Management’s Discussion and AnalysisFor the three months and year ended December 31, 2024
DEVELOPMENT PROJECTS
Los Filos Expansion, Guerrero, Mexico
On October 19, 2022, the Company released the results of an updated feasibility study for a potential expansion that would increase production and extend the mine life of Los Filos by developing the Bermejal underground deposit and constructing a 10,000 tpd CIL processing plant that would process higher-grade ore and operate concurrently with the existing heap leach facilities.
While the economic and production estimates outlined in the feasibility study were predicated on construction of the CIL plant commencing in 2023, Equinox Gold has not made a construction decision at this time. Any decision to proceed with the Los Filos expansion will be made considering the operating stability in the region, the ability to successfully execute new land access agreements, receipt of an amended environmental permit, market conditions, and availability and cost of capital. Currently the Los Filos team is focused on implementation of operational improvements, advancing community agreements, and social investment projects.
Castle Mountain Expansion, California, USA
In March 2021, the Company announced the results of the feasibility study for a Phase 2 expansion at Castle Mountain. Phase 2 is expected to increase production to an average of 218,000 ounces per year for 14 years followed by leach pad residual leaching to recover additional gold. On a standalone basis, Phase 2 is expected to produce 3.2 million ounces of gold with AISC in the lower third of global gold mining costs.
The Company continues to advance optimization work on Phase 2. While Phase 2 is expected to operate within the existing approved mine boundary, the changes to previously analyzed effects, such as increased land disturbance within the mine boundary and increased water use, require modification to the Company’s approved Mine and Reclamation Plan (“Plan”) for the project. The Plan amendment application was submitted to the lead agencies (San Bernardino County and U.S. Bureau of Land Management (“BLM”)) in March 2022. The Company received the BLM’s Plan completeness determination in Q1 2024. During Q2 2024, the project lead agencies and Equinox Gold awarded the project management for permitting and environmental analysis to SWCA Environmental Consultants. Later in 2024, the project lead agencies determined they must complete an Environmental Impact Statement (“EIS”) / Environmental Impact Report (“EIR”) to analyze the potential environmental effects of the Phase 2 expansion project and in compliance with the National Environmental Policy Act (NEPA) and the California Environmental Quality Act (CEQA), respectively. The Company expects the lead agencies to publish a Notice of Intent in 2025, which commences the formal permitting review process.
A Memorandum of Understanding among the project lead agencies to prepare the joint EIS/EIR has been approved and is expected to be signed by both agencies during H1 2025. The Company anticipates the EIS/EIR stage of formal environmental analysis to occur throughout 2025 and 2026.
In August 2024, given the increasing costs associated with contract mining, crushing, and agglomeration, and increasing complexity and variability in mining low-grade historical backfill, the Company suspended mining at Castle Mountain Phase 1 for the duration of the Phase 2 permitting process. Residual leaching and gold production are expected to continue through the first half of 2025, at which point both mining and processing will be suspended until the completion of Phase 2 permitting.
Aurizona Expansion, Brazil
The Company sees potential to extend the Aurizona mine life to more than 10 years and increase annual production through development of a new underground mine and several satellite open pit deposits. The underground mine would operate concurrently with the open pits.
The Company continues to advance engineering studies for an underground mine below the Piaba pit. The Company is focused on improving accuracy for underground work areas of ventilation, access from the portals for mining layouts and ore extraction, as well as planning that is required prior to construction of a portal and underground decline. As a result of the geotechnical event in the Piaba pit during Q1 2024, the construction of a portal and underground decline was deferred to late 2025. To support the additional power requirements of the underground operations, the Company signed a contract to proceed with an upgrade of the existing 69kV power transmission line which will increase the available power to 18 MW by 2026, and also for a new power line that would provide additional power, totaling 21 MW, in January 2028.