, incentivize low-carbon infrastructure or initiatives, or ban or restrict the exploration and production of fossil fuels. For example, executive orders may be issued or federal legislation or regulatory initiatives may be adopted to achieve U.S. goals under the Paris Agreement.

Current wording

Greenhouse Gases/Climate Change. The threat of climate change continues to attract considerable attention in the United States and around the world. Numerous proposals have been made and could continue to be made at the international, national, regional and state government levels to monitor and limit existing and future GHG emissions. As a result, our operations are subject to a series of risks associated with the processing, transportation, and use of fossil fuels and emission of GHGs. In the United States to date, no comprehensive climate change legislation has been implemented at the federal level, although various individual states and state coalitions have adopted or considered adopting legislation, regulations or other regulatory initiatives, including GHG cap and trade programs, carbon taxes, reporting and tracking programs, and emission restrictions, pollution reduction incentives, or renewable energy or low-carbon replacement fuel quotas. At the international level, the United Nations-sponsored “Paris Agreement” was signed by 197 countries who agreed to limit their GHG emissions through non-binding, individually-determined reduction goals every five years after 2020. On January 20, 2025, President Trump signed an executive order announcing the withdrawal of the United States from the Paris Agreement. Though most other countries (including those where we operate or plan to operate) have signed or acceded to this agreement. The scope of future climate and GHG emissions-focused regulatory requirements, if any, remains uncertain. Governmental, scientific, and public concern over the threat of climate change arising from GHG emissions has resulted in increasing political uncertainty in the United States and worldwide. For example, based in part on the publicized climate plan and pledges by the U.S. government, there may be significant legislation, rulemaking, or executive orders that seek to address climate change, incentivize low-carbon infrastructure or initiatives, or ban or restrict the exploration and production of fossil fuels. Executive orders may be issued or federal legislation or regulatory initiatives may be adopted to achieve U.S. goals under the Paris Agreement. President Trump, however, has generally expressed opposition to regulatory initiatives aimed at restricting oil and gas operations and the impact his administration will have on any of these initiatives cannot be predicted.

Previous wording

Fossil Fuels. Our business activities depend upon a sufficient and reliable supply of natural gas feedstock, and are therefore subject to concerns in certain sectors of the public about the exploration, production and transportation of natural gas and other fossil fuels and the consumption of fossil fuels more generally. For example, PHMSA has promulgated detailed regulations governing LNG facilities under its jurisdiction to address siting, design, construction, equipment, operations, maintenance, personnel qualifications and training, fire protection and security. While the Miami Facility is subject to these regulations, none of our LNG facilities currently under development are subject to PHMSA’s jurisdiction, but regulators and governmental agencies in the other jurisdictions in which we operate can impose similar siting, design, construction and operational requirements that can affect our projects, facilities, infrastructure and operations. Legislative and regulatory action, and possible litigation, in response to such public concerns may also adversely affect our operations. We may be subject to future laws, regulations, or actions to address such public concern with fossil fuel generation, distribution and combustion, greenhouse gases and the effects of global climate change. Our customers may also move away from using fossil fuels such as LNG for their power generation needs for reputational or perceived risk-related reasons. These matters represent uncertainties in the operation and management of our business, and could have a material adverse effect on our financial position, results of operations and cash flows.

Current wording

Fossil Fuels. Our business activities depend upon a sufficient and reliable supply of natural gas feedstock, and are therefore subject to concerns in certain sectors of the public about the exploration, production and transportation of natural gas and other fossil fuels and the consumption of fossil fuels more generally. For example, PHMSA has promulgated detailed regulations governing LNG facilities under its jurisdiction to address siting, design, construction, equipment, operations, maintenance, personnel qualifications and training, fire protection and security.None of our LNG facilities currently under development are subject to PHMSA’s jurisdiction, but regulators and governmental agencies in the other jurisdictions in which we operate can impose similar siting, design, construction and operational requirements that can affect our projects, facilities, infrastructure and operations. Legislative and regulatory action, and possible litigation, in response to such public concerns may also adversely affect our operations. We may be subject to future laws, regulations, or actions to address such public concern with fossil fuel generation, distribution and combustion, greenhouse gases and the effects of global climate change. Our customers may also move away from using fossil fuels such as LNG for their power generation needs for reputational or perceived risk-related reasons. These matters represent uncertainties in the operation and management of our business, and could have a material adverse effect on our financial position, results of operations and cash flows.

Previous wording

Indigenous Communities. Indigenous communities—including, in Brazil, Afro-indigenous (“Quilombola”) communities—are subject to certain protections under international and national laws. Brazil has ratified the International Labor Organization’s Indigenous and Tribal Peoples Convention (“ILO Convention 169”), which states that governments are to ensure that members of tribes directly affected by legislative or administrative measures, including the grant of government authorizations, such as are required for our Brazilian operations, are consulted through appropriate procedures and through their representative institutions, particularly using the principle of consultation and participation of indigenous and traditional communities under the basis of free, prior, and informed consent (“FPIC”). Brazilian law does not specifically regulate the FPIC process for indigenous and traditional people affected by undertakings, nor does it set forth that individual members of an affected community shall render their FPIC on an undertaking that may impact them. However, in order to obtain certain environmental licenses for our operations, we are required to comply with the requirements of, consult with, and obtain certain authorizations from a number of institutions regarding the protection of indigenous interests: IBAMA, local environmental authorities in the localities in which we operate, the Federal Public Prosecutor’s Office and the National Indian Foundation (Fundação Nacional do Índio or “FUNAI”) (for indigenous people) or Palmares Cultural Foundation (Fundação Cultural Palmares) (for Quilombola communities).

Current wording

Indigenous Communities. Indigenous communities—including, in Brazil, Afro-indigenous (“Quilombola”) communities—are subject to certain protections under international and national laws. Brazil has ratified the International Labor Organization’s Indigenous and Tribal Peoples Convention (“ILO Convention 169”), which states that governments are to ensure that members of tribes directly affected by legislative or administrative measures, including the grant of government authorizations, such as are required for our Brazilian operations, are consulted through appropriate procedures and through their representative institutions, particularly using the principle of consultation and participation of indigenous and traditional communities under the basis of free, prior, and informed consent (“FPIC”). Brazilian law does not specifically regulate the FPIC process for indigenous and traditional people affected by undertakings, nor does it set forth that individual members of an affected community shall render their FPIC on an undertaking that may impact them. However, in order to obtain certain environmental licenses for our operations, we are required to comply with the requirements of, consult with, and obtain certain authorizations from a number of institutions regarding the protection of indigenous interests: The Brazilian Institute of Enviornment and Renewable Resources, local environmental authorities in the localities in which we operate, the Federal Public Prosecutor’s Office and the National Indian Foundation (Fundação Nacional do Índio or “FUNAI”) (for indigenous people) or Palmares Cultural Foundation (Fundação Cultural Palmares) (for Quilombola communities).

Previous wording

Environmental Protection of the Hydrocarbons Sector (“ASEA”), among other relevant Mexican regulatory bodies. The laws and regulations governing activities in the Mexican energy sector have undergone significant reformation over the past decade, and the legal regulatory framework continues to evolve as SENER, the CNH and other Mexican regulatory bodies issue new regulations and guidelines as the industry develops. Such regulations are subject to change, so it is possible that SENER, the CNH or other Mexican regulatory bodies may impose new or revised requirements that could increase our operating costs and/or capital expenditures for operations in Mexican offshore waters. In addition, our operations in waters off the coast of Mexico are subject to regulation by ASEA. The laws and regulations governing the protection of health, safety and the environment from activities in the Mexican energy sector are also relatively new, having been significantly reformed in 2013 and 2014, and the legal regulatory framework continues to evolve as ASEA and other Mexican regulatory bodies issue new regulations and guidelines as the industry modernizes and adapts to market changes. Such regulations are subject to change, and it is possible that ASEA or other Mexican regulatory bodies may impose new or revised requirements that could increase our operating costs and/or capital expenditures for operations in Mexican offshore waters.

Current wording

In particular, development of offshore operations of natural gas and LNG are subject to extensive environmental, industry, maritime and social regulations. For example, the development and operation of our new FLNG facility off the coast of Altamira, State of Tamaulipas, is subject to regulation by Mexico’s Ministry of Energy (Secretaría de Energía) (“SENER”), Mexico's National Hydrocarbon Commission (“CNH”), the National Agency of Industrial Safety and Environmental Protection of the Hydrocarbons Sector (“ASEA”), among other relevant Mexican regulatory bodies. The laws and regulations governing activities in the Mexican energy sector have undergone significant reformation over the past decade, and the legal regulatory framework continues to evolve as SENER, the CNH and other Mexican regulatory bodies issue new regulations and guidelines as the industry develops. Such regulations are subject to change, so it is possible that SENER, the CNH or other Mexican regulatory bodies may impose new or revised requirements that could increase our operating costs and/or capital expenditures for operations in Mexican offshore waters. In addition, our operations in waters off the coast of Mexico are subject to regulation by ASEA. The laws and regulations governing the protection of health, safety and the environment from activities in the Mexican energy sector are also relatively new, having been significantly reformed in 2013 and 2014, and the legal regulatory framework continues to evolve as ASEA and other Mexican regulatory bodies issue new regulations and guidelines as the industry modernizes and adapts to market changes. Such regulations are subject to change, and it is possible that ASEA or other Mexican regulatory bodies may impose new or revised requirements that could increase our operating costs and/or capital expenditures for operations in Mexican offshore waters.

Showing the first 40 of 60 pairs. Open the source sections for the rest.

Rearranged current paragraphs (1)

Current report — wording carried from elsewhere

The design, construction and operation of our infrastructure, facilities and businesses, including our FSRUs, FLNG units and LNG carriers, the import and export of LNG, exploration and development activities, and the transportation of natural gas, among others, are highly regulated activities at the national, state and local levels and are subject to various approvals and permits. The process to obtain the permits, approvals and authorizations we need to conduct our business, and the interpretations of those rules, is complex, time-consuming, challenging and varies in each jurisdiction in which we operate. We may be unable to obtain such approvals on terms that are satisfactory for our operations and on a timeline that meets our commercial obligations. Many of these permits, approvals and authorizations require public notice and comment before they can be issued, which can lead to delays to respond to such comments, and even potentially to revise the permit application. Jurisdiction-specific employment, labor, and subcontracting laws may also affect contracting strategies and impact construction and operations. We may also be (and have been in select circumstances) subject to local opposition, including citizens groups or non-governmental organizations such as environmental groups, which may create delays and challenges in our permitting process and may attract negative publicity, which may create an adverse impact on our reputation. In addition, such rules change frequently and are often subject to discretionary interpretations, including administrative and judicial challenges by regulators, all of which may make compliance more difficult and may increase the length of time it takes to receive regulatory approval for our operations, particularly in countries where we operate, such as Mexico and Brazil. For example, in Mexico, we have obtained substantially all permits but are awaiting final approvals for our power plant and permits necessary to operate our terminal. In connection with our application to the U.S. Maritime Administration ("MARAD") related to our FLNG project off the coast of Louisiana (as discussed further below),
Rearranged previous paragraphs (18)

Previous report — wording carried elsewhere

•If securities or industry analysts do not publish research or reports about our business, if they adversely change their recommendations regarding our Class A common stock or if our operating results do not meet their expectations, our share price could decline; and

Previous report — wording carried elsewhere

Failure to maintain sufficient working capital could limit our growth and harm our business, financial condition and results of operations.

Previous report — wording carried elsewhere

Our contracts with our customers are subject to termination under certain circumstances.

Previous report — wording carried elsewhere

Competition in the LNG industry is intense, and some of our competitors have greater financial, technological and other resources than we currently possess.

Previous report — wording carried elsewhere

Any use of hedging arrangements may adversely affect our future operating results or liquidity.

Previous report — wording carried elsewhere

Vessel values may fluctuate substantially and, if these values are lower at a time when we are attempting to dispose of vessels, we may incur a loss.

Previous report — wording carried elsewhere

Maritime claimants could arrest our vessels, which could interrupt our cash flow.

Previous report — wording carried elsewhere

We have incurred, and may in the future incur, a significant amount of debt.

Previous report — wording carried elsewhere

We have entered into, and may in the future enter into or modify existing, joint ventures that might restrict our operational and corporate flexibility or require credit support.

Previous report — wording carried elsewhere

In particular, development of offshore operations of natural gas and LNG are subject to extensive environmental, industry, maritime and social regulations. For example, 1the development and operation of our new FLNG facility off the coast of Altamira, State of Tamaulipas, is subject to regulation by Mexico’s Ministry of Energy (Secretaría de Energía) (“SENER”), Mexico's National Hydrocarbon Commission (“CNH”), the National Agency of Industrial Safety and

Previous report — wording carried elsewhere

We may not own the land on which our projects are located and are subject to leases, rights-of-ways, easements and other property rights for our operations.

Previous report — wording carried elsewhere

We could be negatively impacted by environmental, social, and governance (“ESG”) and sustainability-related matters.

Previous report — wording carried elsewhere

Our Certificate of Incorporation and By-Laws, as well as Delaware law, contain provisions that could discourage acquisition bids or merger proposals, which may adversely affect the market price of our Class A common stock and could deprive our investors of the opportunity to receive a premium for their Class A common stock.

Previous report — wording carried elsewhere

Our By-Laws designate the Court of Chancery of the State of Delaware as the sole and exclusive forum for certain types of actions and proceedings that may be initiated by our stockholders, which could limit our stockholders’ ability to obtain a favorable judicial forum for disputes with us or our directors, officers, employees or agents.

Previous report — wording carried elsewhere

We may issue preferred stock, the terms of which could adversely affect the voting power or value of our Class A common stock.

Previous report — wording carried elsewhere

An active, liquid and orderly trading market for our Class A common stock may not be maintained and the price of our Class A common stock may fluctuate significantly.

Previous report — wording carried elsewhere

If we fail to develop or maintain an effective system of internal controls, we may not be able to accurately report our financial results or prevent fraud. As a result, current and potential stockholders could lose confidence in our financial reporting, which would harm our business and the trading price of our Class A common stock.

Previous report — wording carried elsewhere

We are unable to predict the extent to which global pandemics and health crises will negatively affect our operations, financial performance, nor our ability to achieve our strategic objectives. We are also unable to predict how a global pandemic may affect our customers and suppliers.