Skip to main content

NextDecade Corp

For the period ended Dec 31, 2025. Filed Mar 2, 2026.

View on SEC.gov

About this filing

A company's yearly report to the SEC, with audited financial statements. It is the fullest account a company gives of its business, its finances and the risks it sees.

FY2025 · Filed Mar 2, 2026

NEXT$5.80-0.9%Stored close · as of Nov 6, 2026

What changed in Management’s Discussion and Analysis?

Read the current filing

Previous report: 10-K

Period ended 2024-12-31; filed 2025-02-28.

0001628280-25-008841

Item 7. Management’s Discussion and Analysis of Financial Condition and Results of Operations

Current report: 10-K

Period ended 2025-12-31; filed 2026-03-02.

0001612720-26-000009

Item 7. Management’s Discussion and Analysis of Financial Condition and Results of Operations

The baseline is this issuer’s latest earlier reporting period of the same form that was filed before the current report. A previous 10-Q is a different quarter, not a year-over-year comparison. Amendments are excluded.

Compared 95 previous paragraphs and 105 current paragraphs.

37 unchanged; 22 reworded; 45 added; 35 removed; 1 previous and 1 current paragraphs rearranged.

Tables are not compared: 3 previous and 3 current tables excluded. Dates, whitespace, punctuation and numbering changes are ignored; changes to financial figures remain significant.

A changed paragraph is not evidence that risk increased or decreased. An unchanged paragraph does not establish that risk stayed the same.

Added paragraphs (45)

Current report

•Under the engineering, procurement, and construction (“EPC”) contracts with Bechtel Energy, Inc. (“Bechtel”), as of January 2026:

Current report

•The overall project completion percentage for Train 3 at the Rio Grande LNG Facility was 39.8%. Within this project completion percentage, engineering was 88.0% complete, procurement was 75.6% complete, and construction was 8.5% complete.

Current report

•The overall project completion percentage for Train 4 at the Rio Grande LNG Facility was 7.8%. Within this project completion percentage, engineering was 28.1% complete, procurement was 15.1% complete, and construction was 0.0% complete.

Current report

•The overall project completion percentage for Train 5 at the Rio Grande LNG Facility was 3.3%. Progress since the positive final investment decision (“FID”) on Train 5 in October 2025 has primarily focused on procurement.

Current report

◦We are evaluating multiple areas on the site for the development of Trains 7 and 8, which have a total expected LNG production capacity of approximately 12 MTPA. We expect to advance the development of Trains 7 and 8 throughout 2026.

Current report

•On September 9, 2025, we announced a positive FID on Train 4 and related infrastructure at the Rio Grande LNG Facility and issued full notice to proceed ("NTP") to Bechtel under the EPC contract for Train 4. Total project costs for Train 4 and related infrastructure are expected to total approximately $6.7 billion. Train 4 has an expected LNG production capacity of approximately 6 MTPA, and guaranteed substantial completion of Train 4 is in the third quarter of 2030.

Current report

•On October 16, 2025, we announced a positive FID on Train 5 and related infrastructure at the Rio Grande LNG Facility and issued full NTP to Bechtel under the EPC contract for Train 5. Total project costs for Train 5 and related infrastructure are expected to total approximately $6.7 billion. Train 5 has an expected LNG production capacity of approximately 6 MTPA, and guaranteed substantial completion of Train 5 is in the second quarter of 2031.

Current report

•In March 2026, we announced that we expect to begin commissioning activities at the Rio Grande LNG Facility in 2026, and we expect first LNG production from Train 1 in the first half of 2027.

Current report

•In April 2025, we announced TotalEnergies’ exercise of its LNG purchase option with respect to Train 4 and the execution of a 20-year LNG SPA with TotalEnergies, pursuant to which TotalEnergies will purchase 1.5 MTPA of LNG from Train 4 at the Rio Grande LNG Facility for 20 years, on an FOB basis at a price indexed to Henry Hub.

Current report

•In May 2025, we announced a 20-year LNG SPA with JERA, pursuant to which JERA will purchase 2.0 MTPA of LNG from Train 5 at the Rio Grande LNG Facility for 20 years, on an FOB basis at a price indexed to Henry Hub.

Current report

•In June 2025, we finalized a pricing refresh of the Company's lump-sum, turnkey EPC contract with Bechtel for the construction of Train 4 and related infrastructure and executed a lump-sum, turnkey EPC contract with Bechtel for the construction of Train 5 and related infrastructure.

Current report

•In September 2025, we announced a 20-year LNG SPA with EQT Corporation ("EQT"), pursuant to which EQT will purchase 1.5 MTPA of LNG from Train 5 at the Rio Grande LNG Facility for 20 years, on an FOB basis at a price indexed to Henry Hub.

Current report

•In September 2025, we announced a 20-year LNG SPA with ConocoPhillips, pursuant to which ConocoPhillips will purchase 1.0 MTPA of LNG from Train 5 at the Rio Grande LNG Facility for 20 years, on an FOB basis at a price indexed to Henry Hub.

Current report

•In early 2026, we began the marketing of early cargoes that we expect to produce in 2027 and 2028 prior to the commencement of our long-term LNG SPAs. We have entered into LNG sales agreements for the sale of over 175 TBtu of LNG on an FOB basis, with fixed liquefaction fees that are expected to achieve a cargo margin, calculated as the FOB LNG sales price less our expected costs of natural gas feedstock and fuel, of over $3.00 per MMBtu. This volume represents 33% of our expected open volumes from 2027 through early 2029.

Current report

•In April 2025, Phase 1 LLC elected to terminate $250 million of commitments under its working capital facility due to a decrease in expected requirements for credit support during construction, which reduced the outstanding commitments under the working capital facility to $250 million and is expected to reduce related commitment fees by approximately $2 million annually.

Current report

•In May 2025, our wholly owned subsidiary Rio Grande LNG Super Holdings, LLC, entered into an amendment to the credit agreement with the lender of its existing senior secured loan (the "Super Holdings Loan") to increase the loan amount by $50 million to a total of $225 million initial principal. Incremental proceeds from the Super Holdings Loan were disbursed at closing on May 14, 2025, and net proceeds were used to fund working capital and general corporate purposes, including pre-FID expenses for Trains 4 and 5 and development expenses for expansion trains at the Rio Grande LNG Facility.

Current report

•On September 9, 2025, in conjunction with the positive FID on Train 4 at the Rio Grande LNG Facility, we and certain of our subsidiaries closed an approximately $6.7 billion project financing for Train 4, which included the closing of:

Current report

◦A joint venture agreement which included approximately $1.69 billion of financial commitments from Global Infrastructure Partners, a part of BlackRock ("GIP"), GIC, Mubadala Investment Company, and TotalEnergies;

Current report

◦A commitment by the Company to invest approximately $1.13 billion in Train 4; and

Current report

◦A senior secured, non-recourse bank credit facility of $3.85 billion with a seven-year maturity.

Current report

•On September 9, 2025, to fully fund the Company's approximately $1.13 billion equity commitments for Train 4, certain of our wholly owned subsidiaries entered into a delayed draw, senior secured term loan bank facility of $734 million with a five-year maturity (the "FinCo Loan") and term loans of $600 million with a maturity date of the earlier of eight years or the 85th day prior to the maturity date of the FinCo Loan (the "SuperFinCo Loan").

Current report

•On October 16, 2025, in conjunction with the positive FID on Train 5 at the Rio Grande LNG Facility, we and certain of our subsidiaries closed an approximately $6.7 billion project financing for Train 5, which included the closing of:

Current report

◦A joint venture agreement which included approximately $1.29 billion of financial commitments from GIP, GIC, and Mubadala Investment Company;

Current report

◦A commitment by the Company to invest approximately $1.29 billion in Train 5;

Current report

◦A senior secured, non-recourse bank credit facility of $3.59 billion with a seven-year maturity; and

Current report

◦An offering of $500 million senior secured, non-recourse private placement notes, which will bear interest at 6.56%, will be funded in multiple tranches from December 2025 through October 2026, and will amortize over a period of 20 years beginning in September 2031, with a final maturity in September 2050. In December 2025, the Company issued the first tranche of $150 million of these notes.

Current report

•On October 16, 2025, to fully fund the Company's approximately $1.29 billion equity commitments for Train 5, we contributed $233 million cash to Train 5 LLC, and certain of our wholly owned subsidiaries increased the size of the FinCo Loan by $729 million, to a total of approximately $1.46 billion, and increased the size of the SuperFinCo Loan by $600 million, to a total of $1.2 billion.

Current report

•In November 2025, Rio Grande LNG Super Holdings, LLC entered into an Amended and Restated Credit Agreement with the lenders of the Super Holdings Loan to refinance $50 million of the existing loan amount and provide $50 million of incremental capital in the form of an exchangeable loan with total initial principal of $100 million (the "Exchangeable Loan"). The Exchangeable Loan bears interest at 8%, payable in cash or in-kind at the Company's election, and matures in November 2030. The initial principal of the Exchangeable Loan and any amounts of interest paid in-kind are exchangeable into shares of our common stock at $9.50 per share. Pursuant to this transaction, the interest rate on the remaining balance of the Super Holdings Loan was amended to 13.5%.

Current report

•In March 2025, the U.S. Court of Appeals for the D.C. Circuit (the “D.C. Circuit Court”) issued a revision to its August 2024 decision regarding the Company's FERC order, resulting in a remand without vacatur of the FERC order for the first five liquefaction trains at the Rio Grande LNG Facility. Pursuant to the remand, FERC was to consider the issue of a supplemental Environmental Impact Statement (“SEIS”) in view of several executive orders issued since January 20, 2025.

Current report

•In July 2025, the FERC issued a final SEIS for the first five liquefaction trains at the Rio Grande LNG Facility, following a draft SEIS in March 2025.

Current report

•In August 2025, the FERC issued a final order on remand reaffirming its authorization for the siting, construction, and operation of the first five liquefaction trains at the Rio Grande LNG Facility, and as of October 30, 2025, the order is no longer appealable to FERC. In December 2025, certain intervenors petitioned the D.C. Circuit Court to review the order on remand, and their request remains pending.

Current report

Progress on Phase 1 as of January 2026 is ahead of the guaranteed completion schedule under the EPC contracts. During the fourth quarter of 2025 and early 2026, the construction team continued piping fabrication, rebar installation, equipment setting and concrete placement, and structural steel erection in the areas of Trains 1, 2, and 3. Tank construction continued to progress with insulation installation and inner tank shell erection, and construction of the tug and loading berths is underway. Across the site, Bechtel also continued installing concrete foundations, instrument air receivers, floodgates, security systems, permanent fencing, temporary facilities, and other siteworks.

Current report

Progress on Train 4 as of January 2026 is in line with the EPC contract. Since FID of Train 4 in September 2025, progress has been focused primarily on engineering drawings and issuance of purchase requisitions for key equipment, and soil stabilization in the Train 4 area has commenced.

Current report

Progress on Train 5 as of January 2026 is in line with the EPC contract. Since FID of Train 5 in October 2025, progress has been focused primarily on issuance of purchase requisitions for key equipment.

Current report

In April 2025, Phase 1 LLC elected to terminate $250 million of commitments under its working capital facility due to a decrease in expected requirements for credit support during construction, which reduced the outstanding commitments under the working capital facility to $250 million.

Current report

In connection with the FID on Train 4, Train 4 LLC obtained approximately $2.8 billion in equity capital commitments, inclusive of commitments from NextDecade, and entered into a senior secured non-recourse bank credit facility of approximately $3.8 billion (the "Train 4 Credit Facility"). Train 4 LLC expects to utilize these capital resources to fully fund the total cost of Train 4 and related infrastructure, which is currently estimated at approximately $6.7 billion and consists of EPC costs, owner’s costs and contingencies, interest during construction and other financing costs, and other costs, including a payment for usage of common infrastructure at the Rio Grande LNG Facility.

Current report

In connection with the FID on Train 5, Train 5 LLC obtained approximately $2.6 billion in equity capital commitments, inclusive of commitments from NextDecade, entered into a senior secured non-recourse bank credit facility of approximately $3.6 billion (the "Train 5 Credit Facility" and, together with the Phase 1 Credit Facilities and the Train 4 Credit Facility, the "Project Credit Facilities"), and closed a $500 million senior secured non-recourse private notes offering. Train 5 LLC expects to utilize these capital resources to fund the total cost of Train 5 and related infrastructure, which is currently estimated at approximately $6.7 billion and consists of EPC costs, owner’s costs and contingencies, interest during construction and financing costs, and other costs, including a payment for usage of common infrastructure at the Rio Grande LNG Facility.

Current report

Following the respective FIDs of Phase 1, Train 4 and Train 5, costs associated with the EPC agreements, Rio Grande site lease, and other Phase 1, Train 4, and Train 5 related costs are being funded by debt and equity proceeds received by the Rio Grande Project Entities. Our primary corporate cash needs are capital contributions to Trains 4 and 5, development expenses for expansion projects and general and administrative expenses.

Showing the first 40 of 45 passages. Open the source sections for the rest.

Removed paragraphs (35)

Previous report

•Under the EPC contracts with Bechtel, Phase 1 progress is tracked for Train 1, Train 2, and the common facilities on a combined basis and Train 3 on a separate basis. As of January 2025:

Previous report

◦The overall project completion percentage for Train 3 of the Rio Grande LNG Facility was 15.3%, which is also in line with the schedule under the EPC contract. Within this project completion percentage, engineering was 33.5% complete, procurement was 32.8% complete, and construction was 0.4% complete.

Previous report

◦Trains 7 and 8, with a total expected LNG production capacity of approximately 12 MTPA, are being developed on the site outside of the existing levee.

Previous report

•In June 2024, the Company entered into a non-binding Heads of Agreement (HoA) with Aramco for a 20-year LNG SPA for offtake from Train 4 at the Rio Grande LNG Facility. Under the terms of the HoA, Aramco expects to purchase 1.2 MTPA of LNG for 20 years, on an FOB basis at a price indexed to Henry Hub. Aramco and the Company are in the process of negotiating a binding LNG SPA, and once executed, the SPA will be subject to a positive FID on Train 4.

Previous report

•In July 2024, the Company appointed Tarik Skeik as Chief Operating Officer. Mr. Skeik has over 20 years of experience delivering complex global mega projects in LNG, oil and petrochemicals across North America, the Middle East, and Asia. He led the completion and start-up of six greenfield assets, and his experience includes the planning and execution through initial operation of projects including the Huizhou Chemicals Complex in China, Gulf Coast Growth Ventures in the U.S., Banyu Urip in Indonesia, Kearl Expansion in Canada, and QatarGas 2 in Qatar.

Previous report

•In August 2024, the Company entered into an EPC contract with Bechtel for Train 4 and related infrastructure. Pricing under the EPC contract for Train 4 and related infrastructure was valid through December 31, 2024, and a pricing refresh is in process and is expected to be completed in 2025.

Previous report

•In January 2024, the Company's wholly-owned subsidiary, NextDecade LNG, LLC ("NextDecade LLC"), entered into a credit agreement that provided for a $50 million senior secured revolving credit facility with additional capacity of $12.5 million to cover interest. Borrowings under the revolving credit facility were used for general corporate purposes, including development costs related to Train 4 at the Rio Grande LNG Facility. Borrowings under the revolving credit facility bore interest at SOFR or the base rate plus an applicable margin as defined in the credit agreement. All outstanding borrowings under the revolving credit facility and interest term loan were repaid in December 2024 utilizing proceeds from the senior secured loan issued in December 2024 and described below.

Previous report

•In February 2024, Rio Grande issued and sold $190 million of senior secured notes in a private placement transaction to finance a portion of Phase 1. The senior secured notes were issued on February 9, 2024, and resulted in a reduction in the commitments outstanding under Rio Grande's existing bank credit facilities for Phase 1. These senior secured notes will be amortized over a period of approximately 18 years beginning in mid-2029, with a final maturity in June 2047. These senior secured notes bear interest at a fixed rate of 6.85% and rank pari passu to Rio Grande's existing senior secured financings.

Previous report

•In June 2024, Rio Grande issued $1.115 billion of senior secured notes in a private placement, and net proceeds were utilized to reduce outstanding borrowings and commitments under existing Rio Grande bank credit facilities for Phase 1. These senior secured notes will be amortized over a period of 18 years beginning in September 2029, with a final maturity in September 2047. These senior secured notes bear interest at a fixed rate of 6.58% and rank pari passu to Rio Grande's existing senior secured financings. Including this transaction, the Company has refinanced a total of over $1.85 billion of the original $11.1 billion Rio Grande term loan facilities since a positive FID was reached on Phase 1 at the Rio Grande LNG Facility in July 2023.

Previous report

•In December 2024, the Company's wholly-owned subsidiary, Rio Grande LNG Super Holdings, LLC ("Super Holdings"), entered into a credit agreement (the "Corporate Credit Agreement") which provided for a $175 million senior secured loan. Proceeds from the senior secured loan were disbursed at closing on December 31, 2024, and net proceeds were used to repay outstanding borrowings under the NextDecade LLC January 2024 $50 million revolving credit facility and $12.5 million interest term loan, and will be used to fund working capital and general corporate purposes, including development expenses for expansion trains at the Rio Grande LNG Facility. Borrowings under the senior secured loan bear interest at 12.0%, with interest payable quarterly. Interest may be paid in-kind until March 31, 2027 and up to 50% in-kind thereafter. The senior secured loan matures six years from the closing date.

Previous report

•In August 2024, the U.S. Court of Appeals for the D.C. Circuit (the "Court") issued a decision vacating FERC's reauthorization of the Rio Grande LNG Facility on the grounds that FERC should have issued a supplemental Environmental Impact Statement ("EIS") during its reauthorization process.

Previous report

•On September 13, 2024, FERC issued notice of its intent to prepare a supplemental EIS in response to the Court's decision. The notice set forth a schedule providing for the issuance of a draft of the supplemental EIS in March 2025, the final supplemental EIS by the end of July 2025, and issuance of a final order by November 20, 2025.

Previous report

•On October 21, 2024, the Company filed a petition for rehearing and rehearingen banc with the Court. On December 9, 2024, petitioners in the case and FERC filed responses to the Company's request for rehearing, and the Court's decision is pending.

Previous report

•The Court's decision will not be effective until the Court has issued its mandate, which is not expected to occur until after the appeals process has been completed. At this time, construction continues on Phase 1 at the Rio Grande LNG Facility.

Previous report

•The Company expects to take all available legal and regulatory actions, including appellate actions, to ensure that construction on Phase 1 will continue and that necessary regulatory approvals will be maintained to enable a positive final investment decision (FID) on Trains 4 and 5 at the Rio Grande LNG Facility.

Previous report

In July 2023, construction commenced on Phase 1 of the Rio Grande LNG Facility following a positive FID and the closing of project financing by Rio Grande, which owns Phase 1 of the Rio Grande LNG Facility. Phase 1 includes three liquefaction trains with a total expected nameplate capacity of approximately 18 MTPA of LNG production, two 180,000 cubic meter full containment LNG storage tanks, two jetty berthing structures designed to load LNG carriers up to 216,000 cubic meters in capacity, and associated site infrastructure and common facilities including feed gas pretreatment facilities, electric and water utilities, two totally enclosed ground flares for the LNG tanks and marine facilities, two ground flares for the liquefaction trains, roads, levees surrounding the development area, and warehouses, administrative, operations control room and maintenance buildings.

Previous report

As of January 2025, progress on Trains 1 through 3 is in line with the schedule under the EPC contracts. During the fourth quarter and early 2025, the construction team continued steel assembly in the Train 1 area and adjacent pipe racks. Within Train 2, foundations were progressed and steel assembly began. Tank 1 roof panels were set in place, and the first wall concrete pour for Tank 2 was completed. Across the site, Bechtel’s work also continues on installing underground structures, loading berths, piling, concrete foundations, and other siteworks. Bechtel has materially completed purchase orders for critical and high-value items for Phase 1.

Previous report

Trains 4 and 5 at the Rio Grande LNG Facility are being commercialized, and we expect to make a positive final investment decision and commence construction of Trains 4 and 5 and related infrastructure at the Rio Grande LNG Facility, subject to, among other things, maintaining requisite governmental approvals, finalizing and entering into EPC contracts, entering into appropriate commercial arrangements, and obtaining adequate financing to construct each train and related infrastructure.

Previous report

In January 2024, NextDecade LLC entered into a credit agreement that provided for a $50 million senior secured revolving credit facility with additional capacity of $12.5 million to cover interest. Borrowings under the revolving credit facility were used for general corporate purposes, including development costs related to Train 4 at the Rio Grande LNG Facility. Borrowings under the revolving credit facility bore interest at SOFR or the base rate plus an applicable margin as defined in the credit agreement. All outstanding borrowings under the revolving credit facility and interest term loan were repaid in December 2024 utilizing proceeds from the senior secured loan issued in December 2024 and described below.

Previous report

In December 2024, the Company's wholly-owned subsidiary, Rio Grande LNG Super Holdings, LLC ("Super Holdings"), entered into a credit agreement (the "Corporate Credit Agreement") which provided for a $175 million senior secured loan. Proceeds from the senior secured loan were disbursed at closing on December 31, 2024, and net proceeds were used to repay outstanding borrowings under the NextDecade LLC January 2024 $50 million revolving credit facility and $12.5 million interest term loan, and will be used to fund working capital and general corporate purposes, including development expenses for expansion trains at the Rio Grande LNG Facility. Borrowings under the senior secured loan bear interest at 12.0%, with interest payable quarterly. Interest may be paid in-kind until March 31, 2027 and up to 50% in-kind thereafter. The senior secured loan matures six years from the closing date.

Previous report

In conjunction with the closing of the Corporate Credit Agreement, the Company issued warrants in two equal tranches that are exercisable for an aggregate of approximately 7.2 million shares of NextDecade common stock to the lender of the senior secured loan. The warrants are exercisable for five years after the closing date. The first tranche of the warrants are exercisable at $7.15 per share, which represents the 30-day volume weighted average trading price for the 30 trading-day period immediately preceding the closing date, and the second tranche of the warrants are exercisable at $9.30 per share.

Previous report

In February 2024, Rio Grande entered into a note purchase agreement through which it sold $190 million of senior secured notes to finance a portion of Phase 1. The senior secured notes were issued on February 9, 2024, and resulted in a reduction in the commitments outstanding under Rio Grande's existing bank credit facilities for Phase 1. These senior secured notes will be amortized over a period of approximately 18 years beginning in mid-2029, with a final maturity in June 2047. These senior secured notes bear interest at a fixed rate of 6.85% and rank pari passu to Rio Grande's existing senior secured financings.

Previous report

In June 2024, Rio Grande issued $1.115 billion of senior secured notes in a private placement, and net proceeds were utilized to reduce outstanding borrowings and commitments under existing Rio Grande bank credit facilities for Phase

Previous report

These senior secured notes will be amortized over a period of 18 years beginning in September 2029, with a final maturity in September 2047. These senior secured notes bear interest at a fixed rate of 6.58% and rank pari passu to Rio Grande's existing senior secured financings. Including this transaction, the Company has refinanced a total of over $1.85 billion of the original $11.1 billion Rio Grande term loan facilities since a positive FID was reached on Phase 1 at the Rio Grande LNG Facility in July 2023.

Previous report

In connection with the FID of Phase 1, the Company, through a wholly owned subsidiary, committed to invest approximately $283 million, including $125 million of pre-FID capital investments, into construction of Phase 1 of the Rio Grande LNG Facility. As of December 31, 2024, the Company had funded its full equity commitment.

Previous report

Prior to the FID on Phase 1 of the Rio Grande LNG Facility, our primary cash needs historically were funding development activities in support of the Rio Grande LNG Facility and our CCS projects, which included payments of initial direct costs of the Rio Grande site lease and expenses in support of engineering and design activities, regulatory approvals and compliance, commercial and marketing activities and corporate overhead. Following the FID of Phase 1 of the Rio Grande LNG Facility, costs associated with the Phase 1 EPC contracts, Rio Grande site lease, and other Phase 1 related costs are being funded by debt and equity proceeds received by Rio Grande.

Previous report

Our capital raising activities since January 1, 2024 have included the following:

Previous report

•In January 2024, NextDecade LLC executed a credit agreement that provided for a $50 million revolving credit facility that may be used for general corporate purposes and working capital requirements of NextDecade LLC and its subsidiaries, including development costs related to Train 4 and related common facilities at the Rio Grande LNG Facility. All outstanding borrowings under the revolving credit facility and interest term loan were repaid in December 2024 utilizing proceeds from the senior secured loan issued in December 2024.

Previous report

•In December 2024, Rio Grande LNG Super Holdings, LLC executed the Corporate Credit Agreement, which provided for a $175 million senior secured loan that was used to repay outstanding borrowings under the Company's January 2024 $50 million revolving credit facility and $12.5 million interest term loan and may be used to fund working capital and general corporate purposes, including development expenses for expansion trains at the Rio Grande LNG Facility.

Previous report

Financing cash inflows during the years ended December 31, 2024 and 2023 were $2,768.1 million and $2,058.1 million, respectively. Financing cash inflows during 2024 are primarily comprised of proceeds from the issuance of debt of $3,523.2 million and proceeds from receipt of equity contributions throughout 2024 of $676.0 million The cash inflows for 2024 were partially offset by debt and equity issuances costs of $72.8 million, repayment of debt of $1,338.2 million, costs associated with repayment of debt of $13.4 million and shares repurchased related to share-based compensation of $6.7 million.

Previous report

•Interest expense, net of capitalized interest during the year ended December 31, 2024 increased approximately $37.3 million compared to the same period in 2023 primarily due to an approximate $178.7 million increase in total interest costs, partially offset by a $141.4 million increase in capitalized interest.
Reworded paragraphs (22)

Previous wording

The following discussion and analysis presents management’s view of our business, financial condition and overall performance and should be read in conjunction with our Consolidated Financial Statements and the accompanying notes in “Financial Statements and Supplementary Data.” This information is intended to provide investors with an understanding of our past performance, current financial condition and outlook for the future. Our discussion and analysis include the following subjects:

Current wording

The following discussion and analysis presents management’s view of our business, financial condition and overall performance and should be read in conjunction with our Consolidated Financial Statements and the accompanying notes in “Financial Statements and Supplementary Data.” This information is intended to provide investors with an understanding of our past performance, current financial condition and outlook for the future. Discussion of items for the year ended December 31, 2023, including drivers of variances between the year ended December 31, 2024 and the year ended December 31, 2023, are not included herein and can be found in “Management’s Discussion and Analysis of Financial Condition and Results of Operations” in our annual report on Form 10-K for the fiscal year ended December 31, 2024.

Previous wording

NextDecade Corporation engages in construction and development activities related to the liquefaction of natural gas and sale of LNG and the capture and storage of CO 2 emissions. We are constructing and developing a natural gas liquefaction and export facility located in the Rio Grande Valley near Brownsville, Texas (the “Rio Grande LNG Facility”). The Rio Grande LNG Facility has received Federal Energy Regulatory Commission (“FERC”) approval and Department of Energy (“DOE”) FTA and non-FTA authorizations for the construction of up to five liquefaction trains and LNG exports totaling up to 27 million tonnes per annum (“MTPA”). Please see "Rio Grande LNG Facility Activity - Governmental Permits, Approvals and Authorizations" for more information regarding our FERC permit. The Rio Grande LNG Facility has three liquefaction trains and related infrastructure ("Phase 1") under construction and liquefaction trains 4 and 5 are currently being commercialized. We are also developing and beginning the permitting process for expansion trains 6 through 8 at the Rio Grande LNG Facility and developing a potential carbon capture and storage (“CCS”) project at the Rio Grande LNG Facility.

Current wording

NextDecade Corporation, a Delaware corporation, is a Houston-based energy company primarily engaged in construction and development activities related to the liquefaction of natural gas and sale of LNG. We are constructing and developing a natural gas liquefaction and export facility located in the Rio Grande Valley near Brownsville, Texas (the “Rio Grande LNG Facility”). The first five liquefaction trains and related infrastructure (together, “Phase 1”, “Train 4”, and “Train 5”) at the Rio Grande LNG Facility are currently under construction. We are also developing and advancing the permitting process for expansion Trains 6 through 8 and exploring a potential carbon capture and storage ("CCS") project at the Rio Grande LNG Facility.

Previous wording

◦The overall project completion percentage for Trains 1 and 2 and the common facilities of the Rio Grande LNG Facility was 38.1%, which is in line with the schedule under the EPC contract. Within this project completion percentage, engineering was 84.9% complete, procurement was 69.2% complete, and construction was 10.6% complete.

Current wording

•The overall project completion percentage for Trains 1 and 2 and the common facilities at the Rio Grande LNG Facility was 64.5%. Within this project completion percentage, engineering was 97.8% complete, procurement was 94.0% complete, and construction was 42.9% complete.

Previous wording

•In February 2025, the Company provided additional information regarding its development of additional liquefaction capacity at the Rio Grande LNG Facility. beyond Trains 1 through 5. Trains 6 through 8 are wholly owned by NextDecade and are cumulatively expected to increase the Company's total liquefaction capacity by approximately 18 MTPA once constructed and placed into operation.

Current wording

•In February 2025, we provided additional information regarding our development of Trains 6 through 8 at the Rio Grande LNG Facility. Trains 6 through 8 are currently wholly owned by NextDecade and are cumulatively expected to increase the Company's total liquefaction capacity by approximately 18 million tonnes per annum ("MTPA") once constructed and placed into operation.

Previous wording

◦Train 6, with expected LNG production capacity of approximately 6 MTPA, is being developed inside the existing levee at the site and adjacent to Trains 1 through 5. A pre-filing application with FERC for Train 6 is expected in 2025, and a full FERC application is expected in early 2026.

Current wording

◦Train 6, which has an expected LNG production capacity of approximately 6 MTPA, is being developed inside the existing levee at the site and adjacent to Trains 1 through 5. In November 2025, we initiated the pre-filing process with the Federal Energy Regulatory Commission ("FERC") for expansion at the Rio Grande LNG Facility that includes Train 6 and an additional marine berth, and we expect to file a full FERC application for this expansion in mid-2026.

Previous wording

•In May 2024, the Company entered into a 20-year LNG SPA with ADNOC for the sale of 1.9 MTPA of LNG from Train 4 at the Rio Grande LNG Facility for 20 years, on a free on board (“FOB”) basis at a price indexed to Henry Hub, subject to a positive FID on Train 4.

Current wording

•In April 2025, we announced a 20-year LNG Sale and Purchase Agreement (“SPA”) with a subsidiary of Saudi Aramco (“Aramco”), pursuant to which the Aramco subsidiary will purchase 1.2 MTPA of LNG from Train 4 at the Rio Grande LNG Facility for 20 years, on a free on board (“FOB”) basis at a price indexed to Henry Hub.

Previous wording

•In conjunction with the closing of the Corporate Credit Agreement, the Company issued warrants in two equal tranches that are exercisable for an aggregate of approximately 7.2 million shares of NextDecade common stock to the lender of the senior secured loan. The warrants are exercisable for five years after the closing date. The first tranche of the warrants are exercisable at $7.15 per share, which represents the 30-day volume weighted average trading price for the 30 trading-day period immediately preceding the closing date, and the second tranche of the warrants are exercisable at $9.30 per share.

Current wording

•In conjunction with the closing of the May 2025 amendment to the Super Holdings Loan, we issued warrants that are exercisable for an aggregate of approximately 2.0 million shares of our common stock to the lenders of the Super Holdings Loan. The warrants are exercisable at $9.30 per share, which represented a 30% premium to the volume weighted average price for the 30 trading-day period immediately preceding the amendment date.

Previous wording

We are constructing the Rio Grande LNG Facility on the north shore of the Brownsville Ship Channel in south Texas through our partially owned subsidiary, Rio Grande. The site is located on 984 acres of land which has been leased long-term and includes 15,000 feet of frontage on the Brownsville Ship Channel. We believe the site is advantaged due to its proximity to abundant natural gas resources in the Permian Basin and Eagle Ford Shale, access to an uncongested waterway for vessel loading, and location in a region that has historically been subject to fewer and less severe weather events relative to other locations along the US Gulf Coast. The Rio Grande LNG Facility has been approved by the FERC and authorized by the DOE to export up to 27 MTPA of LNG from up to five liquefaction trains. Please see "Rio Grande LNG Facility Activity - Governmental Permits, Approvals and Authorizations" for more information regarding our FERC permit. Phase 1 at the Rio Grande LNG Facility is under construction, Trains 4 and 5 are currently being commercialized, and we are developing and beginning the permitting process for Trains 6 through 8.

Current wording

We are constructing and developing the Rio Grande LNG Facility on the north shore of the Brownsville Ship Channel in south Texas. The site is located on approximately 1,000 acres of land, which has been leased long-term and includes 15,000 feet of frontage on the Brownsville Ship Channel. We believe the site is advantaged due to its proximity to abundant natural gas resources in the Permian Basin and Eagle Ford Shale, access to an uncongested waterway for vessel loading, location in a region that has historically been subject to fewer and less severe weather events relative to other locations along the U.S. Gulf Coast, access to a large, skilled local labor force, and strong geotechnical conditions requiring less piling for soil stabilization. Trains 1 through 5 at the Rio Grande LNG Facility are under construction, and we are developing and advancing the permitting process for Trains 6 through 8. There is sufficient space at the Rio Grande LNG Facility site for up to 10 liquefaction trains.

Previous wording

Following FID of Phase 1 and the project financing obtained by Rio Grande, NextDecade and Rio Grande operate with independent capital structures. Although our sources and uses are presented from a consolidated standpoint, certain restrictions under debt and equity agreements limit the ability of NextDecade and Rio Grande to use and distribute cash. Rio Grande is required to deposit all cash received under its debt agreements into restricted accounts. The usage or withdrawal of such cash is restricted to the payment of obligations related to Phase 1 and other restricted payments, and such cash and capital resources are not available to service the obligations of NextDecade.

Current wording

Following FID on Trains 1 through 5 and the project financing obtained by the Company's subsidiaries, the Rio Grande Project Entities and the NextDecade Group operate with independent capital structures. Although our sources and uses are presented from a consolidated standpoint, certain restrictions under debt and equity agreements limit the ability of the NextDecade Group and the Rio Grande Project Entities to use and distribute cash. The Rio Grande Project Entities are required to deposit all cash received under their respective debt agreements into restricted accounts. The usage or withdrawal of such cash is restricted to the payment of obligations related to their respective trains and common infrastructure and other restricted payments, and such cash and capital resources are not available to service the obligations of the NextDecade Group.

Previous wording

In connection with the FID of Phase 1 of the Rio Grande LNG Facility, Rio Grande obtained approximately $6.2 billion in equity capital commitments, inclusive of commitments from NextDecade, entered into senior secured non-recourse bank credit facilities of $11.6 billion, consisting of $11.1 billion in construction term loans and a $500 million working capital facility, and closed a $700 million senior secured non-recourse private notes offering. Rio Grande will utilize these capital resources to fund the approximately $18.0 billion total cost of Phase 1, including EPC cost, owner’s costs and contingencies, dredging for the improvement project at the Brazos Island Harbor Channel, conservation of more than 4,000 acres of wetland and wildlife habitat area and installation of utilities, and interest during construction and other financing costs.

Current wording

In connection with the FID on Phase 1 at the Rio Grande LNG Facility, Phase 1 LLC obtained approximately $6.2 billion in equity capital commitments, inclusive of commitments from NextDecade, entered into senior secured non-recourse bank credit facilities of $11.6 billion, consisting of $11.1 billion in construction term loans and a $500 million working capital facility, and closed a $700 million senior secured non-recourse private notes offering. Phase 1 LLC expects to utilize these capital resources to fully fund the total cost of Phase 1, which is currently estimated at $18.0 billion and consists of EPC costs, owner’s costs and contingencies, dredging for the Brazos Island Harbor Channel Improvement Project, conservation of more than 4,000 acres of wetland and wildlife habitat area, installation of utilities, and interest during construction and other financing costs, and including amounts spent prior to FID under limited notices to proceed. Phase 1 LLC has refinanced a total of over $1.85 billion of its original $11.1 billion term loan facilities (the "Phase 1 Credit Facilities") since July 2023 through the issuance of senior secured notes and loans.

Previous wording

Because our businesses and assets are under construction or in development, we have not historically generated significant cash flow from operations, nor do we expect to do so until liquefaction trains at the Rio Grande LNG Facility begin operating or until we develop and install CCS projects. We intend to fund development activities for the foreseeable future with cash and cash equivalents on hand and through the sale of additional equity, equity-based or debt securities in us or in our subsidiaries. There can be no assurance that we will succeed in selling equity or equity-based securities or, if successful, that the capital we raise will not be expensive or dilutive to stockholders.

Current wording

Because our businesses and assets are under construction or in development, we have not historically generated significant cash flow from operations, and we do not expect to do so until liquefaction trains at the Rio Grande LNG Facility begin operating. We intend to fund development activities and general and administrative expenses for the foreseeable future with our cash and cash equivalents on hand, the services fee due in September 2026 and through the sale of additional equity, equity-based or debt securities in us or in our subsidiaries. There can be no assurance that we will succeed in selling such securities or, if successful, that the capital we raise will not be expensive or dilutive to stockholders.

Previous wording

We will not receive significant cash flows from Phase 1 of the Rio Grande LNG Facility until it is operational, and the commercial operation date for the first train of Phase 1 is expected to occur in late 2027 based on the schedule under the EPC contracts. Any future phases of development at the Rio Grande LNG Facility and CCS projects will similarly take an extended period of time to develop, construct and become operational and will require significant capital deployment.

Current wording

We will not receive significant cash flows from liquefaction trains at the Rio Grande LNG Facility until they are operational, and after our trains reach commercial operation, certain restrictions under our debt and equity agreements limit the ability of the NextDecade Group and the Rio Grande Project Entities to use and distribute cash. Any future development of liquefaction trains and any potential CCS project at the Rio Grande LNG Facility will similarly take an extended period of time to develop, construct and become operational and will require significant capital deployment.

Previous wording

We currently expect that the long-term capital requirements for future phases of development at the Rio Grande LNG Facility and any CCS projects will be financed predominantly through the proceeds from future debt, equity-based, and equity offerings by us or our subsidiaries. As a result, our business success will depend, to a significant extent, upon our ability to obtain financing required to fund future phases of development and construction at the Rio Grande LNG Facility and any CCS projects, to bring them into operation on a commercially viable basis and to finance any required increases in staffing, operating and expansion costs during that process. There can be no assurance that we will succeed in securing additional debt and/or equity financing in the future to fund future phases of development and construction at the Rio Grande LNG Facility or complete any CCS projects or, if successful, that the capital we raise will not be expensive or dilutive to stockholders. Additionally, if these types of financing are not available, we will be required to seek alternative sources of financing, which may not be available on terms acceptable to us, if at all.

Current wording

We currently expect that the long-term capital requirements for future development of liquefaction trains and any potential CCS project at the Rio Grande LNG Facility will be financed predominantly through the proceeds from future debt, equity-based, and equity offerings by us or our subsidiaries. As a result, our business success will depend, to a significant extent, upon our ability to obtain financing required to fund future development and construction at the Rio Grande LNG Facility, to bring assets into operation on a commercially viable basis and to finance any required increases in staffing, operating and expansion costs during that process. There can be no assurance that we will succeed in securing additional debt and/or equity financing in the future to fund future development and construction at the Rio Grande LNG Facility or, if successful, that the capital we raise will not be expensive or dilutive to stockholders. Additionally, if these types of financing are not available, we will be required to seek alternative sources of financing, which may not be available on terms acceptable to us, if at all.

Previous wording

Operating cash outflows during the years ended December 31, 2024 and 2023 were $95.6 million and $73.6 million, respectively. The increase in operating cash outflows in 2024 compared to 2023 was primarily due to an increase in employee costs and professional fees after achieving a positive FID in Phase 1 of the Rio Grande LNG Facility in July 2023, as we prepare for operations.

Current wording

Operating cash outflows during the years ended December 31, 2025 and 2024 were $169.4 million and $95.6 million, respectively. The increase in operating cash outflows in 2025 compared to 2024 was primarily due to an increase in headcount to support the commencement of operations at the Rio Grande LNG Facility and a decrease in derivative settlements.

Previous wording

Investing cash outflows during the years ended December 31, 2024 and 2023 were $2,574.2 million and $1,752.8 million, respectively. Investing cash outflows primarily consist of cash used in the construction of Phase 1 of the Rio Grande LNG Facility. The increase in investing cash outflows in 2024 compared to 2023 was primarily due to positive FID in Phase 1 of the Rio Grande LNG Facility, the mobilization of the Bechtel workforce that began in July 2023 and subsequent progress payments made to Bechtel.

Current wording

Investing cash outflows during the years ended December 31, 2025 and 2024 were $4.9 billion and $2.6 billion, respectively. The increase in investing cash outflows in 2025 compared to 2024 was primarily due to increased expenditures associated with construction of the Rio Grande LNG Facility, including expenditures related to Trains 4 and 5, which achieved positive FID and began construction in 2025.

Previous wording

Net loss attributable to common stockholders was approximately $61.8 million, or $(0.24) per common share (basic and diluted) for the year ended December 31, 2024 compared to a net loss of approximately $182.7 million, or $(0.94) per common share (basic and diluted), for the year ended December 31, 2023. The approximately $121.0 million decrease was primarily a result of the following:

Current wording

Net loss attributable to common stockholders was approximately $306.4 million, or $(1.17) per common share (basic and diluted) for the year ended December 31, 2025 compared to a net loss attributable to common stockholders of approximately $61.8 million, or $(0.24) per common share (basic and diluted), for the year ended December 31, 2024. The approximately $244.7 million increase was primarily a result of the following:

Previous wording

•General and administrative expenses during the year ended December 31, 2024 increased approximately $38.6 million compared to the same period in 2023 primarily due to an increase in professional fees and employee costs, partially offset by a decrease in share-based compensation expense.

Current wording

•General and administrative expenses during the year ended December 31, 2025 increased approximately $52.2 million compared to the same period in 2024 primarily due to an increase in headcount to support the commencement of operations at the Rio Grande LNG Facility and share-based compensation expense recognized in connection with FID on Train 4 and Train 5.

Previous wording

•Derivative gains during the year ended December 31, 2024 increased approximately $631.3 million compared to the same period in 2023 primarily due to an increase in forward SOFR rates when compared to the prior period.

Current wording

•Derivative losses during the year ended December 31, 2025 increased approximately $597.5 million compared to the same period in 2024 primarily due to lower forward SOFR rates when compared to the prior period, which increased the loss on the Company's interest rate swap portfolio.

Previous wording

•Loss on debt extinguishment during the year ended December 31, 2024 increased approximately $39.8 million compared to the same period in 2023 due to approximately $1,338.2 million in debt repayments compared to approximately $233.0 million in the prior year.

Current wording

•Loss on debt extinguishment and modification cost during the year ended December 31, 2025 decreased approximately $19.2 million compared to the same period in 2024 due to a lack of debt repayments during the current period.

Previous wording

•Due to the changes in derivatives, interest expense, net of capitalized interest and loss on debt extinguishment described above, net income attributable to non-controlling interest during the year ended December 31, 2024 increased approximately $398.6 million as those activities are a component of Intermediate Holdings net income and loss.

Current wording

•Net income attributable to non-controlling interest during the year ended December 31, 2025 decreased approximately $462.4 million primarily due to changes in interest rate swap derivatives and interest expense as those activities are a component of the Joint Ventures’ net loss and income and are consolidated in the Company's results. These changes were partially offset by a decrease in loss on debt extinguishment as the prior year extinguishment was a component of the Joint Ventures’ net income.

Previous wording

The preparation of our Condensed Consolidated Financial Statements in conformity with accounting principles generally accepted in the United States of America (“GAAP”) requires management to make certain estimates and assumptions that affect the amounts reported in the Consolidated Financial Statements and the accompanying notes. Management evaluates its estimates and related assumptions regularly, including those related to the value of properties, plant, and equipment, share-based compensation, common stock warrant liabilities, and income taxes. Changes in facts and circumstances or additional information may result in revised estimates, and actual results may differ from these estimates. Management considers the following to be its most critical accounting estimates that involve significant judgment.

Current wording

The preparation of our Consolidated Financial Statements in conformity with accounting principles generally accepted in the United States of America (“GAAP”) requires management to make certain estimates and assumptions that affect the amounts reported in the Consolidated Financial Statements and the accompanying notes. Management evaluates its estimates and related assumptions regularly, including those related to the value of properties, plant, and equipment, share-based compensation, common stock warrant liabilities, and income taxes. Changes in facts and circumstances or additional information may result in revised estimates, and actual results may differ from these estimates. Management considers the following to be its most critical accounting estimates that involve significant judgment.

Previous wording

Our derivative instruments primarily consist of interest rate swaps. We value our interest rate swaps using observable inputs including interest rate curves, risk adjusted discount rates, credit spreads and other relevant data.

Current wording

Our derivative instruments primarily consist of interest rate swaps. We value our interest rate swaps based on observable market inputs, including SOFR forward curves.
Rearranged current paragraphs (1)

Current report — wording carried from elsewhere

Our discussion and analysis includes the following subjects:
Rearranged previous paragraphs (1)

Previous report — wording carried elsewhere

The Company is developing and beginning the permitting process for additional liquefaction capacity at the Rio Grande LNG Facility. Trains 6 through 8 are wholly owned by NextDecade and are cumulatively expected to increase the Company's total liquefaction capacity by approximately 18 MTPA once constructed and placed into operation.