Trekor Metals Ltd
For the period ended Dec 31, 2023. Filed Mar 28, 2024.
View on SEC.govAbout this filing
The yearly report of certain Canadian companies, filed under a joint US and Canadian system. It is the main yearly account these companies give US investors, largely as filed in Canada.
FY2023 · Filed Mar 28, 2024
Use the contents to explore the available documents and sections.
Contents
EX-99.2 · 24. COMMITMENTS AND CONTINGENCIES (CONTINUED)
24. COMMITMENTS AND CONTINGENCIES (CONTINUED)
(c) Mitsui financing
On December 19, 2022, the Company signed agreements with Mitsui & Co. (U.S.A.) Inc. ("Mitsui") to form a strategic partnership to develop the Company's Florence Copper project. Mitsui has committed to an initial investment of US$50 million conditional on receipt of the final Underground Injection Control permit from the Environmental Protection Agency, with proceeds to be used for construction of the commercial production facility. The initial investment will be in the form of a copper stream agreement (the "Copper Stream") on 2.67% of the copper produced at Florence Copper and Mitsui to pay a delivery price equal to 25% of the market price of copper delivered under the contract.
In addition, Mitsui has acquired an option to invest an additional US$50 million for a 10% equity interest in Florence Copper (the "Equity Option"). The Equity Option is exercisable by Mitsui at any time up to three years following completion of construction of the commercial production facility. If Mitsui elects to exercise its Equity Option, the Copper Stream will terminate. If the Equity Option is not exercised by Mitsui by its expiry date, the Company will have the right to buy-back 100% of the Copper Stream, otherwise, it will terminate when 40 million pounds of copper have been delivered under the agreement.
As part of the arrangement, Taseko and Mitsui have entered into an offtake contract for 81% of the copper cathode produced at Florence during the initial years of production. The initial offtake agreement will cease and be replaced with a marketing agency agreement if the Equity Option is exercised by Mitsui. Mitsui's offtake entitlement would also reduce to 30% if the Equity Option is not exercised by its expiry date until the Copper Stream deposit has been reduced to nil.
For accounting purposes, the Mitsui agreements include derivatives that are required to be fair valued at each reporting period. The Company has determined that the fair value of the derivatives is negligible as of December 31, 2023 based on the contingent nature of the Mitsui agreements and the consideration of other relevant factors.
On January 26, 2024, the Company received the first US$10 million of the US$50 million Copper Stream. The remaining amounts are payable on a quarterly instalment basis.
TASEKO MINES LIMITEDNotes to Consolidated Financial Statements(Cdn$ in thousands)
The text of this filing, as the company filed it with the SEC, without its images or exhibits. This is not investment advice.