The White Mesa Mill

General

The White Mesa Mill is a fully licensed uranium, vanadium and REE processing facility located in southeastern Utah, approximately six miles south of the city of Blanding, Utah. The Mill offices are located at 37°32’3.749” north latitude and 109°30’10.297” west longitude. It is within trucking distance of the Company’s conventional properties in Utah, Colorado, Arizona and New Mexico, including the Pinyon Plain Project, the Roca Honda Project, the Bullfrog Project, the La Sal Project and the Whirlwind Project. The Mill is the only fully operational and licensed conventional uranium mill in the U.S. It is capable of functioning independently of off-site support except for commercial power from Rocky Mountain Power and as-needed supplemental water supply from the City of Blanding, Utah, and the San Juan Water Conservancy District. The Mill is a uranium, vanadium and REE processing and recovery facility. It is not an underground or open pit project.

The Mill is licensed to process an average of 2,000 tons of ore per day and to extract over 8.0 million pounds of U 3 O 8 per year. In addition to the conventional circuit, the Mill has a separate vanadium co-product recovery circuit. The mill recently constructed a rare earth separation circuit which allows the Mill to process up to 10,000 tonnes of monazite and produce high purity separated NdPr along with a heavy rare earth concentrate.

In addition to the Mill processing equipment, which includes the grinding and leaching circuits, CCD (liquid–solid separation), solvent extraction, and precipitation and drying circuits, the Mill has several days of reagent storage for sulfuric acid, hydrochloric acid, ammonia, salt, soda ash, caustic soda, ammonium sulfate, flocculants, kerosene, amines, and liquefied natural gas.

The onsite infrastructure also includes a stockpile area capable of storing up to 450,000 tons of mineralized material, and existing tailings capacity of approximately 2.5 million tons of solids. In addition, the Mill has approximately 90 acres of evaporation capacity.

Synthetic lined cells are used to contain tailings and solutions for evaporation. The Company operates two tailings cells and one or more evaporation ponds during normal operations. As each tailings cell is filled, the water is drawn off and pumped to an evaporation pond and the tailings solids are allowed to dry. As each tailings cell reaches final capacity, reclamation begins with the placement of interim cover over the tailings. Additional cells are excavated, and the overburden is used to reclaim previous cells. In this way, there is an ongoing reclamation process.

Currently the Mill employees approximately 100 people. This number varies depending on what circuits (uranium, vanadium or rare earth element) are being operated.

Alternate Feed Materials

The Mill License (defined below) also gives the Company the right to process other uranium-bearing materials known as Alternate Feed Materials pursuant to an Alternate Feed Guidance published by the NRC. Alternate Feed Materials are uranium-bearing materials, other than natural or native ore, usually classified as waste products by the generators of the materials, which can be recycled by the Mill for the recovery of U 3 O 8. The Mill License does not permit the processing of uranium-bearing materials that have undergone enrichment. Requiring a routine amendment to the Mill License for each different Alternate Feed Material, the Company can process these uranium-bearing materials and recover uranium, in some cases at a fraction of the cost of processing conventionally mined material. In other cases, the generators of the Alternate Feed Materials are willing to pay a recycling fee to the Company to process these materials to recover uranium and then dispose of the remaining by-product in the Mill’s licensed tailings cells, rather than directly disposing of the materials at a disposal site. By working with the Company and taking the recycling approach, the suppliers of Alternate Feed Materials can significantly reduce their remediation costs, as there are only a limited number of disposal sites for such materials in the U.S. Alternate Feed Materials are particularly attractive to Energy Fuels because they carry no associated mining costs.

Throughout its history, the Mill has received 18 license amendments, authorizing it to process 22 different Alternate Feed Materials. Of these amendments, twelve have involved the processing of feeds provided by nuclear fuel cycle facilities and private industry, and one has involved the processing of material from the DOE. These thirteen feed materials have been relatively high in uranium content and relatively low in volume. The remaining five amendments have allowed the Mill to process uranium-bearing soils from former defense sites, known as FUSRAP sites, which were being remediated by the USACE. These materials are typically relatively low in uranium content but relatively high in volume.

The Mill has a separate circuit for processing certain types of Alternate Feed Materials, which was built in 2009. This circuit enables the Mill to process both conventionally mined material and Alternate Feed Materials simultaneously.

Rare Earth Elements

In 2021, the Company announced its plans to utilize the Mill to process REEs at commercial scale from a monazite feed source. Monazite is typically produced as part of HMS mining operations and contains elevated quantities of the rare earth suite of elements as well as uranium. Between 2021 and 2023, the Mill successfully recovered rare earths as a mixed RE Carbonate product, which was sold into the rare earth market. Starting in 2023 and completed in early 2024, the Mill installed an RE separation facility (the Phase 1 Circuit), that allows for the production of NdPr oxalate as well as a heavy RE concentrate. The Mill commissioned this facility in 2024 by processing 500 tonnes of monazite and producing 38 tonnes of NdPr oxide. This facility shares the front end crack and leach portion with the uranium circuit, so only one feed (uranium or monazite) can be processed at any given time. The Phase 1 Circuit is capable of processing the equivalent of 8,000 to 10,000 tonnes of monazite annually. The Mill produced pilot-scale quantities of Dy oxide in 2025 and expects to produce pilot-scale quantities of Tb oxide in early 2026. The Company is planning further enhancements to expand its heavy REE production at its existing Phase 1 Circuit for the planned recovery of Dy, Tb, Sm, Eu and Gd, with the ability to separate other heavy REEs such as Y and Lu if market conditions warrant, subject to the receipt of regulatory approvals, financing, completion of engineering and the receipt of sufficient feed materials. The Company also plans to expand its NdPr, Dy and Tb production capability and potentially other REE material production capability in the future through the development, subject to the receipt of regulatory approvals, financing, completion of engineering and the receipt of sufficient feed materials, of its proposed stand-alone Phase 2 Circuit with a total planned capability (from the Phase 1 Circuit and Phase 2 Circuit) of up to approximately 6,000 tonnes of NdPr, 200 tonnes of Dy and 60 tonnes of Tb per year, along with other REEs, described in more detail below, from monazite concentrates, MREC or similar feed materials. A Feasibility Study on the expanded monazite processing Phase 2 Circuit was completed in December 2025. The Mill is uniquely suited to process monazite and extract both the REEs as well as the uranium. See Part I, Item 1. The Company’s Rare Earth Elements Business and Part II, Item 7. Rare Earth Elements Segmentfor a more detailed discussion of the Company’s REE initiatives.

Potential Recovery of Radioisotopes for use in Advanced Cancer Therapeutics

In 2021, the Company announced the execution of a Strategic Alliance Agreement with RadTran, a technology development company focused on closing critical gaps in the procurement of medical isotopes for emerging TAT cancer therapeutics and other applications. RadTran was acquired by the Company in 2024. The Company is evaluating the feasibility of recovering Th-232, and Ra-226, from its existing REE and uranium process streams at the Mill and is evaluating the feasibility of recovering Ra-228 from the Th-232, potentially Th-228 from the Ra-228 and concentrating Ra-226 at the Mill. Recovered Ra-228, Th-228 and Ra-226 would then be sold to pharmaceutical companies and others to produce Pb-212, Ac-225, Bi-213, Ra-224 and/or Ra-223, which are the leading medically attractive TAT isotopes for the treatment of cancer. Existing supplies of these isotopes for TAT applications are in short supply, and methods of production are costly and currently cannot be scaled to meet the demand created as new drugs are developed and approved. This is a major roadblock in the R&D of new TAT drugs as pharmaceutical companies wait for scalable and affordable production technologies to become available. Under this initiative, the Company has the potential to recover valuable isotopes from its existing process streams, thereby recycling back into the market material that would otherwise be lost to disposal for use in treating cancer. See Part I, Item 1. Business Overview - The Company’s Strategic Alliance for the Development of Radioisotopes for Medical Therapeutics for a more detailed discussion of this initiative.

The Mill is located in central San Juan County, Utah, approximately six miles (9.5 km) south of the city of Blanding. It can be reached by taking a private road for approximately 0.5 miles west of U.S. Highway 191.

The climate of southeastern Utah is classified as dry to arid continental. Although varying somewhat with elevation and terrain, the climate in the vicinity of the Mill can be considered as semi-arid with normal annual precipitation of about 13.4 inches. The weather in the Blanding area is typified by warm summers and cold winters. The mean annual temperature in Blanding is about 50°F. Winds are usually light to moderate in the area during all seasons, although occasional stronger winds may occur in the late winter and spring.

The Mill site is located on a gently sloping mesa that, from the air, appears similar to a peninsula, as it is surrounded by steep canyons and washes and is connected to the Abajo Mountains to the north by a narrow neck of land. On the mesa, the topography is relatively flat, sloping at less than one (1) percent to the south and nearly horizontal from east to west.

The natural vegetation presently occurring within a 25-mile (40-km) radius of the Mill site is very similar to that of the region, characterized by pinyon-juniper woodland integrating with big sagebrush (Artemisia tridentata) communities.

Off-site infrastructure includes paved highway access from U.S. Highway 191 and rights-of-way for commercial power and a water supply pipeline from Recapture Reservoir, which brings up to 1,000 acre-feet of water per year to the Mill site. The Mill also has three deep (2,000+ foot) water supply wells, which are available to supply process water during normal operations.

The White Mesa Mill is located on 4,816 acres of private land owned in fee by Energy Fuels. This land is located in Township 37S and 38S Range 22E Salt Lake Principal Meridian. Energy Fuels also holds 253 acres of mill site claims and a 320-acre Utah state lease. No facilities are planned on the mill site claims or leased land, which are used as a buffer to the operations. Total holding costs for the Mill in 2025 were $15,600.

All operations authorized by the Mill’s License are conducted within the confines of the existing site boundary. The milling facility currently occupies approximately 50 acres, and the current tailings disposal cells encompass another 250 acres.

The White Mesa Mill holds a Radioactive Materials License through the State of Utah (the “Mill License”). Uranium milling in the U.S. is primarily regulated by the NRC pursuant to the Atomic Energy Act of 1954, as amended. The NRC’s primary function is to ensure the protection of employees, the public and the environment from radioactive materials, and it also regulates most aspects of the uranium recovery process. The NRC regulations pertaining to uranium recovery facilities are codified in Title 10 of the Code of Federal Regulations. These regulations also apply to our ISR facilities in Wyoming and Texas.

On August 16, 2004, the State of Utah became an Agreement State for the regulation of uranium mills. This means that the primary regulator for the Mill is the UDEQ rather than the NRC. At that time, the Source Material License, which was previously issued and regulated by the NRC, was transferred to the State and became a Radioactive Materials License. The

State of Utah incorporates, through its own regulations or by reference, all aspects of Title 10 pertaining to uranium recovery facilities. The Mill License was due for renewal on March 31, 2007. Energy Fuels’ predecessor timely submitted its application for its Mill License renewal on February 28, 2007. The renewed Mill License was issued by UDEQ on January 19, 2018, then reissued on February 16, 2018, for a period of ten years (with a number of Amendments issued since), after which another application for renewal will need to be submitted. During the review period for each application for renewal, the Mill can continue to operate under its then existing Mill License until such time as the renewed Mill License is issued. The Mill License was initially issued in 1980 and was also renewed in 1987 and 1997.

When the State of Utah became an Agreement State, it required that a GWDP be put in place for the Mill. The GWDP is required for all similar facilities in the State of Utah and implements the State groundwater regulations to the Mill site. The State of Utah requires that every operating uranium mill have a GWDP, regardless of whether the facility discharges to groundwater. The GWDP for the Mill was finalized and implemented in March 2005. The GWDP required that the Mill add over 40 additional monitoring parameters and 15 additional monitoring wells at the site. The GWDP came up for renewal in 2010, at which time an application for renewal was timely submitted. The renewed GWDP was issued by UDEQ on January 19, 2018 for a period of five years. An application for renewal of the GWDP was submitted on July 15, 2022, prior to expiration of the current GWDP. The application remains under consideration at this time. During the review period for each application for renewal, the Mill can continue to operate under its then existing GWDP until such time as the renewed GWDP is issued. The Mill also maintains a permit for air emissions with the UDEQ, Division of Air Quality.

The Mill is subject to decommissioning liabilities. Energy Fuels, as part of the Mill License, is required to annually review its estimate for the decommissioning of the Mill site and submit it to UDEQ for approval. The estimate of closure costs for the Mill is $25.7 million as of December 31, 2025, and financial assurances will be in place for the total amount in early 2026. However, there can be no assurance that the ultimate cost of such reclamation obligations will not exceed the estimated liability contained in the Company’s financial statements.

History

The Mill was originally constructed and owned by Energy Fuels Nuclear, Inc. (“EFN”) and its affiliates (no relation to the Company). It was licensed by the NRC and commenced operations in June 1980. In 1984, EFN transferred a 70% interest in the Mill to UMETCO Minerals Corp., a subsidiary of Union Carbide Corporation (“UMETCO”). UMETCO became the operator of the Mill in 1984 and continued to be the operator until 1994, at which time UMETCO transferred its interest in the Mill back to EFN and its affiliates. The Mill was acquired by Denison Mines Corp. (“Denison”), then named International Uranium Corporation (“IUC”) and its affiliates in 1997 and was operated by Denison until it was acquired by the Company in June 2012. From the original commissioning in 1980 through December 31, 2025, the Mill has recovered a total of approximately 40 million pounds of U 3 O 8 and 46 million pounds of vanadium.

In late 2006, Denison began a program to refurbish the Mill. The refurbishment program included the purchase of mobile equipment, restoration of the vanadium roasting, fusion and packaging circuits, replacement of major pumps and component drives, modernization of the Mill’s instrumentation and process control systems, and completion of relining tailings Cell 4A. The total cost of the refurbishment program was approximately $31.0 million and was completed in 2008.

The Mill has historically operated on a campaign basis. In 2008, the Mill began processing uranium/vanadium conventional mined material, extracting uranium concentrate in the form of U 3 O 8, and vanadium in the form of V 2 O 5. Mineral processing continued through the end of March 2009, at which time maintenance activities were performed at the Mill. Mineral processing recommenced near the end of April 2009 but was discontinued due to a decline in uranium prices at the time. The Mill began mineral processing again in March 2010 and continued through June 2011. Conventional processing recommenced in November 2011 and continued until early March 2012, at which time it ceased for routine maintenance. Conventional mineral processing recommenced at the Mill in August 2012 and continued until early June 2013. Mineral processing began again in May 2014 and continued through August 2014. The alternate feed circuit processed materials from January through December 2014 and continued processing Alternate Feed Materials through December 2015. In 2016, the Company continued processing several Alternate Feed Materials and processed 45,057 tons of mineralized material from its Pinenut mine. In 2017 and 2018, the Mill continued processing Alternate Feed Materials as well as the recovery of uranium from tailings pond solutions at the site. In 2020, Mill activities focused solely on processing Alternate Feed Materials and uranium and vanadium recovery from tailings pond solutions at the site. In 2021, Mill activities focused solely on processing monazite from HMS operation for the recovery of U 3 O 8 and REEs. In 2023, the Mill processed monazite feeds to produce approximately 260 metric tonnes of partially separated rare earth oxides in the form of REE carbonate, and in 2024 the Mill processed 500 tonnes of monazite for the production of 38 tonnes of NdPr oxide.

Energy Fuels acquired the Mill from Denison Mines Corp. on June 29, 2012. All mineral processing after that date has been for the account of Energy Fuels.

Project or Source(1)20252024202320222021
Conventional Feed Materials (Conventional Uranium Mineralized Material)(2)
Tons (000)134.555———
Contained Grade % U3O80.320.11———
Recovered Pounds U3O8 (000)765.578———
Conventional Feed Materials (Uranium Mineralized Material – Monazite)(3)
Tons (000)—0.550.360.40.39
Contained Grade % U3O8—0.380.460.450.5
Contained Grade % TREO—46.3347.2546.7953.45
Recovered Pounds U3O8 (000)(9)—2—1—
Recovered Metric Tons Total Rare Earth Oxide (TREO)(4)—381609374
Recovered Metric Tons NdPr Oxide (or equivalent)(5)—38———
Alternate Feed Materials(6)
Tons (000)3.01—3—
Ave. % U3O85.05.27—3.3—
Recovered Pounds U3O8 (000)18677.4—161—
Tailings Solution Recycle & Production from In-Circuit Material(8)
Recovered Pounds U3O8 (000)63————
Recovered Pounds V2O5 (000)—————
Recovered Metric Tons Total Rare Earth Oxide (TREO)—————
Total Pounds of U3O8 Recovered (000)1,014.5157.4—162—
Total Pounds of V2O5 Recovered (000)—————
Total Metric Tons of TREO Recovered——1609374
Total Metric Tons of NdPr Oxide (or equivalent) Recovered—38———

Notes:

(1)Mineralized material is shown as being processed and pounds recovered during the year in which the materials were processed at the Mill, which is not necessarily the year in which the materials were extracted from the project facilities.

(2)Conventional mineralized material include uranium mineralized material produced at conventional uranium mines owned by the Company (the Pinyon Plain, La Sal and Pandora mines) and third-party ore received from regional uranium mines.

(3)Includes uranium and TREO recovered from monazite processing.

(4)Inclusive of recovered metric tonnes NdPr oxide (or equivalent) in line below.

(5)In 2024, the Mill produced an NdPr oxalate. The number reported is the equivalent quantity of NdPr oxide assuming that the NdPr oxalate was calcined and converted to an oxide.

(6)All Alternate Feed Materials were processed at the Mill. A number of different Alternate Feed Materials were processed during the period from 2021 through 2025. The table shows the average uranium grades and the total pounds recovered from all Alternate Feed Materials processed at the Mill during each of the years in that period. Because of the variability in uranium grades, pounds recovered is considered to be the relevant metric and tons fed is not considered to be relevant.

(7)The 1,014,500 pounds recovered in 2025 include nil pounds recovered for the accounts of third parties. The 77,400 pounds recovered in 2024 include nil pounds recovered for the accounts of third parties. The 161,000 pounds recovered in 2022 include nil pounds recovered for the accounts of third parties.

(8)Pounds contained in tailings solutions containing previously unrecovered uranium and vanadium, together with in-circuit mineralized material from previous conventional mine material processing, were recovered at the Mill, though tons and grade are not available because they cannot be tied to any specific source.

(9)Uranium recovered in 2022 from monazite processing includes the uranium remaining in circuit from 2021 processing of monazite, and uranium recovered in 2024 includes the uranium remaining in circuit from previous 2023 processing of monazite. Uranium recovered in 2025 from monazite processing is the uranium remaining in circuit from 2024 processing of monazite.

Present Condition of the Property

Planned Operations and Maintenance

The Mill recovered 1,015,000 pounds of U 3 O 8 during 2025. The uranium was produced from a combination of alternate feeds and conventional ore.

Environmental Matters

Prior to Energy Fuels’ acquisition of the Mill from Denison, chloroform in the shallow aquifer at the Mill site was discovered. The chloroform appears to have resulted from the operation of a temporary laboratory facility that was located at the site prior to and during the construction of the Mill, and from septic drain fields that were used for laboratory and sanitary wastes prior to construction of the Mill’s Tailings Management System (“TMS”). In April 2003, Denison commenced an interim remedial program of pumping the chloroform affected water from the groundwater to the Mill’s TMS. This action enabled Energy Fuels to begin cleanup of the affected areas and to take a further step towards resolution of this outstanding issue. Pumping from the wells continued through 2015. On September 14, 2015, the State of Utah approved a long-term Corrective Action Plan (“CAP”) for cleanup of the chloroform, which involves additional pumping wells and continued pumping of the affected water to the Mill’s TMS. While the investigations to date indicate that this chloroform appears to be contained in a manageable area, the scope and costs of final remediation have not yet been determined and could be significant.

Prior to Energy Fuels’ acquisition of the Mill from Denison, elevated concentrations of nitrate and chloride were observed in some of the monitoring wells at the Mill site in 2008, a number of which are upgradient of the Mill’s TMS. Pursuant to a Stipulated Consent Agreement with UDEQ, Denison retained INTERA, Inc., an independent professional engineering firm, to investigate these elevated concentrations and to prepare a Contamination Investigation Report for submittal to UDEQ. The investigation was completed in 2009, and the Contamination Investigation Report was submitted to UDEQ in January 2010. INTERA concluded in the Report that: (1) the nitrate and chloride are co-extensive and appear to originally come from the same source; and (2) the source is upgradient of the Mill property and is not the result of Mill activities. UDEQ reviewed the Report and concluded that further investigations were required before it could determine the source of the contamination and the responsibility for cleanup. Such investigations were performed in 2010 and 2011 but were considered inconclusive by UDEQ. As a result, after the investigations, it was determined that there are site conditions that make it difficult to ascertain the source(s) of contamination at the site, and that it was not possible at that time to determine the source(s), causes(s), attribution, magnitude(s) of contribution, and proportion(s) of the local nitrate and chloride in groundwater. For those reasons, UDEQ decided that it could not eliminate Mill activities as a potential cause, either in full or in part, of the contamination. The Company and UDEQ have therefore agreed that resources are better spent in developing and implementing a CAP, rather than continuing with further investigations as to the source(s) and attribution of the groundwater contamination. Pursuant to a revised Stipulated Consent Agreement, Denison submitted a draft CAP for remediation of the contamination to UDEQ in November 2011. The CAP proposed a program of pumping the nitrate contaminated groundwater to the Mill’s tailings cells, similar to the chloroform remedial program. On December 12, 2012, the Utah DWMRC, signed the Stipulation and Consent Order (“SCO”), Docket Number UGW12-04, which approved the Mill’s CAP dated May 7, 2012 and required the Mill to fully implement all elements of it. In accordance with the CAP, in 2013 the Company commenced pumping nitrate/chloride contaminated water from four monitoring wells for use in Mill processing or discharge into the Mill’s process or TMS. In December 2017 the Mill filed its first Corrective Action Comprehensive Monitoring Evaluation (“CACME”), required under the CAP every five years. By letter dated June 22, 2018, the DWMRC requested the implementation of Phase III actions specified in the CAP. Phase III actions include modeling, and study of plume dynamics and assessment of future actions if any. The Phase III report was submitted to DWMRC in December 2018 and is currently under review by DWMRC. Although the contamination appears to be contained in a manageable area, the scope and costs of final remediation have not yet been determined and could be significant.

The Mill has reported consecutive exceedances of groundwater compliance limits (“GWCLs”) under the Mill’s GWDP for several constituents in several wells. These exceedances include wells that are up-gradient of the Mill facilities, far down-gradient of the Mill site cross-gradient of the Mill site and at the site itself. As required by the GWDP, these consecutive exceedances of GWCLs have resulted in the completion of constituent specific assessments and additional studies which are documented in Source Assessment Reports. Source Assessment Reports were submitted addressing each exceedance at the site. UDEQ has accepted the Source Assessment Reports and has concluded that such exceedances are due to natural background influences at the site. Amendments to the GWDP issued on January 19, 2018, March 19, 2019 and March 8, 2021, respectively, include revised GWCLs intended to account for these background influences and put the constituents back into compliance. Most recently, a GWDP renewal application was submitted in July 2022 and remains under consideration by DWMRC at this time.

Total Cost of Project

The Mill was acquired by the Company in June 2012, through the acquisition of the U.S. Mining Division from Denison. The cost of the Mill was fully impaired. As a result of capital investments made at the Mill over the last year, primarily to the Phase 1 Circuit, and the total net book value attributable to the Mill and its associated equipment on the financial statements of the Company was $28.79 million, as of December 31, 2025.

During 2026, the Company expects to continue the processing of conventional ores. Rare earth products may be produced depending on market conditions and the availability of monazite feedstocks. In addition, The Company plans to advance permitting, detailed engineering and financing on its planned Phase 2 Circuit as well as advance permitting, engineering and financing on its proposed expansions to its existing Phase 1 Circuit.

The Company is planning enhancements to expand its heavy REE production at its Phase 1 Circuit for the planned commercial-level recovery of Dy, Tb, Sm, Eu and Gd, with the ability to separate other heavy REEs such as Y and Lu if market conditions warrant. Subject to receipt of all required regulatory approvals, financing, the successful development of these enhancements and the receipt of sufficient quantities of monazite sand feedstock, the expanded Phase 1 Circuit is expected to be operational in 2027 with planned production recovery of up to approximately 35 tonnes of Dy, 12 tonnes of Tb per year and potentially other heavy REEs, in addition to the 850 – 1,000 tonnes of NdPr, from processing up to approximately 10,000 tonnes of monazite per year. The Company had previously announced its intention to start commercial production of Dy and Tb by the end of 2026, but has changed those plans in order to expand the enhancements to the Mill’s Phase 1 Circuit to allow for the additional production of Sm, Eu and Gd and to provide the ability to separate other heavy REEs in the 2027 time frame.

At the same time as these enhancements are being made to the Phase 1 Circuit, the Company plans to make further enhancements to the Phase 1 Circuit to allow for the processing of uranium- and REE-bearing MREC or similar intermediary REE products from third-party sources in the Phase 1 Circuit, subject to receipt of all regulatory approvals, financing and the successful development of these further enhancements. As MREC or similar intermediary REE products would not need to utilize the Phase 1 Circuit’s crack and leach circuits it is expected that such products could be separated into NdPr and heavy REEs separately from uranium production, thereby allowing such feedstocks to be separated into REE oxides through the Phase 1 Circuit’s SX circuits without interfering with normal Mill conventional uranium ore processing, which could be run simultaneously with the separation of such feedstocks. These enhancements are expected to be made and the Phase 1 Circuit operational to accept MREC and similar intermediary REE products in 2027.

The Company also plans to expand its NdPr, Dy and Tb production capability and potentially other REE material production capability through the development of its stand-alone Phase 2 Circuit, subject to the receipt of regulatory approvals, financing, completion of engineering and the receipt of sufficient feed materials. The Company submitted a license amendment application to DWMRC for approval of the proposed Phase 2 Circuit in November 2025.

In January 2026, the Company announced the results of a new AACE International Class 3 Bankable Feasibility Study (“BFS”) evaluating a planned Phase 2 Circuit expansion of REE processing capabilities at the Mill. The BFS evaluated the construction of the Phase 2 Circuit designed to materially expand the Mill’s ability to process monazite and other REE-bearing feedstocks into separated REE oxides. Upon commissioning, the Phase 2 Circuit is expected to increase the Mill’s REE oxide production capacity from approximately 850 to 1,000 tpa of NdPr oxide from the Phase 1 Circuit, to over 6,000 tpa of NdPr oxide, along with approximately 60 tpa of Tb and 200 tpa of Dy oxides from the combined Phase 1 Circuit and Phase 2 Circuit. This would provide the capability to produce sufficient NdPr up to approximately 7.0 million EVs/hybrid EVs per year. The Phase 2 Circuit would also add a dedicated monazite “crack-and-leach” circuit to the Mill’s existing leach circuits, which would allow the Phase 2 Circuit to be run completely independent of (and simultaneously with) the Mill’s conventional uranium and uranium/vanadium production.

The BFS estimates initial capital costs of approximately $410.0 million and indicates attractive projected economics, including significant expected annual earnings before interest, taxes, depreciation and amortization (“EBITDA”) over the modeled project life. As the BFS evaluates a processing facility rather than a mineral property, it is not intended to constitute, and does not constitute, a feasibility study prepared in accordance with S-K 1300 on NI 43-101.

The Phase 2 Circuit expansion is intended to position the Company as a leading domestic processor of both light and heavy REE oxides, supporting the restoration of a secure U.S.-based REE supply chain. The BFS assumes feedstock supply from the Company’s existing HMS and monazite projects, as well as third-party sources including MREC and similar feedstocks, subject to permitting, development and market conditions.