Item 1A. Risk Factors

Current report: 10-Q

Period ended 2026-06-30; filed 2026-08-13.

0001628280-26-056457

Item 1A. Risk Factors

The baseline is this issuer’s latest earlier reporting period of the same form that was filed before the current report. A previous 10-Q is a different quarter, not a year-over-year comparison. Amendments are excluded.

Compared 441 previous paragraphs and 443 current paragraphs.

418 unchanged; 21 reworded; 4 added; 0 removed; 2 previous and 0 current paragraphs rearranged.

Tables are not compared: 0 previous and 0 current tables excluded. Dates, whitespace, punctuation and numbering changes are ignored; changes to financial figures remain significant.

A changed paragraph is not evidence that risk increased or decreased. An unchanged paragraph does not establish that risk stayed the same.

Added paragraphs (4)

Current report

However, data center development has faced increasing public scrutiny and community opposition, including in states where we plan to develop projects, based on concerns about electricity rates, infrastructure costs, land use, grid strain and water consumption. In response, governmental authorities, utility regulators, and interest groups have proposed or adopted measures affecting data center development and energy procurement. These include siting restrictions or moratoria, specialized tariffs for large loads, ratepayer protection and cost-allocation requirements, and changes in the treatment of co-located or behind-the-meter arrangements.

Current report

Our existing federal environmental approvals may not be sufficient to support the full capacity we anticipate developing at Cape Station.

Current report

Developing the full capacity we anticipate at Cape Station may require federal environmental reviews and approvals beyond those we have already obtained. Those approvals are based on assumptions regarding the amount and location of surface disturbance associated with well pads, roads, pipelines, power plants, interconnection facilities and the spacing of our GeoBlocks. These assumptions depend on project design, drilling methods and subsurface conditions and may change as development progresses.

Current report

If the surface disturbance required for development exceeds that contemplated by our existing approvals, we may be required to amend those approvals, complete supplemental environmental review or obtain additional permits or other governmental approvals. The timeline to obtain such amendments or additional approvals is uncertain. We may not obtain any required amendments or additional approvals on our anticipated timeline, on acceptable terms or at all, and applicable government agencies may impose additional mitigation measures, operating restrictions or project design changes. Any resulting delays, conditions or denials could increase costs, delay construction, reduce the capacity we are able to develop or require changes to our development plans, any of which could materially and adversely affect our business, financial condition and results of operations.
Reworded paragraphs (21)

Previous wording

The capital expenditures we expect to incur as we complete the development of our future projects will be significant, including wellfield drilling and completions for EGS reservoirs and procurement of binary, air-cooled ORC power plants. Our standardized modular approach contemplates deployment across GeoClusters via 50-megawatt GeoBlocks, and our estimate of capital expenditures to construct a single GeoBlock was approximately $7,000/kW as of March 31, 2026, inclusive of wellfield, surface facilities and plant equipment. We currently estimate capital expenditures of approximately $1.2 billion over the next twelve months, of which approximately $1.1 billion relates to our Cape Station Phase I and Phase II facilities. Although we currently hold certain federal approvals that have already undergone National Environmental Policy Act (“NEPA”) review covering approximately 2 gigawatts of capacity potential, a portion of these capital expenditures (including exploration, geophysical surveys, test and delineation wells, stimulation, and other reservoir development activities) must be incurred before we obtain, or can finalize, certain material permits, land use authorizations, and approvals that are outside the scope of NEPA review, including site‑specific well permits (e.g., drilling, injection and production well permits), water rights and related authorizations, and state and local permits and approvals (such as land use, building, grading, cultural and environmental, and air and noise permits). As of the date of this filing, 79 out of 80 permits of the governmental permits and approvals necessary to commence commercial operations at Cape Station Phase I have been received, and the single remaining necessary permit is in process. Moreover, 82 out of 179 permits of the governmental permits and approvals necessary to commence commercial operations at Cape Station Phase II have been received, and the remaining 97 are in process. Of those in-process approvals and permits, all are individual, administrative geothermal well permits or administrative county permits, and we do not currently expect any material delays, conditions or denials with respect to any of these pending permits. If any such permits or approvals are delayed, impose burdensome conditions, or are not granted, the investments we make ahead of permitting may be stranded, impaired, or require redesign, leading to write‑offs, additional costs, and schedule slippage.

Current wording

The capital expenditures we expect to incur as we complete the development of our future projects will be significant, including wellfield drilling and completions for EGS reservoirs and procurement of binary, air-cooled ORC power plants. Our standardized modular approach contemplates deployment across GeoClusters via 50-megawatt GeoBlocks, and our estimate of capital expenditures to construct a single GeoBlock was approximately $7,000/kW as of June 30, 2026, inclusive of wellfield, surface facilities and plant equipment. As of June 30, 2026, we currently estimate capital expenditures of approximately $850.0 million to $900.0 million for the remainder of 2026, a majority of which relates to our facilities at Cape Station. Although we currently hold certain federal approvals that have already undergone National Environmental Policy Act (“NEPA”) review covering approximately 2 gigawatts of capacity potential, a portion of these capital expenditures (including exploration, geophysical surveys, test and delineation wells, stimulation, and other reservoir development activities) must be incurred before we obtain, or can finalize, certain material permits, land use authorizations, and approvals that are outside the scope of NEPA review, including site‑specific well permits (e.g., drilling, injection and production well permits), water rights and related authorizations, and state and local permits and approvals (such as land use, building, grading, cultural and environmental, and air and noise permits). As of the date of this filing, 79 out of 80 governmental permits and approvals necessary to commence commercial operations at Cape Station Phase I have been received, and the single remaining necessary permit is in process. Moreover, 82 out of 179 governmental permits and approvals necessary to commence commercial operations at Cape Station Phase II have been received, and the remaining 97 are in process. Of those in-process approvals and permits, all are individual, administrative geothermal well permits or administrative county permits, and we do not currently expect any material delays, conditions or denials with respect to any of these pending permits. If any such permits or approvals are delayed, impose burdensome conditions, or are not granted, the investments we make ahead of permitting may be stranded, impaired, or require redesign, leading to write‑offs, additional costs, and schedule slippage.

Previous wording

We depend on transmission facilities owned and operated by others to deliver the power we sell from our power plants to our customers. If transmission is disrupted, or if the transmission capacity infrastructure is inadequate, or if there is a failure that requires long shutdown for repair, or if curtailment is required due to load system inefficiency, our ability to sell and deliver power to our customers may be adversely impacted and we may either incur additional costs or forego revenues. For example, if a transmission provider curtails our facility or recalls our transmission rights, we could experience prolonged or repeated outages, face liquidated damages or termination under our PPAs, face damages under tax credit sales agreements, and face potential defaults under financing arrangements. In addition, lack of access to new transmission capacity may affect our ability to develop new projects. Existing congestion of transmission capacity, as well as expansion of transmission systems and competition from other developers seeking access to expanded systems, could also affect our performance. Although our modular GeoCluster approach may offer interconnection optionality at multi-gigawatt sites, new transmission remains uncertain, and behind-the-meter opportunities with data centers may not be available or sufficient to offset transmission constraints.

Current wording

We depend on transmission facilities owned and operated by others to deliver the power we sell from our power plants to our customers. If transmission is disrupted, or if the transmission capacity infrastructure is inadequate, or if there is a failure that requires a long shutdown for repair, or if curtailment is required due to load system inefficiency, our ability to sell and deliver power to our customers may be adversely impacted and we may either incur additional costs or forego revenues. For example, if a transmission provider curtails our facility or recalls our transmission rights, we could experience prolonged or repeated outages, face liquidated damages or termination under our PPAs, face damages under tax credit sales agreements, and face potential defaults under financing arrangements. In addition, lack of access to new transmission capacity may affect our ability to develop new projects. Existing congestion of transmission capacity, as well as expansion of transmission systems and competition from other developers seeking access to expanded systems, could also affect our performance. Although our modular GeoCluster approach may offer interconnection optionality at multi-gigawatt sites, new transmission remains uncertain, and behind-the-meter opportunities with data centers may not be available or sufficient to offset transmission constraints.

Previous wording

Prior to February 2017, we conducted no business operations and we recorded no revenue or expenses. During the three months ended March 31, 2026 and 2025, we reported net losses of $31.8 million and $9.1 million, respectively.

Current wording

Prior to February 2017, we conducted no business operations and we recorded no revenue or expenses. During the three and six months ended June 30, 2026, we reported net losses of $55.9 million and $87.7 million, respectively. During the three and six months ended June 30, 2025, we reported net losses of $11.4 million and $20.6 million, respectively.

Previous wording

Our ability to generate sales of electricity following COD at each of our projects depends on our ability to successfully commence and maintain production under our PPAs. We expect to begin delivering first power from our 500-megawatt Cape Station project by late 2026, and to reach approximately 100 megawatts of operating capacity by early 2027. However, there is no guarantee that we will achieve such CODs within those timeframes or at all. We may fail to receive the required approvals and permits from governmental and regulatory agencies for our projects. As a result, there can be no assurance as to when we will commence deliveries under our PPAs, and therefore when, if at all, we will commence generating revenues and operating cash flows from our PPAs. If we do not commence operations under our PPA on Cape Station Phase I (Unit 1) by October 1, 2026, Cape Station Phase I

Current wording

Our ability to generate sales of electricity following COD at each of our projects depends on our ability to successfully commence and maintain production under our PPAs. We expect to begin delivering first power from our 500-megawatt Cape Station project in the fourth quarter of 2026, and to reach approximately 100 megawatts of operating capacity in the first quarter of 2027. However, there is no guarantee that we will achieve such CODs within those timeframes or at all. We may fail to receive the required approvals and permits from governmental and regulatory agencies for our projects. As a result, there can be no assurance as to when we will commence deliveries under our PPAs, and therefore when, if at all, we will commence generating revenues and operating cash flows from our PPAs. If we do not commence operations under our PPA on Cape Station Phase I (Unit 1), Cape Station Phase I (Units 2-3), and Cape Station Phase II by the COD under the applicable PPA, we will incur liquidated damages under the provisions of the applicable PPA. If we do not commence operations within six months of the applicable PPA COD deadline, our counterparty has the right to terminate the contract. Accordingly, there is significant uncertainty about our ability to maintain profitability and operating cash flows.

Previous wording

We are exposed to the credit and financial condition of our offtakers. We have two long-term PPAs relating to Cape Station Phase I, and two long-term PPAs relating to Cape Station Phase II. Because our contracts are long-term, we may be adversely affected if the credit quality of any of these customers were to decline or if their respective financial conditions were to deteriorate or if they are otherwise unable to perform their obligations under our long-term contracts. While we have executed binding offtake agreements with credit-worthy counterparties in certain cases, long-term exposure to a concentrated offtaker base remains a risk.

Current wording

We are exposed to the credit and financial condition of our offtakers. We currently have [two] long-term PPAs related to Cape Station. Because our contracts are long-term, we may be adversely affected if the credit quality of any of these customers were to decline or if their respective financial conditions were to deteriorate or if they are otherwise unable to perform their obligations under our long-term contracts. While we have executed binding offtake agreements with credit-worthy counterparties in certain cases, long-term exposure to a concentrated offtaker base remains a risk.

Previous wording

Our failure to meet these milestones and other criteria, including minimum quantities, may result in price concessions and may result in the termination of our PPAs, in which case we would lose any future cash flow from the relevant project and may be required to pay fees and penalties to our counterparty. Specifically, with respect to project completion risk, if we do not commence operations under our PPA on Cape Station Phase I (Unit 1) by October 1, 2026, Cape Station Phase I (Units 2-3) by January 1, 2027, and Cape Station Phase II by June 1, 2028, we will incur liquidated damages under the provisions of the applicable PPA. If we do not commence operations within six months of the applicable PPA COD deadline, our counterparty has the right to terminate the contract. If our PPAs are terminated, it could materially and adversely affect the development of our geothermal power plants, our results of operations, and cash flow unless we are able to replace the PPA on similar terms. Additionally, we cannot assure you that we will be able to perform our obligations under such agreements or that we will have sufficient funds to pay any fees or penalties thereunder.

Current wording

Our failure to meet these milestones and other criteria, including minimum quantities, may result in price concessions and may result in the termination of our PPAs, in which case we would lose any future cash flow from the relevant project and may be required to pay fees and penalties to our counterparty. Specifically, with respect to project completion risk, if we do not commence operations under our PPA on Cape Station Phase I (Unit 1), Cape Station Phase I (Units 2-3) and Cape Station Phase II by the COD under the applicable PPA, we will incur liquidated damages under the provisions of the applicable PPA. If we do not commence operations within six months of the applicable PPA COD deadline, our counterparty has the right to terminate the contract. If our PPAs are terminated, it could materially and adversely affect the development of our geothermal power plants, our results of operations, and cash flow unless we are able to replace the PPA on similar terms. Additionally, we cannot assure you that we will be able to perform our obligations under such agreements or that we will have sufficient funds to pay any fees or penalties thereunder.

Previous wording

We do not own the land on which the projects in our portfolio are located and they generally are, and our future projects may be, located on land occupied under long-term easements, leases and rights-of-way. As of March 31, 2026, approximately 66.0% of our acreage was located on land owned by the United States federal government,

Current wording

We do not own the land on which the projects in our portfolio are located and they generally are, and our future projects may be, located on land occupied under long-term easements, leases and rights-of-way. As of June 30, 2026, approximately 63.3% of our acreage was located on land owned by the United States federal government,

Previous wording

6.0% was located on state lands, and 28.0% was located on privately-owned land. As of March 31, 2026, our easements, leases and rights-of-way had a weighted average remaining term of approximately 7 years with scheduled expirations of approximately 6.0% in years 2026 to 2028, 55.0% in years 2029 to 2031, and 39.0% thereafter, in each case excluding any unexercised renewal options. A majority of our leases are issued by the BLM and include renewal options exercisable at our discretion. The standard BLM lease provides an initial ten-year term followed by two five-year renewal options. We currently anticipate exercising renewal options for our leases, including those with near-term scheduled expirations in 2026 to 2028, and we do not expect any material lease expirations in the near term. Additionally, these BLM leases contain acreage that is subject to extension provided certain conditions are met, including a minimum amount of expenditures per acre and the provision of certain geologic information to the BLM, which enables us to extend the lease term for as long as we continue to meet such conditions.

Current wording

5.7% was located on state lands, and 31.0% was located on privately-owned land. As of June 30, 2026, our easements, leases and rights-of-way had a weighted average remaining term of approximately 7 years with scheduled expirations of approximately 6.0% in years 2026 to 2028, 55.0% in years 2029 to 2031, and 39.0% thereafter, in each case excluding any unexercised renewal options. A majority of our leases are issued by the BLM and include renewal options exercisable at our discretion. The standard BLM lease provides an initial ten-year term followed by two five-year renewal options. We currently anticipate exercising renewal options for our leases, including those with near-term scheduled expirations in 2026 to 2028, and we do not expect any material lease expirations in the near term. Additionally, these BLM leases contain acreage that is subject to extension provided certain conditions are met, including a minimum amount of expenditures per acre and the provision of certain geologic information to the BLM, which enables us to extend the lease term for as long as we continue to meet such conditions.

Previous wording

The ownership interests in the land subject to these easements, leases and rights-of-way may be subject to mortgages securing loans or other liens and other easements, lease rights and rights-of-way of third parties that were created prior to our projects’ easements, leases and rights-of-way. As a result, some of our projects’ rights under such easements, leases or rights-of-way may be subject to the rights of these third parties. While we perform title searches, record our interests in the real property records of the projects’ localities and enter into non-disturbance agreements to protect ourself against these risks, such measures may be inadequate to protect against all risk that our rights to use the land on which our projects are or will be located and our projects’ rights to such easements, leases and rights-of-way could be lost or curtailed. Additionally, our operations located on properties owned by others are subject to termination for violation of the terms and conditions of the various easements, leases or rights-of-way under which such operations are conducted.

Current wording

The ownership interests in the land subject to these easements, leases and rights-of-way may be subject to mortgages securing loans or other liens and other easements, lease rights and rights-of-way of third parties that were created prior to our projects’ easements, leases and rights-of-way. As a result, some of our projects’ rights under such easements, leases or rights-of-way may be subject to the rights of these third parties. While we perform title searches, record our interests in the real property records of the projects’ localities and enter into non-disturbance agreements to protect ourselves against these risks, such measures may be inadequate to protect against all risk that our rights to use the land on which our projects are or will be located and our projects’ rights to such easements, leases and rights-of-way could be lost or curtailed. Additionally, our operations located on properties owned by others are subject to termination for violation of the terms and conditions of the various easements, leases or rights-of-way under which such operations are conducted.

Previous wording

As of March 31, 2026, we held approximately 610,000 acres of geothermal leasehold interests across seven jurisdictions, including California, Colorado, Idaho, Nevada, New Mexico, Utah, and Washington, consisting of approximately 65.6% federal leases and approximately 34.4% state or private leases, and a majority of our leases have a 10-year initial term, and in most cases, extension options. Our growth strategy depends on our ability to add to this lease position on acceptable terms. Geothermal lease auctions and negotiated lease processes are becoming more competitive as interest in geothermal development increases among incumbent energy companies, independent developers, and financial investors. We may be out-competed by better-capitalized counterparties—including large integrated energy companies and “super majors” that can bid more aggressively, accept more burdensome terms, or move more quickly in lease processes. Greater competition for attractive acreage could result in higher bonus bids, rentals, royalties, work commitments, or other burdensome lease terms, as well as longer lead times to secure rights. As a result, we may be unable to secure prospective acreage in our target areas, or may be forced to accept higher-cost or less favorable terms than those assumed in our business plan. Moreover, we assembled our current position at a weighted average of approximately $4 per acre during a period of minimal competition between 2019 and 2021, in sharp contrast to current U.S. Bureau of Land Management lease sales in Utah and Nevada, where maximum bids reached $344 and $410 per acre, respectively, in 2025. There is no assurance that we will be able to obtain additional lease rights in the locations, quantities, timing, or at the cost we anticipate, or at all. If we are unable to expand or maintain our lease position at competitive prices, our project pipeline, drilling schedule, and long-term growth plans could be delayed, downsized, or otherwise adversely affected, and our capital intensity and unit costs could increase materially.

Current wording

As of June 30, 2026, we held approximately 630,000 acres of geothermal leasehold interests across seven jurisdictions, including California, Colorado, Idaho, Nevada, New Mexico, Utah, and Washington, consisting of approximately 63.3% federal leases and approximately 36.7% state or private leases, and a majority of our leases have a 10-year initial term, and in most cases, extension options. Our growth strategy depends on our ability to add to this lease position on acceptable terms. Geothermal lease auctions and negotiated lease processes are becoming more competitive as interest in geothermal development increases among incumbent energy companies, independent developers, and financial investors. We may be out-competed by better-capitalized counterparties—including large integrated energy companies and “super majors” that can bid more aggressively, accept more burdensome terms, or move more quickly in lease processes. Greater competition for attractive acreage could result in higher bonus bids, rentals, royalties, work commitments, or other burdensome lease terms, as well as longer lead times to secure rights. As a result, we may be unable to secure prospective acreage in our target areas, or may be forced to accept higher-cost or less favorable terms than those assumed in our business plan. Moreover, we assembled our current position at a weighted average of approximately $4.0 per acre during a period of minimal competition between 2019 and 2021, in sharp contrast to current U.S. Bureau of Land Management lease sales in Utah and Nevada, where maximum bids reached $344.0 and $410.0 per acre, respectively, in 2025. There is no assurance that we will be able to obtain additional lease rights in the locations, quantities, timing, or at the cost we anticipate, or at all. If we are unable to expand or maintain our lease position at competitive prices, our project pipeline, drilling schedule, and long-term growth plans could be delayed, downsized, or otherwise adversely affected, and our capital intensity and unit costs could increase materially.

Previous wording

However, there is no assurance that these forecasts of load growth will be accurate or that the anticipated load growth will occur as projected. Factors such as evolving technology, improvements in energy efficiency, changes in economic conditions, shifts in government policy or regulation, community opposition to data center development, and project delays or cancellations by significant expected offtakers (including data center facilities) could reduce or slow demand for electricity relative to current expectations. If the anticipated load growth fails to materialize, it could have a material adverse effect on our business, financial condition, and results of operations. Reduced need for behind-the-meter power, delayed or cancelled data center builds or increased baseload power on the grid could lead to fewer PPAs with creditworthy offtakers, lower revenue and diminished growth prospects, materially harming our financial condition and operating results.

Current wording

Additionally, there is no assurance that these forecasts of load growth will be accurate or that the anticipated load growth will occur as projected. Factors such as evolving technology, improvements in energy efficiency, changes in economic conditions, shifts in government policy or regulation, community opposition to data center development, and project delays or cancellations by significant expected offtakers (including data center facilities) could reduce or slow demand for electricity relative to current expectations. If the anticipated load growth fails to materialize, it could have a material adverse effect on our business, financial condition, and results of operations. Reduced need for behind-the-meter power, delayed or cancelled data center builds or increased baseload power on the grid could lead to fewer PPAs with creditworthy offtakers, lower revenue and diminished growth prospects, materially harming our financial condition and operating results.

Previous wording

Unlike conventional generators that procure external fuel, our “fuel” is the heat extracted from reservoirs where permeability has been enhanced through stimulation. If reservoir performance does not meet expectations or declines faster than anticipated, whether due to subsurface heterogeneity, thermal drawdown, hydraulic connectivity, mineral scaling, or operational imbalances, available heat may be insufficient to support targeted output or availability. In such cases, we may be required to incur additional capital to drill new wells or laterals, remediate wells, or modify plant operations, and we could be unable to meet fixed minimum performance or availability standards under certain PPAs. Any resulting shortfalls, damages, capacity de‑rates, or termination rights could materially and adversely affect our business, financial condition, results of operations and cash flows. As of March 31, 2026, we had supplier contractual commitments of $496.3 million, which primarily relate to our Cape Station Phase I and Cape Station Phase II facilities.

Current wording

Unlike conventional generators that procure external fuel, our “fuel” is the heat extracted from reservoirs where permeability has been enhanced through stimulation. If reservoir performance does not meet expectations or declines faster than anticipated, whether due to subsurface heterogeneity, thermal drawdown, hydraulic connectivity, mineral scaling, or operational imbalances, available heat may be insufficient to support targeted output or availability. In such cases, we may be required to incur additional capital to drill new wells or laterals, remediate wells, or modify plant operations, and we could be unable to meet fixed minimum performance or availability standards under certain PPAs. Any resulting shortfalls, damages, capacity de‑rates, or termination rights could materially and adversely affect our business, financial condition, results of operations and cash flows. As of June 30, 2026, we had supplier contractual commitments of $488.3 million, which primarily relate to our Cape Station Phase I and Cape Station Phase II facilities.

Previous wording

Our wellfields and operations may be subject to frequent low‑level seismic disturbances, natural or induced. Serious seismic disturbances are possible, including earthquakes, volcanic eruptions and lava flows, and could result in damage to equipment or degraded subsurface resources to such an extent that we could not perform under the PPA for the affected power plant, which in turn could reduce our net income and adversely affect our financial condition and cash flow. Researchers and regulators have identified a potential link between hydraulic‑stimulation activities and seismic events, which may lead to heightened scrutiny and potential litigation in certain jurisdictions.

Current wording

Our wellfields and operations may be subject to frequent low‑level seismic disturbances, natural or induced. Serious seismic disturbances are possible, including earthquakes, volcanic eruptions and lava flows, and could result in damage to equipment or degraded subsurface resources to such an extent that we could not perform under the PPA for the affected power plant, which in turn could reduce our net income and adversely affect our financial condition and cash flow. Researchers and regulators have identified a potential link between hydraulic‑stimulation activities and seismic events, which may lead to heightened scrutiny and potential litigation in certain jurisdictions. Another aspect of geothermal operations is the management and stabilization of subsurface impacts, including ground subsidence or inflation, related to reservoir creation and injection. Inflation and subsidence, if not controlled, can adversely affect agricultural operations and infrastructure at or near the land surface, prompt new permit conditions or setbacks, result in curtailments that impair our ability to perform under affected PPAs, and increase potential exposure to third-party claims.

Previous wording

As of March 31, 2026, we had $189.8 million in aggregate principal amount outstanding under our XRC Facility, Mercuria Credit Facility, and Project Granite Facility. On April 14, 2026, we used the proceeds from the new Project Granite Facility to repay the XRC Facility. The Project Granite Facility is secured by the project-level assets and equity interests of the borrower subsidiaries, contains customary covenants and includes customary events of default, the occurrence of which could result in acceleration of the obligations thereunder or foreclosure on the pledged collateral. Our ability to meet our payment obligations under our existing financing arrangements depends on our future cash flow performance. This is subject to general economic, financial, competitive, legislative and regulatory factors, as well as other factors that may be beyond our control. There can be no assurance that our business will generate positive cash flow from operations, or that additional capital will be available to us, in an amount sufficient to enable us to meet our debt payment obligations and to fund other liquidity needs. If we are unable to generate sufficient cash flow to service our debt obligations, we may need to refinance or restructure our debt, sell assets, reduce or delay capital investments, or seek to raise additional capital. Our ability to refinance our indebtedness will depend on the capital markets and our financial condition at such time. We may not be able to engage in any of these activities or engage in these activities on desirable terms, which could result in a default on our debt obligations. As a result, we may be more vulnerable to economic downturns, less able to withstand competitive pressures and less flexible in responding to changing business and economic conditions. In addition, delays in GeoBlock deployment, interconnection, or permitting within a GeoCluster could affect project-level cash flows and covenant compliance.

Current wording

As of June 30, 2026, we had $242.3 million in aggregate principal amount outstanding under our Mercuria Credit Facility and Project Granite Facility. On April 14, 2026, we used the proceeds from the new Project Granite Facility to repay the XRC Facility. The Project Granite Facility is secured by the project-level assets and equity interests of the borrower subsidiaries, contains customary covenants and includes customary events of default, the occurrence of which could result in acceleration of the obligations thereunder or foreclosure on the pledged collateral. Our ability to meet our payment obligations under our existing financing arrangements depends on our future cash flow performance. This is subject to general economic, financial, competitive, legislative and regulatory factors, as well as other factors that may be beyond our control. There can be no assurance that our business will generate positive cash flow from operations, or that additional capital will be available to us, in an amount sufficient to enable us to meet our debt payment obligations and to fund other liquidity needs. If we are unable to generate sufficient cash flow to service our debt obligations, we may need to refinance or restructure our debt, sell assets, reduce or delay capital investments, or seek to raise additional capital. Our ability to refinance our indebtedness will depend on the capital markets and our financial condition at such time. We may not be able to engage in any of these activities or engage in these activities on desirable terms, which could result in a default on our debt obligations. As a result, we may be more vulnerable to economic downturns, less able to withstand competitive pressures and less flexible in responding to changing business and economic conditions. In addition, delays in GeoBlock deployment, interconnection, or permitting within a GeoCluster could affect project-level cash flows and covenant compliance.

Previous wording

We mitigate tariff risk through diversified sourcing from allied jurisdictions, multi‑year procurement frameworks for ORC and balance‑of‑plant equipment, and a modular development approach that provides scheduling flexibility. Notwithstanding these measures, adverse changes in trade policy or market conditions could still negatively affect our operating results, cash flows, and overall financial performance.

Current wording

Adverse changes in trade policy or market conditions could still negatively affect our operating results, cash flows, and overall financial performance.

Previous wording

We are subject to extensive regulation by North American Electric Reliability Corporation (“NERC”) standards, and non-compliance or changes in these standards could materially and adversely affect our business and operations.

Current wording

We are subject to extensive regulation by North American Electric Reliability Corporation standards, and non-compliance or changes in these standards could materially and adversely affect our business and operations.

Previous wording

Our Class B common stock is beneficially owned by our Co-Founders, Tim Latimer and Jack Norbeck, PhD., who also serve as our Chief Executive Officer and Chief Technical Officer, respectively, whose interests may differ from or conflict with the interests of our other stockholders. Each share of our Class A common stock is entitled to one vote per share. Each share of our Class B common stock is entitled to 40 votes per share. Because of the forty-to-one voting ratio between our Class B and Class A common stock, the holders of our Class B common stock collectively continue to control a significant percentage of the combined voting power of our common stock and therefore are able to control all matters submitted to our stockholders for approval. Our Co-Founders hold all of the issued and outstanding shares of our Class B common stock and, accordingly, beneficially own approximately 2.7% of our outstanding capital stock and control approximately 52.1% of the voting power of our outstanding capital stock. Assuming all outstanding stock options held by the Co-Founders that are vested or will vest within 60 days of April 30, 2026 vest and are exercised, the Co-Founders would control approximately 61.1% of the combined voting power of our outstanding capital stock. As a result, our Co-Founders will have the ability to exercise control over our affairs, including control over the outcome of all matters submitted to our stockholders for approval, including the election of directors and significant corporate transactions. The directors so elected will have the authority, subject to the terms of our indebtedness and applicable rules and regulations, to issue additional stock, implement stock repurchase programs, declare dividends and make other decisions. Our Co-Founders may have interests that differ from yours and may vote in a way with which you disagree and which may be adverse to your interests. For example, our Co-Founders may have a different tax position or other differing incentives from other stockholders that could influence their decisions regarding whether and when to cause us to dispose of assets, incur new or refinance existing indebtedness or take other actions. Additionally, our Co-Founders may cause us to make strategic decisions or pursue acquisitions that could involve risks to you or may not be aligned with your interests.

Current wording

Our Class B common stock is beneficially owned by our Co-Founders, Tim Latimer and Jack Norbeck, PhD., who also serve as our Chief Executive Officer and Chief Technical Officer, respectively, whose interests may differ from or conflict with the interests of our other stockholders. Each share of our Class A common stock is entitled to one vote per share. Each share of our Class B common stock is entitled to 40 votes per share. Because of the forty-to-one voting ratio between our Class B and Class A common stock, the holders of our Class B common stock collectively continue to control a significant percentage of the combined voting power of our common stock and therefore are able to control all matters submitted to our stockholders for approval. Our Co-Founders hold all of the issued and outstanding shares of our Class B common stock and, accordingly, beneficially own approximately 2.6% of our outstanding capital stock and control approximately 52.0% of the voting power of our outstanding capital stock. Assuming all outstanding stock options held by the Co-Founders that are exercisable on or before December 31, 2026 are exercised (2,792,155 shares), the Co-Founders would control approximately 59.6% of the combined voting power of our outstanding capital stock. As a result, our Co-Founders will have the ability to exercise control over our affairs, including control over the outcome of all matters submitted to our stockholders for approval, including the election of directors and significant corporate transactions. The directors so elected will have the authority, subject to the terms of our indebtedness and applicable rules and regulations, to issue additional stock, implement stock repurchase programs, declare dividends and make other decisions. Our Co-Founders may have interests that differ from yours and may vote in a way with which you disagree and which may be adverse to your interests. For example, our Co-Founders may have a different tax position or other differing incentives from other stockholders that could influence their decisions regarding whether and when to cause us to dispose of assets, incur new or refinance existing indebtedness or take other actions. Additionally, our Co-Founders may cause us to make strategic decisions or pursue acquisitions that could involve risks to you or may not be aligned with your interests.

Previous wording

As of June 17, 2026, we had 286,859,562 shares of Class A common stock outstanding and 7,785,412 shares of Class B common stock outstanding. Our Amended Charter authorizes us to issue these shares of Class A common stock and options relating to Class A common stock for the consideration and on the terms and conditions established by our board of directors in its sole discretion, whether in connection with acquisitions or otherwise. We have reserved shares for issuance under the Fervo 2026 Incentive Award Plan (the “2026 Plan”). Any Class A common stock and Class B common stock that we issue, including under the 2026 Plan or other incentive plans that we have adopted or we may adopt in the future, would dilute the percentage ownership held by our existing stockholders. In the future, we may also issue our securities in connection with investments or acquisitions. The number of shares of our Class A common stock issued in connection with an investment or acquisition could constitute a material portion of our then-outstanding common stock. Any issuance of additional securities in connection with investments or acquisitions may result in additional dilution to you.

Current wording

As of August 10, 2026, we had 286,977,787 shares of Class A common stock outstanding and 7,785,412 shares of Class B common stock outstanding. Our Amended Charter authorizes us to issue these shares of Class A common stock and options relating to Class A common stock for the consideration and on the terms and conditions established by our board of directors in its sole discretion, whether in connection with acquisitions or otherwise. We have reserved shares for issuance under the Fervo 2026 Incentive Award Plan (the “2026 Plan”). Any Class A common stock and Class B common stock that we issue, including under the 2026 Plan or other incentive plans that we have adopted or we may adopt in the future, would dilute the percentage ownership held by our existing stockholders. In the future, we may also issue our securities in connection with investments or acquisitions. The number of shares of our Class A common stock issued in connection with an investment or acquisition could constitute a material portion of our then-outstanding common stock. Any issuance of additional securities in connection with investments or acquisitions may result in additional dilution to you.

Previous wording

In connection with our IPO, we and all directors and executive officers and the holders of approximately 99.0% of our outstanding stock and stock options agreed to lock-up restrictions that, subject to certain exceptions, prohibit sales or hedging of our Class A common stock without the prior written consent of J.P. Morgan Securities LLC and BofA Securities, Inc. have reserved 35,107,737 shares under our 2026 Incentive Award Plan that will become eligible for sale once issued. As these shares reach the market, or are perceived as likely to, the market price of our Class A common stock could decline.

Current wording

In connection with our IPO, we and all directors and executive officers and the holders of approximately 99.0% of our outstanding stock and stock options agreed to lock-up restrictions that, subject to certain exceptions, prohibit sales or hedging of our Class A common stock without the prior written consent of J.P. Morgan Securities LLC and BofA Securities, Inc. The lock-up period is expected to expire on or about November 10, 2026. We have reserved 35,107,737 shares under our 2026 Incentive Award Plan that will become eligible for sale once issued. As these shares reach the market, or are perceived as likely to, the market price of our Class A common stock could decline.

Previous wording

These provisions could make it more difficult for a third-party to acquire us, even if the third-party’s offer may be considered beneficial by many of our stockholders. As a result, our stockholders may be limited in their ability to obtain a premium for their shares. See “Description of Capital Stock.”

Current wording

These provisions could make it more difficult for a third-party to acquire us, even if the third-party’s offer may be considered beneficial by many of our stockholders. As a result, our stockholders may be limited in their ability to obtain a premium for their shares.

Previous wording

The choice of forum provision may limit a stockholder’s ability to bring a claim in a judicial forum that it finds favorable for disputes with us or our directors, officers or other employees, which may discourage such lawsuits against us and our directors, officers and other employees and result in increased costs for investors to bring a claim. Alternatively, if a court were to find the choice of forum provision contained in our Amended Charter to be inapplicable or unenforceable in an action, we may incur additional costs associated with resolving such action in other jurisdictions, which could harm our business, results of operations and financial condition. For example, Section 22 of the Securities Act creates concurrent jurisdiction for federal and state courts over all suits brought to enforce any duty or liability created by the Securities Act or the rules and regulations thereunder. Accordingly, there is uncertainty as to whether a court would enforce such a forum selection provision as written in connection with claims arising under the Securities Act. Any person or entity purchasing or otherwise acquiring or holding any interest in shares of our capital stock shall be deemed to have notice of and consented to the forum provisions in our Amended Charter. See “Description of Capital Stock—Exclusive Forum.”

Current wording

The choice of forum provision may limit a stockholder’s ability to bring a claim in a judicial forum that it finds favorable for disputes with us or our directors, officers or other employees, which may discourage such lawsuits against us and our directors, officers and other employees and result in increased costs for investors to bring a claim. Alternatively, if a court were to find the choice of forum provision contained in our Amended Charter to be inapplicable or unenforceable in an action, we may incur additional costs associated with resolving such action in other jurisdictions, which could harm our business, results of operations and financial condition. For example, Section 22 of the Securities Act creates concurrent jurisdiction for federal and state courts over all suits brought to enforce any duty or liability created by the Securities Act or the rules and regulations thereunder. Accordingly, there is uncertainty as to whether a court would enforce such a forum selection provision as written in connection with claims arising under the Securities Act. Any person or entity purchasing or otherwise acquiring or holding any interest in shares of our capital stock shall be deemed to have notice of and consented to the forum provisions in our Amended Charter.
Rearranged previous paragraphs (2)

Previous report — wording carried elsewhere

(Units 2-3) by January 1, 2027, and Cape Station Phase II by June 1, 2028, we will incur liquidated damages under the provisions of the applicable PPA. If we do not commence operations within six months of the applicable PPA COD deadline, our counterparty has the right to terminate the contract. Accordingly, there is significant uncertainty about our ability to maintain profitability and operating cash flows.

Previous report — wording carried elsewhere

Another aspect of geothermal operations is the management and stabilization of subsurface impacts, including ground subsidence or inflation, related to reservoir creation and injection. Inflation and subsidence, if not controlled, can adversely affect agricultural operations and infrastructure at or near the land surface, prompt new permit conditions or setbacks, result in curtailments that impair our ability to perform under affected PPAs, and increase potential exposure to third-party claims.