FIRSTENERGY CORP
For the period ended Dec 31, 2025. Filed Feb 18, 2026.
View on SEC.govAbout this filing
A company's yearly report to the SEC, with audited financial statements. It is the fullest account a company gives of its business, its finances and the risks it sees.
FY2025 · Filed Feb 18, 2026
What changed in Risk Factors?
Read the current filingPrevious report: 10-K
Period ended 2024-12-31; filed 2025-02-27.
0001031296-25-000006
Item 1A. RISK FACTORSCurrent report: 10-K
Period ended 2025-12-31; filed 2026-02-18.
0001031296-26-000046
Item 1A. RISK FACTORSThe baseline is this issuer’s latest earlier reporting period of the same form that was filed before the current report. A previous 10-Q is a different quarter, not a year-over-year comparison. Amendments are excluded.
Compared 156 previous paragraphs and 141 current paragraphs.
62 unchanged; 69 reworded; 9 added; 24 removed; 1 previous and 1 current paragraphs rearranged.
Tables are not compared: 0 previous and 0 current tables excluded. Dates, whitespace, punctuation and numbering changes are ignored; changes to financial figures remain significant.
A changed paragraph is not evidence that risk increased or decreased. An unchanged paragraph does not establish that risk stayed the same.
Added paragraphs (9)
Current report
FERC, at the instruction of the U.S. Secretary of Energy, is also considering whether to develop regulations intended to speed interconnection of AI data centers and “hybrid” data center/electric generation facilities (collectively, “large loads”) to the transmission system. Final regulations, if any, from FERC are expected in the second quarter of 2026. To the extent the new regulations promulgated by FERC do not permit transmission utilities to fully recover costs associated with transmission network upgrades required to serve new large loads, our strategy of investing in transmission could be adversely affected.
Current report
External pressures beyond our control may increase customer rates and, when combined with state and federal regulatory action to mitigate bill impacts, may impair our ability to earn a fair and equitable return on our investments and execute our strategy.
Current report
PJM’s recent capacity auctions have been subject to a “price collar” that has resulted from all-time high generation capacity prices in recent auction outcomes. These all-time high capacity prices ultimately are passed through in retail rates and can result in material increases in retail customers’ monthly electric utility bills. On January 16, 2026, the PJM board along with various federal and state officials, expressed interest in extending the price collar through mid-2030.
Current report
In addition, the parties to the Statement of Principles suggested that PJM should conduct a “backstop” auction to procure additional generation capacity, with the costs to be allocated first to “new” data centers and second to existing PJM loads. If the PJM capacity auctions continue to clear at the auction cap, and if PJM conducts a “backstop” capacity auction that clears at a high price point, customer resistance to the resulting market driven increases on the generation portion of their bills could lead to increased pressure for state and federal utility regulators to limit the needed capital investment in transmission and distribution systems required for safe, reliable and resilient service to customers, which may impair our ability to earn a fair and equitable return on our investments and execute our strategy.
Current report
Our investments in transmission and distribution infrastructure modernization, reliability improvements, environmental compliance and storm hardening may increase customer bills over time and the resulting higher electric bills, when combined with the external pressures discussed above, may place pressure on residential customers’ affordability, particularly in portions of our service territory with lower median household income or high energy burdens and/or amongst those customers who have already seen significant retail bill increases. State and federal regulators may also adopt or modify policies intended to mitigate customer bill impacts – including disallowance or delayed recovery of certain capital investments or operating expenses, mandated bill assistance programs, changes to rate design, or restrictions on rate increases. Customer concerns regarding affordability may result in increased regulatory scrutiny, constraints on the size and timing of rate increases, expanded bill mitigation requirements, or disallowances, any of which could adversely affect our ability to recover costs or earn our authorized return on equity. In addition, sustained increases in customer bills may lead to reduced electricity usage through conservation, energy efficiency, or distributed generation, which could limit future load growth and revenues.
Current report
Regulatory agencies may also require utilities to offset portions of rising costs related to grid modernization, resilience investments, environmental compliance, or rapidly evolving market conditions if they determine that such costs would unduly affect customer affordability. Any such actions could limit or delay our ability to recover costs or investments, earn a fair and equitable return, or maintain expected cash flows and could have an adverse effect on our businesses, financial condition, results of operations and cash flows.
Current report
Additionally, the operations of the Electric Companies are affected by the economic conditions in their respective service territories and those conditions could negatively impact the rate of delinquent customer accounts and our collections of accounts receivable, which could adversely impact our financial condition, results of operations and cash flows.
Current report
JCP&L may recognize impairments of recorded goodwill, which would result in write-offs of the impaired amounts and could have an adverse effect on its results of operations. (Applies to JCP&L)
Current report
JCP&L had approximately $1.8 billion of goodwill on our balance sheet as of December 31, 2025. Goodwill is tested for impairment annually, as of July 31, or whenever events or circumstances indicate impairment may have occurred. JCP&L is unable to predict the actual timing and amounts of any impairments in future years, which would depend on many factors, including interest rates, sector market performance, JCP&L’s capital structure, results of future rate proceedings, operating and capital expenditure requirements, the value of comparable acquisitions, environmental regulations and other factors. The recognition of impairments of goodwill, which may result in write-offs of such impaired amount, could have an adverse effect on JCP&L’s results of operations.
Removed paragraphs (24)
Previous report
The HB 6 related state regulatory investigations could have a material adverse effect on our reputation, business, financial condition, results of operations, liquidity or cash flows.
Previous report
There are several ongoing HB 6 related state regulatory matters including, but not limited to, the below HB 6-related matters, each of which was stayed for a third time by the PUCO on August 23, 2023, at the request of the U.S. Attorney for the Southern District of Ohio, for a period of an additional six months. The stay on the following matters was lifted on February 26, 2024:
Previous report
•On September 8, 2020, the OCC filed motions in the Ohio Companies’ corporate separation audit and DMR audit dockets, requesting the PUCO to open an investigation and management audit, hire an independent auditor, and require FirstEnergy to show it did not improperly use money collected from consumers or violate any utility regulatory laws, rules or orders in its activities regarding HB 6. On February 26, 2024, this proceeding was consolidated with the expanded DCR rider audit proceeding described below and on November 22, 2024, the administrative law judge ordered that the bifurcated portion of the corporate separation audit, discussed further below, be consolidated with the already-consolidated DMR audit and expanded DCR rider audit proceeding. Evidentiary hearings are scheduled to begin May 13, 2025;
Previous report
•On September 15, 2020, the PUCO opened a new proceeding to review the political and charitable spending by the Ohio Companies in support of HB 6 and the subsequent referendum effort. On September 30, 2024, the third-party auditor’s report was filed. See ”Outlook - State Regulation - Ohio” below for additional information regarding the auditor’s findings. Comments have been filed on the audit report and remain pending with the PUCO;
Previous report
•On December 30, 2020, the PUCO directed PUCO staff to solicit a third-party auditor and conduct a full review of the DMR to ensure funds collected from customers through the DMR were only used for the purposes established in ESP IV. The auditor’s report was filed on January 14, 2022, and the parties submitted final comments and responses in the second quarter 2022. See ”Outlook - State Regulation - Ohio” below for additional information regarding the auditor’s findings. On February 26, 2024, this proceeding was consolidated with the expanded DCR rider audit proceeding described below and on November 22, 2024, the administrative law judge ordered that the bifurcated portion of the corporate separation audit, discussed further below, be consolidated with the already-consolidated DMR audit and expanded DCR rider audit proceeding. Evidentiary hearings are scheduled to begin May 13, 2025; and
Previous report
•On March 10, 2021, the PUCO expanded the scope of an ongoing annual audit of the Ohio Companies’ Rider DCR for 2020 to include a review of certain transactions that were either improperly classified, misallocated, or lacked supporting documentation, and to determine whether funds collected from customers were used to pay the vendors, and if so, whether or not the funds associated with those payments should be returned to customers through Rider DCR or through an alternative proceeding. On February 26, 2024, this proceeding was consolidated with the Rider DMR audit proceeding described above, and further lifted the stay of the portion of the investigation relating to an apparent nondisclosure of a side agreement. On November 22, 2024, the administrative law judge ordered that the bifurcated portion of the corporate separation audit be consolidated with the already-consolidated DMR audit and the expanded DCR rider audit proceeding. Evidentiary hearings are scheduled to begin May 13, 2025.
Previous report
See Note 14, "Regulatory Matters" of the Notes to Consolidated Financial Statements and “Management’s Discussion and Analysis of Financial Condition and Results of Operations—Critical Accounting Policies and Estimates” for additional details on the state regulatory investigations surrounding HB 6.
Previous report
While FirstEnergy is committed to pursuing an open dialogue with stakeholders in an appropriate manner with respect to the numerous regulatory proceedings currently underway, FirstEnergy shareholders in particular are at risk of being adversely impacted because the rates our Electric Companies and Transmission Companies are allowed to charge may be decreased as a result of actions taken by a regulator to which our Electric Companies and Transmission Companies are subject to jurisdiction, whether as a result of the DPA, any failure to have complied with anti-corruption laws, or otherwise.
Previous report
We are unable to predict the adverse impacts of such regulatory matters, including with respect to rates, and, therefore, any of these risks could impact us significantly beyond expectations. Moreover, we are unable to predict the potential for any additional regulatory actions, any of which could exacerbate these risks or expose us to adverse outcomes in pending or future rate cases, and could have a material adverse effect on our reputation, business, financial condition, results of operations, liquidity or cash flows.
Previous report
In the ordinary course of our business, we depend on information technology systems that utilize sophisticated operational systems and network infrastructure to run all facets of our generation, transmission and distribution services. Additionally, we store sensitive data, intellectual property and proprietary or personally identifiable information regarding our business, employees, shareholders, customers, suppliers, business partners and other individuals in our data centers and on our networks. We may also need to provide sensitive data to vendors and service providers who require access to this information. The secure maintenance of information and information technology systems is critical to our operations.
Previous report
Over the last several years, there has been an increase in the frequency of cyber-attacks by terrorists, hackers, international activist organizations, foreign governments and individuals. These and other unauthorized parties may attempt to gain access to our network systems or facilities, or those of third parties with whom we do business, including directly through our network infrastructure or through fraud, trickery, or other forms of deception against our employees, contractors and temporary staff. Additionally, our information and information technology systems and those of our vendors and service providers may be increasingly vulnerable to data security breaches, damage and/or interruption due to viruses, ransomware, unauthorized physical access, theft of access devices, human error, malfeasance, faulty password management or other malfunctions and disruptions. Further, hardware, software, or applications we develop or procure from third parties may contain defects in design or manufacture or other problems that could unexpectedly compromise information and/or security.
Previous report
As a source of critical infrastructure, the energy industry is at heightened threat of cyber-attacks, which are becoming increasingly more difficult to anticipate and prevent due to their rapidly evolving nature. We cannot anticipate, detect, or implement fully preventive measures against all cybersecurity threats because the techniques used are increasingly sophisticated and constantly evolving and in some cases, assisted by artificial intelligence.
Previous report
In addition, the increased use of smartphones, tablets, and other wireless devices, as well as ongoing remote work-from-home arrangements, may also heighten these and other operational risks.
Previous report
Our generation, transmission and distribution infrastructure, as well as the transmission facilities of third parties with whom we are interconnected, may be increasingly vulnerable to such attacks as a result of the rapidly evolving and increasingly sophisticated means by which attempts to defeat security measures and gain access to our information technology systems may be made. As our transmission facilities are interconnected with those of third parties, the operation of our facilities could be adversely affected by cyber-attacks or other unexpected or uncontrollable events occurring on the systems of such third parties.
Previous report
Any actual or perceived cyber-attack, data security breach, damage, interruption and/or defect could: (i) disable our generation, transmission and/or distribution services for a significant period of time; (ii) delay development and construction of new facilities or capital improvement projects; (iii) adversely affect our customer operations; (iv) expose us to increased risk of lawsuits; (v) expose us to increased risk of regulatory penalties; (vi) expose us to increased risk of loss of potential or existing customers; (vii) expose us to increased risk of damage relating to loss of proprietary information; (viii) corrupt data; and/or (ix) result in unauthorized access to the information stored in our data centers and on our networks and those of our vendors and service providers, including company proprietary information, supplier information, employee data and personal customer data, causing the information to be publicly disclosed, lost or stolen or result in incidents that could result in economic loss and liability and harmful effects on the environment and human health, including loss of life.
Previous report
As cyber threats continually evolve and become more difficult to detect and successfully defend against, there can be no assurance that we can implement or maintain adequate preventive measures, accurately assess the likelihood of a cyber-incident or quantify potential liabilities or losses. Also, we may not discover any data security breach and loss of information for a significant period of time after the data security breach occurs, particularly when the breach has occurred on the systems of our vendors and service providers.
Previous report
We have a minority ownership stake in a coal mine that requires governmental permits and approvals to operate, and a failure of the coal mine to renew and maintain such permits and approvals may adversely affect our results of operations and cash flow.
Previous report
FEV currently holds a 33-1/3% equity ownership in Global Holding, the holding company for a joint venture in the Signal Peak mining and coal transportation operations with coal sales predominantly in international markets. The viability of our investment depends upon several factors beyond our control, including, but not limited to: Signal Peak’s ability to renew and maintain governmental permits and approvals and remain in compliance with federal, state, and local safety and environmental statutes, rules, and regulations affecting the coal mining industry. Failure by Signal Peak to renew and maintain necessary permits and approvals, and to comply with any such statutes, rules and regulations, may impair its operations and the ability to generate cash flows necessary for Global Holding to pay future dividends and contribute to FirstEnergy’s earnings.
Previous report
Signal Peak operates a single underground coal mine in south-central Montana and must obtain numerous governmental permits and approvals that impose strict conditions and obligations relating to, among other things, various environmental and safety matters in connection with its mining and coal transportation operations. The rules applicable to these permits and approvals are complex and can change over time. Regulatory authorities exercise considerable discretion in the timing and scope of permit issuance. In addition, the public has the right to comment on permit applications and otherwise participate in the permitting process, including through court intervention. Limitations on Signal Peak’s ability to conduct its mining operations due to its inability to obtain or renew necessary permits or similar approvals could materially reduce or even halt production at the mine resulting in an adverse effect on our balance sheet, results of operations and cash flow.
Previous report
Our results of operations and financial condition may be adversely affected by certain risks related to our minority interest in a coal mine.
Previous report
FEV currently holds a 33-1/3% equity ownership in Global Holding, the holding company for a joint venture in the Signal Peak mining and coal transportation operations with coal sales predominantly in international markets. In the second quarter of 2022, FEV received its first dividend of $20 million after more than ten years of equity ownership in the joint venture and received total dividends in 2022, 2023, and 2024 of $170 million, $165 million, and $80 million, respectively. Additionally, during 2022, 2023, and 2024, FirstEnergy recognized approximately $168 million, $175 million, and $72 million of pre-tax equity earnings, excluding impairments, respectively, from its investment in Global Holding. Global Holding’s ability to positively affect our results of operations or pay future dividends depends upon several factors beyond our control, including, but not limited to: the market price of coal, the availability and reliability of transportation facilities and other systems, geopolitical stability in international markets, and Global Holding’s ability to renew and maintain governmental permits and approvals and remain in compliance with safety and environmental regulations affecting the coal mining industry.
Previous report
The price for Signal Peak’s coal depends upon factors beyond our control, including but not limited to: overall global economic and geopolitical conditions, the effect of worldwide energy consumption, including the impact of technological advances on energy consumption; international developments impacting the supply of coal; international developments impacting the supply of oil & gas; and the impact of domestic and foreign governmental laws and regulations, including environmental and climate change regulations. Any adverse change in these factors could result in weaker demand and lower prices for Global Holding’s products, and, as a result, could impact Global Holding’s ability to pay future dividends, which in turn could adversely affect our cash flow and results of operations.
Previous report
The IRA of 2022 could change the rate of taxes imposed on us and could negatively affect our cash flows and financial condition.
Previous report
We cannot predict whether, when or to what extent new U.S. tax laws, regulations, interpretations or rulings will be issued. A reform of U.S. tax laws may be enacted in a manner that negatively impacts our cash flow, results of operations, and financial condition.
Reworded paragraphs (69)
Previous wording
We operate in a business environment that involves significant risks, many of which are beyond our control. Management regularly evaluates the most significant risks of its businesses and reviews those risks with the FE Board and appropriate Committees of the FE Board. The following risk factors and all other information contained in this report should be considered carefully when evaluating FirstEnergy. These risk factors could affect our financial results and cause such results to differ materially from those expressed in any forward-looking statements made by or on behalf of us. Below, we have identified risks we consider material. The risks that we face are not limited to those in this section. There may be additional risks and uncertainties (either currently unknown or not currently believed to be material) that could adversely affect our business, financial condition, results of operations, liquidity or cash flows. Although the risks are organized by headings, and each risk is discussed separately, many are interrelated. These risk factors should be read in conjunction with Item 1, "Business,” Item 7, "Management’s Discussion and Analysis of Financial Condition and Results of Operations,” and in other sections of this Form 10-K that include forward-looking and other statements involving risks and uncertainties that could impact our business, financial condition, results of operations, liquidity or cash flows.
Current wording
We operate in a business environment that involves significant risks, many of which are beyond the Registrants’ control. The Registrants regularly evaluate the most significant risks of their businesses and review those risks with their respective boards of directors and, if appropriate, committees of those boards of directors. The following risk factors and all other information contained in this report should be considered carefully when evaluating the Registrants, and unless a risk factor expressly excludes a Registrant or the context requires otherwise, references to “we,” “us,” and “our” refer to both Registrants. These risk factors could affect our financial results and cause such results to differ materially from those expressed in any forward-looking statements made by or on behalf of us. Below, we have identified risks we consider material. The risks that we face are not limited to those in this section. There may be additional risks and uncertainties (either currently unknown or not currently believed to be material) that could adversely affect our business, financial condition, results of operations, liquidity or cash flows. Although the risks are organized by headings, and each risk is discussed separately, many are interrelated. These risk factors should be read in conjunction with Item 1., "Business,” Item 7., "Management’s Discussion and Analysis of Financial Condition and Results of Operations,” and in other sections of this Form 10-K that include forward-looking and other statements involving risks and uncertainties that could impact our business, financial condition, results of operations, liquidity or cash flows.
Previous wording
Risks Associated with Damage to Our Reputation and HB 6 Related Litigation and Investigations
Current wording
Risks Associated with Damage to Our Reputation and Securities Class-Action Litigation
Previous wording
HB 6-related investigations and litigation could have a material adverse effect on our reputation, business, financial condition, results of operations, our ability to access capital, liquidity or cash flows.
Current wording
Securities class-action litigation against us could have a material adverse effect on our reputation, business, financial condition, results of operations, our ability to access capital, liquidity or cash flows.
Previous wording
On July 21, 2021, we entered into a three-year DPA with the U.S. Attorney’s Office that, subject to court proceedings, resolves the previously disclosed U.S. Attorney’s Office investigation into us relating to our lobbying and governmental affairs activities concerning HB 6. Under the DPA, we paid a $230 million monetary penalty in 2021 and agreed to the filing of a criminal information charging FirstEnergy with one count of conspiracy to commit honest services wire fraud.
Current wording
On July 21, 2021, FE entered into a three-year DPA with the U.S. Attorney’s Office that, subject to court proceedings, resolves the previously disclosed U.S. Attorney’s Office investigation into us relating to our lobbying and governmental affairs activities concerning HB 6. Under the DPA, we paid a $230 million monetary penalty in 2021 and agreed to the filing of a criminal information charging FirstEnergy with one count of conspiracy to commit honest services wire fraud.
Previous wording
As of July 22, 2024, we successfully completed the obligations required within the three-year term of the DPA. Under the DPA, and until the conclusion of any related investigation, criminal prosecution and civil proceeding brought by the U.S. Attorney’s Office, we have an obligation to continue (i) publishing quarterly a list of all payments to 501(c)(4) entities and all payments to entities known by us to be operating for the benefit of a public official, either directly or indirectly; (ii) not making any statements that contradict the DPA; (iii) notifying the U.S. Attorney’s Office for the S.D. Ohio of any changes in FirstEnergy’s corporate form; and (iv) cooperating with the U.S. Attorney’s Office for the S.D. Ohio. In accordance with the DPA, these obligations will continue until the completion of any related investigation, criminal prosecution, and civil proceeding brought by the U.S. Attorney’s Office related to the conduct set forth in the DPA’s statement of facts, including the January 17, 2025 indictment against two former FirstEnergy senior officers, described below in “Outlook—Other Legal Proceeding –United States v. Larry Householder, et al.” Within 30 days of those matters concluding, and FirstEnergy’s successful completion of its remaining obligations, the U. S. Attorney’s Office will dismiss the criminal information.
Current wording
As of July 22, 2024, we successfully completed the obligations required within the three-year term of the DPA. Under the DPA, and until the conclusion of any related investigation, criminal prosecution and civil proceeding brought by the U.S. Attorney’s Office, we have an obligation to continue (i) publishing quarterly a list of all payments to 501(c)(4) entities and all payments to entities known by us to be operating for the benefit of a public official, either directly or indirectly; (ii) not making any statements that contradict the DPA; (iii) notifying the U.S. Attorney’s Office for the S.D. Ohio of any changes in FirstEnergy’s corporate form; and (iv) cooperating with the U.S. Attorney’s Office for the S.D. Ohio. In accordance with the DPA, these obligations will continue until the completion of any related investigation, criminal prosecution, and civil proceeding brought by the U.S. Attorney’s Office related to the conduct set forth in the DPA’s statement of facts, including the January 17, 2025 indictment against two former FirstEnergy senior officers, described in “Outlook—Other Legal Proceeding – United States v. Larry Householder, et al.,” in Item 7., "Management's Discussion and Analysis of Financial Condition and Results of Operations". Within 30 days of those matters concluding, and FirstEnergy’s successful completion of its remaining obligations, the U.S. Attorney’s Office will dismiss the criminal information. On February 26, 2025, the U.S. Attorney’s Office filed a status report confirming these commitments.
Previous wording
Following the announcement by the U.S. Attorney’s Office for the S.D. Ohio of the investigation surrounding HB 6 in July 2020, certain of our stockholders and customers filed several lawsuits against us and certain current and former directors, officers and other employees, including the federal securities class action litigation In re FirstEnergy Corp. Securities Litigation (Federal District Court, S.D. Ohio). We believe that it is probable that FE will incur a loss in connection with the resolution of In re FirstEnergy Corp. Securities Litigation. Given the ongoing nature and complexity of such litigation, we cannot yet reasonably estimate a loss or range of loss that may arise from its resolution. However, if it is resolved against us substantial monetary damages could result and our reputation, business, financial condition, results of operations, liquidity or cash flows may be materially adversely affected.
Current wording
Following the announcement by the U.S. Attorney’s Office for the S.D. Ohio of the investigation surrounding HB 6 in July 2020, certain of FE’s stockholders and customers filed several lawsuits against us and certain current and former directors, officers and other employees, including the federal securities class action litigation In re FirstEnergy Corp. Securities Litigation (Federal District Court, S.D. Ohio). We believe that it is probable that FE will incur a loss in connection with the resolution of In re FirstEnergy Corp. Securities Litigation. Given the ongoing nature and complexity of such litigation, we cannot yet reasonably estimate a loss or range of loss that may arise from its resolution. However, if it is resolved against us substantial monetary damages could result and our reputation, business, financial condition, results of operations, liquidity or cash flows may be materially adversely affected.
Previous wording
The litigation related to HB 6 could divert management’s focus and have resulted in, and could continue to result in, substantial expenses, and the commitment of substantial corporate resources. The outcome, duration, scope, result or related costs of the in securities class action litigation In re: FirstEnergy Corp. Securities Litigation discussed above, are inherently uncertain. Therefore, any of these risks could impact us significantly beyond expectations. See Note 15, "Commitments, Guarantees and Contingencies" of the Notes to Consolidated Financial Statements and “Management’s Discussion and Analysis of Financial Condition and Results of Operations—Critical Accounting Policies and Estimates.”
Current wording
This securities class-action litigation could divert management’s focus and have resulted in, and could continue to result in, substantial expenses, and the commitment of substantial corporate resources. The outcome, duration, scope, result or related costs of the securities class action litigation In re: FirstEnergy Corp. Securities Litigation discussed above, are inherently uncertain. Therefore, any of these risks could impact us significantly beyond expectations. See Note 14, "Commitments, Guarantees and Contingencies,” of the Combined Notes to Financial Statements of the Registrants and “Management’s Discussion and Analysis of Financial Condition and Results of Operations—Critical Accounting Policies and Estimates.”
Previous wording
These matters are likely to continue to have an adverse impact on the trading prices of our securities, which could be material. See Note 15, “Commitments, Guarantees and Contingencies,” of the Notes to Consolidated Financial Statements, for additional details on the government investigations and subsequent litigation surrounding HB 6.
Current wording
These matters are likely to continue to have an adverse impact on the trading prices of our securities, which could be material. See Note 14., “Commitments, Guarantees and Contingencies,” of the Combined Notes to Financial Statements of the Registrants, for additional details on the government investigations and subsequent litigation surrounding HB 6.
Previous wording
Our reputation is important. Damage to our reputation could materially adversely affect our business, results of operations and financial condition. Such damage may arise from numerous sources further discussed generally within these risk factors. Any damage to our reputation, either generally or as a result of the foregoing, may lead to negative customer perception, which may make it difficult for us to compete successfully for new opportunities, or could adversely impact our ability to launch new sophisticated technology-driven solutions to meet our customer expectations. A damaged reputation could further result in FERC, the state public utility commissions, and other regulatory and legislative authorities being less likely to view us in a favorable light and could negatively impact the rates we charge customers or otherwise cause us to be susceptible to unfavorable legislative and regulatory outcomes, as well as increased regulatory oversight and more stringent legislative or regulatory requirements.
Current wording
Our reputation is important towards maintaining new and ongoing positive relationships with customers, regulators, investors, and other stakeholders. Damage to our reputation could materially adversely affect our business, results of operations and financial condition. Such damage may arise from numerous sources further discussed generally within these risk factors. Any damage to our reputation, either generally or as a result of, among other things, changes in our service reliability, our rate affordability or negative outcomes in the ongoing matters relating to HB 6, may lead to negative customer perception, which may make it difficult for us to compete successfully for new opportunities, or could adversely impact our ability to launch new sophisticated technology-driven solutions to meet our customer expectations. A damaged reputation could further result in FERC, the state public utility commissions, and other regulatory and legislative authorities being less likely to view us in a favorable light and could negatively impact the rates we charge customers or otherwise cause us to be susceptible to unfavorable legislative and regulatory outcomes, as well as increased regulatory oversight and more stringent legislative or regulatory requirements.
Previous wording
Risks Associated with Regulation of Our Distribution and Transmission Businesses
Current wording
Risks Associated with the Execution of Our Strategic Initiatives and the Regulation of Our Distribution and Transmission Businesses
Previous wording
FirstEnergy is engaged in an ongoing effort to create a culture of continuous improvement to strategically reduce our operating expenditures and continually reinvest in a more diverse capital program in support of our long-term strategy. FirstEnergy leverages opportunities to reduce costs – such as filling only critical positions, implementing our facility optimization plans, and exploring other additional, sustainable opportunities, such as reducing contractor spend. There can be no assurance that implementation of our continuous improvement culture will allow us to realize the anticipated benefits to our business, results of operations and financial condition in a timely manner, if at all.
Current wording
FirstEnergy is engaged in an ongoing effort to create a culture of continuous improvement to strategically reduce our operating expenditures and continually reinvest in a more diverse capital program in support of our long-term strategy. FirstEnergy leverages opportunities to reduce costs – such as filling only critical positions, implementing our facility optimization plans, deploying advanced technology, including but not limited to artificial intelligence, and exploring other additional, sustainable opportunities, such as reducing contractor spend. There can be no assurance that implementation of our continuous improvement culture will allow us to realize the anticipated benefits to our business, results of operations and financial condition in a timely manner, if at all.
Previous wording
Our ability to capitalize on investment opportunities available to our transmission business depends, in part, on successful recovery of our transmission investments. Factors that may affect rate recovery of our transmission investments include: (1) FERC’s timely approval of rates to recover such investments; (2) whether the investments are included in PJM's Regional Transmission Expansion Plan; (3) FERC's evolving policies with respect to incentive rates for transmission assets; (4) FERC's evolving policies with respect to the calculation of the base ROE component of transmission rates; (5) consideration and potential impact of the objections of those who oppose such investments and their recovery; and (6) timely development, construction, and operation of the new facilities.
Current wording
The success of our growth strategy will depend, in part, on the successful growth of revenue resulting from our transmission investments in line with our expectations. Factors that may affect our revenue growth may include: (1) FERC’s timely approval of rates to recover such investments; (2) whether investments are included in PJM's RTEP; (3) FERC's evolving policies with respect to incentive rates for transmission investment assets, the calculation of the base ROE component of transmission rates, and the interconnection of AI data centers and transmission network upgrades supporting such large loads; (4) FERC’s potentially-evolving policies regarding whether certain classes of network transmission upgrade costs can be capitalized as part of transmission rates and whether such costs will be direct charged to the connecting customer; (5) consideration and potential impact of the objections of those who oppose such investments and their recovery; and (6) timely development, construction, and operation of the new facilities.
Previous wording
The retail rates for each of the Electric Companies are set by each of its respective regulatory agency for utilities in the state in which it operates - in Maryland by the MDPSC, in New Jersey by the NJBPU, in Ohio by the PUCO, in Pennsylvania by the PPUC, in West Virginia by the WVPSC and in New York by the NYPSC – through traditional, cost-based regulated utility ratemaking. As a result, any of the Electric Companies may not be permitted to recover its costs and, even if it is able to do so, there may be a significant delay between the time it incurs such costs and the time it is allowed to recover them. Factors that may affect outcomes in the distribution rate cases include, but are not limited to: (i) the value of plant in service; (ii) authorized rate of return; (iii) capital structure (including hypothetical capital structures); (iv) depreciation rates; (v) the allocation of shared costs, including consolidated deferred income taxes and income taxes payable across the Electric Companies; (vi) regulatory approval of rate recovery mechanisms for capital investment spending programs; and (vii) the accuracy of forecasts used for ratemaking purposes in "future test year" cases.
Current wording
PPUC, in West Virginia by the WVPSC and in New York by the NYPSC – through traditional, cost-based regulated utility ratemaking. As a result, any of the Electric Companies may not be permitted to recover its costs and, even if it is able to do so, there may be a significant delay between the time it incurs such costs and the time it is allowed to recover them. Factors that may affect outcomes in the distribution rate cases include, but are not limited to: (i) the value of plant in service; (ii) authorized rate of return; (iii) capital structure (including hypothetical capital structures); (iv) depreciation rates; (v) the allocation of shared costs, including consolidated deferred income taxes and income taxes payable across the Electric Companies; (vi) regulatory approval of rate recovery mechanisms for capital investment spending programs; and (vii) the accuracy of forecasts used for ratemaking purposes in "future test year" cases. Evolving legislation and executive actions related to our rates enacted by individual states, such as Ohio Senate Bill 2 of 2025 and Executive Order No. 2 of 2026 issued by the New Jersey governor on January 20, 2026, may also affect outcomes in distribution rate cases or could create uncertainty around our rate strategy.
Previous wording
FERC policy currently permits recovery of prudently incurred costs associated with cost-of-service-based wholesale power rates and the expansion and updating of transmission infrastructure within its jurisdiction. FERC’s policies on recovery of transmission costs continue to evolve, evidenced by ongoing proceedings to determine an appropriate ROE methodology to determine transmission ROEs, and to determine whether FERC’s existing policies on transmission rate incentives should be revised. If FERC were to adopt a different policy regarding recovery of transmission costs or if there is any resulting delay in cost recovery, our strategy of investing in transmission could be adversely affected. If FERC were to lower the rate of return it has authorized for FirstEnergy's cost-based wholesale power rates or transmission investments and facilities, it could reduce future earnings and cash flows, and adversely impact our financial condition.
Current wording
FERC policy currently permits recovery of prudently incurred costs associated with cost-of-service-based wholesale power rates and the expansion and updating of transmission infrastructure within its jurisdiction. FERC’s policies on recovery of transmission costs continue to evolve, evidenced by ongoing proceedings to determine an appropriate ROE methodology to determine transmission ROEs, to determine whether FERC’s existing policies on transmission rate incentives should be revised, and to determine whether certain classes of network transmission upgrade costs can be recovered in transmission rates and whether such costs will be direct charged to the connecting customer. If FERC were to adopt a different policy regarding recovery of transmission costs or if there is any resulting delay in cost recovery, our strategy of investing in transmission could be adversely affected. If FERC were to lower the rate of return it has authorized for FirstEnergy's cost-based wholesale power rates or transmission investments and facilities, it could reduce future earnings and cash flows, and adversely impact our financial condition.
Previous wording
We could be subject to higher costs and/or penalties related to mandatory reliability standards set by NERC/FERC or changes in the rules of organized markets, which could have an adverse effect on our financial condition.
Current wording
We could be subject to higher costs and/or penalties related to mandatory reliability standards set by NERC, FERC, and RFC or changes in the rules of organized markets, which could have an adverse effect on our financial condition.
Previous wording
Owners, operators, and users of the bulk electric system are subject to mandatory reliability standards promulgated by NERC and approved by FERC. The standards are based on the functions that need to be performed to ensure that the bulk electric system operates reliably. NERC, RFC and FERC can be expected to continue to refine existing reliability standards as well as develop and adopt new reliability standards. Compliance with modified or new reliability standards may subject us to higher operating costs and/or increased investments. If we were found not to be in compliance with the mandatory reliability standards, we could be subject to sanctions, including substantial monetary penalties. FERC has authority to impose penalties up to and including $1.5 million per day for failure to comply with these mandatory electric reliability standards.
Current wording
Our operations are subjected to audit by FERC, NERC and RFC, which may conduct routine or special audits and issue requests designed to ensure compliance with applicable rules, regulations, policies and procedures. Among other rules, regulations, policies and procedures, owners, operators, and users of the bulk electric system are subject to mandatory reliability standards promulgated by NERC and approved by FERC. The standards are based on the functions that need to be performed to ensure that the bulk electric system operates reliably. NERC, RFC and FERC continue to refine existing reliability standards as well as develop and adopt new reliability standards. The reliability standards address operation, planning, and security of the bulk electricity system, including requirements with respect to real-time transmission operations, emergency operations, vegetation management, critical infrastructure protection, and personnel training. Compliance with modified or new reliability standards may subject us to higher operating costs and/or increased capital expenditure. If we were found not to be in compliance with one or more of the mandatory reliability standards, we and/or our subsidiaries could be subject to sanctions, including substantial monetary penalties. For example, FERC has the authority under the FPA to impose penalties up to and including $1.5 million per day, subject thereafter to annual adjustments for inflation, for failure to comply with these mandatory reliability standards. Potential non-monetary sanctions include imposing limitations on the violator’s activities or operations.
Previous wording
Recent industry projections reflect the potential for significant growth in energy demand over the next decade. This could be exacerbated if additional generation resources are not available to meet increased demand in the future. For example, data centers have substantially larger load requirements than typical residential or commercial users. New data centers or increase in demand for existing data centers located in our service territories could increase load requirements substantially over the next several years, thereby increasing the aggregate load obligations of the Electric Companies. A need to serve the load obligations of these data centers, which could be up to 5,575 MWs through 2029, has the potential to adversely impact our business, results of operations, financial condition, or cash flows.
Current wording
Recent industry projections reflect the potential for significant growth in energy demand over the next decade. This could be exacerbated if additional generation resources are not available to meet increased demand in the future. For example, data centers have substantially larger load requirements than typical residential or commercial users. New data centers or increase in demand for existing data centers located in our service territories could increase load requirements substantially over the next several years, thereby increasing the aggregate load obligations of the Electric Companies. A need to serve the load obligations of these data centers, which could be up to 16,985 MWs through 2035, has the potential to adversely impact our business, results of operations, financial condition, or cash flows. At the same time, our planning could be adversely affected if electricity usage by data centers is ultimately lower than projected, which could reduce anticipated load growth.
Previous wording
The hazards described above, along with other safety hazards associated with our operations, can cause significant personal injury or loss of life, severe damage to and destruction of property, plant and equipment, contamination of, or damage to, the environment and suspension of operations. The occurrence of any one of these events may result in our being named as a defendant in lawsuits asserting claims for substantial damages, environmental cleanup costs, personal injury and fines and/or penalties.
Current wording
The hazards described above, along with other safety hazards associated with our operations, can cause significant personal injury or loss of life, severe damage to and destruction of PP&E, contamination of, or damage to, the environment and suspension of operations. The occurrence of any one of these events may result in our being named as a defendant in lawsuits asserting claims for substantial damages, environmental cleanup costs, personal injury and fines and/or penalties.
Previous wording
Weather conditions directly influence the demand for electric power. Demand for power generally peaks during the summer and winter months, with market prices also typically peaking at that time. Overall operating results may fluctuate based on weather conditions. In addition, we have historically sold less power, and consequently received less revenue, when seasonal weather conditions are milder. For example, in 2024, heating degree days in 2024 were 1% below 2023 and 15% below normal.
Current wording
Weather conditions directly influence the demand for electric power. Demand for power generally peaks during the summer and winter months, with market prices also typically peaking at that time. Overall operating results may fluctuate based on weather conditions. In addition, we have historically sold less power, and consequently received less revenue, when seasonal weather conditions are milder.
Previous wording
Cyber-attacks, electronic or physical data security breaches and other disruptions to our information technology systems, or those of third parties we are connected to or do business with, could compromise our business operations, critical and proprietary information and employee and customer data, which could have a material adverse effect on our business, results of operations, financial condition and reputation.
Current wording
Cyber-attacks, data security breaches and other disruptions to our information technology systems, or those of third parties we are connected to or do business with, could compromise our business operations, critical and proprietary information and employee and customer data, which could have a material adverse effect on our business, results of operations, financial condition and reputation.
Previous wording
For all of these reasons, any such cyber incident could result in significant lost revenue, the inability to conduct critical business functions and serve customers for a significant period of time, the loss of confidential, sensitive and proprietary information, including but not limited to personal information of our customers, employees, suppliers, vendors and other third parties, the use of significant management resources, legal claims or proceedings, regulatory penalties, significant remediation costs, increased regulation, increased capital costs, increased insurance costs, increased protection costs for enhanced cyber security systems or personnel, and/or damage to our reputation, all of which could materially adversely affect our business, results of operations, financial condition and reputation.
Current wording
We rely on complex information technology systems to operate our generation, transmission and distribution networks and to store sensitive business, employee and customer data. Increasingly sophisticated cyber-attacks, ransomware, and other security breaches—whether targeting us or third parties with whom we do business—could disrupt operations, compromise confidential information, and result in significant financial, legal, and reputational harm. Cybersecurity threats, including those that exploit advances in technologies such as artificial intelligence, continue to grow in frequency and sophistication, and the security controls we implement may not fully prevent or detect all such threats or incidents. Emerging artificial intelligence technologies may be used to develop new hacking tools, obscure malicious activities, exploit vulnerabilities, and increase the difficulty of detecting threats. Despite ongoing investments in cybersecurity, we cannot guarantee prevention or timely detection of all threats, which continue to evolve and may be amplified by interconnected systems. A successful attack or breach could lead to service interruptions, regulatory penalties, litigation, remediation costs, and loss of customer trust. Any such cyber incident could result in significant lost revenue, the inability to conduct critical business functions and serve customers for a significant period of time, the loss of confidential, sensitive and proprietary information, including but not limited to personal information of our customers, employees, suppliers, vendors and other third parties, the use of significant management resources, legal claims or proceedings, regulatory penalties, significant remediation costs, increased regulation, increased capital costs, increased insurance costs, increased protection costs for enhanced cybersecurity systems or personnel, and/or damage to our reputation, all of which could materially adversely affect our business, results of operations, financial condition and reputation.
Previous wording
Economic conditions, including those that may arise from government fiscal policy, tariffs, recessions, inflationary and interest rate pressures, may impact the demand for electricity and, therefore, any decline in economic conditions could lead to declines in the demand for electricity, which would reduce our revenues. Prices for equipment, materials, supplies, employee labor contractor services, together with the cost of variable-rate debt, have increased in recent years and could continue to increase in 2025 and beyond. Long-term inflationary pressures may result in such prices continuing to increase more quickly than expected. Inflation increases costs for labor, materials and services, and we may be unable to secure these resources on economically acceptable terms or offset such costs with increased revenues, operating efficiencies, or cost savings, which may adversely impact our financial condition, results of operations, liquidity, and cash flows.
Current wording
Economic conditions, including those that may arise from government fiscal policy, tariffs, recessions, inflationary and interest rate pressures, may impact the demand for electricity and, therefore, any decline in economic conditions could lead to declines in the demand for electricity, which would reduce our revenues. Prices for equipment, materials, supplies, employee labor contractor services, together with the cost of variable-rate debt, have increased in recent years and could continue to increase in 2026 and beyond. Inflation and broader economic conditions have continued to drive up the price of the cost of essential components used in the construction of transmission infrastructure, such as electrical equipment, steel and aluminum, and we may experience supply chain disruptions and long lead times for critical equipment. Long-term inflationary pressures may result in such prices continuing to increase more quickly than expected. Inflation increases costs for labor, materials and services, and we may be unable to secure these resources on economically acceptable terms or offset such costs with increased revenues, operating efficiencies, or cost savings, which may adversely impact our financial condition, results of operations, liquidity, and cash flows.
Previous wording
Continued supply chain disruptions could have an adverse effect on our results of operations, cash flow and financial condition.
Current wording
Supply chain disruptions could have an adverse effect on our results of operations, cash flow and financial condition.
Previous wording
We continue to experience supply chain challenges due to economic conditions that developed during the COVID-19 pandemic and have continued in the years since, with order lead times increasing across numerous material categories, some of which remained elevated through 2024 and into 2025. The situation is fluid and a prolonged continuation or further increase in supply chain disruptions could have an adverse effect on FirstEnergy’s results of operations, cash flow and financial condition. Such disruptions could be exacerbated by unstable or uncertain macroeconomic conditions, including inflationary pressures. Any significant disruption or increased costs arising from these pressures on our suppliers may inhibit our access to, or require us to spend more money to source, certain products or that we use in our operations.
Current wording
We have in the past and may in the future experience supply chain challenges due to economic conditions that developed during the COVID-19 pandemic and have continued in the years since, with order lead times increasing across numerous material categories. The situation is fluid and a prolonged continuation or further increase in supply chain disruptions could have an adverse effect on FirstEnergy’s results of operations, cash flow and financial condition. Our operations and corporate strategy may also be adversely affected by supply chain disruptions and inflation, including shortages and delays in key materials, equipment and contractor services. Such disruptions could be exacerbated by unstable or uncertain macroeconomic conditions, including inflationary pressures. Any significant disruption or increased costs arising from these pressures on our suppliers may inhibit our access to, or require us to spend more money to source, certain products or that we use in our operations.
Previous wording
Furthermore, change or uncertainty in U.S. policies or the policies of other countries and regions in which our suppliers do business, including any changes or uncertainty with respect to U.S. or international trade policies or tariffs, could also disrupt our key suppliers’ operations. The presidential administration has taken action in 2025 to impose substantial new or increased tariffs. Any widespread imposition of new or increased tariffs could have an adverse effect on our results of operations, cash flow and financial condition. New or increased tariffs could also negatively affect U.S. national or regional economies, which also could negatively impact our business and results of operations.
Current wording
Furthermore, change or uncertainty in U.S. policies or the policies of other countries and regions in which our suppliers do business, including any changes or uncertainty with respect to U.S. or international trade policies or tariffs, could also disrupt our key suppliers’ operations. The presidential administration took action in 2025 to impose substantial new or increased tariffs. Any widespread imposition of new or increased tariffs could have an adverse effect on our results of operations, cash flow and financial condition. New or increased tariffs could also negatively affect U.S. national or regional economies, which also could negatively impact our business and results of operations. The supply chain of goods and services we rely on could be impacted by sanctions, tariffs, manufacturing labor shortages and domestic and international shipping constraints, which could increase our costs and delay delivery of critical materials.
Previous wording
Our business follows economic cycles. The regional economy in which our Electric Companies operate is influenced by conditions in industries in our business territories, e.g., data centers, shale gas, automotive, chemical, steel and other heavy industries, and as these conditions and resultant demand of those industries for electricity generation changes, our revenues will be impacted.
Current wording
Our business follows economic cycles. The regional economy in which the Electric Companies operate is influenced by conditions in industries in our business territories, e.g., data centers, shale gas, automotive, chemical, steel and other heavy industries, and as these conditions and resultant demand of those industries for electricity generation changes, our revenues will be impacted.
Previous wording
We are subject to risks arising from the operation of our power plants and transmission and distribution equipment which could reduce revenues, increase expenses and have a material adverse effect on our business, financial condition and results of operations.
Current wording
FirstEnergy is subject to risks arising from the operation of its electric generation facilities and transmission and distribution equipment which could reduce revenues, increase expenses and have a material adverse effect on our business, financial condition and results of operations.
Previous wording
Operation of generation, transmission and distribution facilities involves risk, including the risk of potential breakdown or failure of equipment or processes due to aging infrastructure, fuel supply or transportation disruptions, accidents, labor disputes or work stoppages by employees, human error in operations or maintenance, acts of terrorism or sabotage, cyber-attacks, construction delays or cost overruns, shortages of or delays in obtaining equipment, material and labor, operational restrictions resulting from environmental requirements and governmental interventions, and operational performance below expected levels. In addition, weather-related incidents and other natural disasters can disrupt generation, transmission and distribution delivery systems. Because our transmission facilities are interconnected with those of third parties, the operation of our facilities could be adversely affected by unexpected or uncontrollable events occurring on the systems of such third parties.
Current wording
Operation of transmission and distribution facilities, and in the case of MP, electric generation facilities, involves risk, including the risk of potential breakdown or failure of equipment or processes due to aging infrastructure, fuel supply or transportation disruptions, accidents, labor disputes or work stoppages by employees, human error in operations or maintenance, acts of terrorism or sabotage, cyber-attacks, construction delays or cost overruns, shortages of or delays in obtaining equipment, material and labor, operational restrictions resulting from environmental requirements and governmental interventions, and operational performance below expected levels. In addition, weather-related incidents and other natural disasters can disrupt generation, transmission and distribution delivery systems. Because our transmission facilities are interconnected with those of third parties, the operation of our facilities could be adversely affected by unexpected or uncontrollable events occurring on the systems of such third parties.
Previous wording
Our Energize365 business plan calls for extensive capital investments totaling approximately $28 billion from 2025 through 2029, including but not limited to our transmission expansion program and our distribution grid modernization, resiliency and reliability programs. We may be exposed to the risk of substantial price increases in, or the adequacy or availability of, the costs of labor and materials used in construction, nonperformance of equipment and increased costs due to inflation, interest rates or other macroeconomic forces, delays, including delays relating to the procurement of permits or approvals, adverse weather or environmental matters. We engage numerous contractors and enter into a large number of construction agreements to acquire the necessary materials and/or obtain the required construction-related services. As a result, we are also exposed to the risk that these contractors and other counterparties could breach their obligations to us. Such risk could include our contractors’ inabilities to procure sufficient skilled labor as well as potential work stoppages by that labor force. Should the counterparties to these arrangements fail to perform, we may be forced to enter into alternative arrangements at then-current market prices that may exceed our contractual prices, with resulting delays in those and other projects. Although our agreements are designed to mitigate the consequences of a potential default by the counterparty, our actual exposure may be greater than these mitigation provisions. Also, because we enter into construction agreements for the necessary materials and to obtain the required construction related services, any cancellation by FirstEnergy of a construction agreement could result in significant termination payments or penalties. Any delays, increased costs or losses, or cancellation of a construction project could adversely affect our business and results of operations, particularly if we are not permitted to recover any such costs in rates.
Current wording
FirstEnergy’s Energize365 business plan calls for extensive capital investments totaling approximately $36 billion from 2026 through 2030. We may be exposed to the risk of substantial price increases in, or the adequacy or availability of, the costs of labor and materials used in construction, nonperformance of equipment and increased costs due to inflation, interest rates or other macroeconomic forces, delays, including delays relating to the procurement of permits or approvals, adverse weather or environmental matters. We engage numerous contractors and enter into a large number of construction agreements to acquire the necessary materials and/or obtain the required construction-related services. As a result, we are also exposed to the risk that these contractors and other counterparties could breach their obligations to us. Such risk could include our contractors’ inabilities to procure sufficient skilled labor as well as potential work stoppages by that labor force. Should the counterparties to these arrangements fail to perform, we may be forced to enter into alternative arrangements at then-current market prices that may exceed our contractual prices, with resulting delays in those and other projects. Although our agreements are designed to mitigate the consequences of a potential default by the counterparty, our actual exposure may be greater than these mitigation provisions. Also, because we enter into construction agreements for the necessary materials and to obtain the required construction related services, any cancellation by FirstEnergy of a construction agreement could result in significant termination payments or penalties. Any delays, increased costs or losses, or cancellation of a construction project could adversely affect our business and results of operations, particularly if we are not permitted to recover any such costs in rates.
Previous wording
As a result of the continued threat of physical acts of war, terrorism, sabotage or other attacks in the United States, our electric generation, fuel storage, transmission and distribution facilities and other infrastructure, including power plants, transformer and high voltage lines and substations, or the facilities or other infrastructure of an interconnected company, could be direct targets of, or indirect casualties of, an act of war, terrorism, sabotage or other attack, which could result in disruption of our ability to generate, purchase, transmit or distribute electricity for a significant period of time, otherwise disrupt our customer operations and/or result in incidents that could result in harmful effects on the environment and human health, including loss of life. Any such disruption or incident could result in a significant decrease in revenue, significant additional capital and operating costs, including costs to implement additional security systems or personnel to purchase electricity and to replace or repair our assets over and above any available insurance reimbursement, higher insurance deductibles, higher premiums and more restrictive insurance policies, legal claims or proceedings, greater regulation with higher attendant costs, generally, and significant damage to our reputation, which could have a material adverse effect on our business, results of operations, cash flows and financial condition.
Current wording
As a result of the continued threat of physical acts of war, terrorism, sabotage or other attacks in the United States, our electric generation, fuel storage, transmission and distribution facilities and other infrastructure, including electric generation facilities, transformer and high voltage lines and substations, or the facilities or other infrastructure of an interconnected company, could be direct targets of, or indirect casualties of, an act of war, terrorism, sabotage or other attack, which could result in disruption of our ability to generate, purchase, transmit or distribute electricity for a significant period of time, otherwise disrupt our customer operations and/or result in incidents that could result in harmful effects on the environment and human health, including loss of life. Any such disruption or incident could result in a significant decrease in revenue, significant additional capital and operating costs, including costs to implement additional security systems or personnel to purchase electricity and to replace or repair our assets over and above any available insurance reimbursement, higher insurance deductibles, higher premiums and more restrictive insurance policies, legal claims or proceedings, greater regulation with higher attendant costs, generally, and significant damage to our reputation, which could have a material adverse effect on our business, results of operations, cash flows and financial condition.
Previous wording
We are committed to providing safe and reliable service and equipment in our franchised service territories. Meeting this commitment requires the expenditure of significant capital resources. However, our employees, contractors and the general public may be exposed to dangerous environments due to the nature of our operations. Failure to provide safe and reliable service and equipment due to various factors, including cyber or physical attacks, equipment failure, accidents, human error, weather or natural disasters, could result in serious injury or loss of life that may harm our business reputation and adversely affect our operating results through reduced revenues, increased capital and operating costs, litigation or the imposition of penalties/fines or other adverse regulatory outcomes.
Current wording
Our employees, contractors and the general public may be exposed to dangerous environments due to the nature of our operations. Failure to provide safe and reliable service and equipment due to various factors, including cyber or physical attacks, equipment failure, accidents, human error, weather or natural disasters, could result in serious injury or loss of life that may harm our business reputation and adversely affect our operating results through reduced revenues, increased capital and operating costs, litigation or the imposition of penalties/fines or other adverse regulatory outcomes.
Previous wording
We are involved in a number of litigation, arbitration, mediation, and similar proceedings, including with respect to asbestos claims. These and other matters may divert financial and management resources that would otherwise be used to benefit our operations. Further, no assurances can be given that the resolution of these matters will be favorable to us. If certain matters were ultimately resolved unfavorably to us, our results of operations and financial condition could be materially adversely impacted. See Note 15. “Commitments, Guaranties and Contingencies” of the Notes to Consolidated Financial Statements for a summary of such matters.
Current wording
We are involved in a number of litigation, arbitration, mediation, and similar proceedings, including with respect to asbestos claims. These and other matters may divert financial and management resources that would otherwise be used to benefit our operations. Further, no assurances can be given that the resolution of these matters will be favorable to us. If certain matters were ultimately resolved unfavorably to us, our results of operations and financial condition could be materially adversely impacted. See Note 14., “Commitments, Guaranties and Contingencies,” of the Combined Notes to Financial Statements of the Registrants.
Previous wording
Additionally, a significant number of our physical workforce are represented by unions. While we believe that our relations with our employees are generally fair, we cannot provide assurances that the company will be completely free of labor disruptions such as work stoppages, work slowdowns, union organizing campaigns, strikes, lockouts or that any labor disruption will be favorably resolved. Mitigating these risks could require additional financial commitments and the failure to prevent labor disruptions and retain and/or attract trained and qualified labor could have an adverse effect on our business.
Current wording
Additionally, a significant number of our physical workforce are represented by unions. We cannot provide assurances that the company will be completely free of labor disruptions such as work stoppages, work slowdowns, union organizing campaigns, strikes, lockouts or that any labor disruption will be favorably resolved. Mitigating these risks could require additional financial commitments and the failure to prevent labor disruptions and retain and/or attract trained and qualified labor could have an adverse effect on our business.
Previous wording
We continually focus on limiting and reducing where possible, our operation and maintenance expenses. However, we expect to continue to face increased cost pressures related to operation and maintenance expenses, including in the areas of health care and pension costs. We have experienced health care cost inflation in recent years, and we expect our cash outlay for health care costs, including prescription drug coverage, to continue to increase despite measures that we have taken requiring employees and retirees to bear a higher portion of the costs of their health care benefits. The measurement of our expected future health care and pension obligations and costs is highly dependent on a variety of assumptions, many of which relate to factors beyond our control. These assumptions include investment returns, interest rates, discount rates, health care cost trends, benefit design changes, salary increases, the demographics of plan participants and regulatory requirements. See “Management’s Discussion and Analysis of Financial Condition and Results of Operations—Critical Accounting Estimates—Pension and OPEB Accounting.” While we anticipate that our operation and maintenance expenses will continue to increase, if actual results differ materially from our assumptions, our costs could be significantly higher than expected which could adversely affect our results of operations, financial condition and liquidity.
Current wording
We continually focus on limiting and reducing where possible, our operation and maintenance expenses. However, we expect to continue to face increased cost pressures related to operation and maintenance expenses, including in the areas of health care and pension costs. We have experienced health care cost inflation in recent years, and we expect our cash outlay for health care costs, including prescription drug coverage, to continue to increase despite measures that we have taken requiring employees and retirees to bear a higher portion of the costs of their health care benefits. The measurement of our expected future health care and pension obligations and costs is highly dependent on a variety of assumptions, many of which relate to factors beyond our control. These assumptions include investment returns, interest rates, discount rates, health care cost trends, benefit design changes, salary increases, the demographics of plan participants and regulatory requirements. See Item 7., "Management's Discussion and Analysis of Financial Condition and Results of Operations—Critical Accounting Estimates—Pension and OPEB Accounting.” While we anticipate that our operation and maintenance expenses will continue to increase, if actual results differ materially from our assumptions, our costs could be significantly higher than expected which could adversely affect our results of operations, financial condition and liquidity.
Previous wording
Traditionally, electricity is generated at large, central station generation facilities distributed by our systems. This method results in economies of scale and lower unit costs than newer generation technologies such as fuel cells, microturbines, windmills and photovoltaic solar cells. It is possible that advances in newer generation technologies will make newer generation technologies more cost-effective, or that legislation addressing climate change at the federal or state level together with changes in regulatory policy will create incentives or benefits that otherwise make these newer generation technologies even more competitive with central station electricity production. To the extent that newer generation technologies are connected directly to load, bypassing the transmission and distribution systems, potential impacts could include decreased transmission and distribution revenues, stranded assets and increased uncertainty in load forecasting and integrated resource planning and could adversely affect our business and results of operations.
Current wording
Traditionally, electricity is generated at large, central generation facilities distributed by our systems. This method results in economies of scale and lower unit costs than newer generation technologies such as fuel cells, microturbines, windmills and photovoltaic solar cells. It is possible that advances in newer generation technologies will make newer generation technologies more cost-effective, or that legislation addressing climate change at the federal or state level together with changes in regulatory policy will create incentives or benefits that otherwise make these newer generation technologies even more competitive with central station electricity production. To the extent that newer generation technologies are connected directly to load, bypassing the transmission and distribution systems, potential impacts could include decreased transmission and distribution revenues, stranded assets and increased uncertainty in load forecasting and integrated resource planning and could adversely affect our business and results of operations.
Previous wording
Energy companies, including the Electric Companies and Transmission Companies, have been the subject of criticism on matters including the reliability of their distribution or transmission services and systems and the speed with which they are able to respond to power outages, such as those caused by storm damage. Adverse publicity of this nature, as well as negative publicity associated with the operation of coal-fired generation or proceedings seeking regulatory recoveries may cause less favorable legislative and regulatory outcomes and damage our reputation, which could have an adverse impact on our business and financial condition.
Current wording
Energy companies, including the Electric Companies and Transmission Companies, have been the subject of criticism on matters including the affordability and reliability of our distribution or transmission services and systems and the speed with which they are able to respond to power outages, such as those caused by storm damage. Adverse publicity of this nature, as well as negative publicity associated with the operation of coal-fired generation or proceedings seeking regulatory recoveries may cause less favorable legislative and regulatory outcomes and damage our reputation, which could have an adverse impact on our business and financial condition.
Previous wording
We have published statements concerning our climate-related goals and aspirations. We are targeting Scope 1 carbon neutrality by 2050, which for us includes emissions, sulfur hexafluoride leaks from transmission and distribution equipment, and our mobile fleet (i.e., vehicles). These statements reflect our aspirations and are not guarantees that we will be able to achieve them. Our failure to adequately update, accomplish or accurately track and report on these goals on a timely basis, or at all, could adversely affect our reputation, financial performance and growth, and expose us to increased scrutiny from the investment community, special interest groups and enforcement authorities, including at the state and local levels. Conversely, certain “anti-environmental, social and governance” sentiment among some individuals and government institutions pose the risk that we may face increasing scrutiny, reputational risk, or lawsuits from these parties.
Current wording
FirstEnergy published statements concerning its climate-related goals and aspirations. FirstEnergy is targeting Scope 1 carbon neutrality by 2050, which includes emissions, sulfur hexafluoride leaks from transmission and distribution equipment, and its mobile fleet (i.e., vehicles). These statements reflect FirstEnergy’s aspirations and are not guarantees that FirstEnergy will be able to achieve them. FirstEnergy’s failure to adequately update, accomplish or accurately track and report on these goals on a timely basis, or at all, could adversely affect its and its subsidiaries’ reputation, financial performance and growth, and expose us to increased scrutiny from the investment community, special interest groups and enforcement authorities, including at the state and local levels. Conversely, certain “anti-environmental, social and governance” sentiment among some individuals and government institutions pose the risk that we may face increasing scrutiny, reputational risk, or lawsuits from these parties.
Previous wording
Our ability to achieve our GHG reduction objective is subject to our ability to make operational changes and is conditioned upon numerous risks, many of which are outside of our control. Examples of such risks include the evolving regulatory requirements in the jurisdictions in which we operate, including the interpretation of such regulations, potential changes to such laws and regulations as a result of the new U.S. presidential administration, the prevalence of certain standards or disclosures, the evolving laws applicable to climate-related and other environmental matters, and the availability of funds to invest in initiatives in times where we are seeking to reduce costs.
Current wording
FirstEnergy’s ability to achieve its GHG reduction objective is subject to its ability to make operational changes and is conditioned upon numerous risks, many of which are outside of its control. Examples of such risks include the evolving regulatory requirements in the jurisdictions in which it and its subsidiaries operate, including the interpretation of such regulations, potential changes to such laws and regulations, the prevalence of certain standards or disclosures, the evolving laws applicable to climate-related and other environmental matters, and the availability of funds to invest in initiatives in times where FirstEnergy is seeking to reduce costs.
Previous wording
Standards for tracking and reporting of climate and other environmental matters continue to evolve. Our selection of voluntary disclosure frameworks and standards, and the interpretation or application of those frameworks and standards, may change from time to time or differ from those of others. Methodologies for reporting this data may be updated and previously reported data may be adjusted to reflect improvement in availability and quality of third-party data, changing assumptions, changes in the nature and scope of our operations and other changes in circumstances. Our processes and controls for reporting these matters across our operations and supply chain are evolving along with multiple disparate standards for identifying, measuring, and reporting these metrics, including climate-related disclosures that are or may be required by the SEC, state legislatures, or other regulators, and such standards may change over time, which could result in significant revisions to our current goals, reported progress in achieving such goals, or ability to achieve such goals in the future. If our practices do not meet evolving investor or other stakeholder expectations and standards, then our reputation or our attractiveness as an investment, business partner, acquiror, service provider or employer could be negatively impacted.
Current wording
Standards for tracking and reporting of climate and other environmental matters continue to evolve. FirstEnergy’s selection of voluntary disclosure frameworks and standards, and the interpretation or application of those frameworks and standards, may change from time to time or differ from those of others. Methodologies for reporting this data may be updated and previously reported data may be adjusted to reflect improvement in availability and quality of third-party data, changing assumptions, changes in the nature and scope of our operations and other changes in circumstances. FirstEnergy’s processes and controls for reporting these matters across its operations and supply chain are evolving along with multiple disparate standards for identifying, measuring, and reporting these metrics, including climate-related disclosures that are or may be required by the SEC, state legislatures, or other regulators, and such standards may change over time, which could result in significant revisions to FirstEnergy’s current goals, reported progress in achieving such goals, or ability to achieve such goals in the future. If FirstEnergy’s practices do not meet evolving investor or other stakeholder expectations and standards, then the reputations of FirstEnergy and its subsidiaries, including ours, or their attractiveness as an investment, or status as a business partner, acquiror, service provider or employer could be negatively impacted.
Previous wording
We have coal-fired generation capacity, which exposes us to risk from regulations relating to coal, GHGs and CCRs, which could lead to increased costs or the need to spend significant resources to defend allegations of violation.
Current wording
MP has coal-fired generation capacity, which exposes it to risk from regulations relating to coal, GHGs and CCRs, which could lead to increased costs or the need to spend significant resources to defend allegations of violation. (Applies to FE)
Showing the first 40 of 69 pairs. Open the source sections for the rest.
Rearranged current paragraphs (1)
Current report — wording carried from elsewhere
The retail rates for each of the Electric Companies are set by each of its respective regulatory agency for utilities in the state in which it operates - in Maryland by the MDPSC, in New Jersey by the NJBPU, in Ohio by the PUCO, in Pennsylvania by the
Rearranged previous paragraphs (1)
Previous report — wording carried elsewhere
Risks Associated with the Execution of Our Strategic Initiatives