EX-99.2 · Operations Analysis

Operations Analysis

Gibraltar

Third Quarter Review

Gibraltar delivered another strong quarter of operating performance, supported by higher grade ore mined from the lower benches of the Connector pit. Gibraltar produced 33.9 million pounds of copper in the quarter, including 1.3 million pounds of copper cathode.

Mill throughput was 7.5 million tons in the third quarter, compared to 7.2 million tons in the second quarter. Copper head grades averaged 0.28% and recoveries averaged 77% and were impacted by lower-recovery supergene ore from the upper benches of the next phase of mining.

The Gibraltar SX/EW plant operated with material from two leach pads during the third quarter following the successful integration of the second heap leach dump, and benefitted from increased PLS flow rates and grade. The additional leach material contributed to higher copper cathode production of 1.3 million pounds in the third quarter.

A total of 26.1 million tons were mined in the third quarter at an average strip ratio of 2.2, as ongoing waste stripping activities continued to provide access to the next phases of the Connector pit.

Gibraltar copper sales totaled 30.4 million pounds in the quarter. Sales were affected by the timing of shipments resulting in a build-up of an additional 3.0 million pounds of inventory during the quarter.

Gibraltar total site costs* were $144.5 million (including capitalized stripping of $10.2 million) in the third quarter, which is in line with the previous two quarters but higher than the prior year. Diesel costs increased $9.6 million compared to the third quarter of 2025, primarily driven by higher diesel prices as a result of the ongoing conflict in the Middle East. Explosives costs increased $3.9 million compared to the third quarter of 2025, primarily driven by higher explosives prices. Other site costs have generally trended higher than 2025 due to broader inflationary pressures.

Molybdenum production was 380 thousand pounds in the third quarter and reflects lower recoveries in the Gibraltar molybdenum plant. At an average molybdenum price of US$32.98 per pound for the quarter, molybdenum provided a by-product credit of US$0.35 per pound of copper produced.

Off-property costs were US$0.24 per pound of copper produced in the third quarter, compared to US$0.17 per pound of copper produced in the third quarter of 2025, reflecting higher treatment and refining charges ("TCRC") for the last year of a longer-term contract.

Total operating costs (C1)* were US$2.72 per pound of copper produced for the third quarter, compared to US$2.87 per pound of copper produced for the third quarter of 2025. The decrease in total operating costs (C1)* was primarily driven by higher copper production and higher capitalized stripping costs, partially offset by higher site costs.

Gibraltar Outlook

Gibraltar continues to provide consistent operating performance. Mining operations are focused in the Connector pit, which will be the primary source of ore for the next several years. Lower grades and recoveries are expected as mining transitions back to the upper benches of the Connector Pit for the next phase of mining. The second heap leach pad was integrated into the Gibraltar SX/EW circuit earlier this year and should continue to provide higher PLS flow rates and grades going forward. Gibraltar is expected to produce 115 to 120 million pounds of copper in 2026, an increase over original production guidance of 110 to 115 million pounds.

Site landed diesel prices remain elevated due to the continued conflict in the Middle East. Diesel prices are currently around $0.85 per litre higher than February pre-war levels. These higher diesel prices have increased Gibraltar's operating costs by approximately US$0.20 per pound over 2025 levels.

Molybdenum production is expected to remain at similar levels as Gibraltar advances through the Connector pit. Strong molybdenum by-product credits are expected to continue with current molybdenum prices around US$33.00 per pound.

The Company has offtake agreements covering Gibraltar's copper concentrate production for the remainder of 2026, which contain low, and in certain cases, negative treatment and refining charges ("TCRCs") reflecting the continued tight copper smelting market. Based on the contract terms, the Company expects overall TCRCs to be nominal in 2026. The Company has also tendered substantially all of its 2027 tonnage to take advantage of favorable market conditions obtaining terms which include payable gold and deeply negative TCRCs.

The Company has a prudent hedging program in place to protect a minimum copper price. Currently, the Company has copper put options in place with a strike price of US$4.75 per pound for 27 million pounds covering the fourth quarter of 2026, and US$5.00 per pound for 45 million pounds covering the first half of 2027. The Company expects to purchase copper put options going forward to provide downside price protection while retaining full exposure to increases in the copper price. Refer to "Financial Condition Review-Hedging Strategy" for details.

Florence Copper

Third Quarter Review

Operating dataQ3 2026Q2 2026
Florence Copper
Average PLS1 flow rate (gpm)4,4543,182
Average PLS grade (g/L)1.51.6
Operating production well count141110
Copper cathode
Production (million pounds Cu)7.05.2
Sales (million pounds Cu)6.95.3
Inventory (million pounds Cu)1.00.8
Per unit data (US$ per Cu pound produced)
Site operating cost*$2.89$4.02
Production royalties2 and other off-property costs*0.650.70
Total operating cost (C1)*$3.54$4.72

1 Pregnant leach solution.

2 Production royalties include royalties payable to the State of Arizona and Conoco Phillips Inc.

Florence Copper is an in-situ copper recovery operation, located in Arizona, USA, designed to produce LME Grade A copper cathode without conventional open-pit mining methods or major surface disturbance. Florence Copper has an annual production capacity of 85 million pounds of copper over the current mine life of 22 years.

Florence Copper is ramping-up production in 2026 and steady progress continued in the third quarter. Copper production increased month-over-month and no wellfield performance issues of any significance were encountered. The operations team has stabilized key process circuits and is focusing on wellfield flow rates and PLS grades. Florence Copper produced 7.0 million pounds of copper cathode in the third quarter compared to 5.2 million pounds in the previous quarter, driven by higher solution flow rates from the wellfield.

There are currently six drill rigs operating on site. The first new production wells were successfully integrated into the system in early June, resulting in higher solution flow rates and PLS grades and increased copper production. At the end of the third quarter, there were 141 production wells providing solutions to the SX/EW plant at flow rates of approximately 5,100 gallons per minute and PLS grades of 1.5 grams per litre.

Copper cathode sales for the third quarter were 6.9 million pounds. Cathode quality has met all customer specifications and trucking logistics have been running smoothly.

Florence Copper site costs(US$ in thousands)Three months endedSeptember 30, 2026Nine months endedSeptember 30, 2026
Wellfield development capital expenditures25,45765,007
Commissioning and start-up costs-15,175
Site operating costs24,45755,684
Total site costs49,914135,866