EX-99.2 · PHASE 2 DEVELOPMENT PROGRESS
PHASE 2 DEVELOPMENT PROGRESS
During the calendar year-ended 2023, Sigma Lithium continued to advance development work for a potential Phase 2 or 2 & 3 production expansion, after announcing the results of the Phase 2 & 3 pre-feasibility study (“PFS”) in December 2022. On April 1st, 2024, Sigma Lithium announced that its Board of Directors had made a Final Investment Decision (“FID”) on its Phase 2 plans. The second Greentech line is expected to increase the Company’s capacity of Green Lithium concentrate by 250,000 tons per year, at a total capital expenditure budgeted of $136 million (see Table 4 below). The full license to build and operate the new industrial plant (“Phase 2”) was awarded to the Company in the first quarter of 2024.
The Phase 2 & 3 PFS investigated the opportunity to fast-track Phase 3 production and to build a dual plant which could process both Phase 2 and Phase 3 ore feed simultaneously to deliver a greater production increase in 2025 (if warranted by feasibility study) versus the sole Phase 2 expansion originally envisioned in the Phase 2 preliminary feasibility study completed in May 2022. However, as lithium markets have evolved, the Company has shifted its plans back towards a more incremental approach to expansion. Accordingly, the Company engaged its local Phase 1 Engineering Purchase Construction Management (“EPCM”) contractor to direct Engineering and Construction initiatives on a rebuild of its Phase 1 plant, which is expected to nearly double the Company’s existing production capacity.
| | | |
|---|---|---|
| | | 5 |
| | | |
|---|---|---|
| SIGMA LITHIUM CORPORATIONMANAGEMENT’S DISCUSSION AND ANALYSISFOR THE THREE & TWELVE MONTHS ENDED DECEMBER 31, 2023(Expressed in thousands of Canadian dollars, except per share amounts or unless stated otherwise) | ||
| | | |
The Phase 2 Project is expected to increase production capacity by 250,000 tons per annum of spodumene concentrate from Sigma’s Grota do Cirilo operations. Once in production, Phase 2 Project is expected to lift Sigma’s total nameplate capacity to roughly 520,000 tonnes per annum. The Company plans to begin Phase 2 earthworks in April 2024 and is targeting commissioning of the crushing circuit to begin in late 2024.