What changed in Management’s Discussion and Analysis?
Read the current filingPrevious report: 10-Q
Period ended 2024-09-30; filed 2024-11-07.
0001628280-24-046065
Item 2. MANAGEMENT’S DISCUSSION AND ANALYSIS OF FINANCIAL CONDITION AND RESULTS OF OPERATIONSCurrent report: 10-Q
Period ended 2025-03-31; filed 2025-05-08.
0001628280-25-023547
Item 2. MANAGEMENT’S DISCUSSION AND ANALYSIS OF FINANCIAL CONDITION AND RESULTS OF OPERATIONSThe baseline is this issuer’s latest earlier reporting period of the same form that was filed before the current report. A previous 10-Q is a different quarter, not a year-over-year comparison. Amendments are excluded.
Compared 275 previous paragraphs and 221 current paragraphs.
120 unchanged; 74 reworded; 26 added; 67 removed; 14 previous and 1 current paragraphs rearranged.
Tables are not compared: 20 previous and 15 current tables excluded. Dates, whitespace, punctuation and numbering changes are ignored; changes to financial figures remain significant.
A changed paragraph is not evidence that risk increased or decreased. An unchanged paragraph does not establish that risk stayed the same.
Added paragraphs (26)
Current report
•Changes in U.S. and foreign government policy, including the imposition of or increases in tariffs and changes to existing trade agreements, could have a material adverse effect on global economic conditions and our business, results of operations, prospects and financial condition.
Current report
•In May 2025, we signed an agreement to acquire the Blue Mountain geothermal power plant from Cyrq Energy. The 20MW facility, located in Humboldt County, NV, will be purchased for $88 million, subject to standard working capital adjustments. The power plant, built using Ormat technology, features an existing 51MW interconnection capacity and a PPA with NV Energy (“NVE”) that expires at the end of 2029. Following the acquisition, Ormat plans to upgrade the power plant and increase its capacity by 3.5MW. Additionally, subject to permit and PPA approval, Ormat intends to add a 13MW solar facility to support the plant's auxiliaries. The acquisition is anticipated to close towards the end of the second quarter of 2025.
Current report
•In February 2025, we won a tender issued by the Israeli Electricity Authority and have been awarded two separate 15-year tolling agreements for two Energy Storage facilities. The facilities under the tolling agreements are expected to have a combined capacity of approximately 300MW/1200MWh. The ownership of the projects will be shared, 50/50 between Ormat and Allied Infrastructure LTD, a leading infrastructure company in Israel.
Current report
•In February 2025, we announced the successful COD for the Ijen geothermal power plant that is owned jointly with PT Medco Power Indonesia (“Medco Power”). The Ijen Geothermal Power Plant, equipped with OEC, began operations with its first phase, delivering 35 MW of electricity power to the Java grid, Ormat’s share of the facility is 17MW.
Current report
•In January 2025, we announced the signing of a 10-year PPA with Calpine Energy Solutions, one of North America’s largest energy suppliers. Under this agreement, Calpine Energy Solutions agreed to purchase up to 15MW of clean, renewable energy from the Mammoth 2 geothermal power plant located near Mammoth Lakes, California, to support demand within its retail portfolio. Energy deliveries under the PPA are scheduled to begin in the first quarter of 2027 and will replace the existing PPA with Southern California Edison. The new PPA includes an increase in production capacity and a higher price point.
Current report
•During and shortly after the first quarter of 2025, the United States introduced actions to increase import tariffs at various rates, including on certain products imported from almost all countries and individualized higher tariffs on certain other countries, such as China. Other countries have announced retaliatory actions or plans for retaliatory actions in response. Some of these tariff announcements have since been followed by announcements of limited exemptions and temporary pauses. Specifically, on April 10, 2025, the United States implemented a 90-day pause on the country-specific tariffs for all countries except China, while maintaining a 10% baseline tariff across all impacted countries. As of the date of this quarterly report, discussions remain ongoing regarding U.S. trade restrictions and tariffs on imports and retaliatory tariffs from numerous countries, including China. Given these events, there continues to be significant uncertainty about the future relationship between the United States and other countries regarding such trade policies, treaties and tariffs, and so we can make no assurance about the eventual impact on our operating results and business. Our Energy Storage segment growth relies on imported batteries from China, and the growth of projects in the United States in the Electricity Segment require raw materials and equipment from various countries. We are working to accelerate imports into the United States as certain tariffs are paused, and expedited Chinese imports prior to when the excess tariff was in place.
Current report
While there is limited impact on short-term growth in both the Energy Storage and Electricity segments, a significant increase in tariffs may lead to a slowdown in the growth of our Energy Storage segment in the U.S. These increases, combined with the uncertainty around the continuation of the Investment Tax Credit (ITC) (as discussed in Part II, Item 7 “Management’s Discussion and Analysis of Financial Condition and Results of Operations—Government Grants and Tax Benefits” in our 2024 Annual Report), could affect our long-term growth, specifically in our Energy Storage segment in the U.S. and, to a lesser extent, across our business.
Current report
For more information, see Part II, Item 1A “Risk Factors—Risks Related to the Company’s Business and Operation—Changes in U.S. and foreign government policy, including the imposition of or increases in tariffs and changes to existing trade agreements, could have a material adverse effect on global economic conditions and our business, results of operations, prospects, and financial condition.”
Current report
Electricity Segment
Current report
Revenues attributable to our Electricity segment for the three months ended March 31, 2025 were $180.2 million, compared to $191.3 million for the three months ended March 31, 2024. This decrease of $11.0 million was mainly attributable to: (i) $3.2 million related to the Dixie Valley power plant primarily as a result of curtailments from SCE; (ii) $2.7 million related to the McGinness Hills complex primarily as a result of mild winter temperature and curtailments from NV Energy; and (iii) $2.3 million related to the Neal Hot Springs and Stillwater power plants, primarily due to maintenance work at both of the power plants.
Current report
Product Segment
Current report
Energy Storage Segment
Current report
Revenues attributable to our Energy Storage segment for the three months ended March 31, 2025 were $17.8 million compared to $8.1 million for the three months ended March 31, 2024. This increase of $9.7 million is primarily related to $6.6 million from new energy storage facilities which commenced commercial operation during or after the first quarter of 2024, such as Bottleneck and Montague in the fourth quarter of 2024, and East Flemington during the first quarter of 2024, as well as higher energy rates at PJM interconnect facilities in the three months ended March 31, 2025, compared to the same period in the previous year.
Current report
Electricity Segment
Current report
Total cost of revenues attributable to our Electricity segment for the three months ended March 31, 2025 was $119.8 million, compared to $116.7 million for the three months ended March 31, 2024 which represents an increase of $3.1 million or 3%.
Current report
Product Segment
Current report
Energy Storage Segment
Current report
Cost of revenues attributable to our Energy Storage segment for the three months ended March 31, 2025 were $12.3 million compared to $7.5 million for the three months ended March 31, 2024. This increase is primarily related to the increase in storage revenue as described above.
Current report
Write-off of unsuccessful exploration and storage activities
Current report
Other non-operating income (expense), net for the three months ended March 31, 2025 was an income of $0.2 million, compared to an immaterial amount for the three months ended March 31, 2024.
Current report
As further described under Note 1 to the condensed consolidated financial statements, the Company entered into three new loan agreements as follows: during February and March 2025, the Company entered into three separate definitive loan agreements with Mizrahi bank, Discount bank and Hapoalim Bank, for $50.0 million, $50.0 million, and $100.0 million, respectively.
Current report
As of March 31, 2025, we did not meet the dividend distribution criteria related to the DAC 1 Senior Secured Notes, which resulted in certain equity distribution restrictions from this related subsidiary. The amount restricted for distribution by this subsidiary was $0.9 million as of March 31, 2025. There were no restrictions on the retained earnings or net income of Ormat Technologies, Inc., as the parent company, in respect of this matter, as of March 31, 2025.
Current report
Non-Recourse, Limited-Recourse, Full-Recourse Third-Party Debt, Financial Liability and Convertible Senior Notes
Current report
The Company has declared and distributed quarterly dividends of $0.12 per share during the past two years.
Current report
Dominica. We are developing the 10MW Dominica geothermal power plant in the Dominica Island. We signed a 25-year PPA with the local utility. At the end of the agreement term, ownership of the power plant will be transferred to the local Government. Construction is progressing. We expect commercial operation by the end of 2025.
Current report
(*) Represents our share of two projects, which are joint ventures.
Removed paragraphs (67)
Previous report
•Reduction in our Products segment backlog may affect our ability to fully utilize our main production and manufacturing facilities.
Previous report
•We may experience difficulties implementing and maintaining our new enterprise resource planning system.
Previous report
•A substantial percentage of our common stock is held by stockholders whose interests may conflict with the interests of our other stockholders.
Previous report
Company Contact and Sources of Information
Previous report
Our website is www.ormat.com. Information contained on our website is not part of this quarterly report. Information that we furnish to or file with the SEC, including our annual reports on Form 10-K, quarterly reports on Form 10-Q, current reports on Form 8-K and any amendments to, or exhibits included in, these reports are made available for download, free of charge, through our website as soon as reasonably practicable. Our SEC filings, including exhibits filed therewith, are also available directly on the SEC’s website at www.sec.gov.
Previous report
We may use our website as a distribution channel of material Company information. Financial and other important information regarding the Company is routinely posted on and accessible through our website at www.ormat.com. Accordingly, investors should monitor this channel, in addition to following our press releases, SEC filings and public conference calls and webcasts.
Previous report
•In October 2024, we announced the successful commencement of commercial operations for our largest energy storage facility, the Bottleneck project. This 80MW/320MWh Battery Energy Storage System (“BESS”), located in the Central Valley of California, will provide ancillary services to San Diego Gas & Electric (“SDG&E”) under the 15-year Tolling Agreement signed in 2022.
Previous report
•In October 2024, we announced that we successfully secured multiple land parcels in Nevada’s Annual Bureau of Land Management (BLM) Auction. We believe that these lease acquisitions will significantly support Ormat's ongoing exploration and expansion efforts in the state, further strengthening the Company's commitment to advancing renewable energy solutions and meeting Nevada's increasing demand for sustainable energy.
Previous report
•In August 2024, we signed two seven-year tolling agreements with Equilibrium Energy for the Lower Rio 60MW/120MWh and Bird Dog 60MW/120MWh Energy Storage facilities in Texas. The Lower Rio project is expected to come online in the second quarter of 2025, while the Bird Dog facility is anticipated to be operational in the fourth quarter of 2025. Both projects are entitled to receive a 40% investment tax credit under the Inflation Reduction Act. The tolling agreements secure fixed revenues for the energy and ancillary services provided by the facilities.
Previous report
•In July 2024, we issued an additional $45.2 million aggregate principal amount of our 2.50% Convertible Senior Notes due 2027. The Additional Notes were issued as additional notes pursuant to the indenture, dated June 27, 2022, as supplemented by the first supplemental indenture, dated July 15, 2024. The proceeds were used for refinancing current debt.
Previous report
•In July 2024, we announced the signing of a 15-year Resource Adequacy Purchase and Sale Agreement (“RA Agreement”) with the City of Riverside, for the 80MW/320MWh Shirk Battery Energy Storage System (BESS) located in Visalia, California. The RA Agreement includes a guaranteed commercial operation date (“COD”) for March 1, 2026, that we believe can be achieved by the end of 2025.
Previous report
•In the second quarter of 2024, we commenced the operation of the 6MW Beowawe Repower geothermal power plant.
Previous report
•On March 4, 2024, we announced the signing of a 30-year PPA with Electricité de France (“EDF”) for the development of a new 10MW geothermal power plant on the island of Guadeloupe, in which we own a 63.75% equity interest. The new plant development will be added to Ormat’s existing 15MW Bouillante geothermal power plant. The project’s field development is completed with resource secured and is expected to be operational by the end of 2025.
Previous report
•On February 12, 2024, we announced that the Hawaii Public Utilities Commission (“HPUC”) approved two final amendments to the PPA between our subsidiary, Puna Geothermal Venture (“PGV”), and Hawaiian Electric. This decision enables PGV to contribute up to an additional 8 megawatts of clean, dispatchable renewable power to the Island of Hawaii, elevating the contract maximum capacity to 46 MW, with a minimum contracted capacity set at 30 MW. The approval follows PGV’s completion and submission of its final Environmental Impact Study (“EIS”) for operations in Puna, Hawai`i. The EIS was a condition set by the HPUC for approval of an amended and restated PPA that was submitted to the HPUC in December 2019.
Previous report
•On January 4, 2024 we announced the closing of the acquisition of a portfolio of geothermal and solar assets from Enel Green Power North America (“EGPNA”), a subsidiary of Enel SpA (ENEL.MI, LLC), that was announced in October 2023. Under the agreement, Ormat paid $272 million for 100% of the equity interest in the portfolio assets. The acquired portfolio includes two contracted operating geothermal power plants and one triple hybrid geothermal, solar PV and solar thermal power plant with a total geothermal capacity of approximately 40 MW and Solar PV of 20MW, two Solar assets with a total nameplate capacity of 40 MW, and two greenfield development assets.
Previous report
Revenues attributable to our Electricity segment for the three months ended September 30, 2024 were $164.6 million, compared to $157.2 million for the three months ended September 30, 2023. This increase of $7.4 million was mainly attributable to: (i) $7.5 million related to the geothermal and solar power plants included in the Enel purchase transaction which were consolidated by the Company starting the first quarter of 2024; (ii) $1.8 million related to the Heber 1 power plant which resumed operations in May 2023 after a temporary shutdown due to a fire incident that occurred in February 2022; and (iii) $7.4 million related to the Puna power plant due to its higher power generation in 2024. This increase was partially offset by lower revenues of $4.2 million in the Dixie Valley power plant due to an unscheduled outage during the period in 2024, $1.8 million in the Guadeloupe power plant due to maintenance issues, as well as decreases in power generation in lesser amounts at a number of other power plants.
Previous report
Power generation in our power plants increased by 1.4% from 1,651,880 MWh in the three months ended September 30, 2023 to 1,675,164 MWh in the three months ended September 30, 2024. The increase in the quarter was primarily due to the inclusion of the new projects acquired early in the year, the contribution of the Heber complex repowering and the improved operation at our Puna power plant. This increase was offset by curtailments in our Olkaria complex and lower generation at Dixie Valley as a result of an unplanned outage.
Previous report
Revenues attributable to our Energy Storage segment for the three months ended September 30, 2024 were $9.8 million compared to $11.0 million for the three months ended September 30, 2023. This decrease is primarily related to lower prices in Texas in the third quarter of 2024 due to mild weather conditions, partially offset by the East Flemington energy storage facility which commenced commercial operations in the first quarter of 2024.
Previous report
Total cost of revenues attributable to our Electricity segment for the three months ended September 30, 2024 was $114.9 million, compared to $107.2 million for the three months ended September 30, 2023. This increase of $7.8 million was primarily attributable to $6.9 million related to the geothermal and solar power plants included in the Enel purchase transaction which were consolidated by the Company starting the first quarter of 2024, and $1.5 million related to the Puna power plant due to its higher power generation in 2024. This increase was partially offset by lower costs across the Company’s other power plants in the three months ended September 30, 2024, compared to the same period in the previous year.
Previous report
Cost of revenues attributable to our Energy Storage segment for the three months ended September 30, 2024 were $7.8 million compared to $8.5 million for the three months ended September 30, 2023. This decrease is primarily related to timing of incurring certain expenses.
Previous report
Write-off of long-lived assets for the three months ended September 30, 2024 was $0.3 million compared to none for the three months ended September 30, 2023. The write-off of long-lived assets is related to the termination of the waste heat agreement between the Company's wholly-owned subsidiary, OREG4, and Highline Electric Association, Inc., effective May 2024.
Previous report
Write-off of unsuccessful exploration activities
Previous report
Other non-operating income (expense), net for the three months ended September 30, 2024 was income of $0.0 million, compared to $0.1 million for the three months ended September 30, 2023.
Previous report
Comparison of the Nine Months Ended September 30, 2024 to the Nine Months Ended September 30, 2023
Previous report
Total Revenues
Previous report
The table below compares revenues for the nine months ended September 30, 2024 to the nine months ended September 30, 2023.
Previous report
Revenues attributable to our Electricity segment for the nine months ended September 30, 2024, were $522.1 million, compared to $482.8 million for the nine months ended September 30, 2023. The increase of $39.3 million in our Electricity segment revenues was mainly attributable to: (i) $25.5 million related to the geothermal and solar power plants included in the Enel purchase transaction which were consolidated by the Company starting the first quarter of 2024; (ii) $12.3 million related to the Heber 1 power plant which resumed operations in May 2023 after a temporary shutdown due to a fire incident that occurred in February 2022; (iii) $16.7 million related to the Puna power plant due to its higher generation in 2024; and (iv) $3.5 million related to the North Valley power plant which started commercial operations in May 2023. This increase was partially offset by lower revenues of $7.4 million in the Dixie Valley power plant due to an unscheduled maintenance, and $3.7 million in the Guadeloupe power plant due to maintenance issues, both during the period in 2024, as well as additional decreases in lower amounts at a number of other power plants.
Previous report
Revenues attributable to our Product segment for thenine months ended September 30, 2024 were $100.0 million, compared to $83.3 million for thenine months ended September 30, 2023. This increase of $16.7 million, or 20.0%, is primarily related to the progress in our projects which results in the timing of when revenues are recognized. During thenine months ended September 30, 2024, Product revenues included projects primarily in New Zealand and Dominica, and during thenine months ended September 30, 2023, Product revenues primarily included projects in New Zealand, Indonesia and the Philippines.
Previous report
Revenues attributable to our Energy Storage segment for the nine months ended September 30, 2024 were $26.8 million compared to $21.9 million for the nine months ended September 30, 2023. The increase of$4.9 is mainly related tothe new energy storage facilities which commenced commercial operation during 2023, primarily Bowling Green in May 2023, Andover and Upton in June 2023, and Pomona 2 in July 2023, as well as the East Flemington energy storage facility which commenced commercial operations during the first quarter of 2024. This increase was partially offset by lower prices in Texas due to mild weather conditions in the area in 2024 compared to 2023, and specifically during the third quarter, year over year.
Previous report
Total Cost of Revenues
Previous report
The table below compares cost of revenues for the nine months ended September 30, 2024 to the nine months ended September 30, 2023.
Previous report
Total cost of revenues attributable to our Electricity segment for the nine months ended September 30, 2024 was $342.2 million, compared to $311.3 million for the nine months ended September 30, 2023. This increase of $30.8 million is primarily attributable to: (i) $19.3 million related to the geothermal and solar power plants included in the Enel purchase transaction which were consolidated by the Company starting the first quarter of 2024; (ii) $6.3 million of income from business interruption insurance proceeds related to the Puna power plant as a result of the damage caused by the Kilauea volcano eruption in May 2018, which were included in cost of revenues in 2023, compared to none in 2024; (iii) $2.9 million related to maintenance issues in the Guadeloupe power plant; and (iv) $3.1 million related to the start of commercial operation of the North Valley power plant in May 2023. This increase was partially offset by lower cost of revenues in other power plants.
Previous report
Our total Electricity segment cost of revenues for the nine months ended September 30, 2024 was 65.5% of Electricity revenues, compared to 64.5% for the nine months ended September 30, 2023, including the impact from business interruption insurance proceeds described above. The cost of revenues attributable to our international power plants for the nine months ended September 30, 2024 was 18.0% of our total Electricity segment cost of revenues for this period, compared to 17.5% for the same period in the prior year.
Previous report
Cost of revenues attributable to our Energy Storage segment for the nine months ended September 30, 2024 was $23.7 million compared to $19.4 million for the nine months ended September 30, 2023. This increase is related to the new storage facilities and corresponding increase in Energy Storage revenues as described above.
Previous report
Research and Development Expenses, Net
Previous report
Research and development expenses for the nine months ended September 30, 2024 were $5.1 million, compared to $4.8 million for the nine months ended September 30, 2023. The increase in research and development expenses is mainly attributable to the timing of research and development projects that took place during the nine months ended September 30, 2024 compared to the corresponding period in 2023.
Previous report
Selling and Marketing Expenses
Previous report
Selling and marketing expenses for the nine months ended September 30, 2024 were $13.5 million compared to $14.0 million for the nine months ended September 30, 2023. Selling and marketing expenses for the nine months ended September 30, 2024, constituted 2.1% of total revenues for such period, compared to 2.4% for the nine months ended September 30, 2023.
Previous report
General and Administrative Expenses
Previous report
General and administrative expenses for the nine months ended September 30, 2024 were $60.5 million compared to $49.5 million for the nine months ended September 30, 2023. The increase of $11.0 million in general and administrative expenses is primarily attributable to consulting fees related to a settlement agreement with a third-party battery systems supplier of $4.8 million, insurance costs, amortization of stock-based awards, and the timing of when we incur services from our vendors.
Showing the first 40 of 67 passages. Open the source sections for the rest.
Reworded paragraphs (74)
Previous wording
A summary of the risks that may cause actual results to differ from our expectations include, but are not limited to the following:
Current wording
During the period covered by this quarterly report on Form 10-Q, there have been no material changes in our risk factors previously disclosed in our 2024 Annual Report. A summary of the risks that may cause actual results to differ from our expectations include, but are not limited to the following:
Previous wording
•Our investments in BESS technology involves new technologies and expected advanced technologies with relatively limited history with respect to reliability and performance and may not perform as expected. In addition, our investments and profitability may be negatively affected by a number of factors, including increases in storage costs, risk of fire and volatility in merchant prices.
Current wording
•Our investments in BESS technology involves new technologies and expected advanced technologies with relatively limited history with respect to reliability and performance and may not perform as expected. In addition, our investments and profitability may be negatively affected by a number of factors, including increases in storage costs, expanded trade restrictions, risk of fire and volatility in merchant prices.
Previous wording
•Conditions in and around Israel, where the majority of our senior management and our main production and manufacturing facilities are located, including the ongoing military conflicts on the borders of Israel, may adversely affect our operations and may limit our ability to produce and sell our products, and support our Electricity segment.
Current wording
•Conditions in and around Israel, where the majority of our senior management and our main production and manufacturing facilities are located, may adversely affect our operations and may limit our ability to produce and sell our products, and support our Electricity segment.
Previous wording
•Responses in various countries where we have business operations to Israel’s ongoing war with Hamas and military conflicts on some of its borders or future similar conflicts may adversely affect our operations and may limit our ability to produce and sell our products.
Current wording
•Responses in various countries where we have business operations to Israel’s ongoing military conflicts on some of its borders or future similar conflicts may adversely affect our operations and may limit our ability to produce and sell our products.
Previous wording
•Our operations could be adversely impacted by climate change.
Current wording
•Our operations could be adversely impacted by climate change and other extreme weather events..
Previous wording
•We could be negatively impacted by regulatory and other responses to climate change.
Current wording
•We could be impacted by regulatory and other responses to climate change.
Previous wording
•The capped call transactions, into which we entered in connection with the issuance of the June 2022 convertible notes, may affect the value of the Notes and our common stock and we are subject to counterparty risk with respect to the capped call transactions.
Current wording
•The capped call transactions, into which we entered in connection with the issuance of the June 2022 convertible notes , (the "Notes") , may affect the value of the Notes and our common stock and we are subject to counterparty risk with respect to the capped call transactions.
Previous wording
•The price of our common stock may fluctuate substantially, and your investment may decline in value.
Current wording
•The price of our common stock has in the past and may in the future fluctuate substantially, and your investment may decline in value.
Previous wording
The following discussion and analysis of our financial condition and results of operations should be read together with our condensed consolidated financial statements and related notes included elsewhere in this quarterly report and the “Risk Factors” section of our Annual Report on Form 10-K for the year ended December 31, 2023 (the “2023 Annual Report”) and any updates contained herein as well as those set forth in our reports and other filings made with the SEC.
Current wording
The following discussion and analysis of our financial condition and results of operations should be read together with our condensed consolidated financial statements and related notes included elsewhere in this quarterly report and the “Risk Factors” section of our 2024 Annual Report on Form 10-K for the year ended December 31, 2024 and any updates contained herein as well as those set forth in our reports and other filings made with the SEC.
Previous wording
•Electricity Segment. In the Electricity segment, we develop, build, own and operate geothermal, solar PV and recovered energy-based power plants in the United States and geothermal power plants in other countries around the world and sell the electricity they generate. In the three months ended September 30, 2024, we derived 71.0% of our Electricity segment revenues from our operations in the United States and 29.0% from the rest of the world.
Current wording
•Electricity Segment. In the Electricity segment, we develop, build, own and operate geothermal, solar PV and recovered energy-based power plants in the United States and geothermal power plants in other countries around the world and sell the electricity they generate. In the three months ended March 31, 2025, we derived 74.5% of our Electricity segment revenues from our operations in the United States and 25.5% from the rest of the world.
Previous wording
•Product Segment. In the Product segment, we design, manufacture and sell equipment for geothermal and recovered energy-based electricity generation and provide services relating to the engineering, procurement and construction of geothermal and recovered energy-based power plants. In the three months ended September 30, 2024, we derived 8.6% of our Product segment revenues from our operations in the United States and 91.4% from the rest of the world.
Current wording
•Product Segment. In the Product segment, we design, manufacture and sell equipment for geothermal and recovered energy-based electricity generation and provide services relating to the engineering, procurement and construction of geothermal and recovered energy-based power plants. In the three months ended March 31, 2025, we derived 10.2% of our Product segment revenues from our operations in the United States and 89.8% from the rest of the world.
Previous wording
For the nine months ended September 30, 2024, 91.9% of our Electricity segment revenues were from PPAs with fixed energy rates, which are not affected by fluctuations in energy commodity prices. We have a variable price PPA in Hawaii, which provides for payments based on the local utilities’ avoided cost, which is the incremental cost that the power purchaser avoids by not having to generate such electrical energy itself or purchase it from others. In Hawaii, the prices paid for electricity pursuant to the 25 MW PPA for the Puna Complex in Hawai`i change primarily as a result of variations in the price of oil as well as other commodities. In 2019, we signed a new PPA related to Puna with fixed prices, increased capacity and extended the term until 2052. In February 2024, the HPUC approved two final amendments to the PPA that we expect will be in effect by the end of 2026.
Current wording
For the three months ended March 31, 2025, 92.7% of our Electricity segment revenues were from PPAs with fixed energy rates, which are not affected by fluctuations in energy commodity prices. We have a variable price PPA in Hawaii, which provides for payments based on the local utilities’ avoided cost, which is the incremental cost that the power purchaser avoids by not having to generate such electrical energy itself or purchase it from others. In Hawaii, the prices paid for electricity pursuant to the 25 MW PPA for the Puna Complex in Hawaii change primarily as a result of variations in the price of oil as well as other commodities. In 2024, the HPUC approved a new PPA related to Puna with fixed prices, increased capacity and an extension of the term until 2052.
Previous wording
Electricity segment revenues are also subject to seasonal variations and are affected by higher-than-average ambient temperatures, as described below under “Seasonality”.
Current wording
Electricity segment revenues are also subject to seasonal variations and are affected by higher-than-average ambient temperatures, as described below under “Seasonality”. These variations became severe in recent years due to extreme weather events and in some cases cannot be forecasted.
Previous wording
Revenues attributable to our Energy Storage segment are generated by several grid-connected BESS facilities that we own and operate that sell energy, capacity and/or ancillary services in merchant markets like PJM Interconnect, ISO New England, ERCOT and CAISO. The revenues fluctuate over time since a large portion of such revenues are generated in the merchant markets, where price volatility is inherent.
Current wording
Revenues attributable to our Energy Storage segment are generated by several grid-connected BESS facilities that we own and operate that sell energy, capacity and/or ancillary services in merchant markets like PJM Interconnect, ISO New England, ERCOT and CAISO or under tolling agreements that have fixed revenues. The revenues fluctuate over time since a large portion of such revenues are generated in the merchant markets, where price volatility is inherent. We are seeking to reduce volatility by increasing the amount of long-term tolling agreements in our portfolio.
Previous wording
In the nine months ended September 30, 2024 and 2023, 36% and 38% of our total revenues, respectively, were derived from foreign locations. In the three months ended September 30, 2024 and 2023, 39% and 41% of our total revenues, respectively, were derived from foreign locations. Our foreign operations had higher Electricity gross margins than our U.S. operations in each of those periods. A substantial portion of Electricity segment foreign revenues came from Kenya and to a lesser extent, from Honduras, Guadeloupe and Guatemala. Our operations in Kenya contributed disproportionately to gross profit and net income. The contribution to combined pre-tax income of our domestic and foreign operations within our Electricity segment and Product segment differ in a number of ways, as summarized below.
Current wording
In the three months ended March 31, 2025 and 2024, 32.4% and 31.8% of our total revenues, respectively, were derived from foreign locations. Our foreign operations had higher Electricity gross margins than our U.S. operations in each of those periods. A substantial portion of Electricity segment foreign revenues came from Kenya and to a lesser extent, from Honduras, Guadeloupe and Guatemala. Our operations in Kenya contributed disproportionately to gross profit and net income. The contribution to combined pre-tax income of our domestic and foreign operations within our Electricity segment and Product segment differ in a number of ways, as summarized below.
Previous wording
Electricity Segment. Our Electricity segment domestic revenues were approximately 73% and 70% of our total Electricity segment revenues for the nine months ended September 30, 2024 and 2023, respectively, and 71% and 69% of our total Electricity segment revenues for the three months ended September 30, 2024 and 2023. Our Electricity segment foreign revenues were approximately 27% and 30% of our total Electricity segment revenues for the nine months ended September 30, 2024 and 2023, respectively, and 29% and 31% of our total Electricity segment revenues for the three months ended September 30, 2024 and 2023. However, domestic operations have higher costs of revenues and expenses than our foreign operations. Our foreign power plants are located in lower-cost regions, like Kenya, Guatemala, Honduras and Guadeloupe, which favorably impact payroll, maintenance expenses and other items. Our power plants in foreign locations are also newer than most of our domestic power plants and therefore tend to have lower maintenance costs and higher availability factors than our domestic power plants. Consequently, in the nine months ended September 30, 2024 and 2023, our foreign operations of the segment accounted for 40% and 49% of our total gross profits, 80% and 76% of our net income (assuming the majority of corporate operating expenses and financing are recorded under our domestic jurisdiction) and 31% and 39% of our EBITDA, respectively.
Current wording
Electricity Segment. Our Electricity segment domestic revenues were approximately 74.5% and 75.2% of our total Electricity segment revenues for the three months ended March 31, 2025 and 2024, respectively. Our Electricity segment foreign revenues were approximately 25.5% and 24.8% of our total Electricity segment revenues for the three months ended March 31, 2025 and 2024, respectively. However, domestic operations have higher costs of revenues and expenses than our foreign operations. Our foreign power plants are located in lower-cost regions, like Kenya, Guatemala, Honduras and Guadeloupe, which favorably impact payroll, maintenance expenses and other items. Our power plants in foreign locations are also newer than most of our domestic power plants and therefore tend to have lower maintenance costs and higher availability factors than our domestic power plants. Consequently, in the three months ended March 31, 2025 and 2024, our foreign operations of the segment accounted for 34.8% and 33.5% of our total gross profits, 53.8% and 51.0% of our net income (assuming the majority of corporate operating expenses and financing are recorded under our domestic jurisdiction) and 26.5% and 29.3% of our EBITDA, respectively.
Previous wording
Product Segment. Our Product segment foreign revenues were approximately 94% and 93% of our total Product segment revenues for the nine months ended September 30, 2024 and 2023, respectively.
Current wording
Product Segment. Our Product segment foreign revenues were approximately 89.8% and 96.5% of our total Product segment revenues for the three months ended March 31, 2025 and 2024, respectively.
Previous wording
Energy Storage Segment. Our Energy Storage segment domestic revenues were 100% of our total Energy storage segment revenues for each of the three and nine months ended September 30, 2024 and 2023.
Current wording
Energy Storage Segment. Our Energy Storage segment domestic revenues were 100% of our total Energy storage segment revenues for each of the three months ended March 31, 2025 and 2024.
Previous wording
Electricity generation from some of our geothermal power plants is subject to seasonal variations. In the winter, our power plants produce more energy primarily attributable to the lower ambient temperature, which has a favorable impact on the energy component of our Electricity segment revenues as the prices under many of our contracts are fixed throughout the year with no time-of-use impact. The prices paid for electricity under the PPAs for the Mammoth Complex and the North Brawley power plant in California, the Raft River power plant in Idaho, the Neal Hot Springs power plant in Oregon and the Dixie Valley power plant in Nevada are higher in the months of June through September. The higher payments payable under these PPAs in the summer months partially offset the negative impact on our revenues from lower generation in the summer attributable to a higher ambient temperature. As a result, we expect the revenues and gross profit in the winter months to be higher than the revenues and gross profit in the summer months and in general we expect the first and fourth quarters to generate higher revenues than the second and third quarters.
Current wording
Electricity generation from some of our geothermal power plants is subject to seasonal variations. In the winter, our power plants produce more energy primarily attributable to the lower ambient temperature, which has a favorable impact on the energy component of our Electricity segment revenues as the prices under many of our contracts are fixed throughout the year with no time-of-use impact. The prices paid for electricity under the PPAs for the Mammoth Complex and the North Brawley power plant in California, the Raft River power plant in Idaho, the Neal Hot Springs power plant in Oregon and Dixie Valley power plant in Nevada are higher in the months of June through September. The higher payments payable under these PPAs in the summer months partially offset the negative impact on our revenues from lower generation in the summer attributable to a higher ambient temperature. As a result, we expect the revenues and gross profit in the winter months to be higher than the revenues and gross profit in the summer months and in general we expect the first and fourth quarters to generate higher revenues than the second and third quarters. In the Energy Storage segment pursuant to the Bottleneck tolling agreement, approximately 45% of the revenues are generated in the third quarter, and the rest is nearly even between the first, second and fourth quarters.
Previous wording
The principal cost of revenues attributable to our three segments are discussed in our 2023 Annual Report under “Part II - Item 7 – Management Discussion and Analysis of Financial Condition and Results of Operation”.
Current wording
The principal cost of revenues attributable to our three segments are discussed in our 2024 Annual Report under “Part II - Item 7 – “Management Discussion and Analysis of Financial Condition and Results of Operations.”
Previous wording
A comprehensive discussion of our critical accounting estimates and assumptions is included in our 2023 Annual Report under “Part II — Item 7 — Management Discussion and Analysis of Financial Condition and Results of Operation.”
Current wording
A comprehensive discussion of our critical accounting estimates and assumptions is included in our 2024 Annual Report under “Part II, Item 7 — “Management Discussion and Analysis of Financial Condition and Results of Operations.”
Previous wording
Our historical operating results in U.S. dollars and as a percentage of total revenues are presented below. A comparison of the different years described below may be of limited utility due to (i) our recent construction of power plants or enhancement of power plants; and (ii) fluctuation in revenues related to our Product segment.
Current wording
Our historical operating results in U.S. dollars and as a percentage of total revenues are presented below for each of the periods indicated.
Previous wording
Power generation in our power plants increased by 7.9% from 5,258,274 MWh in the nine months ended September 30, 2023 to 5,671,532 MWh in the nine months ended September 30, 2024.
Current wording
Power generation in our power plants decreased by 2.6% from 2,029,849 MWh in the three months ended March 31, 2024 to 1,978,078 MWh in the three months ended March 31, 2025. This decrease was primarily due to 62,602 MWh of curtailments in our U.S. projects.
Previous wording
Revenues attributable to our Product segment for the three months ended September 30, 2024 were $37.4 million, compared to $39.8 million for the three months ended September 30, 2023. This decrease of $2.5 million, or 6.2%, is primarily related to the progress in our projects and timing of when revenues are recognized during the period. During the three months ended September 30, 2024, Product revenues included projects primarily in New Zealand and Dominica, and during the three months ended September 30, 2023, Product revenues included projects primarily in New Zealand and Indonesia.
Current wording
Revenues attributable to our Product segment for the three months ended March 31, 2025 were $31.8 million, compared to $24.8 million for the three months ended March 31, 2024. This increase of $6.9 million, or 27.9%, is primarily related to the progress in our projects and timing of when revenues are recognized during the period. During the three months ended March 31, 2025, Product revenues included projects primarily in Dominica and New Zealand, and during the three months ended March 31, 2024, Product revenues included projects primarily in New Zealand and Indonesia.
Previous wording
Our total Electricity segment cost of revenues for the three months ended September 30, 2024 was 69.8% of Electricity segment revenues, compared to 68.2% for the three months ended September 30, 2023. The cost of revenues attributable to our international power plants for the three months ended September 30, 2024 was 16.9% of our total Electricity segment cost of revenues for this period compared to 16.6% for the same period in the prior year.
Current wording
Our total Electricity segment cost of revenues for the three months ended March 31, 2025 was 66.5% of Electricity segment revenues, compared to 61.0% for the three months ended March 31, 2024. The cost of revenues attributable to our international power plants for the three months ended March 31, 2025 was 17.2% of our total Electricity segment cost of revenues for this period compared to 18.1% for the same period in the prior year.
Previous wording
Total cost of revenues attributable to our Product segment for the three months ended September 30, 2024 was $30.2 million, compared to $32.4 million for the three months ended September 30, 2023, which represented a 6.9% decrease. This decrease is primarily attributable to the decrease in Product segment revenues, as discussed above. As a percentage of total Product segment revenues, total cost of revenues attributable to our Product segment for the three months ended September 30, 2024, and 2023, was 80.8% and 81.3%, respectively, which results from the different profitability of the different projects included in each period.
Current wording
Total cost of revenues attributable to our Product segment for the three months ended March 31, 2025 was $24.7 million, compared to $21.2 million for the three months ended March 31, 2024, which represented a 16.7% increase. This increase is primarily attributable to the increase in Product segment revenues, as discussed above. As a percentage of total Product segment revenues, total cost of revenues attributable to our Product segment for the three months ended March 31, 2025, and 2024, was 77.7% and 85.2%, respectively, which results from the different profitability of the different projects included in each period.
Previous wording
Research and development expenses for the three months ended September 30, 2024 were $1.8 million, compared to $1.4 million for the three months ended September 30, 2023. The increase in research and development expenses, net is primarily related to the timing of when we allocate resources to research and development projects.
Current wording
Research and development expenses for the three months ended March 31, 2025 were $2.5 million, compared to $1.6 million for the three months ended March 31, 2024. The increase in research and development expenses, net is primarily related to the timing of when we allocate resources to research and development projects.
Previous wording
Selling and marketing expenses for the three months ended September 30, 2024 were $4.2 million compared to $4.7 million for the three months ended September 30, 2023. Selling and marketing expenses for the three months ended September 30, 2024 and 2023 constituted 2.0% and 2.3% of total revenues, respectively.
Current wording
Selling and marketing expenses for the three months ended March 31, 2025 were $4.2 million compared to $5.1 million for the three months ended March 31, 2024. Selling and marketing expenses for the three months ended March 31, 2025 and 2024 constituted 1.8% and 2.3% of total revenues, respectively.
Previous wording
General and administrative expenses for the three months ended September 30, 2024 were $23.0 million compared to $14.0 million for the three months ended September 30, 2023. General and administrative expenses for the three months ended September 30, 2024 and 2023 constituted 10.8% and 6.8% of total revenues, respectively. The increase in general and administrative expenses is primarily attributable to consulting fees related to a settlement agreement with a third-party battery systems supplier of $4.8 million, insurance costs, amortization of stock-based awards, and timing of when we incur services from our vendors.
Current wording
General and administrative expenses for the three months ended March 31, 2025 were $17.9 million compared to $19.5 million for the three months ended March 31, 2024. General and administrative expenses for the three months ended March 31, 2025 and 2024 constituted 7.8% and 8.7% of total revenues, respectively. The decrease in general and administrative expenses of $1.6 million is primarily attributable to the timing of when we incur services from our vendors, as well as to $1.3 million of expenses related to the Enel purchase transaction which were included in the first quarter of 2024, compared to no such related expenses in the comparable period in 2025.
Previous wording
Other operating income for the three months ended September 30, 2024 was $6.3 million compared to none for the three months ended September 30, 2024. Other operating income represents the non-refundable portion of the recovery of damages received from a third-party battery systems supplier as part of a settlement agreement entered into in August 2024, for which contingency conditions have been met.
Current wording
Other operating income for the three months ended March 31, 2025 was $3.1 million compared to none for the three months ended March 31, 2024. Other operating income represents the non-refundable portion of the recovery of damages received from a third-party battery systems supplier as part of a settlement agreement entered into in August 2024, for which contingency conditions have been met.
Previous wording
Write-off of unsuccessful exploration activities for the three months ended September 30, 2024 was $0.1 million compared to $2.3 for the three months ended September 30, 2023. This write-off is related to exploration activities that the Company decided to no longer pursue.
Current wording
Write-off of unsuccessful exploration and storage activities for the three months ended March 31, 2025 was $0.5 million compared to none for the three months ended March 31, 2024. This write-off is related to a number of energy storage projects that the Company decided to no longer pursue.
Previous wording
Interest Income for the three months ended September 30, 2024 was $2.1 million, compared to $2.8 million for the three months ended September 30, 2023. Interest income is primarily related to interest earned on cash and cash equivalents held by the Company during the period. The decrease in interest income is primarily related to lower balances of cash and cash equivalents period over period.
Current wording
Interest Income for the three months ended March 31, 2025 was $1.3 million, compared to $1.8 million for the three months ended March 31, 2024. Interest income is primarily related to interest earned on cash and cash equivalents held by the Company during the period. The decrease in interest income is primarily related to lower balances of cash and cash equivalents period over period.
Previous wording
Interest expense, net for the three months ended September 30, 2024 was $34.8 million, compared to $25.1 million for the three months ended September 30, 2023. This increase of $9.8 million was primarily attributable to interest expense relating to loan agreements entered into subsequent to the third quarter of 2023 such as: (i) the Mizrahi 2023 Loan entered into in November 2023; (ii) the short-term commercial paper entered into in October 2023; (iii) the Hapoalim 2024 Loan and the HSBC Bank 2024 Loan entered into in January 2024; (iv) the Mammoth Senior Secured Notes entered into in March 2024; (v) the DEG 4 Loan entered into in April 2024; and (vi) the Discount 2024 Loan entered into in May 2024. This increase was partially offset by lower interest expenses on other existing loans as a result of scheduled payments.
Current wording
Interest expense, net for the three months ended March 31, 2025 was $34.5 million, compared to $31.0 million for the three months ended March 31, 2024. This increase of $3.5 million was primarily attributable to interest expense relating to loan agreements entered into during or subsequent to the first quarter of 2024 such as: (i) the Mammoth Senior Secured Notes entered into in March 2024; (ii) the DEG 4 Loan entered into in April 2024; (iii) the Discount 2024 Loan and the Discount 2024 II loans entered into in May 2024 and September 2024, respectively; (iv) the Bottleneck Loan entered into in November 2024; and (v) the Mizrahi 2025 Loan entered into in February 2025. This increase was partially offset by lower interest expenses on other existing loans as a result of scheduled payments.
Previous wording
Derivatives and foreign currency transaction gains and losses for the three months ended September 30, 2024 was a gain of $2.0 million, compared to a loss of $0.8 million for the three months ended September 30, 2023. Derivatives and foreign currency transaction gains (losses) primarily includes losses from foreign currency forward contracts which were not accounted for as hedge transactions, and the impact of changes in foreign currency exchange rate against the U.S. Dollar.
Current wording
Derivatives and foreign currency transaction gains and losses for the three months ended March 31, 2025 was a gain of $2.1 million, compared to a loss of $1.6 million for the three months ended March 31, 2024. Derivatives and foreign currency transaction gains (losses) primarily includes gain and losses from foreign currency forward contracts which were not accounted for as hedge transactions, and the impact of changes in foreign currency exchange rate against the U.S. Dollar.
Previous wording
Income attributable to the sale of tax benefits for the three months ended September 30, 2024 was $19.8 million, compared to $14.9 million for the three months ended September 30, 2023. This income primarily represents the value of production tax credits (“PTCs”) and taxable income or loss generated by certain of our power plants which are allocated to investors under tax equity transactions, and to income related to the expected sale of transferable production tax credits under the new IRA regulations. This increase of $4.8 million is primarily attributable to the Heber 1 power plant which resumed operations in May 2023, and to the Beowawe Repower power plant which commenced operations in the second quarter of 2024.
Current wording
Income attributable to the sale of tax benefits for the three months ended March 31, 2025 was $17.6 million, compared to $17.5 million for the three months ended March 31, 2024. This income primarily represents the value of production tax credits (“PTCs”) and taxable income or loss generated by certain of our power plants which are allocated to investors under tax equity transactions, as well as to income related to the expected sale of transferable PTCs under the IRA regulations.
Previous wording
Income tax benefit for the three months ended September 30, 2024 was $1.2 million compared to income tax benefit of $7.1 million for the three months ended September 30, 2023. Our effective tax rate for the three months ended September 30, 2024 and 2023, was (4.8)% and (24.1)%, respectively. The effective rate differs from the federal statutory rate of 21% primarily due to the generation of investment tax credits of $9.6 million, and $6.6 million for the three months ended September 30, 2024 and 2023, respectively, and the jurisdictional mix of earnings at differing tax rates.
Current wording
Income tax benefit for the three months ended March 31, 2025 was $3.8 million compared to income tax benefit of $0.1 million for the three months ended March 31, 2024. Our effective tax rate for the three months ended March 31, 2025 and 2024, was (10.1)% and (0.4)%, respectively. The effective rate differs from the federal statutory rate of 21% primarily due to the generation of investment tax credits of $13.9 million, and $11.5 million for the three months ended March 31, 2025 and 2024, respectively, and the jurisdictional mix of earnings at differing tax rates.
Previous wording
Equity in earnings of investees, net for the three months ended September 30, 2024 was losses of $1.6 million, compared to losses of $0.4 million for the three months ended September 30, 2023. Equity in earnings (losses) of investees, net is derived from our 12.75% share in the earnings or losses in the Sarulla Consortium ("Sarulla") and our 49% share in the earnings or losses in the Ijen geothermal project. In the second quarter of 2022, Sarulla agreed with its banks on a framework that will enable it to perform remediation works that are aimed to restore the power plants' performance. The first phase of the recovery plan included the drilling of an additional production well that was successful, and certain modifications to surface equipment that are still underway. Following the positive indications from the first phase, during the second quarter of 2024, Sarulla commenced discussions with the banks towards implementation of the additional phases. As we determined that the current situation and circumstances related to our equity method investment in Sarulla are temporary, no impairment testing was required for the period.
Current wording
Equity in earnings of investees, net for the three months ended March 31, 2025 was a loss of $0.4 million, compared to earnings of $0.8 million for the three months ended March 31, 2024. Equity in earnings (losses) of investees, net is derived from our 12.75% share in the earnings or losses in the Sarulla Consortium ("Sarulla") and our 49% share in the earnings or losses in the Ijen geothermal project. In the second quarter of 2022, Sarulla agreed with its banks on a framework that will enable it to perform remediation works that are aimed to restore the power plants' performance. The first phase of the recovery plan included the drilling of an additional production well, which was successful, and certain modifications to surface equipment are still underway. Following the positive indications from the first phase, during the second quarter of 2024, Sarulla commenced discussions with the banks towards implementation of the additional phases.
Previous wording
Net income attributable to the Company’s stockholders for the three months ended September 30, 2024 was $22.1 million, compared to $35.5 million for the three months ended September 30, 2023, which represents a decrease of $13.4 million. This decrease is attributable to a decrease of $12.0 million in net income which was affected by the explanations described above, and an increase of $1.3 million in net income attributable to noncontrolling interest in the three months ended September 30, 2024, compared to the three months ended September 30, 2023, which is primarily related to the noncontrolling share in the net results of the Puna and Guadaloupe power plants.
Current wording
Net income attributable to the Company’s stockholders for the three months ended March 31, 2025 was $40.4 million, compared to $38.6 million for the three months ended March 31, 2024, which represents an increase of $1.8 million. This increase is attributable to a increase of $0.7 million in net income which was affected by the explanations described above, and a decrease of $1.1 million in net income attributable to noncontrolling interest in the three months ended March 31, 2025, compared to the three months ended March 31, 2024.
Previous wording
As of September 30, 2024, we had access to (i) $88.1 million in cash and cash equivalents, of which $46.2 million is held by our foreign subsidiaries; and (ii) $440.2 million of unused corporate borrowing capacity under existing committed lines for credit and letters of credit with different commercial banks.
Current wording
As of March 31, 2025, we had access to (i) $112.7 million in cash and cash equivalents, of which $41.1 million is held by our foreign subsidiaries; and (ii) $364.8 million of unused corporate borrowing capacity under existing committed lines for credit and letters of credit with different commercial banks.
Previous wording
Our estimated capital needs for the remainder of 2024 include $143.0 for capital expenditures on new projects under development or construction including energy storage projects, exploration activity and maintenance capital expenditures for our existing projects. In addition, $45.5 million will be needed for long-term debt repayment.
Current wording
Our estimated capital needs for the remainder of 2025 include $419.0 million for capital expenditures on new projects under development or construction including energy storage projects, exploration activity and maintenance capital expenditures for our existing projects. In addition, $189.9 million will be needed for long-term debt repayment.
Showing the first 40 of 74 pairs. Open the source sections for the rest.
Rearranged current paragraphs (1)
Current report — wording carried from elsewhere
For the Three Months Ended March 31, 2025
Rearranged previous paragraphs (14)
Previous report — wording carried elsewhere
Total cost of revenues attributable to our Product segment for the nine months ended September 30, 2024 was $84.0 million, compared to $71.7 million for the nine months ended September 30, 2023, which represented a 17.1% increase. This increase was primarily attributable to the increase in Product segment revenues as discussed above. As a percentage of total Product segment revenues, our total cost of revenues attributable to our Product segment for the nine months ended September 30, 2024, and 2023, was 84.0% and 86.1%, respectively, which results from the different profitability of the different projects included in each period.
Previous report — wording carried elsewhere
Other operating income for the nine months ended September 30, 2024 was $6.3 million compared to none for the nine months ended September 30, 2023. Other operating income represents the non-refundable portion of the recovery of damages received from a third-party battery systems supplier as part of a settlement agreement entered into in August 2024, for which contingency conditions have been met.
Previous report — wording carried elsewhere
Interest Income for the nine months ended September 30, 2024 was $6.5 million, compared to $9.6 million for the nine months ended September 30, 2023. Interest income is primarily related to interest earned on cash and cash equivalents held by the Company during the period. The decrease in interest income is primarily related to lower balances of cash and cash equivalents period over period.
Previous report — wording carried elsewhere
Interest expense, net for the nine months ended September 30, 2024 was $99.5 million, compared to $73.1 million for the nine months ended September 30, 2023. This increase of $26.4 million is primarily due to loan agreements entered into during, or subsequent to, the first nine months of 2023 such as: (i) the Mizrahi 2023 Loan entered into in November 2023; (ii) the Hapoalim 2023 Loan entered into in February 2023; (iii) the short-term commercial paper entered into in October 2023; (iv) the Hapoalim 2024 Loan entered into in January 2024; (v) the HSBC Bank 2024 Loan entered into in January 2024; (vi) the Mammoth Senior Secured Notes entered into in March 2024; (vii) the DEG 4 Loan entered into in April 2024; and (viii) the Discount 2024 Loan entered into in May 2024. This increase was partially offset by lower interest expenses on other long-term loans as a result of regular principal payments.
Previous report — wording carried elsewhere
Derivatives and Foreign Currency Transaction Gains (Losses)
Previous report — wording carried elsewhere
Derivatives and foreign currency transaction gains (losses) for the nine months ended September 30, 2024 were a gain of $0.1 million, compared to a loss of $4.0 million for the nine months ended September 30, 2023. Derivatives and foreign currency transaction gains (losses) primarily includes losses from foreign currency forward contracts which were not accounted for as hedge transactions, and the impact of changes in the foreign currency exchange rate related to foreign locations where the Company operates in, against the U.S. Dollar.
Previous report — wording carried elsewhere
Income Attributable to Sale of Tax Benefits
Previous report — wording carried elsewhere
Other Non-Operating Income (Expense), Net
Previous report — wording carried elsewhere
Income tax benefit for the nine months ended September 30, 2024 was $4.5 million compared to income tax benefit of $2.2 million for the nine months ended September 30, 2023. Our effective tax rate for the nine months ended September 30, 2024 and 2023, was (5.4)% and (2.4)%, respectively. The effective rate differs from the federal statutory rate of 21% for the nine months ended September 30, 2024 primarily due to the generation of investment tax credits of $27.3 million, compared to $17.2 million for the nine months ended September 30, 2023, and the jurisdictional mix of earnings at differing tax rates.
Previous report — wording carried elsewhere
Equity in Earnings (losses) of Investees, Net
Previous report — wording carried elsewhere
Net Income Attributable to the Company’s Stockholders
Previous report — wording carried elsewhere
Non-Recourse and Limited-Recourse Third-Party Debt
Previous report — wording carried elsewhere
Interest rate increases for both short-term and long-term debt have increased sharply. Although our outstanding debt mostly bears fixed interest rates, as we refinance it, or borrow additional amounts, we may incur additional interest expense versus expiring loans.
Previous report — wording carried elsewhere