Soluna Holdings, Inc
For the period ended Dec 31, 2024. Filed Mar 31, 2025.
View on SEC.govAbout this filing
A company's yearly report to the SEC, with audited financial statements. It is the fullest account a company gives of its business, its finances and the risks it sees.
FY2024 · Filed Mar 31, 2025
What changed in Management’s Discussion and Analysis?
Read the current filingPrevious report: 10-K
Period ended 2023-12-31; filed 2024-04-01.
0001493152-24-012303
Item 7. Management’s Discussion and Analysis of Financial Condition and Results of OperationsCurrent report: 10-K
Period ended 2024-12-31; filed 2025-03-31.
0001641172-25-001756
Item 7. Management’s Discussion and Analysis of Financial Condition and Results of OperationsThe baseline is this issuer’s latest earlier reporting period of the same form that was filed before the current report. A previous 10-Q is a different quarter, not a year-over-year comparison. Amendments are excluded.
Compared 141 previous paragraphs and 110 current paragraphs.
31 unchanged; 31 reworded; 47 added; 79 removed; 0 previous and 1 current paragraphs rearranged.
Tables are not compared: 11 previous and 12 current tables excluded. Dates, whitespace, punctuation and numbering changes are ignored; changes to financial figures remain significant.
A changed paragraph is not evidence that risk increased or decreased. An unchanged paragraph does not establish that risk stayed the same.
Added paragraphs (47)
Current report
Recent Developments
Current report
Soluna Cloud – Termination of HPE*** Agreement***
Current report
Soluna launched Project Ada- its GPU-as-a-Service business via Soluna Cloud, Inc. (“Soluna Cloud”) earlier in 2024 in order to achieve two primary goals:
Current report
As a point of entry into Project Ada, Soluna AL CloudCo, LLC (“CloudCo”), a subsidiary of Soluna Cloud, entered into the HPC & AI Cloud Services Agreement and HPE Greenlake Services Custom Statement of Work with Hewlett Packard Enterprise Company (“HPE”) on June 18, 2024 (together with the associated Statement of Work, the “HPE Agreement”), that provided data center and cloud services for artificial intelligence (“AI”) and supercomputing applications, utilizing NVIDIA H100 Graphic Processing Units (“GPUs”).
Current report
At the time of launch, the market for NVIDIA H100 GPUs was characterized by constrained supply and strong pricing, which aligned with the economics of the fixed-cost HPE Agreement. However, by the end of 2024, the GPU market shifted significantly. Lead times for NVIDIA H100 GPUs shortened from over 50 weeks in 2023 to 8–12 weeks by the end of 2024, easing supply constraints and reducing urgency among buyers. At the same time, market demand shifted toward larger GPU clusters than those available under the HPE Agreement, making it difficult to secure long-term, reserved contracts at profitable rates. The expected release of NVIDIA’s H200 Blackwell architecture also caused some customers to delay purchases. Although release timelines were impacted by design issues, the prospect of next-generation technology contributed to hesitancy in NVIDIA H100 GPU acquisition. Competitive pressure from alternative GPU vendors further softened demand and market pricing. As a result, Soluna Cloud’s business progressed more slowly than anticipated. Revenues were first recognized in December 2024, with modest growth in early 2025. During the last six months, our engagement with potential financing and operating partners for AI/HPC confirmed that rather than continuing the effort to lease and resell GPU/HPC chips, refocusing on our core strength - creating, developing, financing and operating our extensive pipeline of potential bitcoin and AI hosting facilities - will create far more value for us and our shareholders.
Current report
In light of these developments, on March 24, 2025, CloudCo sent notice of its termination of the HPE Agreement for convenience. Subsequently, on March 26, 2025, HPE sent notice of its termination of the HPE Agreement for cause, effective immediately, due to CloudCo’s material breach of its payment obligations that remained uncured for more than thirty (30) days. In accordance with the terms of the HPE Agreement, upon a termination for cause by HPE, CloudCo must pay HPE the remaining payment stream under the term of the HPE Agreement of approximately $19.3 million as of March 31, 2025 (approximately $20.0 million as of December 31, 2024), including all upfront payments and monthly charges, plus any fees incurred for the terminated Services (as defined in the HPE Agreement).
Current report
SEPA
Current report
On August 12, 2024, we entered into a Standby Equity Purchase Agreement (the “SEPA”) with YA II PN, LTD., a Cayman Islands exempt limited company (“YA”). Pursuant to the terms of the SEPA, we agreed to issue and sell to YA, from time to time, and YA agreed to purchase from us, up to $25 million of shares of our common stock (the “SEPA Shares”). We and YA also entered into a registration rights agreement (the “Registration Rights Agreement”), pursuant to which we agreed to prepare and file with the SEC a Registration Statement on Form S-1, registering the resale of the SEPA Shares. On November 12, 2024, we filed a registration statement on Form S-1 (File No. 333-282559) with the SEC for the resale by YA of 3,000,000 SEPA Shares, which was declared effective by the SEC on February 5, 2025. As of the date of this Annual Report, we have issued and sold approximately 1.5 million shares of our common stock to YA pursuant to the SEPA for aggregate net proceeds to us of approximately $2.0 million. We intend to continue issuing shares of our common stock to YA pursuant to the SEPA in future periods.
Current report
Assignment and Assumption Agreements
Current report
CloudCo, Soluna Cloud, and the Company, entered into assignment and assumption agreements on October 1, 2024, with one of the accredited investors issued convertible notes and Class A, Class B and Class C common stock purchase warrants on October 25, 2021(the “ Purchasers”), and two other parties introduced by that Purchaser, with respect to an aggregate of $1.25 million of notes (“Additional Notes”) issued by CloudCo (the “Assignment Agreements”). Pursuant to the Assignment Agreements, we will be able to purchase such notes for a purchase price of $750 thousand, or 60% of face value. The assignment and assumption will be effective once all conditions of the agreement are met including fulfilling the purchase price. As of December 31, 2024, the assignment and assumption of the Additional Notes has not been become effective, however on March 14, 2025, the Company has fulfilled the agreement and assumed the assignment and assumption of the Additional Notes for the remaining outstanding balance.
Current report
Galaxy Note
Current report
On March 12, 2025, Soluna SW LLC (the “SW Borrower”), a Delaware limited liability company and a subsidiary of Soluna SW Holdings LLC (“SW Holdings”), a Delaware limited liability company and a subsidiary of Soluna Digital, Inc. (“SDI”), a Nevada corporation and a subsidiary of Soluna Holdings, Inc. (the “Company”), entered into a Loan Agreement (the “Galaxy Loan Agreement”) with SW Holdings and Galaxy Digital LLC (the “Lender”). The Galaxy Loan Agreement comprises a term loan facility in the principal amount of $5.0 million (the “Term Loan Facility”). The Term Loan Facility bears interest at 15.0% per annum, unless an Event of Default (as defined therein) has occurred and is continuing, in which case the Galaxy Term Loan Facility shall bear interest at a rate of 5% above the then applicable interest rate. The Term Loan Facility will mature on March 12, 2030 and will be paid over a five-year term.
Current report
June SPA Modification
Current report
On June 20, 2024, pursuant to the terms and subject to the conditions of a Note Purchase Agreement (the “June SPA”) by and among (i) Soluna AL CloudCo, LLC, a Delaware limited liability company (“CloudCo”), and indirect wholly owned subsidiary of the Company, (ii) Soluna Cloud, Inc., a Nevada corporation, indirect wholly owned subsidiary of the Company, and parent of CloudCo (“Soluna Cloud”), (iii) the Company and (iv) the accredited investor named therein (the “Investor” and collectively, the “Note Parties), CloudCo issued to the Investor a secured promissory note in a principal amount equal to $12.5 million (the “Note”).
Current report
On March 23, 2025, the Note Parties entered into a Modification Agreement (the “Modification Agreement”) to, among other things, (i) provide for the deposit of 1,000,000 shares (the “Escrow Shares”) of our common stock into an escrow account maintained by Northland Securities, Inc., pursuant to an escrow agreement (as further described below), (ii) provide for the issuance to the Investor of a warrant to purchase shares of our common stock upon the release by the Investor of its lien on our property, (iii) amend the payment schedule of the Note to provide (a) for each of the six scheduled payments occurring after the earlier of the effectiveness of a registration statement for the resale of the Registrable Securities (as defined below) or the date that the Registrable Securities may be sold pursuant to Rule 144 under the Securities Act of 1933, as amended (the “Securities Act”), without any information requirements, the amount of principal and interest payable on such date shall be reduced by 50% (the aggregate amount of the six months of such reductions, the “Specified Amount”) and (b) if the aggregate amount of payments on the Amended Note applied from the proceeds of the sale of the Escrow Shares on or prior to the last six scheduled payments is less than the Specified Amount (such difference, the “Make Whole Amount”), than the amount of each of the remaining scheduled payments shall be increased by an amount equal to the Make Whole Amount divided by the number of remaining scheduled payments, (iv) modify the Note such that the Note is now convertible into up to 2,500,000 shares (the “Conversion Shares”) of Common Stock based on a conversion price of $5.00, (v) amend the Note to provide that we will be a direct co-obligor with CloudCo under the Note, and (vi) amend the SPA to allow us to organize or incorporate any subsidiary, over which we shall have voting or beneficial control, which is being formed with the intent to engage in a business or line of business substantially similar to that of Soluna Cloud or the Company, without first paying all of the principal and interest due under the Note and without first obtaining Investor’s prior written consent.
Current report
The net proceeds from dispositions of the Escrow Shares (i) at a price of up to $4.00 per share shall be applied to reduce the outstanding principal balance of the Note and (ii) at a price greater than $4.00 per share shall be applied first to reduce the outstanding principal balance of the Note in an amount equal to $4.00 per share of our common stock and then to the Investor.
Current report
Also under the Modification Agreement, we agreed to register for resale the Escrow Shares and Conversion Shares (together, the “Registrable Securities”) as promptly as commercially practicable, as determined by us, following the registration for resale of certain other securities. We also agreed to register for resale the shares of our common stock issuable upon exercise of the Warrant as promptly as commercially practicable, as determined by us, after the issuance of the Warrant.
Current report
Project Specific Developments
Current report
Project Dorothy 2
Current report
We are constructing Project Dorothy 2 which is a 48MW expansion of our flagship Project Dorothy that will be dedicated to Bitcoin Hosting. The site is expected to energize soon in the second quarter of 2025. This will enable the commencement of the commissioning of the first of 3 phases, each of 16MW, that will occur between May and October 2025 when the site is expected to be fully operational. As each phase is commissioned, it will begin to generate revenue, both due to Bitcoin Hosting and Demand Response Services.
Current report
Project Rosa
Current report
We are developing Project Rosa which is expected to be a 187MW data center for AI and Bitcoin hosting and other computing-intensive applications, as well as joint venture potential. It will be co-located with a wind farm in Texas. We have signed term sheets for both power and land purchase agreements in connection with this project.
Current report
Project Kati
Current report
We are developing Project Kati which is expected to be a 166MW data center for AI, machine learning, Bitcoin hosting and other computing-intensive applications, as well as joint venture potential. It will be co-located with a wind farm in Texas. We have received final ERCOT approval for the Reactive Power Study which is the last study required to exit planning. It is also waiting for required amendments to Las Majadas Wind Farm’s agreement with the transmission service provider to be completed.
Current report
Project Grace
Current report
We continue to develop a 2MW AI/HPC data center to be co-located with the same windfarm as Project Dorothy that will be the first construction of Soluna’s proprietary Helix design that remains in the concept design phase.
Current report
Cryptocurrency Mining Revenue: Cryptocurrency mining revenue increase year over year consists of revenue recognized from Soluna’s cryptocurrency mining operations related to Project Dorothy 1B, which began energization in the third quarter of 2023. Project Marie discontinued site operations in the second quarter of 2023 and Project Sophie converted to a hosting facility within the 2023 year.
Current report
Data Hosting Revenue: Cryptocurrency hosting services provide energized space and operating services to third-party mining companies who locate their mining hardware at our mining locations. Services include fees for hosting the miners which could be fixed fees or profit sharing, as well as potential additional fees for services provided such as installation charges or other services fees. The increase was due to a full year of revenues in Project Dorothy 1A and Project Sophie switched their business model from proprietary mining to data hosting in the second quarter of 2023 resulting in a full year of revenue in 2024.
Current report
Demand Response Service: We saw an increase in demand response service revenue due to a full year of service for the year ended December 31, 2024 compared to only one month of service for the year ended December 31, 2023.
Current report
The increase in costs during the year ended December 31, 2024 compared to 2023 were due to the full Project Dorothy 1B site being active the entire year ended December 31, 2024, versus as a startup beginning in the second quarter of 2023. Also noted, Project Sophie was no longer a proprietary mining site by the second quarter of 2023. The increase was slightly offset with the Company operating only one facility for the year ended December 31, 2024, compared to three facilities for the year ended December 31, 2023.
Current report
***Cost of High-Performance Computing Services:***Cost of high-performance computing services include operating expenses related to high performance computing services.
Current report
***Loss on contract:***Due to CloudCo’s termination of the HPE Agreement on March 24, 2025, and HPE’s subsequent termination of the HPE Agreement on March 26, 2025, and the acceleration of the remaining unpaid amounts of the contract in accordance with Section 8(h)(ii) of the HPE Agreement, a Type 1 Subsequent Event, we have recognized a liability for the remainder of the HPE Agreement on the consolidated balance sheet of our subsidiary CloudCo, and corresponding loss on contract on our consolidated income statement, in line with the terms and conditions of the HPE Agreement and relevant accounting standards. We have also recognized a loss on the termination of the HPE Agreement for $28.6 million representing the remaining obligations, and a contract liability in the same amount. In addition, the outstanding balance of the prepaid deposit of $8.6 million was offset to the liability, leaving a net liability balance of $20.0 million as of December 31, 2024.
Current report
Loss on Debt Extinguishment and Revaluation, net: For the year ended December 31, 2024, we recorded a loss on debt extinguishment and revaluation of approximately $7.3 million. On February 28, 2024, we entered into the Fourth Amendment Agreement with the Noteholders, dated February 28, 2024 (the “Fourth Amendment”), and lowered the conversion price of the Convertible Notes as well as issued new warrants and repriced additional warrants with certain exercise features. The issuance and reprice of warrants created a loss on extinguishment of debt of approximately $5.8 million, which was partially offset by a gain on debt revaluation of the convertible debt of approximately $1.3 million as of February 28, 2024 (date of the Fourth Amendment) and March 31, 2024 due to several factors including assumptions on conversions and payouts, annual volatility, and stock price conditions on the dates of revaluations. In addition, there was a revaluation of the warrant liability, as a result of which we recorded a gain on revaluation of approximately $1.5 million. We also performed a fair value assessment of the Convertible Notes as of June 30, 2024, as a result of which we recorded a loss on revaluation of approximately $4.0 million due to factors including assumptions on conversions and payouts, annual volatility, and stock price conditions on the dates of revaluations compared to what the noteholders could convert at as of June 30, 2024. The Convertible Notes were revalued again on September 30, 2024, as a result of which we recorded a gain of approximately $2.3 million due mainly to the change in the price or our common stock offsetting the previous quarter assessments. In the fourth quarter of 2024, we had additional conversions and ultimately fully converted the Convertible Notes payable creating an additional $247 thousand gain on debt extinguishment. As of December 31, 2024, no Convertible Notes remain outstanding. In addition, in the second quarter of fiscal year 2024, we performed a revaluation of the warrants through May 30, 2024, the date of Annual Shareholder approval to approve the repricing of the existing warrants, as a result of which we recorded a loss on revaluation of approximately $1.6 million. In addition to the revaluation of the Convertible Notes and warrants, we also recorded an additional loss on debt extinguishment of approximately $1.4 million due to the satisfaction and redemption of the Dorothy 2 equipment loan through issuance of Class B Membership interests in the Dorothy 2 project valued at three times the borrowing amount (i.e., $2.16 million).
Current report
To supplement our consolidated financial statements included in this Annual Report presented under U.S. generally accepted accounting principles (“GAAP”), we are presenting certain non-GAAP financial measures. We are providing these non-GAAP financial measures to disclose additional information to facilitate the comparison of past and present operations by providing perspective on results absent one-time or significant non-cash items. We utilize these measures in the business planning processto understand expected operating performance and to evaluate results against those expectations. We believe that these non-GAAP financial measures, when considered together with our GAAP financial results, provide management and investors with an additional understanding of our business operating results regarding factors and trends affecting our business and provide a reasonable basis for comparing our ongoing results of operations.
Current report
These non-GAAP financial measures are providedas supplemental measures to our performance measures calculated in accordance with GAAP and therefore, are not intended to be considered in isolation or as a substitute for comparable GAAP measures. Further, these non-GAAP financial measures have no standardized meaning prescribed by GAAP and are not prepared under any comprehensive set of accounting rules or principles. Because of the non-standardized definitions of non-GAAP financial measures, we caution investors that the non-GAAP financial measures as used by us in this Annual Report have limits in their usefulness to investors and may be calculated differently from, and therefore may not be directly comparable to, similarly titled measures used by other companies. Further, investors should be aware that when evaluating these non-GAAP financial measures, these measures should not be construed as an inference that our future results will be unaffected by unusual or non-recurring items. In addition, from time to time in the future there may be items that we may exclude for purposes of our non-GAAP financial measures and we may in the future cease to exclude items that we have historically excluded for purposes of our non-GAAP financial measures. Likewise, we may determine to modify the nature of the adjustments to arrive at our non-GAAP financial measures. Investors should review the non-GAAP reconciliations provided below and not rely on any single financial measure to evaluate our business.
Current report
EBITDA and Adjusted EBITDA
Current report
In addition to financial measures calculated in accordance with GAAP, we also use “EBITDA” and “Adjusted EBITDA.” “EBITDA” is defined as earnings before interest, taxes, and depreciation and amortization.“Adjusted EBITDA” is defined as EBITDA adjusted for stock-based compensation costs, loss on sale of fixed assets, loss on debt extinguishment and revaluation, placement agent release expense, loss on contract, provision for credit losses, convertible note inducement expense and impairment on fixed assets. Management believes that EBITDA and Adjusted EBITDA results in a performance measurement that represents a key indicator of our business operations of cryptocurrency mining, hosting customers engaged in cryptocurrency mining, demand service revenue, and high-performance computing services.
Current report
We continued positive Adjusted EBITDA from the third quarter of 2023 through the second quarter of 2024. Effective July 1, 2025 we entered into an agreement for services where the quarterly service expense was approximately one million in each third and fourth quarter of 2024.
Current report
As of December 31, 2024, we had a consolidated accumulated deficit of approximately $314.3 million and we had negative working capital of approximately $34.4 million. As of December 31, 2024, we had total debt outstanding of approximately $21.5 million as summarized further below in the Debt table. In addition, we had outstanding commitments related to Soluna Digital Inc. (“SDI”) of approximately $8.5 million in capital expenditures related to Project Dorothy 2. In addition, due to CloudCo’s termination of the HPE Agreement on March 24, 2025, and HPE’s termination of the HPE Agreement on March 26, 2025, and the acceleration of the remaining unpaid amounts of the contract in accordance with Section 8(h)(ii) of the HPE Agreement, a Type 1 Subsequent Event, we have recognized a liability for the remainder of the HPE Agreement on the balance sheet of our subsidiary, CloudCo, of approximately $20.0 million , net of a prepaid deposit of $8.6 million. As of December 31, 2024, we had $7.8 million of cash available to fund our operations.
Current report
We plan to continue funding operations, including working capital and operating deficits, from operating cash flows and cash flow debt and equity financings, including the YA SEPA and others to be closed as needed consistent with management’s plans.
Showing the first 40 of 47 passages. Open the source sections for the rest.
Removed paragraphs (79)
Previous report
Recent Developments and Trends
Previous report
In 2023, we executed on the following four-pronged strategy: (1) Energize Project Dorothy; (2) Cash Flow, Site and Process Optimization; (3) Flagship Expansion; (4) Pipeline growth. A summary of our developments in these areas follows below.
Previous report
Energize Project Dorothy
Previous report
We transitioned our flagship data center Project Dorothy from construction to operations. ERCOT approved the energizing of the first 50 MW of our new data center on April 20, 2023. We completed the construction and ramping of the facility starting in the spring of fiscal year 2023, and completed the full ramp by the end of October 2023. The data center is colocated with Briscoe Wind Farm (“Briscoe”), a 150 MW wind power generation facility in Silverton, Texas. The project is comprised of two elements, Project Dorothy 1A (“D1A”), and Project Dorothy 1B (“D1B”), each 25 MW facilities.
Previous report
D1A is focused on Bitcoin Hosting. On April 26, 2023 we signed a 5 MW 2-year hosting deal with Compass Mining at D1A. On April 24, 2023 we signed a 20 MW 2-year hosting agreement with another strategic hosting partner at Dorothy 1A. In the summer of 2023, we completed the construction of D1A and the installation of approximately 7,700 Bitcoin miners between the two customers, resulting in an installed hashrate of approximately 950 PH/s. As of December 31, 2023, D1A has consumed over 11,900 MWh of Curtailed Energy from the co-located power plant and achieved a power usage effectiveness (“PUE”) of 1.03.
Previous report
The construction of D1A was made possible by a partnership with Spring Lane Capital (“SLC”), a leading venture capital firm focused on sustainability solutions. On April 22, 2022, we finalized agreements with SLC for a $35 million capital pool to finance Soluna projects alongside renewable energy power plants. Approximately $12.5 million of this was designated for the Dorothy Project. In July 2022, Soluna began tapping into the SLC managed funds to finance Dorothy construction and repay prior funding provided by the Company. In return, SLC received approximately 32% of Class B Membership Interests of D1A. On March 10, 2023, we completed a new series of project-level agreements for $7.5 million from SLC-managed funds. Due to limited liquidity, and access to the capital markets, we sold a portion of our ownership to SLC in 2023. The funds raised aided in the completion of the substation interconnection, and the final stages of project Dorothy. It also provided capital to fund Soluna’s corporate operations. SLC, increased its stake in D1A from approximately 32% to 85%, reducing Soluna’s ownership from 68% to 15%. After SLC achieves an 18% Internal Rate of Return hurdle, Soluna retains 50% of the profits on D1A.
Previous report
D1B is focused on Bitcoin Mining through a strategic partnership with Navitas Global (“Navitas”). On May 9, 2023, we consummated a project-level financing with Navitas, which included a $2 million loan to D1B to complete the construction and a $12.1 million equity investment in the project. After consummating the financing, Navitas owns 49% of D1B and Soluna owns 51%. In June 2023, D1B purchased 8,378 Bitmain Antminer S19s, S19j Pro and S19j Pro+ machines for the partnership. The purchase resulted in an estimated 868 PH/s of hashrate with an average efficiency of 29.9 J/TH and at a cost of $10.59 $/TH. As of December 31, 2023, over 7,900 of the miners had been deployed. D1B was fully energized and began ramping in late October 2023. D1B now has an installed hashrate of 817 PH/s. As of December 31, 2023, D1B has consumed over 10,600 MWh of Curtailed Energy from the co-located power plant and achieved a power usage effectiveness (“PUE”) of 1.03.
Previous report
The Company consolidated the accounts of D1A, Variable Interest Entities (“VIE”) as of December 31, 2023 and December 31, 2022 respectively, and for D1B as of December 31, 2023.
Previous report
Demand Response Services at Dorothy
Previous report
In November 2023, we completed our registration of Project Dorothy for one of ERCOT’s demand response programs establishing the project as key contributor to intelligent and flexible energy solutions, promoting environmental and economic advantages for the state of Texas. It also allowed us to diversify our revenue. Under the program, we have a single promise to stand ready, on a monthly basis, to deliver a set amount of curtailment (committed capacity) per month when and if called upon by ERCOT. Soluna will be able to make additional revenue for Project Dorothy by providing this grid resilience support and potentially reduce its power costs, making it among the lowest cost players in the industry.
Previous report
Cash Flow, Site and Process Optimization
Previous report
In the second quarter of 2023, we shifted our business from primarily proprietary Bitcoin Mining to Bitcoin Hosting. We signed 50 MW of hosting agreements at Dorothy 1A and Sophie.
Previous report
Sophie
Previous report
Project Sophie is a 25 MW data center, based in Murray, Kentucky connected to the grid, (“Sophie”). The project has a Power Purchase Agreement (“PPA”) that requires the curtailment of the site during certain hours of the day to help balance the Kentucky grid.
Previous report
The Company owns 100% of the facility and completed its construction in 2021. In the second quarter of fiscal year 2023, we shifted Project Sophie to Data Hosting, signing contracts with leading Bitcoin miners. We sold older, less efficient Bitcoin mining equipment and used the cash to make operational improvements to the site and to fund corporate operations. Throughout 2023, Sophie progressively secured new more profitable hosting contracts. We have deployed over 8,000 mining machines for hosting in 2023 at the site. The Data Hosting agreements are a combination of a fixed services fee and a profit share component. The cost of power is passed through to customers. Customers at the site now include leading public Bitcoin Miners such as Bit Digital, Compass Mining, and other leading sustainability focused customers.
Previous report
Marie
Previous report
In February 2023, Project Marie, our 20 MW data center in Kentucky was decommissioned. The decision was sparked by following events:
Previous report
As a result, we disposed of all remaining assets at the site, terminated the Atlas hosting agreement, and decommissioned the site.
Previous report
Edith
Previous report
Project Edith was a project permitted to consume up to 3.3 MWs located in Wenatchee, Washington. In September 2022, we sold the mining assets and other mining equipment at the site for $790 thousand. Soluna has committed to providing certain facilities contracts at cost plus a markup to facilitate the continued operations for the mining assets for the new ownership.
Previous report
Cost Cutting and Process Optimization
Previous report
In 2023, we implemented a number of cost cutting measures including staff reductions, renegotiations or termination of key advisory agreements. We ramped up a new Financial Planning and Analysis (“FP&A”) function to provide our management and operations teams better insight into the financial performance of our data centers. This helped us find opportunities to improve profitability and proactively address critical issues with infrastructure equipment at all sites. Our MaestroOS software platform managed the efficient operations of projects Dorothy and Sophie through record setting temperatures (hot and cold) in both Texas and Kentucky in 2023.
Previous report
Expand Flagship, Dorothy 2
Previous report
In 2023, we began the planning process for building out the second 50 MW phase of Project Dorothy – Dorothy 2. We completed the design, established new procurement partners, and submitted an updated approval to ERCOT for approval.
Previous report
Grow Pipeline
Previous report
We signed a term sheet for a new 166 MW data center called Kati that will be integrated with a 300 MW wind farm that has surplus energy due to increasing curtailment by the grid. We worked throughout 2023 to advance the project through grid operator’s, ERCOT planning process.
Previous report
Data Center Locations and Ownership
Previous report
Below is a table showing our operating sites, business models, the Company’s ownership percentages and power source to guide the influence on our financials. We currently operate 75 MW of facilities across two locations.
Previous report
Convertible Noteholders
Previous report
In 2023, the Company negotiated three amendments to the October Convertible Notes. In early 2024, a fourth amendment was negotiated. These amendments were focused on extending the maturity date of the notes, lowering the conversion price of the notes, adding features to the notes to allow early payoff with predetermined cost, and the repricing of certain warrants to assist the company in raising capital for operations.
Previous report
The second half of 2022 was a tumultuous period for the company. Bitcoin declined from a high of $50 thousand to nearly $16 thousand. The decline in price was triggered by a collapse of key players in the cryptocurrency ecosystem including 3AC and FTX. The war in Ukraine had a profound impact on power costs, due to rising gas prices. And, ERCOT instituted a new interim protocol for Crypto related power consumers called Large Flexible Load (“LFL”), which significantly slowed progress at our flagship site, Project Dorothy. Our June 2022 financing plan was put on hold due to market volatility and reduced appetite for new issuances. By the end of 2022, we began to plan a transition away from proprietary mining to Bitcoin hosting.
Previous report
Industry Trends
Previous report
Soluna’s business is influenced by several industry trends, including: (1) challenges in the Bitcoin ecosystem, (2) the Bitcoin Halving, (3) the Inflation Reduction Act, (4) the global Supply Chain, (5) the growth of AI.
Previous report
Bitcoin Ecosystem
Previous report
Fiscal years 2022 and 2023 proved challenging for the Bitcoin Mining industry. In 2022, several companies in the ecosystem initiated bankruptcy proceedings due to the severe decline in the price of Bitcoin and, the impact on energy prices of the war in Ukraine. This turmoil continued into most of 2023 with many companies working their way through chapter 11 and flooding the market with equipment sales. The trial of Sam Backman Fried, founder and CEO of FTX, the industry’s largest digital asset exchange, dominated the news and continued to compress the value of Bitcoin. Later in the year Changpeng Zhao, the founder of Binance, the largest cryptocurrency exchange in the world, pleaded guilty to money laundering violations. By the end of 2023, tides began to turn for Bitcoin as major asset managers like Black Rock, Greyscale, and Bitwise filed for Bitcoin Spot ETFs. This caused a surge in Bitcoin price beginning in the tail end of 2023 that has benefited revenues in the ecosystem.
Previous report
Bitcoin Halving
Previous report
In April 2024, Bitcoin will undergo its fourth halving event, occurring approximately every four years or after every 210,000 blocks are mined. During a halving, miners’ rewards for validating transactions and creating new blocks on the Bitcoin blockchain are cut in half, reducing the rate of new Bitcoin generation. This event typically triggers anticipation and speculation within the Bitcoin community and among investors, leading to increased market activity. Price volatility tends to rise before and after a halving as the market reacts to perceived supply scarcity. Mining profitability decreases post-halving, potentially prompting some miners to shut down operations. This often sparks consolidations in the space reducing the number of mining companies. However, the network automatically adjusts mining difficulty to ensure consistent block production. The halving also causes a supply shock, reducing Bitcoin’s inflation rate and potentially driving long-term price appreciation, although past performance does not guarantee future outcomes. The 2024 halving will be the first to happen during a high interest rate environment, and in the presence of strong institutional demand for Bitcoin driven by ETFs.
Previous report
Inflation Rate Act
Previous report
The Inflation Reduction Act of 2022 (“IRA”), signed into law by President Biden, is a significant investment in climate and energy in the U.S. At the time of its passage, legislators estimated that the bill would allocate $370 billion, primarily in the form of tax credits, to a wide array of decarbonization efforts. Recent private estimates are much higher. In March, the Brookings Institute released a study estimating the spending at $1.2 trillion, which is three times the Congressional estimate. The Act aims to tackle the climate crisis, advance environmental justice, secure America’s position as a world leader in clean energy manufacturing, and work towards achieving a net-zero economy by 2050. Since its enactment, the Inflation Reduction Act has driven substantial investment in clean energy projects, with over $110 billion announced in new clean-energy manufacturing investments. This includes investments in electric vehicle supply chains and solar manufacturing. Overall, the IRA stimulates economic growth through renewable energy development and infrastructure reinvestment in the United States.
Showing the first 40 of 79 passages. Open the source sections for the rest.
Reworded paragraphs (31)
Previous wording
The following table summarizes the balances for the Project sites for cryptocurrency mining revenue, data hosting revenue, cost of cryptocurrency mining revenue, exclusive of depreciation, cost of data hosting revenue, exclusive of depreciation, and cost of depreciation during the year ended December 31, 2023:
Current wording
The following table summarizes the balances for the Project sites for cryptocurrency mining revenue, data hosting revenue, high-performance computing service revenue, demand response revenue, cost of cryptocurrency mining revenue, exclusive of depreciation, cost of data hosting revenue, exclusive of depreciation, cost of high-performance computing services, and cost of depreciation during the year ended December 31, 2024:
Previous wording
The following table summarizes the balances for the Project sites for cryptocurrency mining revenue, data hosting revenue, cost of cryptocurrency mining revenue, exclusive of depreciation, cost of data hosting revenue, exclusive of depreciation, and cost of depreciation during the year ended December 31, 2022:
Current wording
The following table summarizes the balances for the Project sites for cryptocurrency mining revenue, data hosting revenue, high-performance computing service revenue, demand response revenue, cost of cryptocurrency mining revenue, exclusive of depreciation, cost of data hosting revenue, exclusive of depreciation, cost of high-performance computing services, and cost of depreciation during the year ended December 31, 2023:
Previous wording
Cost of Cryptocurrency Revenue, exclusive of depreciation*:* Cost of cryptocurrency mining revenue includes direct utility costs, site overhead expenses, and overhead costs that relate to the operations of our cryptocurrency mining facilities in Washington, Kentucky, and Texas. Going forward, cost of cryptocurrency revenue will include any additional cryptocurrency mining facilities that are part of the Company’s future pipeline.
Current wording
Cost of Cryptocurrency Mining Revenue, exclusive of depreciation*:* Cost of cryptocurrency mining revenue includes direct utility costs, site overhead expenses, and overhead costs that relate to the operations of our cryptocurrency mining facilities in Kentucky and Texas.
Previous wording
Cost of data hosting revenue was approximately $5.6 million for the year ended December 31, 2023, compared to $3.5 million for the year ended December 31, 2022. This increase was due to Project Dorothy 1A which began operations and hosting services in May 2023, creating costs of approximately $4.4 million and had minimal costs in fiscal year 2022. The increase was offset as a direct result by Project Marie’s operations ceasing in February 2023, where the main hosting contract was also simultaneously terminated, creating a decline in costs of approximately $3.3 million. While the Company began data hosting operations at Project Sophie in mid April 2023, which created an increase in costs of approximately $1.0 million, the energy costs associated with the hosting contract arrangements contained pass-through costs for electricity charges. In contrast, a large portion of the fiscal year 2022, the electricity costs werenot pass-through costs, thus reducing the cost of revenue recorded for fiscal year 2023 for Project Sophie and Marie.
Current wording
Cost of data hosting revenue increase was due to Project Dorothy 1A which began operations and hosting services in May 2023 with full year hosting expense in 2024. Also, we transitioned to data hosting at Project Sophie in April 2023, which created an increase in costs.
Previous wording
General and administrative expenses include cash and non-cash compensation, benefits and related costs in support of our general corporate operations, including general management, finance and accounting, human resources, marketing, information technology, corporate development, and legal services.
Current wording
General and Administrative Expenses, exclusive of depreciation and amortization: General and administrative expenses, exclusive of depreciation and amortization include cash and non-cash compensation, benefits, and related costs in support of our general corporate operations, including general management, finance and accounting, human resources, marketing, information technology, corporate development, and legal services.
Previous wording
Depreciation and Amortization associated with general and administrative expenses: Depreciation and amortization expense for the year ended December 31, 2023 totaled approximately $9.5 million, consistent with year ended December 31, 2022. The amortization expense related to the strategic pipeline contract that was acquired in October 2021.
Current wording
Depreciation and Amortization associated with general and administrative expenses: Depreciation and amortization expense was comparable for the year ended December 31, 2024 and the year ended December 31, 2023 in which the balances totaled approximately $9.6 million and $9.5 million, respectively. The balances mainly related to amortization expense related to the strategic pipeline contract that was acquired in October 2021.
Previous wording
Interest Expense: Interest expense for the year ended December 31, 2023 was approximately $2.7 million and related to default and continuing interest expense of the NYDIG loan of approximately $1.4 million*(see legal proceedings)*, a financing loan with Navitas of approximately $228 thousand, interest and other charges of approximately $212 thousand for the promissory notes issued in January and February of 2023 to certain investors, and interest on amortization of warrants for the convertible debt of approximately $475 thousand, as well as default interest charged through March 10, 2023 for the convertible holders of approximately $420 thousand. Interest expense for the year ended December 31, 2022 was $8.4 million primarily related to $6.7 million of interest expense in relation to the October Secured Notes issued on October 25, 2021 (“Convertible Note agreement”) and certain promissory notes issued in each of February, March, and April 2022 and repaid as part of the offering of Series A preferred stock in June 2022. The amortization of warrants and debt discounts was at a higher value in the year ended December 31, 2022 by approximately $6.2 million, due to the value associated with the warrants from when the Company entered into the October Secured Note agreement in 2021, in which was subsequently amended in July and September of 2022, in which the Company needed to extinguish the original debt and establish a new fair value of debt, in which less amortization was associated. Interest expense of $1.7 million for the year ended December 31, 2022, respectively was also incurred under the NYDIG facility and due to its December 2022 default.
Current wording
Interest expense: Interest expense for the year ended December 31, 2024 was approximately $2.5 million related to approximately $1.5 million to the NYDIG loan, $900 thousand to compounded interest and deferred financing amortization expense of equipment financing loan and June and July 2024 secured note financing, and $138 thousand to the Navitas loan. Interest expense for the year ended December 31, 2023 was $2.7 million and related to default and continuing interest expense of the NYDIG loan of approximately $1.4 million, a financing loan with Navitas of approximately $228 thousand, interest and other charges of approximately $212 thousand for the promissory notes issued in January and February of 2023, and interest on amortization of warrants for the convertible debt of approximately $475 thousand, as well as default interest charged through March 10, 2023 for the convertible holders of approximately $420 thousand.
Previous wording
Loss on Debt Extinguishment and Revaluation, net: During the fiscal year ended December 31, 2022, the Company entered into the Convertible Debt Addendum and Convertible Debt Addendum Amendment, in which per guidance in ASC 470, the Convertible Notes were treated as a debt extinguishment in our consolidated financial statements. The Company incurred a loss on the fair value valuation of approximately of approximately $12.9 million for the debt extinguishment and revaluation of debt through September 31, 2022. The Company did a fair value assessment of the Convertible Notes as of December 31, 2022 and recognized a gain from previous valuation of $1.8 million; therefore, the net loss for extinguishment and revaluation for the year ended December 31, 2022 was approximately $11.1 million. The Company incurred a loss on debt extinguishment and revaluation of approximately $3.9 million for the year ended December 31, 2023. On May 11, 2023, the Company entered into a new debt amendment agreement (“Second Amendment”) with the convertible noteholders and issued new warrants, creating a debt extinguishment and loss of $1.8 million. The main factor for the loss was the valuation of the new warrants. On November 20, 2023, the Company completed another new amendment (the “Third Amendment”) of the convertible notes and incurred an additional loss on extinguishment and revaluation of approximately $911 thousand. With quarterly fair value assessments and conversions of debt throughout the year ending December 31, 2023, Company incurred an additional loss on revaluation of approximately $1.2 million with changes in annual volatility of the debt at each quarter end, in addition to note conversions that occurred throughout the year. See Note 9 for further details.
Current wording
We incurred a loss on debt extinguishment and revaluation of approximately $3.9 million for the year ended December 31, 2023. On May 11, 2023, we entered into a new debt amendment agreement (the “Second Amendment”) with the Noteholders and issued new warrants, creating a loss on debt extinguishment of approximately $1.8 million. The main factor for the loss was the valuation of the new warrants. On November 20, 2023, we entered into another amendment with the convertible noteholders (the “Third Amendment”) and incurred an additional loss on extinguishment and revaluation of approximately $911 thousand. With quarterly fair value assessments and conversions of debt throughout the year ending December 31, 2023, we incurred an additional loss on revaluation of approximately $1.2 million with changes in annual volatility of the debt at each quarter end, in addition to note conversions that occurred throughout the year. See Note 8 to our consolidated financial statements included in this Annual Reportfor further details.
Previous wording
***Other expense, net:***For the year ended December 31, 2023, there was approximately $1.5 million other expense, net. The main reason for the balance was due to an approximately $1.0 million penalty charge in relation to moving further in the settlement litigation with NYDIG. In addition, there was a $250 thousand expense in relation to an extension fee for the noteholders of the convertible debt when the 2nd Amendment was signed on May 11, 2023, in addition to the prepayment penalty for the notes payable in the third quarter of fiscal 2023. There were no material other expenses for the year ended December 31, 2022.
Current wording
***Other expense, net:***For the year ended December 31, 2024, other expense, net was approximately $3.4 million respectively, compared to $1.5 million for the year ended December 31, 2023. The increase in other expense, net, for the year ended December 31, 2024 was primarily as a result of $1.0 million general release agreement with our former placement agent; approximately $1.9 million in consent fees, waiver fees, and other financing expenses in relation to the SEPA and related consents for the SEPA on October 1, 2024; a conversion debt inducement expense of approximately $388 thousand; and an extension fee expense of approximately $325 thousand, partially offset by a gain on settlement of litigation with Atlas of approximately $254 thousand. For the year ended December 31, 2023, other expense, net was approximately $1.5 million, consisting of primarily an approximate $1.0 million penalty charge in relation to moving further in the settlement litigation with NYDIG and a $250 thousand expense in relation to an extension fee for the Noteholders when the Second Amendment was signed on May 11, 2023, in addition to the prepayment penalty for the notes payable in the third quarter of fiscal 2023.
Previous wording
Income Tax Benefit from Continuing Operations: Income tax benefit from continuing operations for the year ended December 31, 2023 was $1.1 million compared to an income tax benefit of $1.3 million for the year ended December 31, 2022. The income tax benefit for the fiscal year ended December 31, 2023 and 2022 related to deferred tax amortization impact of acquiring an asset in a transaction that is not a business combination when the amount paid exceeds the tax basis on the acquisition date. As such, the Company is required to adjust the value of the strategic contract pipeline by approximately $10.9 million at inception date (October 29, 2021), in which was recorded as a deferred tax liability and this amount will be amortized over the life of the asset. For the years ended December 31, 2023 and 2022 the Company amortized approximately $2.2 million. For the year ended December 31, 2023, these amounts were offset with a timing difference due to significant increase for in-service capital assets at the Dorothy entities which created an offset of approximately $1.1 million in deferred income tax expense. Income tax benefit from continuing operations for the year ended December 31, 2022 was $1.3 million, which mainly related to the amortization of deferred tax liability for the strategic pipeline discussed above, offset by a $295 thousand deferred tax expense incurred in the second quarter of 2022 related to increasing the Company’s valuation allowance associated with the deferred tax asset, as well as a $503 thousand deferred tax state adjustment.
Current wording
Income Tax Benefit: Income tax benefit for the year ended December 31, 2024 was approximately $2.5 million, compared to approximately $1.1 million thousand for the year ended December 321, 2023. The balances were mainly related to deferred tax amortization impact of acquiring an asset in a transaction that is not a business combination when the amount paid exceeds the tax basis on the acquisition date. As such, we are required to adjust the value of the strategic contract pipeline by approximately $10.9 million at inception date (October 29, 2021), in which was recorded as a deferred tax liability and this amount will be amortized over the life of the asset. For the year ended December 31, 2024 and 2023, we amortized approximately $2.2 million in each year, respectively. In addition, for the year ended December 31, 2023, there were timing differences due to significant increase for in-service capital assets for the year ended December 31, 2023 which created an offset of approximately $1.1 million in deferred income tax expense.
Previous wording
Net Income (loss) attributable to non-controlling interest: Net income attributable to non-controlling interest for the year ended December 31, 2023 was approximately $1.5 million compared to a net loss attributable to non-controlling interest for the year ended December 31, 2022 of approximately $380 thousand. This amount relates to Springlane’s 85% noncontrolling interest of the net profit in Soluna DVSL and Navitas 49% noncontrolling interest of the net profit in Soluna DV ComputeCo for the year ended December 31, 2023, compared to the Springlane’s 32.2% noncontrolling interest of Net loss in Soluna DVSL for the year ended December 31, 2022. Note, there was no noncontrolling interest of DV ComputeCo for the year ended December 31, 2022. The change in non-controlling interest relates to continued profitability at Dorothy 1A and Dorothy 1B, creating a total net profit which started to grow in the third quarter of fiscal year 2023. There was no minority interest for Dorothy 1B (DV ComputeCo), until the 2nd quarter of 2023, when Navitas obtained interest in DV ComputeCo. Dorothy 1A had a net profit of approximately $896 thousand for year ended December 31, 2023 compared to a $1.2 million net loss in year-ended 2022. It should also be noted that the non-controlling interest for DVSL with Springlane was 32.2% for fiscal year 2022, compared to 85% beginning January 1, 2023. As such, DVSL (Dorothy 1A) had a net profit for minority interest of $765 thousand for the year ended December 31, 2023 compared to $380 thousand net loss in minority interest for year ended December 31, 2022, a $1.1 million increase. In addition, the increase also related to Dorothy 1B, which had a zero balance in year-ended December 31, 2022 for non-controlling interest to a non-controlling interest profit of $733 thousand beginning in May 2023 through the year ended December 31, 2023. As the Company was generating revenue from energization at Project Dorothy, the Company began to see a shift from a net loss to profit within non-controlling interest.
Current wording
Net income attributable to non-controlling interest: Net income attributable to non-controlling interest for the year ended December 31, 2024 was approximately $5.0 million compared to a net income of approximately $1.5 million for the year ended December 31, 2023. This amount relates to Spring Lane’s 85% noncontrolling interest of the net profit in Soluna DVSL ComputeCo, LLC (“DVSL”) and Navitas 49% noncontrolling interest of the net profit in Soluna DV ComputeCo, LLC (“DVCC”) for the year ended December 31, 2024. The change in non-controlling interest relates to continued profitability at Dorothy 1A and Dorothy 1B, creating a total net profit in noncontrolling interest of approximately $6.9 million attributable to non-controlling interest for the year ended December 31, 2024, which started to grow in the third quarter of fiscal year 2023. The total net income was offset by noncontrolling interest loss of approximately $1.9 million associated with Dorothy 2, which site is in development stage and would expect losses, where Spring Lane had noncontrolling interest of 58% - 85% for the year ended December 31, 2024. The $1.5 million net income attributable to non-controlling interest for the year ended December 31, 2023 related only to Dorothy 1A and Dorothy 1B. For the first six months of fiscal 2023, DVSL was generating a non-controlling interest net loss, but with the energization at Dorothy 1A in effect beginning in the second quarter of 2023, the DVSL entity began to generate net profits, while DVCC was generating a net loss for the first four months of operations, but with energization beginning in the third quarter of fiscal 2023, the DVCC entity began to generate a net profit in non-controlling interest
Previous wording
We believe Adjusted EBITDA can be an important financial measure because it allows management, investors, and the Board to evaluate and compare our operating results, including our return on capital and operating efficiencies, from period-to-period by making such adjustments. Non-GAAP financial measures are subject to material limitations as they are not in accordance with, or a substitute for, measurements prepared in accordance with U.S. GAAP. For example, we expect that stock-based compensation costs, which is excluded from the non-GAAP financial measures, will continue to be a significant recurring expense over the coming years and is an important part of the compensation provided to certain employees, officers, and directors. Similarly, we expect that depreciation and amortization of fixed assets will continue to be a recurring expense over the term of the useful life of the assets.
Current wording
We believe EBITDA and Adjusted EBITDA can be important financial measures because they allow management, investors, and the Board to evaluate and compare our operating results, including our return on capital and operating efficiencies, from period-to-period by making such adjustments. Non-GAAP financial measures are subject to material limitations as they are not in accordance with, or a substitute for, measurements prepared in accordance with GAAP. For example, we expect that stock-based compensation costs, which is excluded from the non-GAAP financial measures, will continue to be a significant recurring expense over the coming years and is an important part of the compensation provided to certain employees, officers, and directors. Similarly, we expect that depreciation and amortization of fixed assets will continue to be a recurring expense over the term of the useful life of the assets.
Previous wording
Adjusted EBITDA is provided in addition to and should not be considered to be a substitute for, or superior to net income, the comparable measure calculated in accordance with U.S. GAAP. Further, Adjusted EBITDA should not be considered as an alternative to revenue growth, net income, diluted earnings per share or any other performance measure calculated in accordance with U.S. GAAP, or as an alternative to cash flow from operating activities as a measure of our liquidity. Adjusted EBITDA has limitations as an analytical tool, and you should not consider such measures either in isolation or as substitutes for analyzing our results as reported under U.S. GAAP.
Current wording
EBITDA and Adjusted EBITDA are provided in addition to and should not be considered to be substitutes for, or superior to net income, the comparable measure calculated in accordance with GAAP. Further, EBITDA and Adjusted EBITDA should not be considered as alternatives to revenue growth, net income, or any other performance measure calculated in accordance with GAAP, or as alternatives to cash flow from operating activities as a measure of our liquidity. EBITDA and Adjusted EBITDA have limitations as analytical tools, and you should not consider such measures either in isolation or as substitutes for analyzing our results as reported under GAAP.
Previous wording
Reconciliations of Adjusted EBITDA to net income from continuing operations, the most comparable U.S. GAAP financial metric, for historical periods are presented in the table below:
Current wording
Reconciliations of EBITDA and Adjusted EBITDA to net loss, the most comparable GAAP financial metric, for historical periods are presented in the table below:
Previous wording
The following table represents the Adjusted EBITDA activity between each three-month period for the year ended December 31, 2023.
Current wording
The following table represents the EBITDA and Adjusted EBITDA activity between each three-month period from January 1, 2024 through December 31, 2024.
Previous wording
The following table represents the Adjusted EBITDA activity between each three-month period for the year ended December 31, 2022.
Current wording
The following table represents the EBITDA and Adjusted EBITDA activity between each three-month period from January 1, 2023 through December 31, 2023.
Previous wording
Based on business developments, including changes in production levels, staffing requirements, and network infrastructure improvements, we will require additional capital equipment in the foreseeable future. With the Company’s shift in focus of the business, and the sale of the MTI Instruments business that occurred in April 2022, the Company has now exited the instrumentation business and is focused on developing and monetizing green, zero-carbon computing and cryptocurrency mining facilities, as well as facilities capable of hosting customers engaged in cryptocurrency mining.
Current wording
Based on business developments, including changes in production levels, staffing requirements, and network infrastructure improvements, we will require additional capital equipment in the foreseeable future. We are focused on developing and monetizing green, zero-carbon computing and cryptocurrency mining facilities, as well as facilities capable of hosting customers engaged in cryptocurrency mining, and data centers to provide specialized AI Cloud and colocation services.
Previous wording
Net cash used in operating activities from continuing operations was approximately $3.0 million for the year ended December 31, 2023. The Company had a net loss of approximately $27.7 million, in which was offset by non-cash items of approximately $22.5 million. The non-cash items consisted primarily of approximately $13.4 million of amortization and depreciation expenses for the intangible assets acquired in 2021 and the fixed assets still in service and capital additions in 2023. There was also approximately $4.3 million in stock-based compensation expenses, $3.9 million on loss on debt extinguishment and revaluation, and additional $1.2 million in relation to fixed asset impairments, loss on sale of fixed assets, and amortization of operating lease assets. The non-cash items were offset with a $1.1 million deferred income tax benefit. The change in assets and liabilities of approximately $2.4 million related to increases in accrued expenses of $3.9 million in which related to interest for the NYDIG loan, sales and real estate tax accruals, and bonus accrual, as well as increase in customer deposits of $2.8 million with data hosting customers for the facility sites, offset with an increase in accounts receivable related to performing further hosting services and demand response services as of December 31, 2023.
Current wording
Net cash used in operating activities from continuing operations was approximately $3.0 million for the year ended December 31, 2023. We had a net loss of approximately $27.7 million, which was offset by non-cash items of approximately $22.5 million. The non-cash items consisted primarily of approximately $13.4 million of amortization and depreciation expenses for the intangible assets acquired in 2021 and the fixed assets still in service and capital additions in 2023. There was also approximately $4.3 million in stock-based compensation expenses, $3.9 million on loss on debt extinguishment and revaluation, and additional $1.2 million in relation to fixed asset impairments, loss on sale of fixed assets, and amortization of operating lease assets. The non-cash items were offset with a $1.1 million deferred income tax benefit. The change in assets and liabilities of approximately $2.4 million related to increases in accrued expenses of $3.9 million in which related to interest for the NYDIG loan, sales and real estate tax accruals, and bonus accrual, as well as increase in customer deposits of $2.8 million with data hosting customers for the facility sites, offset with an increase in accounts receivable related to performing further hosting services and demand response services as of December 31, 2023.
Previous wording
Net cash used in investing activities during the year ended December 31, 2023 was approximately $10.3 million consisting mainly of capital expenditures of $12.7 million, less cash proceeds from sale of equipment of $2.3 million.
Current wording
Net cash used in investing activities during the year ended December 31, 2024 was approximately $13.2 million consisting mainly of capital expenditures of $9.2 million and increase in deposits on equipment of $4.1 million, primarily related to the development build of Project Dorothy 2. Net cash used in investing activities during the year ended December 31, 2023 was approximately $10.3 million consisting mainly of capital expenditures of $12.7 million, primarily related to the completion of the build of Project Dorothy 1A and 1B, less cash proceeds from sale of equipment of $2.3 million, primarily from the sale of miners located at Project Sophie in connection with the decision to convert to a hosting facility.
Previous wording
Net cash provided by financing activities was approximately $21.8 million during the year ended December 31, 2023, which consisted of cash contributions for noncontrolling interest of approximately $20.4 million, offset with distributions for non-controlling interest of $1.0 million. The Company also received net proceeds of approximately $817 thousand from the subsequent SPA offerings, in addition to proceeds from debt issuances of $3.1 million less debt payment costs of $1.1 million on promissory notes and the Navitas loan, and $350 thousand for payment on the Company’s line of credit.
Current wording
For fiscal year 2024, funds from financing activities were used to fund an initial deposit for the HPE Agreement, fund construction of D2, continued project pipeline development and general operating cash. Net cash provided by financing activities was approximately $18.3 million consisting mainly of proceeds from financing of approximately $14.5 million in which $13.75 million was from 2024 secured loan financing in June and July, and $720 thousand was drawn down for equipment financing. In addition, there was $2.3 million in warrants exercised, as well as $14.7 million in contributions of non-controlling membership interest. Offsetting the net cash provided by financing activities was $8.3 million in cash distributions to non-controlling interest members, and payments of $4.9 million relation to Navitas loan, the June and July 2024 note agreements, and payments in relation to the convertible holders. Net cash provided by financing activities was approximately $21.8 million during the year ended December 31, 2023, which consisted of cash contributions for noncontrolling interest of approximately $20.4 million, offset with distributions for non-controlling interest of $1.0 million. We also received net proceeds of approximately $817 thousand from the subsequent SPA offerings, in addition to proceeds from debt issuances of $3.1 million less debt payment costs of $1.1 million on promissory notes and the Navitas loan, and $350 thousand for payment on the Company’s line of credit.
Previous wording
On January 14, 2022, the Company effected an initial drawdown under the Master Equipment Finance Agreement with NYDIG in the aggregate principal amount ofapproximately $4.6 million that bore interest at 14%. On January 26, 2022, the Company had a subsequent drawdown of $9.6 million. On December 20, 2022, Soluna MC Borrowing 2021-1 LLC (“Borrower”) received a Notice of Acceleration and Repossession (the “NYDIG Notice”) from NYDIG with respect to the Master Agreement, by and between Borrower and NYDIG. The obligations of Borrower under the Master Agreement and reflected in the NYDIG Notice are ring-fenced to Borrower and its direct parent company, Soluna MC LLC. The Company is not a party to any guaranty, collateral agreement or other support agreement with or for the benefit of NYDIG. As such, the principal balance of $10.5 million as of December 31, 2022 became due immediately and the Borrower shall bear interest, at a rate per annum equal to 2.0% plus the rate per annum otherwise applicable to such obligations set forth in the Master Agreement. On February 23, 2023, NYDIG proceeded to foreclose on all of the collateral securing the MEFA, and repossessed the collateralized assets that totaled approximately $3.4 million, in which approximately $560 thousand was first used to pay off accrued interest and penalty to date. On September 5, 2023, NYDIG provided a letter finalizing the accounting for the repossessed collateralized assets totaling proceeds of approximately $3.4 million. This included legal and other expenses associated with the sale of the assets net a modest gain on the estimated net book value of the assets totaling $251 thousand that was expensed as a loss on disposition of assets for the year ended December 31, 2023. On December 7, 2023, NYDIG filed its Motion for Summary Judgment seeking entry of a judgment against Soluna in the approximate amount of $10.3 million for principal and interest and penalties. On January 12, 2024, Soluna filed its objection to NYDIG’s motion for summary judgment on the grounds that NYDIG failed to explain what collateral of which loan was sold and how the sale proceeds were allocated to each loan. A summary judgment motion was performed on February 13, 2024, and was agreed upon by both NYDIG and the Borrower, that the total outstanding loan principal balance would be approximately $9.2 million, in which a penalty fee was applied of approximately $1.0 million to the repossessed collateralized assets, and outstanding interest and penalty balance would be approximately $936 thousand as of December 31, 2023.
Current wording
On January 14, 2022, the Company effected an initial drawdown under the Master Equipment Finance Agreement (“MEFA”) with NYDIG in the aggregate principal amount of approximately $4.6 million that bore interest at 14%. On January 26, 2022, the Company had a subsequent drawdown of $9.6 million. On December 20, 2022, Soluna MC Borrowing 2021-1 LLC (“Borrower”) received a Notice of Acceleration and Repossession (the “NYDIG Notice”) from NYDIG with respect to the MEFA, by and between Borrower, a subsidiary of Soluna MC, LLC, a subsidiary of Soluna Digital, a subsidiary of the Company, and NYDIG. The obligations of Borrower under the MEFA and reflected in the NYDIG Notice are ring-fenced to Borrower and its direct parent company, Soluna MC LLC. The Company is not a party to any guaranty, collateral agreement, or other support agreement with or for the benefit of NYDIG. As such, the principal balance of $10.5 million as of December 31, 2022 became due immediately and the Borrower shall bear interest, at a rate per annum equal to 2.0% plus the rate per annum otherwise applicable to such obligations set forth in the MEFA. On February 23, 2023, NYDIG proceeded to foreclose on all of the collateral securing the MEFA, and repossessed the collateralized assets that totaled approximately $3.4 million, in which approximately $560 thousand was first used to pay off accrued interest and penalty to date. On September 5, 2023, NYDIG provided a letter finalizing the accounting for the repossessed collateralized assets totaling proceeds of approximately $3.4 million. A summary judgment motion was performed on February 13, 2024 and was agreed upon by both NYDIG and the Borrower, that the total outstanding loan principal balance would be approximately $9.2 million, in which a penalty fee was applied of approximately $1.0 million to the repossessed collateralized assets, and outstanding interest and penalty balance would be approximately $936 thousand as of December 31, 2023. As of December 31, 2024, the Company still has an outstanding loan principal of approximately $9.2 million and outstanding interest and penalty balance of approximately $2.3 million.
Previous wording
On May 9, 2023, Soluna DV ComputeCo, LLC and Navitas West Texas Investments SPV, LLC entered into a 2-year Loan Agreement for $2,050,000. The unpaid principal balance of the Term Loan shall bear interest at per annum rate equal to 15%. As of December 31, 2023, the Company has an outstanding principal balance of approximately $1.7 million and incurred approximately $204 thousand in interest expense and $25 thousand in deferred amortization expense.
Current wording
On May 9, 2023, DVCC and Navitas West Texas Investments SPV, LLC entered into a 2-year Loan Agreement for $2,050,000. The unpaid principal balance of the Term Loan shall bear interest at per annum rate equal to 15%. As of December 31, 2024, the Company has an outstanding principal balance of approximately $137 thousand. As of the date of these consolidated financial statements, the Navitas loan has been fully paid off.
Previous wording
Critical Accounting Policies and Significant Judgments and Estimates
Current wording
Critical Accounting Policies and Use of Estimates
Previous wording
The prior discussion and analysis of our financial condition and results of operations is based upon our consolidated financial statements, which have been prepared in accordance with GAAP. Note 2 of the Consolidated Financial Statements included in this Annual Report on Form 10-K includes a summary of our most significant accounting policies. The preparation of these consolidated financial statements requires management to make estimates and judgments that affect the reported amounts of assets, liabilities, revenue, expenses, and related disclosure of assets and liabilities. On an ongoing basis, we evaluate our estimates and judgments, including those related to revenue recognition, income taxes and share-based compensation. We base our estimates on historical experience and on various other factors that we believe are reasonable under the circumstances, the results of which form the basis for making judgments about the carrying values of assets and liabilities that are not readily apparent from other sources. Actual results may differ from these estimates under different assumptions or conditions. Periodically, our management reviews our critical accounting estimates with the Audit Committee of our Board of Directors.
Current wording
The prior discussion and analysis of our financial condition and results of operations is based upon our consolidated financial statements, which have been prepared in accordance with GAAP. Note 2 of the Consolidated Financial Statements included in this Annual Report includes a summary of our most significant accounting policies. The preparation of these consolidated financial statements requires management to make estimates and judgments that affect the reported amounts of assets, liabilities, revenue, expenses, and related disclosure of assets and liabilities. On an ongoing basis, we evaluate our estimates and judgments, including those related to revenue recognition, income taxes and share-based compensation. We base our estimates on historical experience and on various other factors that we believe are reasonable under the circumstances, the results of which form the basis for making judgments about the carrying values of assets and liabilities that are not readily apparent from other sources. Actual results may differ from these estimates under different assumptions or conditions. Periodically, our management reviews our critical accounting estimates with the Audit Committee of our Board of Directors.
Previous wording
Cryptocurrency revenue consists of revenue recognized from the Company’s cryptocurrency mining facilities. Revenue is recognized at the cryptocurrency’s realized cash value based upon the rates at cryptocurrency exchanges where we are registered. Cryptocurrencies are earned when the miners solve complex computations and cryptocurrency is issued as a result. The mined cryptocurrency is immediately paid to the Coinbase wallet. Cryptocurrency is converted to U.S. dollars on a daily basis. Also, the Company has entered into customer hosting contracts whereby the Company provides electrical power to cryptocurrency mining customers, and the customers pay a stated amount per megawatt-hour (“MWh”) (“Contract Capacity”) as well as a percentage of the profit share of the daily net income from the customer’s mining operations. The actual monthly amounts are calculated after the close of each month and billed to the customers.
Current wording
We have entered into customer hosting contracts whereby we provide hosting services which include, electrical power to cryptocurrency mining customers, other utilities, and management of hosting facilities. Customer contracts can be a combination of a stated fixed amount per megawatt-hour (“MWh”) (“Contract Capacity”), a percentage of the profit share of the daily net income from the customer’s mining operations, or a combination thereof. Some contracts also include pass-through expenses which are not recognized in revenue. The actual monthly amounts are calculated after the close of each month and billed to the customers.
Previous wording
The estimated fair value of certain financial instruments, including cash, accounts receivable and short-term debt approximates their carrying value due to their short maturities and varying interest rates. “Fair value” is the price that would be received to sell an asset or transfer a liability in an orderly transaction between market participants at the measurement date. The Company utilizes valuation techniques that maximize the use of observable inputs and minimize the use of unobservable inputs. Based on the observability of the inputs used in the valuation methods, the Company is required to provide the following information according to the fair value accounting standards. These standards established a fair value hierarchy as specified that ranks the quality and reliability of the information used to determine fair values. Financial assets and liabilities are classified and disclosed in one of the following three categories:
Current wording
The estimated fair value of certain financial instruments, including cash, accounts receivable and short-term debt approximates their carrying value due to their short maturities and varying interest rates. “Fair value” is the price that would be received to sell an asset or transfer a liability in an orderly transaction between market participants at the measurement date. We utilize valuation techniques that maximize the use of observable inputs and minimize the use of unobservable inputs. Based on the observability of the inputs used in the valuation methods, we are required to provide the following information according to the fair value accounting standards. These standards established a fair value hierarchy as specified that ranks the quality and reliability of the information used to determine fair values. Financial assets and liabilities are classified and disclosed in one of the following three categories:
Previous wording
The Company had Warrants included within the SPA agreement as noted in Note 9. The Warrants are considered freestanding equity-classified instruments due to their detachable and separately exercisable features and meet the indexation criteria within derivative accounting. Accordingly, the Warrants are presented as a component of Stockholders’ Equity in accordance with derivative accounting.
Current wording
We had Warrants included within the SPA agreement as noted in Note 8. The Warrants are considered freestanding equity-classified instruments due to their detachable and separately exercisable features and meet the indexation criteria within derivative accounting. Accordingly, the Warrants are presented as a component of Stockholders’ Equity in accordance with derivative accounting.
Previous wording
Following the debt extinguishment on July 19, 2022 as noted further in Note 9, the Convertible Notes will be recorded at fair value upon issuance (e.g., upon execution of the Addendum) per guidance within ASC 480, and at each subsequent reporting period, with changes in fair value reported in earnings.
Current wording
Following the debt extinguishment on July 19, 2022 as noted further in Note 2 and 8, the Convertible Notes will be recorded at fair value upon issuance (e.g., upon execution of the Addendum) per guidance within ASC 480, and at each subsequent reporting period, with changes in fair value reported in earnings.
Previous wording
Consistent with the guidance in purchase accounting, the value of the Strategic Pipeline Contract as of the acquisition date was estimated using an expected value approach, which probability-weights various future outcomes and uses certain Level 3 inputs.
Current wording
Consistent with the guidance in purchase accounting, the value of the Strategic Pipeline Contract, see Note 5, as of the acquisition date of October 2021 was estimated using an expected value approach, which probability-weights various future outcomes and uses certain Level 3 inputs.
Previous wording
We grant options to purchase our common stock and award restricted stock to our employees and directors under our equity incentive plans. The benefits provided under these plans are share-based payments and we account for stock-based awards exchanged for employee service in accordance with the appropriate share-based payment accounting guidance. Stock-based compensation represents the cost related to stock-based awards granted to employees and directors. We measure stock-based compensation cost at grant date based on the estimated fair value of the award and recognize the cost as expense on a straight-line basis in accordance with the vesting of the options (net of estimated forfeitures) over the option’s requisite service period. We estimate the fair value of stock-based awards on the grant date using a Black-Scholes valuation model. We use the fair value method of accounting with the modified prospective application, which provides for certain changes to the method for valuing share-based compensation. The valuation provisions apply to new awards and to awards that are outstanding on the effective date and subsequently modified.
Current wording
We award restricted stock to our employees and directors under the 2021 Plan and the Soluna Holdings, Inc. Amended and Restated 2023 Stock Incentive Plan (the “2023 Plan,” together with the 2021 Plan, the “Plans”). The benefits provided under these plans are share-based payments and we account for stock-based awards exchanged for employee service in accordance with the appropriate share-based payment accounting guidance. Stock-based compensation represents the cost related to stock-based awards granted to employees and directors. We measure stock-based compensation cost at grant date based on the estimated fair value of the award and recognize the cost as expense on a straight-line basis in accordance with the vesting of the options (net of estimated forfeitures) over the option’s requisite service period. We estimate the fair value of stock-based awards on the grant date using a Black-Scholes valuation model. We use the fair value method of accounting with the modified prospective application, which provides for certain changes to the method for valuing share-based compensation. The valuation provisions apply to new awards and to awards that are outstanding on the effective date and subsequently modified.
Previous wording
A discussion of recently adopted and new accounting pronouncements is included in Note 2 of the Consolidated Financial Statements in Part II, Item 8 of this Annual Report on Form 10-K.
Current wording
A discussion of recently adopted and new accounting pronouncements is included in Note 2 of the Consolidated Financial Statements included in this Annual Report.
Rearranged current paragraphs (1)
Current report — wording carried from elsewhere
Cryptocurrency revenue consists of revenue recognized from our cryptocurrency mining facilities. Revenue is recognized at the cryptocurrency’s realized cash value based upon the rates at cryptocurrency exchanges where we are registered. Cryptocurrencies are earned through participation with mining pool operators where the company provides hash rate services to the mining pool. The consideration received is payable in BitCoin based on a published formula Cryptocurrency is converted to U.S. dollars on a daily basis.