ORMAT TECHNOLOGIES INC
For the period ended Dec 31, 2024. Filed Feb 27, 2025.
View on SEC.govAbout this filing
A company's yearly report to the SEC, with audited financial statements. It is the fullest account a company gives of its business, its finances and the risks it sees.
FY2024 · Filed Feb 27, 2025
What changed in Risk Factors?
Read the current filingPrevious report: 10-K
Period ended 2023-12-31; filed 2024-02-23.
0001437749-24-005322
Item 1A. RISK FACTORSCurrent report: 10-K
Period ended 2024-12-31; filed 2025-02-27.
0001628280-25-008531
Item 1A. RISK FACTORSRisks Related to Governmental Regulations, Laws and Taxation Risks Related to Economic and Financial ConditionsRisks Related to Force MajeureRisks Related to StockThe baseline is this issuer’s latest earlier reporting period of the same form that was filed before the current report. A previous 10-Q is a different quarter, not a year-over-year comparison. Amendments are excluded.
Compared 170 previous paragraphs and 243 current paragraphs.
106 unchanged; 50 reworded; 82 added; 14 removed; 0 previous and 5 current paragraphs rearranged.
Tables are not compared: 74 previous and 0 current tables excluded. Dates, whitespace, punctuation and numbering changes are ignored; changes to financial figures remain significant.
A changed paragraph is not evidence that risk increased or decreased. An unchanged paragraph does not establish that risk stayed the same.
Added paragraphs (82)
Current report
•regular and unexpected maintenance and replacement expenditures;
Current report
•shutdowns due to the breakdown or failure of our equipment or third-party equipment of the transmission serving utility;
Current report
•labor disputes or collective bargaining arrangements with employees that successfully unionize;
Current report
•the presence of hazardous materials on our power plant sites;
Current report
•catastrophic events such as fires, explosions, earthquakes, volcanic activity, landslides, floods, releases of hazardous materials, severe weather storms or other weather events (including weather conditions associated with climate change, or similar occurrences affecting our power plants or any of the power purchasers or other third parties providing services to our power plants, such as the 2018 volcanic eruption that occurred in Hawaii's Big Island that impacted our Puna project;
Current report
•the aging of power plants (which may reduce their availability and increase the cost of their maintenance);
Current report
•unsuccessful augmentation of batteries or other necessary equipment; and
Current report
•cyber-attacks that may interrupt the operation of our power plants.
Current report
•strengthen our core geothermal business in the U.S. as well as globally;
Current report
•establishing a strong market position in the IFM energy storage market; and
Current report
•exploring opportunities in new areas by looking for synergistic growth opportunities utilizing our core competence, market reputation as a successful company and new market opportunities focused upon environmental solutions.
Current report
•our ability to compete with the large number of other companies pursuing similar business opportunities in energy storage and solar PV power generation, many of which already have established businesses in these areas and/or have greater financial, strategic, technological or other resources than we have;
Current report
•our ability to obtain financing on terms we consider acceptable, or at all, which we may need, for example, to develop new projects, to obtain any technology, personnel, intellectual property, or to acquire one or more existing businesses as a platform for our expansion, or to fund internal research and development, for energy storage and solar PV electric power generation products and services;
Current report
•our ability to provide energy storage services that keep pace with rapidly changing technology, customer preferences, equipment costs, increasing raw materials and transportation costs, market conditions and other factors that are unknown to us now that will impact these markets;
Current report
•our ability to manage the risks and uncertainties associated with our operating storage facilities and future development of storage and geothermal projects which may operate as facilities without long-term sales agreements, including the variability of revenues and profitability of such projects;
Current report
•our ability to devote the amount of management time and other resources required to implement this plan, while continuing to grow our core geothermal and recovered energy businesses; and
Current report
•our ability to recruit appropriate employees and labor market challenges.
Current report
•opportunity costs associated with foregone alternative uses of our resources;
Current report
•various expense items that will impact our current financial results; and
Current report
•asset revaluations (for example, businesses or other assets acquired for new energy storage or solar PV power generation products or services may suffer impairment charges, as a result of rapidly changing technology, market conditions or otherwise).
Current report
Our investments in BESS facilities may also be negatively affected by the prospect of expanded trade restrictions between the governments of the U.S. and where our global supply chain partners operate. As of early 2025, the Trump administration has imposed a 10% tariff on goods imported from China. We source the components of our batteries used in our battery energy storage services primarily from China, including into the U.S. At this time, it is unclear how further expanded trade restrictions may impact our investments or our global supply chain partners’ businesses, although they pose the risk of making it more expensive to source and profitably run our battery storage services.
Current report
•Selective or inconsistent enforcement of laws or regulations, sometimes in ways that have been perceived as being motivated by political or financial considerations;
Current report
•A perceived lack of judicial and prosecutorial independence from political, social and commercial forces;
Current report
•A high degree of discretion on the part of the judiciary and governmental authorities;
Current report
•Legal and bureaucratic obstacles and corruption;
Current report
•Rapidly evolving legal systems may not always coincide with market developments.
Current report
•restrictions on currency transfer or convertibility;
Current report
•the adoption or expansion of trade restrictions, such as Turkey’s ban on trade with Israel, the occurrence or escalation of a “trade war,” or other governmental action related to tariffs or trade agreements or policies among the governments of the U.S. and countries where we operate (such as ones similar to the tariffs imposed by the U.S. in early 2025 on Canada and Mexico, which were subsequently paused, and on China, despite not being countries where we do business, could be illustrative of trade wars with countries where we do have operations and/or customers);
Current report
•political instability and civil unrest, and risk of war;
Current report
•changes in the local electricity and/or geothermal markets;
Current report
•difficulties enforcing our rights against a governmental agency because of the doctrine of sovereign immunity and foreign sovereignty over international operations;
Current report
•breach or repudiation of important contractual undertakings by governmental entities; and
Current report
•expropriation and confiscation of assets and facilities, including without adequate compensation.
Current report
Starting October 7, 2023, Israel has been engaged in a complex multifront war, fighting against large-scale, repeated attacks on civilians from Iran, Hamas in the Gaza Strip, Hezbollah in Lebanon, the Houthis in Yemen, militant terrorist groups in the West Bank and others. Although Israel has since agreed to ceasefires with each of Hamas and Hezbollah with respect to the conflicts in the Gaza Strip and Lebanon, these conflicts could re-escalate if the ceasefires are violated. Iran, which has launched missiles directly at civilian targets in Israel twice during the current conflict, and other proxy forces and terrorist organizations have threatened to escalate the fighting throughout Israel, including targeting major infrastructure facilities. Additionally, the Houthis launched repeated attacks on marine vessels in the Red Sea, an important maritime route for international trade.
Current report
Since the beginning of the current war, several hundred thousand Israeli reservists have been drafted at various points in time to perform military service, including, an average of six percent of our workforce in Israel (average of two percent of our total global workforce), the vast majority of whom work in our Product segment. Some rockets have also landed during the war near our facilities. While these disruptions have caused an increase in insurance premium costs for shipments into and out of the seaport, as of the date of this Annual Report, none of our facilities or infrastructure have been damaged nor have our supply chains been significantly impacted since the war broke out. However, a prolonged war could result in further military reserve duty call-ups as well as irregularities to our supply chain and to our ability to ship our products from Israel, which could disrupt the operations of our Product segment and potentially delay some of its growth plans in the Electricity segment, materially impacting our financial position and results of operations.
Showing the first 40 of 82 passages. Open the source sections for the rest.
Removed paragraphs (14)
Previous report
In addition, our investments in BESS facilities may be negatively affected by increases in storage costs, and the industry has recently experienced, and it is still facing, challenges in the development of new energy storage projects due to global supply chain constraints and inflation, which has caused an increase in prices and a shortage of core components of energy storage projects, specifically batteries. Our projects under development have experienced delays as a result of these challenges.
Previous report
On October 7, 2023, Hamas terrorists and members of other terrorist organizations infiltrated Israel’s southern border from the Gaza Strip and conducted a series of attacks on civilian and military targets, including widespread killings and kidnappings. They also launched extensive rocket attacks on the Israeli civilian population. Shortly following the attack, Israel declared war against Hamas, and several hundred thousand Israeli reservists were drafted to perform immediate military service.
Previous report
The intensity and duration of Israel’s current war against Hamas and military conflicts at some of its borders are difficult to predict, as are its economic implications on the Company’s business and operations in Israel and on Israel’s economy in general. As of the date of this report, approximately six percent of our workforce in Israel (approximately two percent of our total global workforce), the vast majority of whom work in our Product segment, have been called up for military service, and may be absent for an extended period. Operations in our Product segment (which accounted for approximately 16.1% of our total consolidated revenues and $48.5 million in intersegment revenues for 2023, have been, and may continue to be, disrupted by such absences, which could materially and adversely affect our business and operating results. Clashes between Israel and Hezbollah around the Lebanon-Israel border are also ongoing and may escalate in the future into a greater regional conflict.
Previous report
Continued reduction in our Products backlog may affect our ability to fully utilize our main production and manufacturing facilities and may have a materially adverse effect on our business.
Previous report
In our Product segment, reduction in our backlog may affect our ability to fully utilize our manufacturing facility and we may incur higher costs that our Product segment revenues may not be able to cover or increase capital costs to develop our own power plants, which could materially and adversely affect our business, financial condition, future results, and cash flow.
Previous report
We could be negatively impacted by regulatory and other responses to climate change.
Previous report
In addition to legal and regulatory requirements, growing stakeholder engagement with respect to sustainability matters could cause us to alter our business operations, which could require them to incur substantial expense. Any failure to comply with stakeholder requests, in particular, the ability to meet customer requirements or sustainability targets, could adversely impact the demand of our services and subject us to significant costs and liabilities and reputational risks, any of which could adversely affect our business, financial condition and results of operations.
Previous report
We may experience difficulties implementing and maintaining our new enterprise resource planning system
Previous report
We purchased and in early 2023 implemented a new enterprise resource planning (“ERP”) system. ERP implementations are complex and time-consuming. The ERP system is critical to our ability to provide important information to our management, obtain and deliver products, provide services and customer support, send invoices and track payments, fulfill contractual obligations, accurately maintain books and records, provide accurate, timely and reliable reports on our financial and operating results or otherwise file our financial statements with the SEC and operate our business. ERP implementations also require transformation of business and financial processes in order to reap the benefits of the ERP system; any such transformation involves risks inherent in the conversion to a new computer system, including loss of information and potential disruption to our normal operations. In addition, any disruptions, delays or deficiencies in the ongoing maintenance of the new ERP system could adversely affect our ability to process orders, ship products, provide services and customer support, send invoices and track payments, fulfill contractual obligations, accurately maintain books and records, provide accurate, timely and reliable reports on our financial and operating results, or otherwise file our financial statements with the SEC and operate our business. Additionally, if the new system does not operate as intended, the effectiveness of our internal control over financial reporting could be adversely affected or our ability to assess it adequately could be delayed.
Previous report
We are also involved in the ordinary course of business in regulatory investigations and other administrative proceedings, and we are exposed to the risk that we become the subject of additional regulatory investigations or administrative proceedings. For example, we are providing information to the SEC and Department of Justice ("DOJ") related to their investigation into certain claims made in a report published by a short seller regarding the Company’s compliance with anti-corruption laws and formed a Special Committee of independent directors, which worked with outside legal counsel to investigate the claims made.
Previous report
A substantial percentage of our common stock is held by stockholders whose interests may conflict with the interests of our other stockholders.
Previous report
As of December 31, 2023, ORIX holds 11.06% of our shares of common stock outstanding. Pursuant to the Governance Agreement between us and ORIX entered into in connection with this stock purchase transaction, based on its current level of ownership of our shares, ORIX has the right to designate one director to our Board for as long as ORIX and its affiliates collectively hold at least 5% of the voting power of all of our outstanding voting securities, the right to representation on certain committees of our Board as well as preemptive rights pursuant to the Governance Agreement. In addition, the Governance Agreement provides ORIX preemptive rights in the event we issue common stock or other securities that entitle the holder to vote for the election of directors. ORIX may also exercise certain registration rights pursuant to the Registration Rights Agreement, as amended, between us and ORIX.
Previous report
As a result of these rights and ORIX’s beneficial ownership of our common stock, ORIX could exert influence through its Board representation on our and our subsidiaries’ business, operations and management, including our strategic plans, or, as a significant stockholder, on matters submitted to a vote of our stockholders, including mergers, consolidations and the sale of all or substantially all of our assets. This concentration of ownership of our common stock could delay or prevent proxy contests, mergers, tender offers, or other purchases of our common stock that might otherwise give our stockholders the opportunity to realize a premium over the then-prevailing market price for our shares. If ORIX requires us to register for sale the common stock held by ORIX or ORIX otherwise sells its common stock in the public markets, the price of our common stock may decline. This concentration of ownership may also adversely affect the liquidity of our common stock.
Reworded paragraphs (50)
Previous wording
Our financial performance depends on the successful operation of our geothermal REG and Solar PV power plants. In connection with such operations, we derived 80.4% of our total revenues for the year ended December 31, 2023 from the sale of electricity. The cost of operation and maintenance and the operating performance of our geothermal power, REG and Solar PV power plants may be adversely affected by a variety of factors, including:
Current wording
Our financial performance depends on the successful operation of our geothermal, REG, and solar PV power plants. In connection with such operations, we derived 79.8% of our total revenues for the year ended December 31, 2024 from the sale of electricity and 4.3% from the sale of services in the Storage segment. The cost of operation and maintenance and the operating performance of our geothermal power, REG, and solar PV power plants and our storage facilities may be adversely affected by a variety of factors, including:
Previous wording
Our primary business involves the exploration, development, and operation of geothermal energy resources. These activities are subject to uncertainties that, in certain respects, are similar to those typically associated with oil and gas exploration, development, and exploitation, such as dry holes, uncontrolled releases, and pressure and temperature decline. Any of these uncertainties may increase our capital expenditures and our operating costs or reduce the efficiency of our power plants. We may not find geothermal resources capable of supporting a commercially viable power plant at exploration sites where we have conducted tests, acquired land rights, and drilled test wells, which would adversely affect our development of geothermal power plants and as a result would adversely affect our growth plans. Further, since the commencement of their operations, several of our power plants have experienced geothermal resource cooling, uncontrolled flow and/or reservoir pressure decline in the normal course of operations. Because geothermal reservoirs are complex geological structures, we can only estimate their geographic area and sustainable output. The viability of geothermal power plants depends on different factors directly related to the geothermal resource (such as the temperature, pressure, storage capacity, transmissivity, and recharge) as well as operational factors relating to the extraction or reinjection of geothermal fluids. Our geothermal energy power plants may also suffer an unexpected decline in the capacity of their respective geothermal wells and are exposed to a risk of geothermal reservoirs not being sufficient for sustained generation of the electrical power capacity desired over time. A recent example is the Olkaria complex, which experienced a reduction in generation due to lower performance of the wellfield. We are working to increase the capacity back. Also, in the Sarulla complex, we experienced a reduction in generation primarily due to wellfield issues at one of its power plants, as well as equipment failures which resulted in a decrease in profitability. In the second quarter of 2022, Sarulla agreed with its banks on a framework to perform remediation works that are aimed to restore the power plants' performance. The outcome of the first phase of the recovery plan is under evaluation after which we will make a decision regarding the implementation of the second phase. As we determined that the current situation and circumstances related to our equity method investment in Sarulla are temporary, no impairment testing was required for the period. For example, in the fourth quarter 2022 we recorded a non-cash impairment loss of $30.5 million related to our Brawley power plant in California that has been generating electricity that is lower than its generating capacity of 13MW due to continuous wellfield issues which resulted in higher than expected operating costs and lower than expected electricity revenues. We are following…
Excerpt shortened here; the source contains the full paragraph.
Current wording
Our primary business involves the exploration, development, and operation of geothermal energy resources. These activities are subject to uncertainties that, in certain respects, are similar to those typically associated with oil and gas exploration, development, and exploitation, such as dry holes, uncontrolled releases, and pressure and temperature decline. Any of these uncertainties may increase our capital expenditures and our operating costs or reduce the efficiency of our power plants. We may not find geothermal resources capable of supporting a commercially viable power plant at exploration sites where we have conducted tests, acquired land rights, and drilled test wells, which would adversely affect our development of geothermal power plants and as a result would adversely affect our growth plans. Further, since the commencement of their operations, several of our power plants have experienced geothermal resource cooling, uncontrolled flow and/or reservoir pressure decline in the normal course of operations. Because geothermal reservoirs are complex geological structures, we can only estimate their geographic area and sustainable output. The viability of geothermal power plants depends on different factors directly related to the geothermal resource (such as the temperature, pressure, storage capacity, transmissivity, and recharge) as well as operational factors relating to the extraction or reinjection of geothermal fluids. Our geothermal energy power plants may also suffer an unexpected decline in the capacity of their respective geothermal wells and are exposed to a risk of geothermal reservoirs not being sufficient for sustained generation of the electrical power capacity desired over time. Recent examples include the Olkaria complex, which experienced a reduction in generation due to lower performance of the well field; the Sarulla complex, where we experienced a reduction in generation primarily due to wellfield issues at one of its power plants, as well as equipment failures which resulted in a decrease in profitability; and our Brawley power plant in California, where we recorded a non-cash impairment loss due to electricity generation lower than its generating capacity due to continuous wellfield issues. For more information on the ongoing impacts of these, see “Property, Plant and Equipment and Construction-In-Process – Impairment of Long-Lived Assets.
Previous wording
Our investments in battery energy storage system (BESS) technology involves new technologies and new advanced technologies with relatively limited history with respect to reliability and performance and may not perform as expected. In addition, our investments and profitability may be negatively affected by a number of factors, including increases in storage costs, risk of fire and volatility in merchant prices.
Current wording
Our investments in battery Energy Storage System (BESS) technology involves new technologies and new advanced technologies with relatively limited history with respect to reliability and performance and may not perform as expected. In addition, our investments and profitability may be negatively affected by a number of factors, including increases in storage costs, expanded trade restrictions, risk of fire and volatility in merchant prices.
Previous wording
The revenues from our BESS facilities fluctuate over time since a large portion of such revenues are generated in the merchant markets, where price volatility is inherent. This volatility in merchant prices may adverse affect our Energy Storage profitability. Developments in alternative technologies may materially and also adversely affect demand for battery energy storage.
Current wording
The revenues from our BESS facilities fluctuate over time since a large portion of such revenues are generated in the merchant markets, where price volatility is inherent. This volatility in merchant prices may adversely effect our Energy Storage profitability. Developments in alternative technologies may materially and also adversely affect demand for battery energy storage.
Previous wording
Our BESS projects are also subject to current permitting and regulatory compliance requirements and an evolving regulatory landscape at both the federal and state level. Our projects under development have experienced delays and] may in the future experience delays as a result of these requirements. In addition, we may be required by local governmental agencies to restrict our battery charging services, and in February 2021, as a result of the power crisis in Texas, we incurred $9.1 million in losses associated with our Rabbit Hill facility because ERCOT restricted us from providing battery charging services from February 16, 2021 to February 19, 2021.
Current wording
Our BESS projects are also subject to current permitting and regulatory compliance requirements and an evolving regulatory landscape at both the federal and state level. Our projects under development have experienced delays and may in the future experience delays as a result of these requirements. In addition, we may be required by local governmental agencies to restrict our battery charging services. For example, in February 2021, as a result of the power crisis in Texas, we incurred $9.1 million in losses associated with our Rabbit Hill facility because ERCOT restricted us from providing battery charging services.
Previous wording
While we have historically been able to collect on substantially all of our receivable balances, we have received late payments and have amounts overdue from certain of our significant customers. In the Electricity segment, we are exposed to the credit and financial condition of KPLC that buys the power generated from our Olkaria III complex in Kenya. In 2023, KPLC accounted for 13.2% of our total revenues. There has been a deterioration in the collection from KPLC that became slower than in the past, and as of December 31, 2023, the amount overdue from KPLC in Kenya was $62.8 million of which $32.2 million was paid in January and February of 2024. In addition, KPLC recently requested more favorable rates on existing PPAs with it. Any change in KPLC’s financial condition or the terms of our agreement with KPLC, may adversely affect us.
Current wording
While we have historically been able to collect on substantially all of our receivable balances, we have received late payments and have amounts overdue from certain of our significant customers. In the Electricity segment, we are exposed to the credit and financial condition of KPLC that buys the power generated from our Olkaria III complex in Kenya. In 2024, KPLC accounted for 13.0% of our total revenues. There has been a deterioration in the collection from KPLC that became slower than in the past, and as of December 31, 2024, the amount overdue from KPLC in Kenya was $38.3 million of which $20.0 million was paid in January and February of 2025. In addition, KPLC recently requested more favorable rates on its existing PPAs with it. Any change in KPLC’s financial condition or the terms of our agreement with KPLC, may adversely affect us.
Previous wording
In Honduras, as of December 31, 2023, the total amount overdue from ENEE was $15.7 million of which $2.5 million was collected in January and February of 2024. In addition, due to the financial situation in Honduras, the Company may experience additional delays in collection. The Company believes it will be able to collect all past due amounts in Honduras.
Current wording
In Honduras, as of December 31, 2024, the total amount overdue from ENEE was $16.2 million of which $2.5 million was collected in January and February of 2025. In addition, due to the financial situation in Honduras, the Company may experience additional delays in collection. The Company believes it will be able to collect all past due amounts in Honduras.
Previous wording
We are also exposed to the credit and financial condition of SCPPA and its municipal utility members that account for 21.2% of our total revenues, as customers that buy the output from seven of our geothermal power plants. Because our contracts with SCPPA are long-term, we may be adversely affected if the credit quality of any of these customers were to decline or if their respective financial conditions were to deteriorate or if they are otherwise unable to perform their obligations under our long-term contracts.
Current wording
We are also exposed to the credit and financial condition of SCPPA and its municipal utility members that account for 20.6% of our total revenues in 2024, as customers that buy the output from seven of our geothermal power plants. Because our contracts with SCPPA are long-term, we may be adversely affected if the credit quality of any of these customers were to decline or if their respective financial conditions were to deteriorate or if they are otherwise unable to perform their obligations under our long-term contracts.
Previous wording
In addition, we generate a significant portion of our revenue from our two largest projects, the McGinness Hills complex in East Nevada and the Olkaria III Complex in Kenya, which together accounted for approximately 27.6% of the total generating capacity of our Electricity segment in 2023. These two facilities accounted for 25.6% of our total revenues for the year ended December 31, 2023. Any disruption to the operation of these facilities would have a disproportionately adverse effect on our revenues and on our profitability.
Current wording
In addition, we generate a significant portion of our revenue from our two largest projects, the McGinness Hills complex in east Nevada and the Olkaria III Complex in Kenya, which together accounted for approximately 23.7% of the total generating capacity of our Electricity segment in 2024. These two facilities accounted for 23.5% of our total revenues for the year ended December 31, 2024. Any disruption to the operation of these facilities would have a disproportionately adverse effect on our revenues and on our profitability. In the fourth quarter of 2024, we experienced high curtailments in the McGinness Hills complex related mostly to third party grid maintenance that impacted our revenues by approximately $3.2 million. We expect these curtailments to continue also in 2025.
Previous wording
Our global operations in countries including Kenya, Turkey, Guadeloupe, Guatemala, Honduras, Indonesia and others require us to comply with the laws and regulations of various governments and regulatory authorities outside the United States in addition to legal and regulatory requirements in the United States. Such foreign laws or regulations may not provide the same type of legal certainty, rights, or judicial processes with respect to our contractual relationships in such countries, as are afforded to our operations in the United States. A failure to receive adequate judicial or enforcement protection of our contractual rights abroad may adversely affect our ability to fulfill our contracts successfully and generate revenues therefrom. In particular, the legal and regulatory systems in the foreign jurisdictions where we operate can be characterized by one or more of the following:
Current wording
Our global operations in countries including Kenya, Turkey, Guadeloupe, Guatemala, Honduras, Indonesia and others require us to comply with the laws and regulations of various governments and regulatory authorities outside the U.S. in addition to legal and regulatory requirements in the U.S. Such foreign laws or regulations may not provide the same type of legal certainty, rights, or judicial processes with respect to our contractual relationships in such countries, as are afforded to our operations in the U.S. A failure to receive adequate judicial or enforcement protection of our contractual rights abroad may adversely affect our ability to fulfill our contracts successfully and generate revenues therefrom. In particular, the legal and regulatory systems in the foreign jurisdictions where we operate can be characterized by one or more of the following:
Previous wording
In particular, our international operations are subject to United States and foreign anti-corruption laws and regulations, such as the Foreign Corrupt Practices Act of 1977, as amended (the “FCPA”) and other local laws that prohibit corrupt payments to governmental officials or certain payments or remunerations to customers. The FCPA prohibits United States companies and their officers, directors, employees and agents acting on their behalf from corruptly offering, promising, authorizing or providing anything of value to foreign officials for the purposes of influencing official decisions or obtaining or retaining business or otherwise obtaining favorable treatment. The FCPA also requires companies to make and keep books, records and accounts that accurately and fairly reflect transactions and dispositions of assets and to maintain a system of adequate internal accounting controls. As part of our business, we deal with state-owned business enterprises, the employees and representatives of which may be considered foreign officials for purposes of the FCPA. As a result, business dealings between our employees and any such foreign official could expose us to the risk of violating anti-corruption laws even if such business practices may be customary or are not otherwise prohibited between us and a private third party. Violations of these legal requirements are punishable by criminal fines and imprisonment, civil penalties, disgorgement of profits, injunctions, debarment from government contracts as well as other remedial measures.
Current wording
In particular, our international operations are subject to U.S. and foreign anti-corruption laws and regulations, such as the Foreign Corrupt Practices Act of 1977, as amended (the “FCPA”) and other local laws that prohibit corrupt payments to governmental officials or certain payments or remunerations to customers. The FCPA prohibits U.S. companies and their officers, directors, employees and agents acting on their behalf from corruptly offering, promising, authorizing or providing anything of value to foreign officials for the purposes of influencing official decisions or obtaining or retaining business or otherwise obtaining favorable treatment. The FCPA also requires companies to make and keep books, records and accounts that accurately and fairly reflect transactions and dispositions of assets and to maintain a system of adequate internal accounting controls. As part of our business, we deal with state-owned business enterprises, the employees and representatives of which may be considered foreign officials for purposes of the FCPA. As a result, business dealings between our employees and any such foreign official could expose us to the risk of violating anti-corruption laws even if such business practices may be customary or are not otherwise prohibited between us and a private third-party. Violations of these legal requirements are punishable by criminal fines and imprisonment, civil penalties, disgorgement of profits, injunctions, debarment from government contracts as well as other remedial measures.
Previous wording
Political, economic and other conditions in the emerging economies where we operate, including Israel, may subject us to greater risk than in the developed U.S. economy, which may have a materially adverse effect on our business.
Current wording
Political, economic and other conditions in the emerging economies where we operate, may subject us to greater risk than in the developed U.S. economy, which may have a materially adverse effect on our business.
Previous wording
We have substantial operations outside of the United States, both in our Electricity segment and our Product segment. In 2023, 38.5% of our total revenues were derived from international operations, and our Electricity segment international operations had higher gross profit than our U.S. operations.*** *** In 2023 a substantial portion of international revenues came from Kenya and, to a lesser extent, from Honduras, Guatemala, Guadeloupe and other countries. Thus, disturbances to and challenges facing our foreign operations, especially in Kenya, could have impacts on our business ranging from moderate to severe. Our foreign operations and our exposure to foreign customers that are in most cases, government owned utilities, subject us to significant political, economic and financial risks, which vary by country, and include:
Current wording
We have substantial operations outside of the U.S., both in our Electricity segment and our Product segment. In 2024, 36.6% of our total revenues were derived from international operations, and our Electricity segment international operations had higher gross profit than our U.S. operations. In 2024 a substantial portion of international revenues came from Kenya and, to a lesser extent, from Honduras, Guatemala, Guadeloupe and other countries. Thus, disturbances to and challenges facing our foreign operations, especially in Kenya, could have impacts on our business ranging from moderate to severe. Our foreign operations and our exposure to foreign customers that are in most cases, government owned utilities, subject us to significant political, economic and financial risks, which vary by country, and include:
Previous wording
Electricity Segment. In 2023, the international operations of the Electricity segment accounted for 23% of our total revenues, but accounted for 44% of our gross profit, 63% of our net income and 36% of our EBITDA. A substantial portion of Electricity segment international revenues came from Kenya (which also contributed disproportionately to our gross profit and net income) and, to a lesser extent, from Guadeloupe, Guatemala and Honduras. In Kenya, any break-up or potential privatization of KPLC, the power purchaser for our power plants located in Kenya, may adversely affect our Olkaria III complex and our overall results of operations. Additionally, in Guatemala the electricity sector was partially privatized, and it is currently unclear whether further privatization will occur in the future. Such developments may affect our Amatitlan and Zunil power plants if, for example, they result in changes to the prevailing tariff regime or in the identity and creditworthiness of our power purchasers.** **
Current wording
Electricity Segment. In 2024, the international operations of the Electricity segment accounted for 22% of our total revenues, but accounted for 39% of our gross profit, 78% of our net income and 31% of our EBITDA. A substantial portion of Electricity segment international revenues came from Kenya (which also contributed disproportionately to our gross profit and net income) and, to a lesser extent, from Guadeloupe, Guatemala and Honduras. In Kenya, any break-up or potential privatization of KPLC, the power purchaser for our power plants located in Kenya, may adversely affect our Olkaria III complex and our overall results of operations.
Previous wording
*Generally.*Outbreaks of civil and political unrest and acts of terrorism have also occurred in several countries in Africa, the Middle East and Latin America, where we have operations, such as Kenya and Honduras. Kenya experienced numerous terrorist attacks in 2014 and 2015, and has experienced an upsurge in attacks in more recent years, including in early 2019, from extremist groups. Continued or escalated civil and political unrest and acts of terrorism in the countries in which we operate could result in our curtailing operations. In the event that countries in which we operate experience civil or political unrest or acts of terrorism, especially in events where such unrest leads to an unseating of the established government, our operations in such countries could be materially impaired.
Current wording
General. Outbreaks of civil and political unrest and acts of terrorism have also occurred in several countries in Africa, the Middle East and Latin America, where we have operations, such as Kenya and Honduras. Kenya experienced numerous terrorist attacks in 2014 and 2015, and has experienced an upsurge in attacks in more recent years, including in early 2019, from extremist groups. Guatemala also experienced several months of anti-government protests in 2023 and 2024. Continued or escalated civil and political unrest and acts of terrorism in the countries in which we operate could result in our curtailing operations. In the event that countries in which we operate experience civil or political unrest or acts of terrorism, especially in events where such unrest leads to an unseating of the established government, our operations in such countries could be materially impaired.
Previous wording
Conditions in and around Israel, where the majority of our senior management and our main production and manufacturing facilities are located, including the ongoing military conflicts in Israel's borders, may adversely affect our operations and may limit our ability to produce and sell our products, and support our Electricity segment.
Current wording
Conditions in and around Israel, where the majority of our senior management and our main production and manufacturing facilities are located, may adversely affect our operations and may limit our ability to produce and sell our products, and support our Electricity segment.
Previous wording
We are a multinational company and do not derive a majority of our revenues from Israel, however, the majority of our senior management and our main production and manufacturing facilities are located in Israel, approximately 26 miles from the border with the Gaza Strip. As such, political, economic and security conditions in Israel and the Middle East region directly affect our operations.
Current wording
We are a multinational company and do not derive a majority of our revenues from Israel; however, the majority of our senior management and our main production and manufacturing facilities are located in Israel, approximately 26 miles from the border with the Gaza Strip, and we receive supplies for and ship products for our Product segment via the Port of Ashdod, which is also close to the Gaza Strip and its coastline. As such, political, economic and security conditions in Israel and the Middle East region directly affect our operations.
Previous wording
Our facilities in Israel, as well as the Port of Ashdod via which we receive supplies for and ship products for our Product segment, are within the range of rockets fired from the Gaza Strip in the war and are close to Gaza’s coastline, and some rockets have landed near our facilities in the ongoing war. More recently, the Houthi movement, which controls parts of Yemen, launched a number of attacks on marine vessels in the Red Sea. The Red Sea is an important maritime route for international trade. As a result of such disruptions, we have experienced, and may continue to experience, extended lead times, delays in supplier deliveries, increased transportation and component costs, and increased costs for expedited shipments. These supply chain disruptions have resulted, and may continue to result in, delayed deliveries of several key components used in the manufacturing of our products and could impact our ability to timely deliver products to our customers in our Product Segment. This has also resulted in an increase in insurance premium costs for shipments into and out of the port. In anticipation of possible operational delays in our Product segment, we have issued force majeure notices preemptively to several customers. If, due to the current war or future similar hostilities, our facilities in Israel are damaged or their operations disrupted, or our access to the Port of Ashdod (or alternative ports at Hifa or Eilat) is impaired, our ability to perform on our contractual obligations to our Product segment customers or to continue growing that business could be impacted. The conflict could additionally result in parties with whom we have agreements involving performance in Israel claiming that they are not obligated to perform their commitments under those agreements pursuant to force majeure provisions in such agreements. In addition, new customers may be reluctant to do business with us, and existing customers may be reluctant to renew their agreements with us, due to their uncertainty regarding our ability to perform under our commitments while the war is ongoing. Limitations on travel to Israel from abroad could make it harder for us to secure contracts in the Product segment with new business partners. We have shelter-in-place and work-from-home measures, government-imposed restrictions on movement and travel and other precautions taken to address the ongoing conflict and which may temporarily disrupt our management and employees’ ability to effectively perform their daily tasks. All of the foregoing factors could negatively affect operations within our Product segment or delay growth in our Electricity segment.
Current wording
Future regional conflicts could additionally result in parties with whom we have agreements involving performance in Israel claiming that they are not obligated to perform their commitments under those agreements pursuant to force majeure provisions in such agreements. In addition, new customers may be reluctant to do business with us, and existing customers may be reluctant to renew their agreements with us, due to their uncertainty regarding our ability to perform under our commitments. Limitations on travel to Israel from abroad could make it harder for us to secure contracts in the Product segment with new business partners. We have shelter-in-place and work-from-home measures, government-imposed restrictions on movement and travel and other precautions taken to address the ongoing conflict and which have temporarily and may continue to disrupt our management and employees’ ability to effectively perform their daily tasks. All of the foregoing factors could negatively affect operations within our Product segment and/or delay growth in our Electricity segment.
Previous wording
Finally, political conditions within Israel could affect our operations or negatively impact the business environment in Israel due to reluctance of foreign investors to invest or conduct business in Israel, increased currency fluctuations, downgrades in credit rating, increased interest rates, increased volatility in securities markets, adverse impacts on the labor market, and other related changes in macroeconomic conditions. We cannot be certain whether this will adversely impact the perception of our business and our share price, or impact our business operations in Israel.
Current wording
Finally, political conditions within Israel could affect our operations or negatively impact the business environment in Israel due to the reluctance of foreign investors to invest or conduct business in Israel, increased currency fluctuations, downgrades in credit rating, increased interest rates, increased volatility in securities markets, adverse impacts on the labor market, and other related changes in macroeconomic conditions. We cannot be certain whether this will adversely impact the perception of our business and our share price, or impact our business operations in Israel.
Previous wording
Responses in various countries where we have business operations to Israel’s ongoing military conflictson*** some of itsborders or future similar conflicts may adversely affect our operations and may limit our ability to produce and sell our products.*** *** ***
Current wording
Responses in various countries where we have business operations to Israel’s ongoing military conflicts on some of its borders or future similar conflicts may adversely affect our operations and may limit our ability to produce and sell our products.
Previous wording
Although we are a multinational company and we do not derive a majority of our revenues from Israel, we have known ties to Israel through the presence of our senior management and a significant portion of our Product segment there. The perception that we are an Israeli company could impair our business and results of operations due to the international response to Israel’s ongoing military conflicts in its boarders or future similar conflicts. Our business could be substantially harmed by the interruption or curtailment of trade between Israel and its trading partners or the use of restrictive laws, policies or practices directed toward Israel or companies having operations in Israel. These restrictions may limit materially our ability to obtain raw materials from these countries or to sell our products to companies and customers in these countries. Deterioration in political relations between Israel and other countries, and/or violence from popular movements or terrorist activities in countries where we do business motivated by anti-Israel sentiment, such as Turkey or Indonesia, could impact our ability to secure new contracts, renew existing contracts and/or carry on business in those countries. Moreover, there have been increased efforts by activists to cause companies and consumers to boycott Israeli companies. Such efforts, particularly if they become more widespread, may materially and adversely impact our ability to sell our products outside of Israel.
Current wording
Although we are a multinational company and we do not derive a majority of our revenues from Israel, we have known ties to Israel through the presence of our senior management and a significant portion of our Product segment there. The perception that we are an Israeli company could impair our business and results of operations due to the international response to Israel’s ongoing military conflicts on its borders or future similar conflicts. Our business could be substantially harmed by the interruption or curtailment of trade between Israel and its trading partners or the use of restrictive laws, policies or practices directed toward Israel or companies having operations in Israel. These restrictions may limit materially our ability to obtain raw materials from these countries or to sell our products to companies and customers in these countries. Deterioration in political relations between Israel and other countries, and/or violence from popular movements or terrorist activities in countries where we do business motivated by anti-Israel sentiment, such as Turkey or Indonesia, could impact our ability to secure new contracts, renew existing contracts and/or carry on business in those countries. Moreover, there have been increased efforts by activists to cause companies and consumers to boycott Israeli companies. Such efforts, particularly if they become more widespread, may materially and adversely impact our ability to sell our products outside of Israel.
Previous wording
Most of our geothermal resource leases are for a fixed primary term, and then continue for so long as geothermal resources are extracted in “commercial quantities” or pursuant to other terms of extension. The land covered by some of our leases (approximately 200,000 acres in the U.S. and approximately 15,000 acres elsewhere) is undeveloped and has not yet produced geothermal resources in commercial quantities. Leases that cover land which remains undeveloped and does not produce, or does not continue to produce, geothermal resources in commercial quantities and leases that we allow to expire, may terminate. In the event that a lease is terminated and we determine that we will need that lease once the applicable power plant is operating, we would need to enter into one or more new leases with the owner(s) of the premises that are the subject of the terminated lease(s) in order to develop geothermal resources from, or inject geothermal resources into, such premises or secure rights to alternate geothermal resources or lands suitable for injection. We may not be able to do this or may not be able to do so without incurring increased costs, which could materially and adversely affect our business, financial condition, future results and cash flow.
Current wording
Most of our geothermal resource leases are for a fixed primary term, and then continue for so long as geothermal resources are extracted in “commercial quantities” or pursuant to other terms of extension. The land covered by some of our leases is undeveloped and has not yet produced geothermal resources in commercial quantities. Leases that cover land which remains undeveloped and does not produce, or does not continue to produce, geothermal resources in commercial quantities and leases that we allow to expire, may terminate. In the event that a lease is terminated and we determine that we will need that lease once the applicable power plant is operating, we would need to enter into one or more new leases with the owner(s) of the premises that are the subject of the terminated lease(s) in order to develop geothermal resources from, or inject geothermal resources into, such premises or secure rights to alternate geothermal resources or lands suitable for injection. We may not be able to do this or may not be able to do so without incurring increased costs, which could materially and adversely affect our business, financial condition, future results and cash flow.
Previous wording
We are in the process of developing and constructing a number of new power plants. Our success in developing a project is contingent upon, among other things, negotiation of satisfactory engineering and construction agreements and obtaining PPAs and transmission services agreements, receipt of required governmental permits (including environmental permits), obtaining adequate financing, and the timely implementation and satisfactory completion of field development, testing and power plant construction and commissioning. We may be unsuccessful in accomplishing any of these matters or doing so on a timely basis such in cases where we have to handle legal proceedings with respect to environmental permits. Although we may attempt to minimize the financial risks attributable to the development of a project by securing a favorable PPA and applicable transmission services agreements, obtaining all required governmental permits and approvals and arranging, in certain cases, adequate financing prior to the commencement of construction, the development of a power project may require us to incur significant expenses for preliminary engineering, permitting and legal and other expenses before we can determine whether a project is feasible, economically attractive or capable of being financed.
Current wording
We are routinely in the process of developing and constructing new power plants in the ordinary course of business. Our success in developing a project is contingent upon, among other things, negotiation of satisfactory engineering and construction agreements and obtaining PPAs and transmission services agreements, receipt of required governmental permits (including environmental permits), obtaining adequate financing, and the timely implementation and satisfactory completion of field development, testing and power plant construction and commissioning. We may be unsuccessful in accomplishing any of these matters or doing so on a timely basis such in cases where we have to handle legal proceedings with respect to environmental permits. Although we may attempt to minimize the financial risks attributable to the development of a project by securing a favorable PPA and applicable transmission services agreements, obtaining all required governmental permits and approvals and arranging, in certain cases, adequate financing prior to the commencement of construction, the development of a power project may require us to incur significant expenses for preliminary engineering, permitting and legal and other expenses before we can determine whether a project is feasible, economically attractive or capable of being financed.
Previous wording
Currently, we have geothermal projects and prospects under exploration, development or construction in the United States, as well as in Indonesia, Ethiopia, Guadeloupe and Guatemala, and we intend to pursue the development of other new plants. In addition, our current growth plans include enhancement and repowering of a number of our operating facilities, including the Zunil, Beowawe, Ijen and Puna power plants and involve replacement of old equipment and optimization of the geothermal field, including repair and enhancement of existing wells and drilling of new wells. Our completion of these facilities’ development and/or enhancement is subject to substantial risks, including:
Current wording
Currently, we have geothermal projects and prospects under exploration, development or construction in the U.S., as well as in Indonesia, Guadeloupe, Guatemala, New Zealand and Dominica and we intend to pursue the development of other new plants. In addition, our current growth plans include enhancement and repowering of a number of our operating facilities, including the Zunil, Beowawe, Ijen and Puna power plants and involve replacement of old equipment and optimization of the geothermal field, including repair and enhancement of existing wells and drilling of new wells. Our completion of these facilities’ development and/or enhancement is subject to substantial risks, including:
Previous wording
Our operations could be adversely impacted by climate change.
Current wording
Our operations could be adversely impacted by climate change and other extreme weather events.
Previous wording
We are susceptible to losses and interruptions caused by extreme weather conditions such as droughts, hurricanes, tsunamis, floods, wildfires, and water or other natural resource shortages, occurrences of which may increase in frequency and severity as a result of climate change. Climate change may also produce general changes in weather or other environmental conditions, including temperature or precipitation levels, and thus may impact consumer demand for electricity. Daily and seasonal fluctuations in temperature generally have a more significant impact on the generating capacity of geothermal energy plants than conventional power plants. Some of our power plants experience reduced generation in warm periods due to the lower heat differential between geothermal fluid and the ambient surroundings. While we generally account for the projected impact seasonal fluctuations in temperature based on our historic experience, the impact of climate change on traditional weather patterns has become more pronounced. This has reduced the certainty of our modelling efforts. For example, in 2019, we experienced prolonged elevated temperatures in the Western United States which impacted generating capacity at our facilities and adversely impacted our revenues in the fourth quarter of the year. To the extent weather conditions continue to be impacted by climate change, the generating capacity of certain of our facilities may be adversely impacted in a manner that we could not predict which may in turn adversely impact our results of operations. In addition, the potential physical effects of climate change, such as increased frequency and severity of storms, floods, and other climatic events, could disrupt our operations and cause us to incur significant costs to prepare for or respond to these effects. If we experience physical damage to our equipment and infrastructure due to climate-related natural disasters, it could lead to the suspension of our operations, additional costs to restore service and repair facilities, and delays in power generation resulting in lost revenue and potential exposure to legal claims. Such events could also impact our ability to obtain insurance coverage and we may experience rising costs of insurance coverage resulting from any damages to our assets, which could have an impact on our profitability.
Current wording
We are susceptible to losses and interruptions caused by extreme weather conditions such as droughts, hurricanes, tsunamis, floods, wildfires, and water or other natural resource shortages, occurrences of which may increase in frequency and severity as a result of climate change. Climate change may also produce general changes in weather or other environmental conditions, including temperature or precipitation levels, and thus may impact consumer demand for electricity. Daily and seasonal fluctuations in temperature generally have a more significant impact on the generating capacity of geothermal energy plants than conventional power plants. Some of our power plants experience reduced generation in warm periods due to the lower heat differential between geothermal fluid and the ambient surroundings. While we generally account for the projected impact seasonal fluctuations in temperature based on our historic experience, the impact of climate change on traditional weather patterns has become more pronounced. This has reduced the certainty of our modelling efforts. For example, at the end of 2024, following wildfires in California, we experienced delays in permitting for our storage facilities as well as a reduction in demand for electricity creating overload on the grid and resulting in unexpected curtailments at some of our power plants, which in turn adversely impacted our revenues in the fourth quarter of 2024. To the extent weather conditions continue to be impacted by climate change, the generating capacity of certain of our facilities may be adversely impacted in a manner that we could not predict which may in turn adversely impact our results of operations. In addition, the potential physical effects of climate change, such as increased frequency and severity of storms, floods, and other climatic events, could disrupt our operations and cause us to incur significant costs to prepare for or respond to these effects. If we experience physical damage to our equipment and infrastructure due to climate-related natural disasters, it could lead to the suspension of our operations, additional costs to restore service and repair facilities, and delays in power generation resulting in lost revenue and potential exposure to legal claims. Such events could also impact our ability to obtain insurance coverage and we may experience rising costs of insurance coverage resulting from any damages to our assets, which could have an impact on our profitability.
Previous wording
Climate change could also affect the availability of a secure and economical supply of water, whether due to an increase in water restrictions, an impact on our ability to obtain water permits, or otherwise. Water is essential for the continued operation of certain of our power plants that use water cooling systems. Ormat monitors water risk carefully. If it is determined that a water supply risk exists that could impact projected generation levels at any plant, risk mitigation efforts are identified and evaluated for implementation.
Current wording
Climate change could also affect the availability of a secure and economical supply of water, whether due to an increase in water restrictions, an impact on our ability to obtain water permits, or otherwise. Water is essential for the continued operation of certain of our power plants that use water cooling systems. We monitor water risk carefully. If it is determined that a water supply risk exists that could impact projected generation levels at any plant, risk mitigation efforts are identified and evaluated for implementation.
Previous wording
As a renewable energy solution provider, we are motivated to identify our opportunities and risks with respect to climate change and take efforts to reduce our GHG emissions and improve our energy efficiency. While we generally view this as an opportunity, uncertainty regarding nascent regulation in this area could also adversely affect us. In the United States, where we have a significant portion of our operations, no comprehensive climate change legislation has been implemented federally. The U.S. Environmental Protection Agency (the “EPA”) has adopted rules that, among other things, establish construction and operating permit reviews for GHG emissions from certain large stationary sources, require the monitoring and reporting of GHG emissions from certain sources and implement standards directing the reduction of methane from certain facilities in the oil and gas sector. Additionally, various states have adopted or are considering adopting legislation and regulation focused on GHG cap-and-trade programs, carbon taxes, reporting and tracking programs and emissions limits. Uncertainty associated with these regulations, our inability to meet the demands of these regulations or our failure to predict accurately the impact of our response to these regulations could adversely affect our business and prospects. We could also face an increase in competition as a result of the energy transition, as new entrants of disruptive technologies and/or competitors, including in the solar, wind, and storage sectors, could adversely impact our ability to renew existing PPAs or sign new contracts.
Current wording
As a renewable energy solution provider, we are motivated to identify our opportunities and risks with respect to climate change and take efforts to reduce our GHG emissions and improve our energy efficiency. While we generally view this as an opportunity, uncertainty regarding recent regulation or reduction in incentives in this area could also adversely affect us. In the U.S., where we have a significant portion of our operations, no comprehensive climate change legislation has been implemented federally.
Previous wording
In addition, the SEC proposed rules in March 2022 that would require public companies to include extensive climate-related disclosures in their SEC filings. Among other things, the proposed SEC rules, if adopted as written, would mandate disclosures on (i) GHG emissions, including Scope 3 emissions if material or part of a company's emissions goal, (ii) financial impact and expenditure metrics relating to severe weather and climate change and (iii) a company's use of scenario analysis and climate targets. Although the SEC has not finalized these rules, we would expect to incur substantial additional compliance costs to the extent these or similar rules are adopted. Such compliance costs could in turn adversely effect on our business or results of operations. We publish an annual Sustainability Report, which describes, among other things, the measurement of our greenhouse gas emissions and our efforts to reduce emissions. In addition, our Sustainability Report provides highlights of how we are supporting our workforce, including our efforts to promote diversity, equity, inclusion and belonging. Our disclosures on these matters, or a failure to meet evolving stakeholder expectations for ESG practices and reporting, may potentially harm our reputation and customer relationships.
Current wording
In addition, the SEC proposed rules in 2022 that would require public companies to include extensive climate-related disclosures in their SEC filings. While these rules are currently stayed and may eventually not go into effect, we would expect to incur substantial additional compliance costs to the extent these or similar rules are adopted. Such compliance costs could in turn adversely effect our business or results of operations. We publish an annual Sustainability Report, which describes, among other things, the measurement of our greenhouse gas emissions and our efforts to reduce emissions. Our disclosures on these matters, a failure to meet evolving stakeholder expectations for ESG practices and reporting, or expenses required to carry on sustainability reporting and/or meet customer requirements or sustainability targets, may potentially harm our customer relationships and/or subject us to significant costs and liabilities and reputational risks, any of which could adversely affect our business, financial condition and results of operations.
Previous wording
A basic premise of our business model is that generating baseload power at geothermal power plants produces electricity at a competitive price. However, traditional coal-fired systems and gas-fired systems may under certain economic conditions produce electricity at lower average prices than our geothermal plants. In addition, there are other technologies that can produce electricity such as hydroelectric systems, fuel cells, microturbines, wind turbines, energy storage systems and solar PV systems. Some of these alternative technologies currently produce electricity at higher average prices than our geothermal plants while others produce electricity at lower average prices. It is possible that technological advances and economies of scale will further reduce the cost of alternate methods of power generation. It is also possible that energy technologies will compete with our basic premise of a firm (non-intermittent) renewable baseload power source by combining renewable technologies with energy storage to provide an alternative to firm baseload energy. If this were to happen, the competitive advantage of our power plants may be significantly impaired and will cause reduction and/or inability to sign new PPAs for our Electricity segment and new supply and EPC contracts for our Products segment.
Current wording
A basic premise of our business model is that generating baseload power at geothermal power plants produces electricity at a competitive price. However, traditional coal-fired systems and gas-fired systems may under certain economic conditions produce electricity at lower average prices than our geothermal plants. In addition, there are other technologies that can produce electricity such as hydroelectric systems, fuel cells, microturbines, wind turbines, energy storage systems and solar PV systems. Some of these alternative technologies currently produce electricity at higher average prices than our geothermal plants while others produce electricity at lower average prices. It is possible that technological advances and economies of scale will further reduce the cost of alternate methods of power generation. It is also possible that intermittent energy technologies will compete with our basic premise of a firm (non-intermittent) renewable baseload power source by combining renewable technologies with energy storage to provide an alternative to firm baseload energy. If this were to happen, the competitive advantage of our power plants may be significantly impaired and will cause reduction and/or inability to sign new PPAs for our Electricity segment and new supply and EPC contracts for our Products segment.
Previous wording
Even if we adequately protect our intellectual property rights, litigation may be necessary to enforce these rights, which could result in substantial costs to us and a substantial diversion of management attention. Furthermore, attempts to enforce our intellectual property rights against third parties could also provoke these third parties to assert their own intellectual property or other rights against us, or result in a holding that invalidates or narrows the scope of our rights, in whole or in part. Our success and ability to compete also depends in part on our ability to operate without infringing, misappropriating or otherwise violating the intellectual or proprietary rights of third parties. While we have attempted to ensure that our technology and the operation of our business does not infringe other parties' patents and other intellectual property or proprietary rights, our competitors or other third parties may assert that certain aspects of our business or technology infringe upon, misappropriate or otherwise violate their intellectual property or proprietary rights. In addition, former employers of our current, former or future employees may assert claims that such employees have improperly disclosed to us the confidential or proprietary information of these former employers. Infringement, misappropriation or other intellectual property violation claims, regardless of merit or ultimate outcome, can be expensive, hard to predict and time-consuming and can divert management’s attention from our core business. An assertion of an intellectual property infringement, misappropriation or other violation claim against us may result in adverse judgments, settlements on unfavorable terms or cause us to pay significant money damages, lose significant revenues, be prohibited from using the relevant technology or other intellectual property, or incur significant license, royalty or technology development expenses. Future litigation may also involve non-practicing entities or other intellectual property owners who have no relevant product offerings or revenue and against whom our own intellectual property may therefore provide little or no deterrence or protection.
Current wording
Even if we adequately protect our intellectual property rights, litigation may be necessary to enforce these rights, which could result in substantial costs to us and a substantial diversion of management attention. Furthermore, attempts to enforce our intellectual property rights against third parties could also provoke these third parties to assert their own intellectual property or other rights against us, or result in a holding that invalidates or narrows the scope of our rights, in whole or in part. Our success and ability to compete also depends in part on our ability to operate without infringing, misappropriating or otherwise violating the intellectual or proprietary rights of third parties. While we have attempted to ensure that our technology and the operation of our business does not infringe on other parties' patents and other intellectual property or proprietary rights, our competitors or other third parties may assert that certain aspects of our business or technology infringe upon, misappropriate or otherwise violate their intellectual property or proprietary rights. In addition, former employers of our current, former or future employees may assert claims that such employees have improperly disclosed to us the confidential or proprietary information of these former employers. Infringement, misappropriation or other intellectual property violation claims, regardless of merit or ultimate outcome, can be expensive, hard to predict and time-consuming and can divert management’s attention from our core business. An assertion of an intellectual property infringement, misappropriation or other violation claim against us may result in adverse judgments, settlements on unfavorable terms or cause us to pay significant money damages, lose significant revenues, be prohibited from using the relevant technology or other intellectual property, or incur significant license, royalty or technology development expenses. Future litigation may also involve non-practicing entities or other intellectual property owners who have no relevant product offerings or revenue and against whom our own intellectual property may therefore provide little or no deterrence or protection.
Previous wording
In addition, we are subject to various legislation, regulations, directives and guidelines from federal, state, local and foreign agencies, such as FERC, that are intended to strengthen cybersecurity measures required for information and operational technology and critical energy infrastructure and that apply to the collection, use, retention, protection, disclosure, transfer and other processing of personal information. In California, for example, the California Consumer Privacy Act (the “CCPA”) imposes obligations on businesses to be transparent with their data privacy practices and vests consumers with rights to access and delete the personal information held by businesses. These requirements will become even more robust under the California Privacy Rights Act (the “CPRA”) which amends the CCPA to, among other things, extend consumer rights and business obligations to employees, and will become effective on January 1, 2023. These cybersecurity, data protection and privacy law regimes continue to evolve and may result in ever-increasing public scrutiny and escalating levels of capital expenditures, regulatory enforcement, sanctions and fines and increased costs for compliance. We have instituted security measures and safeguards to protect our operational systems and information technology assets, including certain safeguards required by FERC. Despite our implementation of security measures and safeguards, any failure to comply with FERC or any of these legal requirements could result in enforcement action against us, including fines, imprisonment of company officials and public censure, any of which could harm our reputation and have a material adverse effect on our financial condition, results of operations, liquidity, and cash flows.
Current wording
In addition, we are subject to various legislation, regulations, directives and guidelines from federal, state, local and foreign agencies, such as FERC, that are intended to strengthen cybersecurity measures required for information and operational technology and critical energy infrastructure and that apply to the collection, use, retention, protection, disclosure, transfer and other processing of personal information. In California, there are obligations on businesses to be transparent with their data privacy practices and vests consumers and employees with rights to access and delete the personal information held by businesses. These cybersecurity, data protection and privacy law regimes continue to evolve and may result in ever-increasing public scrutiny and escalating levels of capital expenditures, regulatory enforcement, sanctions and fines and increased costs for compliance. We have instituted security measures and safeguards to protect our operational systems and information technology assets, including certain safeguards required by FERC. Despite our implementation of security measures and safeguards, any failure to comply with FERC or any of these legal requirements could result in enforcement action against us, including fines, imprisonment of company officials and public censure, any of which could harm our reputation and have a material adverse effect on our financial condition, results of operations, liquidity, and cash flows.
Previous wording
Any changes to applicable laws and regulations or interpretations of those laws and regulations could significantly increase the regulatory-related compliance, tax and other expenses incurred by the power plants and could significantly reduce or entirely eliminate the revenues generated by one or more of the power plants, which in turn would reduce our net income and could materially and adversely affect our business, financial condition, future results and cash flow.
Current wording
Any changes to applicable laws and regulations or interpretations of those laws and regulations could significantly increase the regulatory-related compliance, tax and other expenses incurred by the power plants and could significantly reduce or entirely eliminate the revenues generated by one or more of the power plants, which in turn would reduce our net income and could materially and adversely affect our business, financial condition, future results and cash flow. For more information, see “Risks Related to the Company’s Business and Operation—We could be impacted by regulatory and other responses to climate change.”
Previous wording
If a domestic power plant were to lose its Qualifying Facility status, it would become subject to full regulation as a public utility under the FPA, and the rates charged by such power plant pursuant to its PPAs may be subject to the review and approval of FERC. FERC, upon such review, may determine that the rates currently set forth in such PPAs are not appropriate and may set rates that are lower than the rates currently charged. In addition, FERC may require that the affected domestic power plant refund amounts previously paid by the relevant power purchaser to such power plant. Even if a power plant does not lose its Qualifying Facility status, pursuant to regulations issued by FERC for Qualifying Facility power plants above 20 MW, if a power plant’s PPA is terminated or otherwise expires, and the subsequent sales are not made pursuant to a state’s implementation of PURPA, that power plant will become subject to FERC’s ratemaking jurisdiction under the FPA. Moreover, a loss of Qualifying Facility status also could permit the power purchaser, pursuant to the terms of the particular PPA, to cease taking and paying for electricity from the relevant power plant or, consistent with FERC precedent, to seek refunds of past amounts paid. This could cause the loss of some or all of our revenues payable pursuant to the related PPAs, result in significant liability for refunds of past amounts paid, or otherwise impair the value of our power plants. If a power purchaser were to cease taking and paying for electricity or seek to obtain refunds of past amounts paid, there can be no assurance that the costs incurred in connection with the power plant could be recovered through sales to other purchasers or that we would have sufficient funds to make such payments. In addition, the loss of Qualifying Facility status would be an event of default under the financing arrangements currently in place for some of our power plants, which would enable the lenders to exercise their remedies and enforce the liens on the relevant power plant.
Current wording
If a domestic power plant were to lose its Qualifying Facility status, it would become subject to full regulation as a public utility under the FPA, and the rates charged by such power plant pursuant to its PPAs may be subject to the review and approval of FERC. FERC, upon such review, may determine that the rates currently set forth in such PPAs are not appropriate and may set rates that are lower than the rates currently charged. In addition, FERC may require that the affected domestic power plant refund amounts previously paid by the relevant power purchaser to such power plant. Even if a power plant does not lose its Qualifying Facility status, pursuant to regulations issued by FERC for Qualifying Facility power plants above 20MW, if a power plant’s PPA is terminated or otherwise expires, and the subsequent sales are not made pursuant to a state’s implementation of PURPA, that power plant will become subject to FERC’s ratemaking jurisdiction under the FPA. Moreover, a loss of Qualifying Facility status also could permit the power purchaser, pursuant to the terms of the particular PPA, to cease taking and paying for electricity from the relevant power plant or, consistent with FERC precedent, to seek refunds of past amounts paid. This could cause the loss of some or all of our revenues payable pursuant to the related PPAs, result in significant liability for refunds of past amounts paid, or otherwise impair the value of our power plants. If a power purchaser were to cease taking and paying for electricity or seek to obtain refunds of past amounts paid, there can be no assurance that the costs incurred in connection with the power plant could be recovered through sales to other purchasers or that we would have sufficient funds to make such payments. In addition, the loss of Qualifying Facility status would be an event of default under the financing arrangements currently in place for some of our power plants, which would enable the lenders to exercise their remedies and enforce the liens on the relevant power plant.
Previous wording
Pursuant to the Energy Policy Act of 2005, FERC also has the authority to prospectively lift the mandatory obligation of a utility under PURPA to offer to purchase the electricity from a Qualifying Facility if the utility operates in a workably competitive market. Our existing PPAs between a Qualifying Facility and a utility are not affected. If, in addition to the California utilities’ waiver of the mandatory purchase obligation for QF projects that exceed 20 MW described in the risk factor above, the utilities in the other regions in which our domestic power plants operate were to be relieved of the mandatory purchase obligation, they would not be required to purchase energy from the power plant in the region under Federal law upon termination of the existing PPA or with respect to new power plants, which could materially and adversely affect our business, financial condition, future results and cash flow. Moreover, FERC has the authority to modify its regulations relating to the utility’s mandatory purchase obligation under PURPA, which could result in the reduction in the purchase obligation of California and other utilities to a level below 5 MW, or the elimination of the purchase obligation. If that were to occur it could materially and adversely affect our business, financial condition, future results and cash flow.
Current wording
Pursuant to the Energy Policy Act of 2005, FERC also has the authority to prospectively lift the mandatory obligation of a utility under PURPA to offer to purchase the electricity from a Qualifying Facility if the utility operates in a workably competitive market. Our existing PPAs between a QF and a utility are not affected. If, in addition to the California utilities’ waiver of the mandatory purchase obligation for QF projects that exceed 20MW described in the risk factor above, the utilities in the other regions in which our domestic power plants operate were to be relieved of the mandatory purchase obligation, they would not be required to purchase energy from the power plant in the region under Federal law upon termination of the existing PPA or with respect to new power plants, which could materially and adversely affect our business, financial condition, future results and cash flow. Moreover, FERC has the authority to modify its regulations relating to the utility’s mandatory purchase obligation under PURPA, which could result in the reduction in the purchase obligation of California and other utilities to a level below 5MW, or the elimination of the purchase obligation. If that were to occur it could materially and adversely affect our business, financial condition, future results and cash flow.
Previous wording
Construction and operation of our geothermal power plants and recovered energy-based power plants has benefited, and may benefit in the future, from public policies and government incentives that support renewable energy and enhance the economic feasibility of these projects in regions and countries where we operate. On August 16, 2022, the US President signed into law the Inflation Reduction Act (IRA), which contains tax incentives and other provisions that incentivize investment, development and deployment of renewable energy sources and technologies. We expect that the construction and operations of our geothermal power plants, recovered energy-based power plants, battery energy storage systems and solar PV will benefit in the future from the IRA and enhance the economic feasibility of projects in the United States. There are additional public policy and government incentives that currently benefit and that we expect will benefit the Company in the future in countries outside of the United States as well as States within the United States. For example, these projects may generate PTCs and ITCs that we may use to offset our tax liabilities or that we may monetize.The incentives in these jurisdictions include accelerated depreciation tax benefits, rebates, mandated feed-in tariffs and other similar incentives.
Current wording
Construction and operation of our geothermal power plants and recovered energy-based power plants has benefited, and may benefit in the future, from public policies and government incentives that support energy production (including, in certain cases, renewable energy and enhance the economic feasibility of these projects in regions and countries where we operate.
Previous wording
The availability and continuation of these public policies and government incentives have a significant effect on the economics and viability of our development program and continued construction of new geothermal, recovered energy-based, solar PV facilities and, recently, energy storage projects. Any changes to such public policies, or any reduction in or elimination or expiration of such government incentives, could affect us in different ways. For example, any reduction in, termination or expiration of renewable portfolio standards may result in less demand for generation from our geothermal and recovered energy-based, power plants. Any reductions in, termination or expiration of other government incentives could reduce the economic viability of, and cause us to reduce, the construction of new geothermal, recovered energy-based, solar PV or any other power plants. Policies supporting or deregulating the exploration, production and use of fossil fuels may create regulatory uncertainty in the renewable energy industry. Similarly, any such changes that affect the geothermal energy industry in a manner that is different from other sources of renewable energy, such as wind or solar, may put us at a competitive disadvantage compared to businesses engaged in the development, construction and operation of renewable power projects using such other resources. In addition, although we may have the legal ability to monetize ITCs and PTCs, our ability to do so is subject to market prices and demand, which may be lower than we anticipate.Any of the foregoing outcomes could have a material adverse effect on our business, financial condition, future results, and cash flows.
Current wording
The availability and continuation of these public policies and government incentives have a significant effect on the economics and viability of our development program and continued construction of new geothermal, recovered energy-based, solar PV facilities and, recently, energy storage projects. Changes to such public policies, or any reduction in or elimination or expiration of such government incentives, could affect us in different ways. For example, any reduction in, termination or expiration of renewable portfolio standards may result in less demand for generation from our geothermal and recovered energy-based power plants. Any reductions in, termination or expiration of other government incentives could reduce the economic viability of, and cause us to reduce, the construction of new geothermal, recovered energy-based, solar PV or any other power plants. Policies supporting or deregulating the exploration, production and use of fossil fuels may create regulatory uncertainty in the renewable energy industry.
Previous wording
We may also be subject to litigation seeking to rescind or delay our receipt of environmental permits and governmental approvals. For example, a lawsuit was filed by the Center for Biological Diversity and Fallon Paiute-Shoshone Tribe in 2021 that sought to revoke the BLM’s approval of the development of our Dixie Meadows geothermal power plant in Nevada. While the proceeding has been administratively closed without prejudice to reopening upon a motion by either party, there can be no assurance that the Company will be able to obtain the necessary approvals to develop Dixie Meadows as originally intended, or at all. See also, “Litigation, legal proceedings, regulatory investigations or other administrative proceedings could expose us to significant liabilities and reputational damage that could have a material adverse effect on us” for additional information.
Current wording
We may also be subject to litigation seeking to rescind or delay our receipt of environmental permits and governmental approvals. For example, a lawsuit was filed by the Center for Biological Diversity and the Fallon Paiute-Shoshone Tribe in 2021 that sought to revoke the BLM’s approval of the development of our Dixie Meadows geothermal power plant in Nevada, which was later closed without prejudice. There can be no assurance that the Company will be able to obtain the necessary approvals to develop Dixie Meadows as originally intended, or at all.
Previous wording
Our power plants are subject to numerous domestic and foreign federal, regional, state and local statutory and regulatory standards relating to the generation, handling, transportation, use, storage, treatment and disposal of hazardous substances. We use butane, pentane, industrial lubricants, and other substances at our power plants which are or could become classified as hazardous substances. If any hazardous substances are found to have been released into the environment at or by the power plants in concentrations that exceed regulatory limits, we could become liable for the investigation and removal of those substances, regardless of their source and time of release. If we fail to comply with these laws, ordinances or regulations (or any change thereto), we could be subject to civil or criminal liability, the imposition of liens or fines, and cessation of operations, large expenditures to bring the power plants into compliance or other sanctions. Furthermore, under certain federal and states laws in the United States, we can be held liable for the cleanup of releases of hazardous substances at any of our current or former facilities or at any other locations where we arranged for disposal of those substances, even if we did not cause the release at that location or if the release complied with applicable law at the time it occurred. Liability under these laws can be joint and several. The cost of any remediation activities in connection with a spill or other release of such substances could be significant and could expose us to significant liability.
Current wording
Our power plants are subject to numerous domestic and foreign federal, regional, state and local statutory and regulatory standards relating to the generation, handling, transportation, use, storage, treatment and disposal of hazardous substances. We use butane, pentane, industrial lubricants, and other substances at our power plants which are or could become classified as hazardous substances. If any hazardous substances are found to have been released into the environment at or by the power plants in concentrations that exceed regulatory limits, we could become liable for the investigation and removal of those substances, regardless of their source and time of release. If we fail to comply with these laws, ordinances or regulations (or any change thereto), we could be subject to civil or criminal liability, the imposition of liens or fines, and cessation of operations, large expenditures to bring the power plants into compliance or other sanctions. Furthermore, under certain federal and states laws in the U.S., we can be held liable for the cleanup of releases of hazardous substances at any of our current or former facilities or at any other locations where we arranged for disposal of those substances, even if we did not cause the release at that location or if the release complied with applicable law at the time it occurred. Liability under these laws can be joint and several. The cost of any remediation activities in connection with a spill or other release of such substances could be significant and could expose us to significant liability.
Previous wording
The Organization for Economic Co-operation and Development (OECD) has a framework to implement a global minimum corporate tax of 15% for companies with global revenues and profits above certain thresholds (referred to as Pillar 2), with certain aspects of Pillar 2 effective January 1, 2024 and other aspects effective January 1, 2025. At this time, the Company does not meet the revenue threshold requirements. The Company does anticipate being subject to Pillar 2 in future years based off anticipated growth projections. We will continue to evaluate the impact of proposed and enacted legislative changes to our effective tax rate and cash flows as new guidance becomes available.
Current wording
The Organization for Economic Co-operation and Development (OECD) has a framework to implement a global minimum corporate tax of 15% for companies with global revenues and profits above certain thresholds (referred to as Pillar 2), with certain aspects of Pillar 2 effective January 1, 2024 and other aspects effective January 1, 2025. Several countries in which the Company operates, have enacted Pillar 2. Pillar 2 rules apply to the Company beginning in the year after December 31, 2025. Based on enacted laws, Pillar 2 is not expected to materially impact the Company’s effective tax rate. New legislation or guidance could change this assessment.
Showing the first 40 of 50 pairs. Open the source sections for the rest.
Rearranged current paragraphs (5)
Current report — wording carried from elsewhere
•terrorist acts or other similar events;
Current report — wording carried from elsewhere
Uncertainty associated with these regulations, our inability to meet the demands of these regulations or our failure to predict accurately the impact of our response to these regulations could adversely affect our business and prospects. We could also face an increase in competition as a result of the energy transition, as new entrants of disruptive technologies and/or competitors, including in the solar, wind, and storage sectors, could adversely impact our ability to renew existing PPAs or sign new contracts. On the other hand, anti-ESG related policies, legislation, initiatives, litigation, legal opinions, and scrutiny could result in the Company facing additional compliance obligations, becoming the subject of investigations and enforcement actions, or sustaining reputational harm.
Current report — wording carried from elsewhere
There are additional public policy and government incentives that currently benefit and that we expect will benefit the Company in the future in countries outside of the U.S. as well as States within the U.S. The incentives in these jurisdictions include accelerated depreciation tax benefits, rebates, mandated feed-in tariffs and other similar incentives.
Current report — wording carried from elsewhere
Similarly, any such changes that affect the geothermal energy industry in a manner that is different from other sources of renewable energy, such as wind or solar, may put us at a competitive disadvantage compared to businesses engaged in the development, construction and operation of renewable power projects using such other resources. In addition, although we may have the legal ability to monetize ITCs and PTCs, our ability to do so is subject to market prices and demand, which may be lower than we anticipate. Any of the foregoing outcomes could have a material adverse effect on our business, financial condition, future results, and cash flows.
Current report — wording carried from elsewhere
•loss of one or more of our significant customers;