HAWAIIAN ELECTRIC INDUSTRIES INC
For the period ended Dec 31, 2024. Filed Feb 24, 2025.
View on SEC.govAbout this filing
A company's yearly report to the SEC, with audited financial statements. It is the fullest account a company gives of its business, its finances and the risks it sees.
FY2024 · Filed Feb 24, 2025
What changed in Risk Factors?
Read the current filingPrevious report: 10-K
Period ended 2023-12-31; filed 2024-02-29.
0000354707-24-000012
Item 1A. RISK FACTORSCurrent report: 10-K
Period ended 2024-12-31; filed 2025-02-24.
0000354707-25-000013
Item 1A. RISK FACTORSThe baseline is this issuer’s latest earlier reporting period of the same form that was filed before the current report. A previous 10-Q is a different quarter, not a year-over-year comparison. Amendments are excluded.
Compared 115 previous paragraphs and 66 current paragraphs.
26 unchanged; 25 reworded; 13 added; 61 removed; 3 previous and 2 current paragraphs rearranged.
Tables are not compared: 0 previous and 1 current tables excluded. Dates, whitespace, punctuation and numbering changes are ignored; changes to financial figures remain significant.
A changed paragraph is not evidence that risk increased or decreased. An unchanged paragraph does not establish that risk stayed the same.
Added paragraphs (13)
Current report
Multiple lawsuits have been filed against the Utilities and HEI alleging, among other things, that they were negligent in failing to prevent the wildfires that led to the property destruction and loss of life. The amount of any liability arising from the Maui windstorm and wildfires (which could exceed amounts currently reserved for the settlement liability), whether determined at trial or through a negotiated settlement, could have a material adverse impact on HEI’s and Hawaiian Electric’s financial condition, liquidity, cash flows and results of operations. As of December 31, 2024, HEI and the Utilities have approximately $13 million, nil and $122 million of insurance coverage remaining under the excess liability, professional liability, and directors and officers liability policies, respectively, after deducting applicable retention amounts, amounts that have been recovered under insurance policies (including the One ‘Ohana Initiative contribution), and amounts expected to be recovered for incurred costs and recognized as a receivable as of year-end.
Current report
There may be future conditions or events that raise substantial doubt about our ability to continue as a going concern, and it is possible that any plan developed to alleviate such doubt may be unsuccessful. In addition, any capital raised may result in dilution to our current shareholders. For the year ended December 31, 2024, the Company incurred losses from continuing operations of approximately $1.32 billion. For the year ended December 31, 2024, the Utilities incurred net losses of approximately $1.23 billion. The net losses for the year ended December 31, 2024, were primarily due to the accruals of estimated wildfire liabilities in the second and third quarters of 2024, totaling approximately $1.92 billion related to the Maui windstorm and wildfire tort-related legal claims. The Company previously disclosed in its Quarterly Report on Form 10-Q for the quarter ending June 30, 2024, that based on its financial and liquidity condition, and because it had not yet implemented a capital financing plan to address proposed wildfire settlement payments, there was substantial doubt about HEI’s and the Utilities’ ability to continue as a going concern.
Current report
Management believes the Company’s cash and cash equivalents amount of $751 million and GLST1’s restricted cash amount of $479 million, both as of December 31, 2024, the available capacity on Hawaiian Electric’s asset-based lending facility (ABL Facility) (see Note 6 of the Consolidated Financial Statements included herein), additional liquidity under HEI’s recently registered ATM program as well as expenditure reduction efforts effectively alleviate any conditions that may cause substantial doubt regarding HEI’s and Utilities’ ability to continue as a going concern. The Company has adequate cash to meet its financial obligations and sustain operations in the short term, including available sufficient liquidity to fund the first installment of the settlement of wildfire tort claims expected to be made no earlier than the fourth quarter of 2025 and its other cash obligations for the next 12 months following the issuance of its financial statements. The plans that have been implemented have mitigated the conditions that previously caused the substantial doubt about HEI’s and the Utilities’ ability to continue as a going concern as of the date of filing their 2024 second quarter financial statements. Although the Company has raised sufficient cash to pay the first installment of the settlement of wildfire tort claims, the Company is currently working with its financial advisors on a financing plan to raise the additional capital necessary to fund the remaining settlement of wildfire tort claims. While management believes the Company will be able to raise the necessary capital, there is no assurance that management’s plans will be successful. If the financing plans are unsuccessful, the Company may need to consider other strategic alternatives.
Current report
The recurrence of any substantial doubt about HEI’s and the Utilities’ ability to continue as a going concern may affect the price of our common stock, may impact our relationship with third parties with whom we do business, including our vendors, lenders and employees, may impact our ability to raise additional capital or refinance existing debt and may impact our ability to comply, going forward, with certain covenants in our debt agreements and/or satisfy conditions to draw thereunder, which could significantly and materially restrict our operations.
Current report
If a court-approved definitive settlement agreement to resolve Maui windstorm and wildfire tort-related legal claims is not obtained, or if financing for settlement payments is not available, we may need to consider other alternatives for addressing the outstanding legal claims or settlement payments, and such alternatives could adversely affect our financial results or other factors impacting our finances, operations or stock valuation. As described more fully in Note 2 of the Consolidated Financial Statements included herein, the Company entered into Settlement Agreements effective November 1, 2024, to resolve all Maui windstorm and wildfire tort-related legal claims, including all claims among the defendants. Such Settlement Agreements are subject to court approval, and other conditions including resolution of the claims of the insurance companies that have paid claims for property loss and other damages. If all conditions of the Settlement Agreements are satisfied, the Company has agreed to make substantial payments to settle all Maui windstorm and wildfire tort-related legal claims. As described more fully in Note 2 of the Consolidated Financial Statements included herein, if the conditions of the Settlement Agreements are not satisfied or the agreements are otherwise terminated, the Company intends to vigorously defend against the litigation. There is no assurance that the Company will be successful in the defense of the litigation or that insurance proceeds will be available to fund any potential settlements, judgments, or costs associated with the litigation.
Current report
If all conditions of the Settlement Agreements are satisfied, the Company expects to finance the settlement payments through a mix of debt, common equity, equity-linked securities or other potential options. While management believes the Company will be able to raise the capital necessary to finance the settlement payments, there is no assurance that future financing will be available in sufficient amounts, on a timely basis or on reasonable terms acceptable to us, if at all.
Current report
If the Company’s financing plans are unsuccessful, we may need to consider other strategic alternatives, including delaying strategic initiatives, selling assets, or other strategic measures including, without limitation, obtaining relief under the U.S.
Current report
Bankruptcy Code. Such alternatives could adversely affect our financial results or other factors impacting our finances, operations or stock valuation.
Current report
You may experience future dilution as a result of future equity offerings. In order to raise additional capital, including capital necessary to fund litigation settlement expenses, the Company may in the future offer additional shares of HEI’s Common Stock or other securities convertible into or exchangeable for HEI Common Stock at prices that may not be the same as the current market price per share, and investors purchasing shares or other securities in the future could have rights superior to existing stockholders. The price per share at which the Company may sell additional shares of HEI Common Stock, or securities convertible or exchangeable into HEI Common Stock, in future transactions may be higher or lower than the current market price per share of HEI Common Stock.
Current report
In addition, any future sales of a substantial number of shares of HEI Common Stock in the public market, or the perception that such sales may occur, could adversely affect the price of HEI Common Stock. We cannot predict the effect, if any, that market sales of those shares of Common Stock, or the perception that those shares may be sold, will have on the market price of HEI Common Stock. Further, we may not have the ability to raise the amount of capital necessary on reasonable terms, or at all, to fund our contribution to the Maui wildfire tort litigation settlement, and uncertainties about the Company’s access to capital could have a material adverse effect on the market price of HEI Common Stock.
Current report
The Company does not expect to pay any dividends in the foreseeable future. The Company does not currently intend to pay dividends on HEI Common Stock and currently intends to retain future earnings, if any, to fund the development and growth of the Company’s business. In addition, the terms of certain existing and any future debt agreements may preclude the Company from paying dividends. As a result, capital appreciation, if any, of HEI Common Stock may be your sole source of gain for the foreseeable future.
Current report
Executive orders. In January 2025, President Trump issued multiple Executive Orders (EOs) that impact both IIJA and IRA funding. EO 14154 entitled Unleashing American Energy ordered to immediately pause disbursement of funds appropriated through IIJA and IRA grants, which is causing delays in processing the Utilities’ requests for reimbursement for the Resilience Program and may potentially lead to project delays and economic uncertainty. The EO entitled Ending Radical and Wasteful Government DEI Programs and Preferencing resulted in the federal contracting officer ordering recipients to cease all diversity, equity and inclusion and community benefits plan activities funded by federal grants as of January 28, 2025, which could potentially impact the Utilities’ existing community benefits agreements with some third parties and commitments included in the Resilience Program project costs. The Utilities are unable to predict the timing or amount of the funding the Utilities may receive as a result of the two EOs mentioned above.
Removed paragraphs (61)
Previous report
Multiple lawsuits have been filed against the Utilities and HEI alleging, among other things, that they were negligent in failing to prevent the wildfires that led to the property destruction and loss of life. If the Utilities and HEI are held responsible for damages caused by the Maui windstorm and wildfires, it could have a material impact on HEI’s and Hawaiian Electric’s financial condition, liquidity, cash flows and results of operations. The Company has $165 million in insurance coverage for third party claims, but the aggregate losses associated with the Maui windstorm and wildfires could significantly exceed that amount. Also, the Company is incurring legal and consulting fees to manage the lawsuits and financial implications related to the Maui windstorm and wildfires, and those amounts are likely to be material.
Previous report
•the provisions of an HEI agreement entered into with federal bank regulators in connection with its acquisition of its bank subsidiary, ASB, which requires HEI to contribute additional capital to ASB (up to a maximum amount of additional capital of $28.3 million as of December 31, 2023 under the Regulatory Capital Maintenance/Dividend Agreement dated May 26, 1988, between HEI, HEIDI (HEI Diversified Inc.) and the Federal Savings and Loan Insurance Corporation) upon request of the regulators in order to maintain ASB’s regulatory capital at the level required by regulation;
Previous report
•obligations under federal law and Federal Reserve Board policy, which require that a savings and loan holding company serve as a source of financial and managerial strength for any FDIC-insured depository institution that it controls, and accordingly, if ASB were to be in financial distress or to otherwise be viewed by the regulators as in unsatisfactory condition, HEI could be required to provide additional capital or liquidity support or take other action, in support of ASB. In addition, ASB may continue its suspension of its quarterly dividend to conserve cash to help ensure its maximum possible liquidity and capital position;
Previous report
•the minimum capital and capital distribution regulations of the OCC that are applicable to ASB and capital regulations that become applicable to HEI and ASB Hawaii;
Previous report
•the receipt of a letter from the FRB communicating the OCC’s and the FRB’s non-objection to the payment of any dividend ASB proposes to declare and pay to ASB Hawaii and HEI; and
Previous report
Interest rate risk also represents a market risk factor affecting the fair value of ASB’s investment securities. Increases and decreases in prevailing interest rates generally translate into decreases and increases in the fair values of those instruments, respectively. Disruptions in the credit markets, a liquidity crisis in the banking industry or increased levels of residential mortgage delinquencies and defaults may result in decreases in the fair value of ASB’s investment securities and an impairment, requiring ASB to write down its investment securities. As of December 31, 2023, ASB’s investment in U.S. Treasury and federal agency obligations, and mortgage-backed securities have an implicit guarantee from the U.S. government. Decreases in the fair value of ASB’s investment securities may also result in lower equity capital balances as unrealized losses in the available-for-sale investment securities portfolio are recorded as a decrease in equity capital through accumulated other comprehensive losses. The lower equity capital balance could result in a lower tangible equity capital ratio and restrict ASB’s permissible activities if the tangible equity capital ratio falls below 2%. A negative tangible equity capital ratio would impact ASB’s availability to borrow funds from the FHLB of Des Moines.
Previous report
Substantially all of ASB’s consumer loan customers are Hawaii residents. A significant portion of the commercial loan customers are also located in Hawaii. While a majority of customers are on Oahu, ASB also has customers on the neighbor islands (whose economies are smaller and less diverse than Oahu’s economy). Substantially all of the real estate underlying ASB’s residential and commercial real estate loans are located in Hawaii. These assets may be subject to a greater risk of default due to geographic concentration than other comparable assets held by financial institutions with more diverse geographic exposure in the event of adverse economic, political or business developments or natural disasters affecting Hawaii and affect the ability of ASB’s customers to make payments of principal and interest on their loans.
Previous report
•ASB, one of the largest financial institutions in the state, is in direct competition for deposits and loans not only with two larger institutions that have substantial capital, technology and marketing resources, but also with smaller Hawaii institutions and other U.S. institutions, including credit unions, mutual funds, mortgage brokers, finance companies, non-traditional providers of financial services and investment banking firms. Larger financial institutions may have greater access to capital at lower costs, which could impair ASB’s ability to compete effectively. New or significant advances in technology (e.g., significant advances in internet or mobile banking) or customer adoption of alternative banking channels could render the operations of ASB less competitive or obsolete.
Previous report
ASB. ASB is highly dependent on its ability to process, on a daily basis, a large number of transactions and relies heavily on communication and information systems, including those of third-party vendors and other service providers. If any of these systems fail to operate properly or become disabled even for a brief period of time, ASB could suffer financial loss, business disruptions, liability to customers, regulatory intervention or damage to its reputation, any of which could have a material adverse effect on ASB’s and the Company’s financial condition and results of operations. Communication and information system failures can result from a variety of risks including, but not limited to, events that are wholly or partially out of ASB’s control, such as communication line integrity, weather, terrorist acts, natural disasters, accidental disasters, unauthorized breaches of security systems, energy delivery systems, cyberattacks and other events.
Previous report
ASB is under continuous threat of loss due to cyberattacks, especially as ASB continues to expand customer capabilities to utilize the Internet and other digital channels to transact business. Two of the most significant cyberattack risks that ASB faces are e-fraud and loss of sensitive customer data. Loss from e-fraud occurs when cybercriminals extract funds directly from ASB or its customers’ accounts using fraudulent schemes that may include Internet-based funds transfers. ASB has been subject to e-fraud incidents historically. Loss of sensitive customer data are attempts to steal sensitive customer data, such as account numbers and social security numbers, through unauthorized access to computer systems, including computer hacking. Such attacks could present significant reputational, legal and regulatory costs if successful. Intrusion detection and prevention systems, anti-virus software, firewalls and other general information technology controls have been put in place to help detect and prevent cyberattacks or information system breaches. Disaster recovery and incident response plans have been developed to respond to unplanned incidents such as natural disasters, cyberattacks and other disruptive events. However there can be no assurance that failures, interruptions or security breaches will not occur or, if they do occur, that they will be adequately protected or recovered by ASB or its vendors.
Previous report
Despite the security measures we have implemented, certain cyber incidents could materially disrupt operational systems; result in loss of trade secrets or other proprietary or competitively sensitive information; compromise personally identifiable information regarding customers or employees; delay our ability to deliver products to customers; and/or jeopardize the security of our facilities. Additionally unauthorized access to our computer systems or stored data could result in the theft, including cyber-theft, or improper disclosure of confidential information, and the deletion or modification of records could cause interruptions in our operations.
Previous report
Further, a data breach involving theft, improper disclosure, or other unauthorized access to or acquisition of confidential information could subject the Bank to penalties for violation of applicable privacy laws, claims by third parties, and enforcement actions by government agencies. In addition, ASB’s operational systems may be subject to new cybersecurity risks due to modernizing and interconnecting existing infrastructure with new technologies and control systems, including those owned by third parties. Although ASB has not experienced a material cybersecurity breach to date, such incidents may occur and may have a material adverse effect on the Bank should a material incident occur.
Previous report
ASB generally does not obtain credit enhancements, such as mortgagor bankruptcy insurance, but does require standard hazard and hurricane insurance and may require flood insurance for certain properties. ASB is subject to the risks of borrower defaults and bankruptcies, special hazard losses not covered by the required insurance and the insurance company’s inability to pay claims on existing policies.
Previous report
In July 2007, the State Legislature passed Act 234, which requires a statewide reduction of GHG emissions by January 1, 2020 to levels at or below the statewide GHG emission levels in 1990. On June 20, 2014, the Governor signed the final rules required to implement Act 234 and these rules went into effect on June 30, 2014. In general, Act 234 and the GHG rule require affected sources that have the potential to emit GHGs in excess of established thresholds to reduce their GHG emissions by 16% below 2010 emission levels by 2020. In accordance with state requirements, the Utilities submitted an Emissions Reduction Plan (ERP) to the State of Hawaii Department of Health on June 30, 2015, with the most recent revision filed on June 9, 2020, to reflect the partnership established between the Utilities and several IPPs. In this plan, the partnership committed to a 16% reduction in GHG emissions in accordance with the rule, which the partnership achieved in 2017 in advance of the 2020 requirement. The State of Hawaii Department of Health issued the air permits incorporating the ERP, including provisions to address the period of unavailability of the PGV facility on Hawaii Island. It is expected that with the advent of additional renewable projects and the application to the PUC with respect to the expansion of the PPA for the PGV project, the goals should be attainable.
Previous report
Interest Rate Risk—Fluctuations in interest rates could result in lower net interest income, impair ASB’s ability to originate new loans, impair the ability of ASB’s adjustable-rate borrowers to make increased payment obligations or impact ASB’s ability to attract and retain deposits. Interest rate risk is a significant risk of ASB’s operations. ASB’s net interest income consists primarily of interest income received on fixed-rate and adjustable-rate loans, mortgage-backed securities and investments, less interest expense consisting primarily of interest paid on deposits and other borrowings. Interest rate risk arises when earning assets mature or reprice in a time frame different from that of costing liabilities. Changes in interest rates, including changes in the relationship between short-term and long-term tenors (e.g., a flat or an inverted yield curve) or between different interest rate indices, can impact ASB’s net interest margin. See “Quantitative and Qualitative Disclosures about Market Risk.”
Previous report
Although ASB pursues an asset-liability management strategy designed to mitigate its risk from changes in interest rates, adverse movements in interest rates could result in lower net interest income or net interest margin. Residential 1-4 family fixed-rate mortgage loans comprised about 37% of ASB’s loan portfolio as of December 31, 2023. Increases in market interest rates could have an adverse impact on ASB’s cost of funds. Higher market interest rates could lead to higher interest rates paid on deposits and other borrowings. Significant increases in market interest rates, or the perception that an increase may occur, could adversely affect ASB’s ability to originate new loans. An increase in market interest rates, especially a sudden increase, similar to the rapid federal funds rate increases experienced in 2022, could also adversely affect the ability of ASB’s adjustable-rate borrowers to meet their higher payment obligations. If this occurred, it could cause an increase in nonperforming assets and charge-offs. Conversely, a decrease in interest rates or a mismatching of maturities of interest sensitive financial instruments could result in an acceleration in the prepayment of loans and mortgage-backed securities and impact ASB’s ability to reinvest its liquidity in similar yielding assets.
Previous report
ASB relies on customer deposits as a sizable source of relatively stable and low-cost funding. Changes in interest rates impact the interest paid on deposits and can significantly impact the Bank’s net interest income and net interest margin. Changes in interest rates may also impact the level of low-cost core deposits that the Bank’s customers maintain in their accounts, which may require ASB to seek higher costing wholesale borrowings.
Previous report
Credit Risk—ASB’s allowance for credit losses may not cover actual loan losses. ASB’s allowance for credit losses is ASB’s estimate of lifetime expected credit losses on financial instruments and other commitments to extend credit and is based on a continuing assessment of:
Previous report
•current conditions (for example, economic conditions, real estate market conditions and interest rate environment); and
Previous report
•reasonable and supportable forecasts that affect the collectability of the reported amount.
Previous report
If ASB’s actual loan losses exceed its allowance for credit losses, it may incur losses, its financial condition may be materially and adversely affected, and additional capital may be required to enhance its capital position. In addition, various regulatory agencies, as an integral part of their examination process, regularly review the adequacy of ASB’s allowance. These agencies may require ASB to establish additional allowances based on their judgment of the information available at the time of their examinations. No assurance can be given that ASB will not sustain loan losses in excess of present or future levels of its allowance for credit losses.
Previous report
Operational Risk—ASB’s operations are affected by factors that are beyond its control, that could result in lower revenues, higher expenses or decreased demand for its products and services. ASB’s results of operations depend primarily on the income generated by the supply of, and demand for, its products and services, which primarily consist of loans and deposit services. ASB also generates income from other non-deposit products and services. ASB’s revenues and expenses may be adversely affected by various factors, including:
Previous report
•local, regional, national and other economic and political conditions that could result in declines in employment and real estate values, which in turn could adversely affect the ability of borrowers to make loan payments and the ability of ASB to recover the full amounts owing to it under defaulted loans;
Previous report
•the ability of borrowers to obtain insurance and the ability of ASB to place insurance where borrowers fail to do so, particularly in the event of catastrophic damage to collateral securing loans made by ASB;
Previous report
•faster than expected loan prepayments that can cause an acceleration of the amortization of premiums on loans and investments and the impairment of mortgage servicing assets of ASB;
Previous report
•changes in ASB’s loan portfolio credit profiles and asset quality, which may increase or decrease the required level of allowance for credit losses;
Previous report
•technological disruptions affecting ASB’s operations or financial or operational difficulties experienced by any outside vendor on whom ASB relies to provide key components of its business operations, such as business processing, network access or internet connections;
Previous report
•events of default and foreclosure of loans whereby ASB becomes the owner of mortgage properties that presents environmental risk or potential clean up liability;
Previous report
•the impact of legislative and regulatory changes, including changes affecting capital requirements, increasing oversight of and reporting by banks, or affecting the lending programs or other business activities of ASB;
Previous report
•additional legislative changes regulating the assessment of overdraft, interchange and credit card fees, which can have a negative impact on noninterest income;
Previous report
•public opinion about ASB and financial institutions in general, which, if negative, could impact the public’s trust and confidence in ASB and adversely affect ASB’s ability to attract and retain customers and expose ASB to adverse legal and regulatory consequences;
Previous report
•increases in operating costs (including employee compensation expense and benefits and regulatory compliance costs), inflation and other factors, that exceed increases in ASB’s net interest, fee and other income; and
Previous report
•the ability of ASB to maintain or increase the level of deposits, ASB’s lowest costing funds.
Previous report
Banking Regulatory Risk—Banking and related regulations could result in significant restrictions being imposed on ASB’s business or in a requirement that HEI divest ASB. ASB is subject to examination and comprehensive regulation by the Department of Treasury, the OCC and the FDIC, and is subject to reserve requirements established by the Board of Governors of the Federal Reserve System. In addition, the FRB is responsible for regulating ASB’s holding companies, HEI and ASB Hawaii. The regulatory authorities have extensive discretion in connection with their supervisory and enforcement activities and examination policies to address not only ASB’s compliance with applicable banking laws and regulations, but also capital adequacy, asset quality, management ability and performance, earnings, liquidity and various other factors.
Previous report
Under certain circumstances, including any determination that ASB’s relationship with HEI results in an unsafe and unsound banking practice, these regulatory authorities have the authority to restrict the ability of ASB to transfer assets and to make distributions to its shareholders (including payment of dividends to HEI), or they could seek to require HEI to sever its relationship with or divest its ownership of ASB. Payment by ASB of dividends to HEI may also be restricted by the OCC and FRB under its prompt corrective action regulations or its capital distribution regulations if ASB’s capital position deteriorates. In order to maintain its status as a QTL, ASB is required to maintain at least 65% of its assets in “qualified thrift investments.” Institutions that fail to maintain QTL status are subject to various penalties, including limitations on their activities. In ASB’s case, the activities of HEI and HEI’s other subsidiaries would also be subject to restrictions, and a failure or inability to comply with those restrictions could effectively result in the required divestiture of ASB. Federal legislation has also been proposed in the past that could operate to eliminate the thrift charter or the grandfathered status of HEI as a unitary thrift holding company, which in turn would result in a required divestiture of ASB. In the event of a required divestiture, federal law substantially limits the types of entities that could potentially acquire ASB.
Previous report
Bank Regulatory Risk - Heightened regulatory requirements if ASB’s total assets exceed $10 billion. As of December 31, 2023, ASB had total assets of approximately $9.7 billion and it is possible that total assets could exceed $10 billion in the near future. The Dodd-Frank Act and its implementing regulations impose enhanced supervisory requirements on financial institutions with more than $10 billion in total assets. For financial institutions with more than $10 billion in total assets, such requirements include, among other things:
Showing the first 40 of 61 passages. Open the source sections for the rest.
Reworded paragraphs (25)
Previous wording
Potential losses resulting from the Maui windstorm and wildfires could have a material adverse effect on HEI’s and Hawaiian Electric’s financial condition, liquidity, cash flows and results of operations. On August 8, 2023, a number of brush fires in the West Maui (Lahaina) and Upcountry Maui areas caused widespread property damage, including damage to property of the Utilities, and 101 confirmed fatalities in Lahaina at this time (the Maui windstorm and wildfires). The Maui windstorm and wildfires were fueled by extreme winds and drought-like conditions in those parts of Maui. According to the Maui Police Department’s Preliminary After-Action Report, in addition to the loss of life, over 3,450 acres burned and over 3,000 structures were destroyed in those areas. In Lahaina, a fire was reported at about 6:30 a.m. (the “Morning Fire”) and appears to have been caused by power lines that fell in high winds and spread into a field near Lahaina Intermediate School. The Maui Fire Department responded promptly to the Morning Fire, and according to the Fire Department’s public statement that morning, by 9 a.m. the Morning Fire was “100% contained.” The Maui fire chief subsequently reported that the Fire Department had determined that the Morning Fire was “extinguished” and left the scene. Shortly before 3 p.m. that day, while the power remained off, Utility crew members saw a small fire in the same field about 75 yards away from Lahainaluna Road. They immediately called 911 and reported the fire (the “Afternoon Fire”). At the time of the Afternoon Fire, the Company’s power lines in the area where that fire ignited were not energized and had not been energized for more than six hours. By the time the Maui Fire Department arrived back on the scene, it was not able to contain the Afternoon Fire and it spread out of control toward Lahaina. No determination as to the cause of the Afternoon Fire has been made. The Company believes that most of the property damage and all of the fatalities are from the Afternoon Fire.
Current wording
Potential losses resulting from the Maui windstorm and wildfires could have a material adverse effect on HEI’s and Hawaiian Electric’s financial condition, liquidity, cash flows and results of operations. On August 8, 2023, a number of brush fires in the West Maui (Lahaina) and Upcountry Maui areas caused widespread property damage, including damage to property of the Utilities, and 102 confirmed fatalities in Lahaina (the Maui windstorm and wildfires). The Maui Department of Fire and Public Safety (MFD) and Bureau of Alcohol, Tobacco, Firearms and Explosives (ATF) reports classified the cause of the fire as “accidental.”
Previous wording
HEI’s and Hawaiian Electric’s access to capital markets and other sources of debt and equity financings in a timely manner and on acceptable terms will continue to be negatively impacted as a result of the downgrades in their debt credit ratings to below investment grade. In August 2023, HEI and Hawaiian Electric received multiple downgrades to their debt, including to ratings below investment grade, by Fitch, Moody’s and S&P. Unless and until these debt ratings are upgraded to investment grade, the Company will continue to have restricted access to capital markets and other sources of debt and equity financings, if at all, in a timely manner and on acceptable terms. Accordingly, the Company’s financial condition, liquidity, cash flows and results of operations may be adversely impacted if debt credit ratings are maintained at below investment grade for an extended period of time.
Current wording
Unless and until these debt ratings are upgraded to investment grade, the Company will continue to have restricted access to capital markets and other sources of debt and equity financings, if at all, in a timely manner and on acceptable terms. Recent projects, such as, wildfire mitigation plan, grid modernization, reliability and resilience all require significant capital expenditures to implement. The Company may not be able to obtain the necessary financing to achieve its business objectives as a result of the downgrades. Accordingly, the Company’s financial condition, liquidity, cash flows and results of operations may be adversely impacted if debt credit ratings are maintained at below investment grade for an extended period of time.
Previous wording
HEI’s and Hawaiian Electric’s credit ratings only reflect the view, at the time the ratings are issued, of the applicable rating agency. There is no assurance that any such credit rating will remain in effect for any given period of time or that such rating will not be lowered, suspended or withdrawn entirely by the applicable rating agency if, in such rating agency’s judgment, circumstances, such as current, past or future effects or events so warrant. Any such lowering, suspension or withdrawal of any rating may have an adverse effect on the availability of capital to the Company or the market price or marketability of HEI’s and/or Hawaiian Electric’s securities, which could increase the cost of capital of HEI and Hawaiian Electric, and such increased costs, including interest charges, under HEI’s and/or Hawaiian Electric’s debt securities and credit facilities, would result in reductions in HEI’s consolidated net income in future periods. Because HEI’s and Hawaiian Electric’s credit ratings were downgraded, HEI and Hawaiian Electric are unable to sell commercial paper and were required to draw on more expensive bank lines of credit and to defer capital or other expenditures. Neither HEI nor Hawaiian Electric management can predict the duration of the downgrades and future rating agency actions or their effects on the future cost of capital of HEI or Hawaiian Electric. Such ratings are not recommendations to buy, sell or hold any securities; such ratings may be subject to revision or withdrawal at any time by the rating agencies; and each rating should be evaluated independently of any other rating.
Current wording
HEI’s and Hawaiian Electric’s credit ratings only reflect the view, at the time the ratings are issued, of the applicable rating agency. There is no assurance that any such credit rating will remain in effect for any given period of time or that such rating will not be lowered, suspended or withdrawn entirely by the applicable rating agency if, in such rating agency’s judgment, circumstances, such as current, past or future effects or events so warrant. Any such lowering, suspension or withdrawal of any rating may have an adverse effect on the availability of capital to the Company or the market price or marketability of HEI’s and/or Hawaiian Electric’s securities, which could increase the cost of capital of HEI and Hawaiian Electric, and such increased costs, including interest charges, under HEI’s and/or Hawaiian Electric’s debt securities and credit facilities, would result in reductions in HEI’s consolidated net income in future periods. Because HEI’s and Hawaiian Electric’s credit ratings were downgraded, HEI and Hawaiian Electric are unable to sell commercial paper and were required to draw on more expensive bank lines of credit and prioritize capital and other expenditures. Neither HEI nor Hawaiian Electric management can predict the duration of the downgrades and future rating agency actions or their effects on the future cost of capital of HEI or Hawaiian Electric. Such ratings are not recommendations to buy, sell or hold any securities; such ratings may be subject to revision or withdrawal at any time by the rating agencies; and each rating should be evaluated independently of any other rating.
Previous wording
Extreme weather events and other natural disasters, particularly those exacerbated by climate change such as the Maui windstorm and wildfires, could materially affect Hawaiian Electric’s assets, particularly if they fail or are found to have contributed to a wildfire. Extreme weather-related incidents and other natural disasters, including volcanic eruptions, mudslides, hurricanes, tsunamis and other storms, can interfere with the generation and transmission of electricity, and can seriously damage the infrastructure necessary to deliver electricity to customers. These risks are increasing, as climate change has exacerbated some of the conditions that lead to these extreme weather events and natural disasters. Such an event can result in lost revenue and increased expenses for the Utilities, but it also can result in regulatory penalties and disallowances if Hawaiian Electric is unable to restore power on a timely basis. Also, an extreme event can lead to significant claims for damages, including for loss of life and property, and has been the case with the Maui windstorm and wildfires. Therefore, these events could materially affect the Company’s business, reputation, financial condition and results of operations.
Current wording
Extreme weather events and other natural disasters, particularly those exacerbated by climate change such as the Maui windstorm and wildfires, could materially affect Hawaiian Electric’s assets and infrastructure, particularly if such infrastructure is damaged or is found to have contributed to other catastrophic events such as a wildfire. Extreme weather-related incidents and other natural disasters, including volcanic eruptions, mudslides, hurricanes, tsunamis and other storms, can interfere with the generation and transmission of electricity, and can seriously damage the infrastructure necessary to deliver electricity to customers. Damage to Hawaiian Electric’s infrastructure can also cause or contribute to additional loss through events such as wildfires. These risks are increasing, as climate change has exacerbated some of the conditions that lead to these extreme weather events and natural disasters. Such an event can result in lost revenue and increased expenses for the Utilities, but it also can result in regulatory penalties and disallowances if Hawaiian Electric is unable to restore power on a timely basis. Also, an extreme event can lead to significant claims for damages, including for loss of life and property, and has been the case with the Maui windstorm and wildfires. Therefore, these events could have a material adverse effect on the Company’s business, reputation, financial condition and results of operations.
Previous wording
Holding Company Risk—HEI is a holding company that derives its income from its operating subsidiaries and depends on the ability of those subsidiaries to pay dividends or make other distributions to HEI and on its own ability to raise capital. HEI is a legal entity separate and distinct from its various subsidiaries. As a holding company with no significant operations of its own, HEI’s cash flows and consequent ability to service its obligations and pay dividends on its common stock is dependent upon its receipt of dividends or other distributions from its operating subsidiaries and its ability to issue common stock or other equity securities and to incur additional debt. A material reduction or delay in dividends or other distributions by one or both of Hawaiian Electric and ASB for an extended period of time, such as a continuation or expansion of the reduction in dividends that HEI currently is experiencing due to the Maui windstorm and wildfires, could have a material adverse effect on the Company’s business, financial condition and results of operations. The ability of HEI’s subsidiaries to pay dividends or make other distributions to HEI, in turn, is subject to the risks associated with their operations and to contractual and regulatory restrictions, including:
Current wording
Holding Company Risk—HEI is a holding company that derives its income from its principal operating subsidiary, Hawaiian Electric, and depends on the ability of Hawaiian Electric to pay dividends or make other distributions to HEI and on its own ability to raise capital. HEI is a legal entity separate and distinct from its subsidiaries. As a holding company with no significant operations of its own, HEI’s cash flows and consequent ability to service its obligations and pay dividends on its common stock is dependent upon its receipt of dividends or other distributions from Hawaiian Electric and its ability to issue common stock or other equity securities and to incur additional debt. A material reduction or delay in dividends or other distributions by Hawaiian Electric for an extended period of time, such as a continuation or expansion of the reduction in dividends that HEI currently is experiencing due to the Maui windstorm and wildfires, could have a material adverse effect on the Company’s business, financial condition and results of operations. The ability of HEI’s subsidiaries to pay dividends or make other distributions to HEI, in turn, is subject to the risks associated with their operations and to contractual and regulatory restrictions, including:
Previous wording
•the provisions of an HEI agreement with the PUC, which could limit the ability of HEI’s principal electric public utility subsidiary, Hawaiian Electric, to pay dividends to HEI in the event that the consolidated common stock equity of the Utilities falls below 35% of total capitalization of the electric utilities;
Current wording
•the provisions of an HEI agreement with the PUC (PUC Agreement), which could limit the ability of HEI’s principal electric public utility subsidiary, Hawaiian Electric, to pay dividends to HEI in the event that the consolidated common stock equity of the Utilities falls below 35% of total capitalization of the electric utilities. As of December 31, 2024, the consolidated common stock equity of HEI’s electric utility subsidiaries was 33% of their total capitalization based on the current definition under the PUC Agreement and, as a result, the Utilities are restricted in cash payment of their dividend to HEI at this time (see Note 15 of the Consolidated Financial Statements.);
Previous wording
Credit and Capital Market Risk—The Company, and its lowered credit rating, is subject to risks associated with the Hawaii economy, including catastrophic events such as the Maui windstorm and wildfire (in the aggregate and on an individual island basis), volatile U.S. capital markets and changes in the interest rate and credit market environment that have or could result in higher retirement benefit plan funding requirements, declines in ASB’s interest rate margins and investment values, higher delinquencies and charge-offs in ASB’s loan portfolio and restrictions on the ability of HEI or its subsidiaries to borrow money or issue securities. The two largest components of Hawaii’s economy are tourism and the federal government (including the military). Because the core businesses of HEI’s subsidiaries are providing local public electric utility services (through Hawaiian Electric and its subsidiaries) and banking services (through ASB) in Hawaii, the Company’s operating results are significantly influenced by: Hawaii’s economy, which in turn is influenced by economic conditions in the mainland U.S. (particularly California) and Asia (particularly Japan) as a result of the impact of those conditions on tourism; by the impact of interest rates on the construction and real estate industries and by the impact of federal government spending in Hawaii, which can be affected by world conditions; and, from time to time, the expiration of federal government appropriations bills. In addition, the Hawaii economy could be directly or indirectly affected by implications and potential impacts of U.S. and foreign capital and credit market conditions and federal, state and international responses to those conditions and the potential impacts of global and local developments (including economic conditions and uncertainties; unrest, terrorist acts, wars (such as the Russia-Ukraine war and the Israel-Hamas war), conflicts, political protests, deadly virus epidemic, pandemics, or other crisis; the effects of changes that have or may occur in U.S. policy, such as with respect to immigration and trade).
Current wording
Credit and Capital Market Risk—The Company, and its lowered credit rating, is subject to risks associated with the Hawaii economy, including catastrophic events such as the Maui windstorm and wildfire (in the aggregate and on an individual island basis), volatile U.S. capital markets and changes in the interest rate and credit market environment that have or could result in higher retirement benefit plan funding requirements and restrictions on the ability of HEI or its subsidiaries to borrow money or issue securities. The two largest components of Hawaii’s economy are tourism and the federal government (including the military). Because the core businesses of HEI’s subsidiaries are providing local public electric utility services (through Hawaiian Electric and its subsidiaries), the Company’s operating results are significantly influenced by: Hawaii’s economy, which in turn is influenced by economic conditions in the mainland U.S. (particularly California) and Asia (particularly Japan) as a result of the impact of those conditions on tourism; by the impact of interest rates on the construction and real estate industries and by the impact of federal government spending in Hawaii, which can be affected by world conditions; and, from time to time, the expiration of federal government appropriations bills. In addition, the Hawaii economy could be directly or indirectly affected by implications and potential impacts of U.S. and foreign capital and credit market conditions and federal, state and international responses to those conditions and the potential impacts of global and local developments (including economic conditions and uncertainties; unrest, terrorist acts, wars (such as the Russia-Ukraine war and the Israel-Hamas war), conflicts, political protests, deadly virus epidemic, pandemics, or other crisis; the effects of changes that have or may occur in U.S. policy, such as with respect to immigration and trade).
Previous wording
Because the earnings of ASB depend primarily on net interest income, interest rate risk is a significant risk of ASB’s operations. HEI and the Utilities are also exposed to interest rate risk primarily due to their periodic borrowing requirements, the discount rate used to determine pension funding requirements and the possible effect of interest rates on the electric utilities’ rates of return. Interest rates are sensitive to many factors, including general economic conditions and the policies of government and regulatory authorities. HEI cannot predict future changes in interest rates, nor be certain that interest rate risk management strategies it or its subsidiaries have implemented will be successful in managing interest rate risk.
Current wording
HEI and the Utilities are also exposed to interest rate risk primarily due to their periodic borrowing requirements, the discount rate used to determine pension funding requirements and the possible effect of interest rates on the electric utilities’ rates of return. Interest rates are sensitive to many factors, including general economic conditions and the policies of government and regulatory authorities. HEI cannot predict future changes in interest rates, nor be certain that interest rate risk management strategies it or its subsidiaries have implemented will be successful in managing interest rate risk.
Previous wording
Geographic Concentration Risk—The Company is subject to the risks associated with the geographic concentration of its businesses and current lack of interconnections that could result in service interruptions at the Utilities or higher default rates on loans held by ASB. The business of the Utilities is concentrated on the individual islands they serve in the State of Hawaii. Their operations are more vulnerable to service interruptions than that of many U.S. mainland utilities because none of the systems of the Utilities are interconnected with the systems on the other islands they serve. Because of this lack of interconnections, it is necessary to maintain higher generation reserve margins than are typical for U.S. mainland utilities to help ensure reliable service. Service interruptions, including, in particular, extended interruptions that could result from a natural disaster or terrorist activity, could adversely impact the revenues and costs of some or all of the Utilities.
Current wording
Geographic Concentration Risk—The Company is subject to the risks associated with the geographic concentration of its businesses and current lack of interconnections that could result in service interruptions at the Utilities. The business of the Utilities is concentrated on the individual islands they serve in the State of Hawaii. Their operations are more vulnerable to service interruptions than that of many U.S. mainland utilities because none of the systems of the Utilities are interconnected with the systems on the other islands they serve. Because of this lack of interconnections, it is necessary to maintain higher generation reserve margins than are typical for U.S. mainland utilities to help ensure reliable service. Service interruptions, including, in particular, extended interruptions that could result from a natural disaster or terrorist activity, could adversely impact the revenues and costs of some or all of the Utilities.
Previous wording
Competitive and Technological Risk—Increasing competition and technological advances could cause HEI’s businesses to lose customers or render their operations obsolete. The banking industry in Hawaii, and certain aspects of the electric utility industry, are competitive. The success of HEI’s subsidiaries in meeting competition and responding to technological advances will continue to have a direct impact on HEI’s consolidated financial performance. For example:
Current wording
Competitive and Technological Risk—Increasing competition and technological advances could cause HEI’s businesses to lose customers or render their operations obsolete. Certain aspects of the electric utility industry are competitive. The success of HEI’s subsidiaries in meeting competition and responding to technological advances will continue to have a direct impact on HEI’s consolidated financial performance. For example:
Previous wording
Uninsured Losses—HEI’s businesses could suffer losses that are uninsured due to a lack of affordable insurance coverage, unavailability of insurance coverage or limitations on the insurance coverage the Company does have. In the ordinary course of business, HEI and its subsidiaries purchase insurance coverages (e.g., property and liability coverages) to protect against loss of, or damage to, their properties and against claims made by third parties and employees for property damage or personal injuries. However, the protection provided by such insurance is limited in significant respects and, in some instances, there is no coverage. Some of the insurance coverages have substantial deductibles or has limits on the maximum amounts that may be recovered. In common with other companies in its line of business, the Utilities’ overhead and underground transmission and distribution systems (with the exception of substation buildings and contents), which have a replacement value roughly estimated at $12 billion, are largely not insured against loss or damage because the amount of transmission and distribution system insurance capacity is limited and the premiums are cost prohibitive. Similarly, the Utilities have no business interruption insurance as the premiums for such insurance would be cost prohibitive, particularly since the Utilities are not interconnected to other systems. If a hurricane or other uninsured catastrophic natural disaster were to occur, and if the PUC did not allow the affected Utilities to recover from ratepayers restoration costs and revenues lost from business interruption, the lost revenues and repair expenses could result in a significant decrease in HEI’s consolidated net income or in significant net losses for the affected periods.
Current wording
Uninsured Losses—HEI’s businesses could suffer losses that are uninsured due to a lack of affordable insurance coverage, unavailability of insurance coverage or limitations on the insurance coverage the Company does have. In the ordinary course of business, HEI and its subsidiaries purchase insurance coverages (e.g., property and liability coverages) to protect against loss of, or damage to, their properties and against claims made by third parties and employees for property damage or personal injuries. However, the protection provided by such insurance is limited in significant respects and, in some instances, there is no coverage. Some of the insurance coverages have substantial deductibles or have limits on the maximum amounts that may be recovered. In common with other companies in its line of business, the Utilities’ overhead and underground transmission and distribution systems (with the exception of substation buildings and contents), which have a replacement value roughly estimated at $13 billion, are largely not insured against loss or damage because the amount of transmission and distribution system insurance capacity is limited and the premiums are cost prohibitive. Similarly, the Utilities have no business interruption insurance as the premiums for such insurance would be cost prohibitive, particularly since the Utilities are not interconnected to other systems. If a hurricane or other uninsured catastrophic natural disaster were to occur, and if the PUC did not allow the affected Utilities to recover from ratepayers restoration costs and revenues lost from business interruption, the lost revenues and repair expenses could result in a significant decrease in HEI’s consolidated net income or in significant net losses for the affected periods.
Previous wording
Company also has $165 million of excess liability insurance, subject to a $0.3 million retention, for third party claims including claims related to wildfires, and $145 million directors and officers liability insurance, subject to a $1.0 million retention, to cover claims related to shareholder and derivative lawsuits. The aggregate damages and costs associated with the Maui windstorm and wildfires could significantly exceed the Company’s policy limits.
Current wording
Related to damages and costs incurred as a result of the Maui windstorm and wildfires, the Company has property insurance with a total policy limit of $500 million, subject to a $1 million retention, for wildfire damages related to Utility-owned non-generating assets, including overhead transmission and distribution assets within 1,000 feet of such assets. The Company also has $165 million of excess liability insurance and $25 million of miscellaneous professional liability insurance for third party claims, including claims related to wildfires, with a retention of $0.3 million and $0.1 million, respectively, and $145 million directors and officers liability insurance to cover claims related to shareholder and derivative lawsuits, with a retention of $1.0 million. The aggregate damages and costs associated with the Maui windstorm and wildfires could significantly exceed the Company’s policy limits.
Previous wording
Regulatory Risk—Actions of the PUC are outside the control of the Utilities and could result in inadequate or untimely rate increases, rate reductions or refunds or unanticipated delays, expenses or writedowns in connection with the construction of new projects. The rates the Utilities are allowed to charge for their services and the timeliness of permitted rate increases are among the most important items influencing the Utilities’ results of operations, financial condition and liquidity. The PUC has broad discretion over the rates that the Utilities charge their customers. On December 23, 2020, as part of the D&O establishing the PBR Framework, the PUC established a five-year Multi-year Rate Period (MRP) during which there will be no general rate cases. In the fourth year of the MRP, the PUC will comprehensively review the PBR Framework to determine if any modifications or revisions are appropriate.
Current wording
Regulatory Risk—Actions of the PUC are outside the control of the Utilities and could result in inadequate or untimely rate increases, rate reductions or refunds or unanticipated delays, expenses or writedowns in connection with the construction of new projects. The rates the Utilities are allowed to charge for their services and the timeliness of permitted rate increases are among the most important items influencing the Utilities’ results of operations, financial condition and liquidity. The PUC has broad discretion over the rates that the Utilities charge their customers. On December 23, 2020, as part of the D&O establishing the PBR Framework, the PUC established a five-year Multi-year Rate Period (MRP) during which there will be no general rate cases. In the fourth year of the MRP, the PUC will comprehensively review the PBR Framework to determine if any modifications or revisions are appropriate. The PUC is currently evaluating the Utilities’ proposal to rebase the rates in the form of a tri-company rate case with a 2026 test year.
Previous wording
Related to the Maui windstorm and wildfires, the Utilities received PUC approval to temporarily suspend Maui Electric’s Transmission and Distribution (T&D) System Average Interruption Duration Index (SAIDI) and System Average Interruption Frequency Index (SAIFI) PIMs from August 8, 2023 through June 30, 2024. If the temporary suspension of Maui Electric’s T&D PIMs is not extended beyond June 30, 2024, Maui Electric’s maximum annual penalty for T&D SAIDI and SAIFI could have a $0.4 million impact on the Utilities’ results of operations. The Utilities also obtained PUC approval to defer certain non-labor expenses incurred from August 8, 2023 through December 31, 2024 that are not already a part of base rates. If the PUC denies recovery of any deferred costs, such costs would be charged to expense in the period that those costs are no longer considered probable of recovery. Additionally, on August 31, 2023, the PUC issued an order temporarily suspending the ESM until further notice. The intent of the order is to address the unintended consequence of customers potentially bearing the costs associated with the Maui windstorm and wildfires through the operation of the ESM without prior PUC review. See “Performance-based regulation framework” and “Regulatory assets for Maui windstorm and wildfires related costs” in Note 4 of the Consolidated Financial Statements.
Current wording
Related to the Maui windstorm and wildfires, the Utilities obtained PUC approval to defer certain non-labor expenses incurred from August 8, 2023 through December 31, 2025 that are not already a part of base rates. If the PUC denies recovery of any deferred costs, such costs would be charged to expense in the period that those costs are no longer considered probable of recovery. Additionally, on August 31, 2023, the PUC issued an order temporarily suspending the ESM until further notice. The intent of the order is to address the unintended consequence of customers potentially bearing the costs associated with the Maui windstorm and wildfires through the operation of the ESM without prior PUC review. See “Performance-based regulation framework” and “Regulatory assets for Maui windstorm and wildfires related costs” in Note 4 of the Consolidated Financial Statements.
Previous wording
Based on the current operations of the Utilities and regulatory framework, including the impact of the approved PBR Framework, the Utilities continue to follow regulatory accounting under Accounting Standards Codification (ASC) 980. Continued accounting in this manner requires that certain criteria relating to the recoverability of such costs through rates be met, including achieved financial results that support the recovery of costs. If events or circumstances should change, such that the criteria are no longer satisfied, the Utilities expect that their regulatory assets (amounting to $295 million as of December 31, 2023), net of regulatory liabilities (amounting to $1,151 million as of December 31, 2023), would be charged to the statement of income in the period of discontinuance. See “Performance-based regulation framework” in Note 4 of the Consolidated Financial Statements.
Current wording
Based on the current operations of the Utilities and regulatory framework, including the impact of the approved PBR Framework, the Utilities continue to follow regulatory accounting under Accounting Standards Codification (ASC) 980. Continued accounting in this manner requires that certain criteria relating to the recoverability of such costs through rates be met, including achieved financial results that support the recovery of costs. If events or circumstances should change, such that the criteria are no longer satisfied, the Utilities expect that their regulatory assets (amounting to $227 million as of December 31, 2024), net of regulatory liabilities (amounting to $1,218 million as of December 31, 2024), would be charged to the statement of income in the period of discontinuance. See “Performance-based regulation framework” in Note 4 of the Consolidated Financial Statements.
Previous wording
Many public utility projects require PUC approval and various permits (e.g., environmental and land use permits) from other governmental agencies. Difficulties in obtaining, or the inability to obtain, the necessary approvals or permits, or any adverse decision or policy made or adopted, or any prolonged delay in rendering a decision, by an agency with respect to such approvals and permits, can result in significantly increased project costs or even cancellation of projects. In the event a project does not proceed, or if the PUC disallows cost recovery for all or part of a project, or if project costs exceed caps imposed by the PUC in its approval of the project, project costs may need to be written off in amounts that could result in significant reductions in Hawaiian Electric’s consolidated net income.
Current wording
Many public utility projects require PUC approval and various permits (e.g., environmental and land use permits) from other governmental agencies. Difficulties in obtaining, or the inability to obtain, the necessary approvals or permits, or any adverse decision or policy made or adopted, or any prolonged delay in rendering a decision, by an agency with respect to such approvals and permits, can result in significantly increased project costs or even cancellation of projects. In the event a project does not proceed, or if the PUC disallows cost recovery for all or part of a project, or if project costs exceed caps imposed by the PUC in its approval of the project, project costs may need to be written off in amounts that could result in significant reductions in Hawaiian Electric’s consolidated net income. In addition, as the Utilities may retire fossil fuel generating units before the full recovery of its investment, if the PUC disallows cost recovery of the undepreciated cost, the write-offs of such amounts could have an adverse impact on the Utilities’ results of operations.
Previous wording
Weather Conditions Risk—Electric utility operations are significantly influenced by weather conditions and natural disasters. The Utilities’ results of operations can be affected by the weather and natural disasters. Weather conditions, particularly temperature and humidity, directly influence the demand for electricity. Additionally, severe weather and natural disasters may become more intense and/or frequent because of global climate changes. Recent natural disasters such as the Kilauea eruption in 2018, Mauna Loa eruption in 2022, and the Maui windstorm and wildfires in 2023, resulted in disruption or destruction of electric utility operations. When these types of events occur, they can cause outages and property damage and require the Utilities to incur significant additional expenses that may not be recoverable.
Current wording
Weather Conditions Risk—Electric utility operations are significantly influenced by weather conditions and natural disasters. The Utilities’ results of operations can be affected by the weather and natural disasters. Weather conditions, particularly temperature and humidity, directly impact the demand for electricity. Additionally, severe weather and natural disasters may become more intense and/or frequent because of global climate changes. Recent natural disasters such as the Kilauea eruption in 2018, Mauna Loa eruption in 2022, and the Maui windstorm and wildfires in 2023, have disrupted electric utility operations. These types of events can cause outages, property damage and result in significant additional expenses that may not always be recoverable.
Previous wording
Climate Change Risk—Electric utility operations may be significantly influenced by climate change. While the timing, extent and ultimate effects of climate change cannot be determined with any certainty, climate change is predicted to result in sea level rise, which could potentially impact coastal and other low-lying areas (where much of the Utilities’ electric infrastructure is sited), and could cause erosion of beaches, saltwater intrusion into aquifers and surface ecosystems, higher water tables and increased flooding and storm damage due to heavy rainfall. The effects of climate change on the weather (for example, floods, hurricanes, heat waves or drought conditions, the latter of which could increase wildfire risk), sea levels, and water availability and quality, all have the potential to materially adversely affect the results of operations, financial condition and liquidity of the Utilities. For example, severe weather and its related impacts could cause significant harm to the Utilities’ physical facilities.
Current wording
Climate Change Risk—Electric utility operations may be significantly influenced by climate change. While the timing, extent and ultimate effects of climate change cannot be determined with any certainty, climate change is predicted to cause sea level rise, which could impact coastal and low-lying areas where much of the Utilities’ electric infrastructure is located. Potential consequences include erosion of beaches, saltwater intrusion into aquifers and surface ecosystems, higher water tables and increased flooding and storm damage due to heavy rainfall. Climate change may also intensify extreme weather conditions including floods, hurricanes, heat waves and drought which could increase wildfire risk. These factors along with changes in sea levels, water availability and water quality have the potential to materially and adversely affect the Utilities’ results of operations, financial condition, and liquidity. For example, severe weather and its related impacts could cause significant harm to the Utilities’ physical facilities.
Previous wording
Third Party Performance Risk—Electric utility operations depend heavily on third-party suppliers of fuel and purchased power. The Utilities rely on fuel suppliers and shippers, and IPPs to deliver fuel and power, respectively, in accordance with contractual agreements. Approximately 79% of the net energy generated or purchased by the Utilities in 2023 was generated from the burning of fossil fuel oil, and purchases of power by the Utilities provided about 38% of their total net energy generated and purchased for the same period. Failure or delay by fuel suppliers and shippers to provide fuel pursuant to existing contracts, or failure by a major IPP to deliver the firm capacity anticipated in its PPA, could disrupt the ability of the Utilities to deliver electricity, affect the Utilities’ maintenance schedules that could affect future reliability and require the Utilities to incur additional expenses to meet the needs of their customers that may not be recoverable. In addition, as the IPP contracts near the end of their terms, there may be less economic incentive for the IPPs to make investments in their units to ensure the availability of their units. Also, as these contractual agreements end, the Utilities may not be able to purchase fuel and power on terms equivalent to the current contractual agreements.
Current wording
Third Party Performance Risk—Electric utility operations depend heavily on third-party suppliers of fuel and purchased power. The Utilities rely on fuel suppliers and shippers, and IPPs to deliver fuel and power, respectively, in accordance with contractual agreements. Approximately 75% of the net energy generated or purchased by the Utilities in 2024 was generated from the burning of fossil fuel oil, and purchases of power by the Utilities provided about 40% of their total net energy generated and purchased for the same period. Failure or delay by fuel suppliers and shippers to provide fuel pursuant to existing contracts, or failure by a major IPP to deliver the firm capacity anticipated in its PPA, could disrupt the ability of the Utilities to deliver electricity, affect the Utilities’ maintenance schedules that could affect future reliability and require the Utilities to incur additional expenses to meet the needs of their customers that may not be recoverable. In addition, as the IPP contracts near the end of their terms, there may be less economic incentive for the IPPs to make investments in their units to ensure the availability of their units. Also, as these contractual agreements end, the Utilities may not be able to purchase fuel and power on terms equivalent to the current contractual agreements.
Previous wording
Related to the Maui windstorm and wildfires, the Utilities continue to expect potential generation shortfalls on Maui in 2024. The Energy Reserve Margin, the planning criteria used to determine generation adequacy, is the percentage which the system generation capacity must exceed the system load in each hour. The Utilities’ Energy Reserve Margin analysis indicates shortfalls in 2024, but is satisfied from 2025 through 2028 with the addition of planned generation and storage resource additions. The Utilities have plans to address this issue in 2024 through managing maintenance schedules of existing generations, and if necessary, may request for voluntary customer conservation during periods of high power demands. The environment for resource planning has increased in complexity and uncertainty and the Utilities will continue using a portfolio approach to meet its obligation to serve. This includes increased renewable energy, energy storage, and other potential options, both supply side and customer programs. If the Utilities are unable to meet customer energy requirements, it could negatively impact the satisfaction of the Utilities’ customers, which could have an adverse impact on the Utilities’ business, reputation and results of operations.
Current wording
The Energy Reserve Margin, the planning criteria used to determine generation adequacy, is the percentage which the system generation capacity must exceed the system load in each hour. The Utilities’ Energy Reserve Margin is satisfied from 2025 through 2029 with the addition of planned generation and storage resource additions for all islands except for Hawaii Island and Lanai, which forecasts are near or slightly below target levels by less than one percent for 2025. The Utilities have plans to address these issues through managing maintenance schedules of existing generations, and if necessary, may request for voluntary customer conservation during periods of high power demands. The environment for resource planning has increased in complexity and uncertainty and the Utilities will continue using a portfolio approach to meet its obligation to serve. This includes increased renewable energy, energy storage, and other potential options, both supply side and customer programs. If the Utilities are unable to meet customer energy requirements, it could negatively impact the satisfaction of the Utilities’ customers, which could have an adverse impact on the Utilities’ business, reputation and results of operations.
Previous wording
Operational Risk—Electric utility generating facilities are subject to operational risks that could result in unscheduled plant outages, unanticipated and/or increased operation and maintenance expenses and increased power purchase costs. Operation of electric generating facilities involves certain risks which can adversely affect energy output and efficiency levels. Included among these risks are facility shutdowns or power interruptions due to insufficient generation or a breakdown or failure of equipment or processes. In addition, operations could be negatively impacted by interruptions in fuel supply, inability to negotiate satisfactory collective bargaining agreements when existing agreements expire or other labor disputes, inability to comply with regulatory or permit requirements, disruptions in delivery of electricity, operator error, adverse weather or environmental conditions and catastrophic events such as earthquakes, tsunamis, hurricanes, fires, explosions, lava flows, floods or other similar occurrences affecting the Utilities’ generating facilities or transmission and distribution systems.
Current wording
Operational Risk—Electric utility generating facilities are subject to operational risks that could result in unscheduled plant outages, unanticipated and/or increased operation and maintenance expenses, increased power purchase costs, and decreased reliability. Operation of electric generating facilities involves certain risks which can adversely affect energy output, efficiency levels, and reliability. Included among these risks are facility shutdowns or power interruptions due to insufficient generation or a breakdown or failure of equipment or processes. In addition, operations could be negatively impacted by interruptions in fuel supply, inability to negotiate satisfactory collective bargaining agreements when existing agreements expire or other labor disputes, inability to comply with regulatory or permit requirements, disruptions in delivery of electricity, operator error, adverse weather or environmental conditions and catastrophic events such as earthquakes, tsunamis, hurricanes, fires, explosions, lava flows, floods or other similar occurrences affecting the Utilities’ generating facilities or transmission and distribution systems.
Previous wording
Legislative Risk—The Utilities may be adversely affected by new legislation or administrative actions. Congress, the Hawaii legislature and governmental agencies periodically consider legislation and other initiatives that could have uncertain or negative effects on the Utilities and their customers. Congress, the Hawaii legislature and governmental agencies have adopted, or are considering adopting, a number of measures that will significantly affect the Utilities, as described below.
Current wording
Legislative Risk—The Utilities may be adversely affected by new legislation, executive orders or administrative actions. The Utilities operations are subject to regulations under a wide variety of federal and state regulations and policies. Changes to federal and state laws, rules, regulations and policies are continuous and ongoing and the federal administration, the U.S. Congress, state legislatures and state administrations may enact and implement new laws, regulations and policies that could adversely and materially affect us. The new federal administration has indicated its intent to implement material changes to the federal government’s structure and operations and to advocate material changes to federal laws, regulations and policies. The Utilities cannot predict future changes in laws,regulations and policies, how they will be implemented and interpreted, or the ultimate effect that this changing environment will have on us. There can be no assurance that laws, regulations and policies will not be changed in ways that have a material adverse effect on the Utilities’ operations, financial condition, results of operations, and cash flows. The federal and state executive branches, Congress, the Hawaii legislature and governmental agencies have adopted, or are considering adopting, a number of measures that will significantly affect the Utilities, as described below.
Previous wording
Renewable Portfolio Standards law. The 2001 Hawaii Legislature adopted a law requiring the Utilities to meet a renewable portfolio standard, which has been amended over the years. The most recent amendment to Hawaii’s RPS law occurred in July 2022, which Governor Ige signed Act 240 (H.B.2089), that amended the RPS calculation from renewable energy as a percentage of sales to renewable energy as a percentage of total generation. The amended RPS calculation results in a lower calculated percentage than the amount calculated under the previous methodology. The change in the definition is to be applied prospectively to future milestone measurements and will require that the Utilities acquire more renewable energy than under the previous RPS calculation to comply with the RPS milestones. The Utilities are committed to achieving these goals and met the 2015 and 2020 RPS; however, due to the exclusion of energy savings in calculating RPS after 2014 and risks such as potential delays in IPPs being able to deliver contracted renewable energy, it is possible the Utilities may not attain the required renewable percentages in the future, and management cannot predict the future consequences of failure to do so (including potential penalties to be assessed by the PUC). On December 19, 2008, the PUC approved a penalty of $20 for every megawatt-hour (MWh) that an electric utility is deficient under Hawaii’s RPS law. The PUC noted, however, that this penalty may be reduced, in the PUC’s discretion, due to events or circumstances that are outside an electric utility’s reasonable control, to the extent the event or circumstance could not be reasonably foreseen and ameliorated, as described in the RPS law and in an RPS framework adopted by the PUC. In addition, the PUC ordered that the Utilities will be prohibited from recovering any RPS penalty costs through rates.
Current wording
Renewable Portfolio Standards law. The 2001 Hawaii Legislature adopted a law requiring the Utilities to meet a renewable portfolio standard, which has been amended over the years. The most recent amendment to Hawaii’s RPS law occurred in July 2022, which former Governor Ige signed Act 240 (H.B.2089), that amended the RPS calculation from renewable energy as a percentage of sales to renewable energy as a percentage of total generation. The amended RPS calculation results in a lower calculated percentage than the amount calculated under the previous methodology. The change in the definition is to be applied prospectively to future milestone measurements and will require that the Utilities acquire more renewable energy than under the previous RPS calculation to comply with the RPS milestones. The Utilities are committed to achieving these goals and met the 2015 and 2020 RPS; however, due to the exclusion of energy savings in calculating RPS after 2014 and risks such as potential delays in IPPs being able to deliver contracted renewable energy, it is possible the Utilities may not attain the required renewable percentages in the future, and management cannot predict the future consequences of failure to do so (including potential penalties to be assessed by the PUC). On December 19, 2008, the PUC approved a penalty of $20 for every megawatt-hour (MWh) that an electric utility is deficient under Hawaii’s RPS law. The PUC noted, however, that this penalty may be reduced, in the PUC’s discretion, due to events or circumstances that are outside an electric utility’s reasonable control, to the extent the event or circumstance could not be reasonably foreseen and ameliorated, as described in the RPS law and in an RPS framework adopted by the PUC. In addition, the PUC ordered that the Utilities will be prohibited from recovering any RPS penalty costs through rates.
Previous wording
Hawaii Revised Statutes (HRS) § 269-6(b) requires that “in making determinations of the reasonableness of the costs pertaining to electric or gas utility system capital improvements and operations, the PUC shall explicitly consider, quantitatively or qualitatively, the effect of the state’s reliance on fossil fuels on price volatility, export of funds for fuel imports, fuel supply reliability risk, and greenhouse gas emissions.” Based on HRS § 269-6(b) and recent case law discussing the scope of this section, the Utilities are performing GHG analyses to quantitatively or qualitatively describe the GHG emissions of proposed projects that are submitted to the PUC for approval.
Current wording
Hawaii Revised Statutes (HRS) § 269-6(b) requires that “in making determinations of the reasonableness of the costs pertaining to electric or gas utility system capital improvements and operations, the PUC shall explicitly consider, quantitatively or qualitatively, the effect of the state’s reliance on fossil fuels on price volatility, export of funds for fuel imports, fuel supply reliability risk, and greenhouse gas emissions.” Based on HRS § 269-6(b) and recent case law discussing the scope of this section, the Utilities are performing GHG analyses to quantitatively or qualitatively describe the GHG emissions of proposed projects that are submitted to the PUC for approval. On June 20, 2024, House Bill 2390 was signed into law as Act 54 and took effect on July 1, 2024. Act 54 authorizes the PUC to waive a lifecycle GHG analysis for energy projects that do not involve combustion. On September 18, 2024, the PUC approved the Utilities’ waiver requests for the Stage 3 solar plus storage and wind projects.
Previous wording
2030 goal was established, delays and cancellations in the commercial operation of new renewable third-party generation resources and higher costs as a result of supply chain disruptions and inflationary pressures, as well as federal policies related to solar panel imports, have slowed the pace of progress toward reducing GHG emissions. The downgrade of Hawaiian Electric’s credit ratings after the Maui windstorm and wildfires is anticipated to be an additional impediment to completion of new renewable energy and storage projects. As a result of these challenges, the Utilities expect the planned 70% reduction in carbon emissions to be achieved later than the original 2030 target date. However, the Utilities will continue to replace significant amounts of fossil fuel generation with renewable energy between now and 2030 and expect to meet or exceed the State of Hawaii’s RPS goals.
Current wording
The Utilities have taken, and continue to identify opportunities to take, direct action to reduce GHG emissions from their operations, including, but not limited to, supporting demand-side management programs that foster energy efficiency, using renewable resources for energy production and purchasing power from IPPs generated by renewable resources, and burning renewable biodiesel at selected Hawaiian Electric and Maui Electric generating units. In November 2021, the Utilities committed to a 70% reduction in power generation GHG emissions by 2030 compared to a 2005 baseline and achievement of net zero carbon emissions from power generation by 2045. While the reduction is not mandated by law, the Utilities could suffer reputational harm if it fails to achieve its commitments, which may negatively impact its business. Since the time the 2030 goal was established, delays and cancellations in the commercial operation of new renewable third-party generation resources and higher costs as a result of supply chain disruptions and inflationary pressures, as well as federal policies related to solar panel imports, have slowed the pace of progress toward reducing GHG emissions. The downgrade of Hawaiian Electric’s credit ratings after the Maui windstorm and wildfires is anticipated to be an additional impediment to completion of new renewable energy and storage projects. As a result of these challenges, the Utilities expect the planned 70% reduction in carbon emissions to be achieved later than the original 2030 target date. However, the Utilities will continue to replace significant amounts of fossil fuel generation with renewable energy between now and 2030 and expect to meet or exceed the State of Hawaii’s RPS goals.
Rearranged current paragraphs (2)
Current report — wording carried from elsewhere
HEI’s and Hawaiian Electric’s access to capital markets and other sources of debt and equity financings in a timely manner and on acceptable terms will continue to be negatively impacted as a result of the downgrades in their debt credit ratings to below investment grade. In August 2023, HEI and Hawaiian Electric received multiple downgrades to their debt, including to ratings below investment grade, by Fitch, Moody’s and S&P. As of February 14, 2025, the Fitch, Moody’s and S&P ratings of HEI and Hawaiian Electric were as follows:
Current report — wording carried from elsewhere
Note: The above ratings reflect only the view, at the time the ratings are issued or affirmed, of the applicable rating agency, from whom an explanation of the significance of such ratings may be obtained. Such ratings are not recommendations to buy, sell or hold any securities; such ratings may be subject to revision or withdrawal at any time by the rating agencies; and each rating should be evaluated independently of any other rating.
Rearranged previous paragraphs (3)
Previous report — wording carried elsewhere
Related to damages and costs incurred as a result of the Maui windstorm and wildfires, the Company has property insurance with a total policy limit of $500 million, subject to a $1 million retention, for wildfire damages related to Utility-owned non-generating assets, including overhead transmission and distribution assets within 1,000 feet of such assets. The
Previous report — wording carried elsewhere
The Utilities have taken, and continue to identify opportunities to take, direct action to reduce GHG emissions from their operations, including, but not limited to, supporting demand-side management programs that foster energy efficiency, using renewable resources for energy production and purchasing power from IPPs generated by renewable resources, and burning renewable biodiesel at selected Hawaiian Electric and Maui Electric generating units. In November 2021, the Utilities committed to a 70% reduction in power generation GHG emissions by 2030 compared to a 2005 baseline and achievement of net zero carbon emissions from power generation by 2045. While the reduction is not mandated by law, the Utilities could suffer reputational harm if it fails to achieve its commitments, which may negatively impact its business. Since the time the
Previous report — wording carried elsewhere