NOTE 14 –COMMITMENTS AND CONTINGENCIES
A summary of the Company's commitments and contingencies can be found in Note 15 to the Consolidated Financial Statements included in the 2024 10-K, which is incorporated by reference herein.
Environmental Matters
Accruals for environmental matters are recorded when it is probable that a liability has been incurred and the amount of the liability can be reasonably estimated, based on current law and existing technologies. At September 30, 2025, the Company had accrued obligations of $1,044 million for probable environmental remediation and restoration costs ($1,113 million at December 31, 2024), including $220 million for the remediation of Superfund sites ($234 million at December 31, 2024). This is management’s best estimate of the costs for remediation and restoration with respect to environmental matters for which the Company has accrued liabilities, although it is reasonably possible that the ultimate cost with respect to these particular matters could range up to approximately two times that amount. Consequently, it is reasonably possible that environmental remediation and restoration costs in excess of amounts accrued could have a material impact on the Company's results of operations, financial condition and cash flows. It is the opinion of the Company’s management, however, that the possibility is remote that costs in excess of the range disclosed will have a material impact on the Company’s results of operations, financial condition and cash flows. Inherent uncertainties exist in these estimates primarily due to unknown conditions, changing governmental regulations and legal standards regarding liability, and emerging remediation technologies for handling site remediation and restoration. As new or additional information becomes available and/or certain spending trends become known, management will evaluate such information in determination of the current estimate of environmental liability.
Litigation
Each quarter, Union Carbide reviews asbestos-related claims filed, settled and dismissed, as well as average settlement and resolution costs by disease category. Union Carbide also considers additional quantitative and qualitative factors such as the nature of pending claims, trial experience of Union Carbide and other asbestos defendants, current spending for defense and processing costs, significant appellate rulings and legislative developments, trends in the tort system, and their respective effects on expected future resolution costs. Union Carbide's management considers these factors in conjunction with the most recent actuarial study and determines whether a change in the estimate is warranted. Based on Union Carbide's review of 2025 activity, it was determined that no adjustment to the accrual was required at September 30, 2025.
Union Carbide’s total asbestos-related liability for pending and future claims and defense and processing costs was $726 million at September 30, 2025 ($791 million at December 31, 2024). At September 30, 2025, approximately 26 percent of the recorded claim liability related to pending claims and approximately 74 percent related to future claims.
Legacy Matters
Groundwater Matters
The Company is the subject of various complaints related to alleged groundwater contamination based on decades-old sales and applications of certain agricultural chemical products ("Groundwater Matters"). The costs associated with these Groundwater Matters were previously covered by insurance policies that have since been depleted. In the first quarter of 2023, the Company completed a study of certain Groundwater Matters related to wells deemed to be probable and estimable based on the public reporting of sampling data and historical information to develop a reasonable estimate of the cost of pending and future claims and accrued a charge based on the estimate. In the second quarter of 2025, the Company completed a reassessment study of these Groundwater Matters based on current known factors, resulting in a reduced estimate of the cost of pending and future claims. As a result, the Company recorded a pretax credit of $106 million, included in "Cost of sales" in the consolidated statements of income and related to Corporate. In the second quarter of 2025, the Company settled a separate claim related to Groundwater Matters at a water storage district, resulting in a pretax charge of $64 million, included in "Cost of sales" in the consolidated statements of income and related to Corporate.
At September 30, 2025, the total liability related to settled claims and the probable and estimable settlement of all alleged Groundwater Matters was $78 million ($155 million at December 31, 2024), which was included in “Accrued and other current liabilities” and "Other noncurrent obligations" in the consolidated balance sheets.
The Company is also the subject of other groundwater contamination complaints, including claims related to 1,4-dioxane. The Company continues to defend itself in this litigation and has determined that the Company's exposure to liability, if any, is not probable or estimable at September 30, 2025.
Other Legacy Matters
On October 10, 2024, the Company executed a settlement agreement related to arbitration for historical product claims from a divested business. As a result, the Company recorded a pretax charge of $75 million in the third quarter of 2024, which was paid in the fourth quarter of 2024. Arbitration on the matter was concluded on March 11, 2025, and, as a result, the Company recorded an additional pretax charge of $98 million in the first quarter of 2025, which is included in "Cost of sales" in the consolidated statements of income, related to Corporate, and was paid in the second quarter of 2025.
Gain Contingency - Dow v. Nova Chemicals Corporation Ethylene Asset Matter
In 2019, the Court of King's Bench of Alberta, Canada ("Court") found Nova Chemicals Corporation ("Nova") liable for engaging in a deliberate and continuing course of conduct of conversion, breach of contract, gross negligence and willful misconduct in the operation of the companies’ jointly-owned ethylene asset in Joffre, Alberta, Canada. As a result of the liability finding, which is now final and non-appealable, the Court signed a judgment ordering Nova to pay $1.43 billion Canadian dollars (equivalent to approximately $1.08 billion U.S. dollars) for damages incurred through 2012. Nova made payment in October 2019. At September 30, 2025, $201 million ($201 million at December 31, 2024) was included in "Other noncurrent obligations" in the Company's consolidated balance sheets related to the disputed portion of the damages judgment.
Following an appeal, on June 10, 2025, the Court signed a separate judgment ordering Nova to pay an additional amount of $1.62 billion Canadian dollars (equivalent to approximately $1.2 billion U.S. dollars) for damages incurred through June 2018, which had not been previously quantified. The Court again found that Nova failed to operate the companies' jointly-owned ethylene asset at full capacity during this time, depriving the Company’s subsidiaries of millions of pounds of ethylene. On August 11, 2025, the Court also awarded fees of approximately $100 million U.S. dollars, bringing Nova’s current payment obligation to approximately $1.3 billion U.S. dollars. While those awards are subject to appeal, Alberta law requires Nova to satisfy the Court’s judgment in full notwithstanding its appeal in order to avoid enforcement measures during the appeal process. Nova has since requested that the Court of Appeal of Alberta stay the execution of the judgment pending its appeal. Nova’s request departs from well-established Alberta law, and would require Nova to show, among other things, that it would be irreparably harmed by making the required payment. Nova’s request for a stay has been fully briefed and argued, and a decision is expected by year-end 2025. It is the Company’s position that Nova cannot meet the legal standard necessary to receive a stay and avoid payment pending its appeal. We expect a decision on the stay from the Court of Appeal of Alberta by year-end 2025. If the Court of Appeal of Alberta grants the stay, Nova will not be required to pay the judgment to the Company while the appeal process is ongoing.
Guarantees
The following table provides a summary of the final expiration, maximum future payments and recorded liability included in the consolidated balance sheets for guarantees:
| Guarantees | Sep 30, 2025 | Dec 31, 2024 | ||||
|---|---|---|---|---|---|---|
| In millions | FinalExpiration | MaximumFuture Payments | Recorded Liability | FinalExpiration | MaximumFuture Payments | Recorded Liability |
| Guarantees | 2038 | $1,223 | $138 | 2038 | $1,456 | $155 |
Guarantees arise during the ordinary course of business from relationships with customers, accounts receivable facilities and nonconsolidated affiliates when the Company undertakes an obligation to guarantee the performance of others (via delivery of cash or other assets) if specified triggering events occur. With guarantees, such as commercial or financial contracts, non-performance by the guaranteed party triggers the obligation of the Company to make payments to the beneficiary of the guarantee. The majority of the Company’s guarantees relate to debt of nonconsolidated affiliates, which have expiration dates ranging from less than one year to 13 years. The Company’s current expectation is that future payment or performance related to the non-performance of others is considered remote.
The Company maintains accounts receivable facilities with various financial institutions, with committed and uncommitted facilities in the United States and a committed facility in Europe. Under the terms of the Programs, the Company continues to service the receivables from the customers, but retains no interest in the receivables, and remits payment to the financial institutions. The Company also has access to accounts receivable discounting facilities, under which receivables are transferred with limited recourse. The Company’s maximum guaranteed liability for the accounts receivable facilities iszero at September 30, 2025 ($239 million at December 31, 2024).
TDCC has entered into guarantee agreements related to Sadara, a nonconsolidated affiliate. Sadara reached an agreement with its lenders to re-profile its outstanding project financing debt in the first quarter of 2021. In conjunction with the debt re-profiling, TDCC entered into a guarantee of up to approximately $1.3 billion of Sadara’s debt, proportionate to the Company's 35 percent ownership interest. The debt re-profiling also includes a grace period until June 2026, during which Sadara is obligated to make interest-only payments which are guaranteed by TDCC in proportion to the Company’s 35 percent ownership interest. The Company does not expect to be required to perform under the guarantees. As part of the debt re-profiling, Sadara established a $500 million revolving credit facility guaranteed by Dow, which would be used to fund Dow’s pro-rata share of any potential shortfall during the grace period.
Asset Retirement Obligations
Asset retirement obligations are recorded as incurred and reasonably estimable, including obligations for which the timing and/or method of settlement are conditional on a future event that may or may not be within the control of the Company. The retirement of assets may involve such efforts as remediation and treatment of asbestos, contractually required demolition, and other related activities, depending on the nature and location of the assets; and retirement obligations are typically realized only upon demolition of those facilities. As a result of the asset shutdowns included in the restructuring activities discussed in Note 5, the Company accrued additional asset retirement obligations of $105 million in the first nine months of 2025. At September 30, 2025, the aggregate carrying amount of the Company's asset retirement obligations was $306 million ($174 million at December 31, 2024), which was included in "Accrued and other current liabilities" and "Other noncurrent obligations" in the consolidated balance sheets.