3. Regulatory Matters
- Regulatory Matters
As discussed in Note 3 — Regulatory Matters of our 2025 Form 10-K, we are involved in various regulatory and legislative proceedings. The following discusses developments in 2026 and updates to the 2025 Form 10-K.
Capacity Interconnection Rights for Crane Clean Energy Center
In 2024, we announced the restart of Three Mile Island Unit 1, renamed as the Crane Clean Energy Center. The restart is supported by a 20-year PPA with Microsoft to purchase the output generated from the renewed plant. The restart of the plant and delivery of electricity under the PPA is subject to certain regulatory approvals, including the NRC comprehensive safety and environmental review, as well as permits from relevant state and local agencies.
PJM's Phase I System Impact Study for Crane identified contingent transmission upgrades that would need to be completed for Crane to be fully deliverable to the grid, some of which suggested projected in-service dates extending as late as December 2030.
In March 2026, we filed a waiver request with FERC to allow the transfer of capacity interconnection rights (CIRs) from Eddystone to Crane with the aim of reducing the number of contingent upgrades that would need to be completed prior to Crane being fully deliverable to the grid. Eddystone Units 3 and 4 were previously announced as having a planned retirement date of May 31, 2025, but have been required to continue operating as energy-only resources under DOE emergency orders issued in 2025 and 2026 for grid reliability. Transferring the Eddystone CIRs to Crane will not affect PJM's ability to operate and dispatch Eddystone for reliability in compliance with the DOE's orders. In June 2026, FERC granted the waiver request.