Skip to main content

enCore Energy Corp.

For the period ended Jun 30, 2026. Filed Aug 13, 2026.

View on SEC.gov

About this filing

A company's report for each of its first three quarters. The financial statements are not audited. It shows how the business has moved since the last annual report, and what management says changed.

Jun 30, 2026 · Filed Aug 13, 2026

EU$0.63-0.2%Stored close · as of Nov 6, 2026

What changed in Management’s Discussion and Analysis?

Read the current filing

Previous report: 10-Q

Period ended 2026-03-31; filed 2026-05-14.

0001628280-26-035003

Item 2. Management's Discussion and Analysis of Financial Condition and Results of Operations

Current report: 10-Q

Period ended 2026-06-30; filed 2026-08-13.

0001628280-26-056452

Item 2. Management’s Discussion and Analysis of Financial Condition and Results of Operations

The baseline is this issuer’s latest earlier reporting period of the same form that was filed before the current report. A previous 10-Q is a different quarter, not a year-over-year comparison. Amendments are excluded.

Compared 105 previous paragraphs and 120 current paragraphs.

39 unchanged; 34 reworded; 37 added; 32 removed; 0 previous and 10 current paragraphs rearranged.

Tables are not compared: 5 previous and 8 current tables excluded. Dates, whitespace, punctuation and numbering changes are ignored; changes to financial figures remain significant.

A changed paragraph is not evidence that risk increased or decreased. An unchanged paragraph does not establish that risk stayed the same.

Added paragraphs (37)

Current report

The following developments are those management believes are most relevant to current and anticipated uranium market conditions and the Company’s business.

Current report

•The U.S. Department of Energy’s (“DOE”) Office of Nuclear Energy is launching an initiative to strengthen the nation’s nuclear fuel supply chain. Through the Defense Production Act (“DPA”) Nuclear Fuel Cycle Consortium, the federal government will work with the domestic nuclear industry to help ensure that the United States has a secure and reliable supply of nuclear fuel for both the existing reactor fleet and the next generation of advanced reactors. Comprised of representatives from more than 90 companies spanning the nuclear industrial base, the consortium will address all facets of the nuclear fuel supply chain, including mining and milling, conversion, enrichment, deconversion, fuel fabrication, recycling, and reprocessing. Under the “Nuclear Dominance-3 by 33” campaign, by 2033 the consortium aims to: (1) catalyze a secure and cost-competitive domestic fuel supply chain; (2) accelerate advanced reactor deployment and help close the nuclear fuel cycle; and (3) explore how the DPA framework can be leveraged to grow and align workforce, financing, innovation and collaboration to support expansion of U.S. nuclear energy.

Current report

•The U.S. Nuclear Regulatory Commission (“NRC”) has accepted for review and docketed the University of Illinois Urbana-Champaign’s application for a construction permit for a research reactor based on NANO Nuclear Energy’s KRONOS Micro Modular Reactor technology. The NRC’s acceptance marks the beginning of the formal licensing process and initiates detailed technical, safety, environmental, and security reviews of the proposed reactor. Acceptance of the application does not constitute approval or issuance of a construction permit. The proposed reactor would be constructed in Champaign County, Illinois, pending completion of the NRC’s review and any subsequent licensing decision.

Current report

•The NRC released a draft Environmental Assessment and draft Finding of No Significant Impact (“FONSI”) concluding that restarting the Crane Clean Energy Center is not expected to result in significant adverse environmental impacts, pending completion of the public comment process and the agency’s final environment review.

Current report

•The DOE announced a conditional $17.5 billion loan commitment to help accelerate the deployment of 10 new Westinghouse AP1000 nuclear reactors at five sites across the United States. The financing is intended to support the purchase of long-lead nuclear components, helping reduce construction timelines by up to three years. Each project is expected to include two reactors and be jointly owned by Westinghouse and a utility or energy company partner. The initiative is intended in part to help meet rapidly growing electricity demand, including that from artificial intelligence data centers.

Current report

•The NRC renewed the operating licenses for the two-unit Diablo Canyon Nuclear Power Plant in California for an additional 20 years, marking the 99th and 100th renewed commercial reactor operating licenses. Pacific Gas & Electric Co.’s Diablo Canyon Units 1 and 2, both pressurized water reactors, are located in Avila Beach, California. Unit 1’s operating license will now expire on November 2, 2044, and Unit 2’s will expire on August 26, 2045. However, operation beyond 2030 will require changes to California state law.

Current report

•The Duane Arnold Energy Center in Iowa could receive the NRC’s package of restart licensing actions by January 2028, according to NRC officials during a public outreach meeting in Cedar Rapids. NextEra Energy announced plans in October 2025 to restart the 601 MWe boiling water reactor. The effort was further supported by a power purchase agreement between NextEra and Google to supply electricity for Google’s Cedar Rapids data center, although the January 2028 licensing target remains subject to the NRC’s review process and regulatory approval.

Current report

•ConverDyn has announced that it has begun analyzing the feasibility of a possible new uranium conversion plant. The Metropolis Works facility in Illinois is currently the only operating commercial uranium conversion facility in the United States. ConverDyn has retained an engineering firm to evaluate how long construction of a new plant would take, the expected cost, and whether a modular design is possible.

Current report

•NextEra Energy and Dominion Energy announced an all-stock merger valued at approximately $67 billion on May 18, 2026, that will create the world’s largest regulated electric utility business by market capitalization. The combined company will operate as NextEra Energy and continue trading on the New York Stock Exchange under the ticker symbol NEE. NextEra is the largest electric utility in the United States by market capitalization while Dominion Energy provides electricity in Virginia, North Carolina, and South Carolina. Together, the two U.S. companies will create “one of the world’s largest energy infrastructure companies, with an unmatched operating platform benefiting customers,” according to NextEra’s press release issued on May 18, 2026. The transaction was unanimously approved by the boards of both companies and is expected to close within 12 to 18 months, subject to regulatory and shareholder approvals.

Current report

•Urenco USA announced plans to expand the capacity of its U.S. uranium enrichment facility by nearly 50%, adding 2.1 million separative work units of capacity. Following the completion of the expansion and ongoing capacity upgrades, the facility’s installed capacity is expected to exceed 7.0 million separative work units.

Current report

•The NRC has granted 20-year license extensions to the Edwin I. Hatch nuclear plant’s two reactors in Georgia. With the extensions, Units 1 and 2 are licensed to operate through August 2054 and June 2058, respectively.

Current report

•The U.S. Energy Information Agency released its annual report on domestic uranium production, finding that U.S. uranium mine production increased from 677,000 pounds U 3 O 8 in 2024 to approximately 1.4 million pounds U3O8 in 2025, the highest annual production since 2017.

Current report

•Santee Cooper, in South Carolina, is moving forward with efforts to restart the construction of Units 2 and 3, both Westinghouse AP1000 reactors, at the V.C. Summer Nuclear Station. The project is currently in the feasibility and development phase, with construction subject to an investment decision.

Current report

•Japan is considering replacing up to five of its aging reactors by the 2040s with a total capacity possibly reaching 5,500 MW. This represents an increase of nearly 20% above existing capacity.

Current report

•The government of Canada is developing a new nuclear strategy, which is expected to be released by the end of the year. According to an official statement by the Canadian government, the new strategy will be structured around four pillars: enabling new builds across Canada, being a global supplier and exporter of choice, expanding uranium production and nuclear fuel opportunities, and developing new Canadian nuclear innovations in fission and fusion.

Current report

Alta Mesa. The Company’s ownership interest is aligned with the current Joint Venture agreement providing for ownership of 70% of Mesteña Grande. The property consists of over 200,000 mostly contiguous acres.

Current report

In May 2026, the first phase of construction on the Upper Spring Creek- Brown satellite facility was completed. This is the largest satellite facility the Company has built to date. The newly constructed portion of the satellite currently can process 1,600 gallons per minute (gpm) through the facility, which represents 50% of the satellite’s planned flow capacity. This new plant is capable of producing from the first wellfield at the Upper Spring Creek Project area. Drilling activities for the first 800-gpm wellfield module are complete, and wellfield infrastructure is almost complete. Drilling and infrastructure activities for the three other 800 gpm modules are underway, with Module 2 drilling activities approximately 90% complete. Uranium extraction can begin as soon as the final authorization is received. Further expansion of the plant is currently underway. Once completed, it is expected to have a total capacity of 3,200 gpm to accommodate any future development or expansion in the immediate area.

Current report

A total of 273 holes have been drilled for the six months ended June 30, 2026, with 104 extraction and monitoring wells installed for Production Authorization Area One (“PAA-1”). The first operational wellfield has been completed and is currently awaiting final authorization for operation. Modules 2, 3 and 4 are expected to be completed before the end of the year.

Current report

In PAA-1, eight additional overlying monitoring wells were installed at the request of the TCEQ in May 2026. A hydrologic pump test and sampling campaign was completed following the installation of these eight wells, and in June 2026, this information was incorporated into a report that was filed with TCEQ. Minor modifications to the Class III Area permit were submitted to accommodate the monitoring wells proximity to the property lines and each other and are currently under TCEQ review.

Current report

TCEQ’s approval of the waste disposal well permit is expected in the third quarter of 2026 and construction is also planned for the third quarter of 2026.

Current report

Radioactive Material License (“RML”) and Area Underground Injection Control (“UIC”) Permit amendments for the Upper Spring Creek Expansion Project onto properties adjacent to the Brown, including Houdmann and Geffer properties, are currently being prepared for submission in the third quarter of 2026. The addition of these adjacent properties will increase the size of the extraction area for additional wellfield development.

Current report

Wellfield development operations at Alta Mesa PAA-8 and PAA-3 extension are ongoing. Monitoring well drilling and installation began in January 2026 at PAA-8 and continues. Wellfield installation at PAA-3 extension has also continued to progress. At least three modules are expected to be completed when the permitting process is completed. Drilling at Alta Mesa for the three and six months ended June 30, 2026 occurred primarily within the two planned production areas: PAA-8 and PAA-3 extension.

Current report

In PAA-8, 435 total holes have been drilled since inception. A total of 219 holes have been drilled for the six months ended June 30, 2026. Of the total wells drilled, 78 wells have been cased and completed, which includes 56 monitor wells and 22 extraction wells. The hydraulic pump test for PAA-8 was completed in March 2026. PAA-8 delineation is ongoing as well as pattern design and construction.

Current report

Development drilling at PAA-3 extension continues and is nearing completion. The PAA-3 extension project began in October 2024, with monitoring well installations occurring in the spring of 2025. During the six months period ended June 30, 2026, 259 holes were drilled, including 63 holes cased and 51 holes cased and completed to date. As of the six months period ended June 30, 2026, a total of 177 delineation holes had been drilled.

Current report

The Alta Mesa RML is in timely renewal, and a second request for additional information regarding the Alta Mesa RML renewal was received from TCEQ in June 2026.

Current report

The PAA-3 extension production area authorization amendment was submitted to the TCEQ in May 2026. The Company is awaiting formal notice of comments per TCEQ’s administrative review process.

Current report

The PAA-8 production area authorization application was submitted to the TCEQ in June 2026. The Company is currently awaiting the TCEQ permit review.

Current report

Permitting applications and other documents are currently being prepared to expand the Alta Mesa project into the adjacent Alta Mesa East project area, currently under exploration. This includes an expanded aquifer exemption, an expanded area underground injection control permit and an amendment to the RML to allow for wellfields on contiguous property. Ecological surveys have been completed in the Alta Mesa East area, and reconnaissance mapping has been completed to identify all surface water impoundments and groundwater wells to be used for baseline water quality sampling.

Current report

Preliminary engineering has been initiated for the Dewey Burdock plant site, evaporation ponds, and deep disposal well. The EPA Class III & V Underground Injection Control permits were received in October 2025, and the Bureau of Land Management Plan of Operations was approved on June 15, 2026.

Current report

The Company received final approval from the NRC for the 20-year license renewal, which was originally issued in 2014. As part of the license renewal process, the Environmental Assessment (“EA”), Finding of No Significant Impact FONSI and Section 106 Programmatic Agreement for the Dewey-Burdock Initial Infrastructure Development Plan of operations were approved on June 16, 2026, and were publicly issued on June 22, 2026. The Final Safety Evaluation Report (“SER”) was completed, and the NRC issued the renewed 20-year source materials license on June 30, 2026. On June 17, 2026, the NRC published Federal Register notice FR 36623 announcing issuance of the final EA, SER, and FONSI for SUA-1600. Completion of these actions occurred four days ahead of the FAST-41 scheduled completion date of June 22, 2026.

Current report

On June 15, 2026, the Company submitted an application to the South Dakota Department of Agriculture and Natural Resources for the Madison and Inyan Kara water appropriations permits and a revision of the Large Surface Mine Permit. As part of the permit revision process, Western Water Consultants have been engaged to update wildlife surveys in support of the application.

Current report

The Company continues to be impacted by delays in the permitting approval process associated with its assets in South Texas, including Alta Mesa and Upper Spring Creek. These delays have resulted in reduced overall production estimates for the year ending December 31, 2026. The Company has maintained its focus on developing its wellfields and has chosen to reduce its rig activity to better align its operational needs and strategic objectives. Beginning in April 2026, the Company began reducing its overall headcount by approximately 20%. As a result of the workforce reduction, the

Current report

Company expects to see annualized cost savings to its overall operations and general and administrative expenses compared to the year ended December 31, 2025.
Removed paragraphs (32)

Previous report

•In January 2026, the DOE awarded $900 million each to Centrus Energy Corp., General Matter, Inc. and Orano. Distribution of the $2.7 billion award is contingent on specific milestones and is aimed at supporting the expansion of US domestic enrichment capacity. According to DOE’s task order, most of the funds will be directed toward construction of high-assay low enriched uranium enrichment capacity while also providing funds for additional low-enriched uranium capacity.

Previous report

•On January 15, 2026, U.S. Senators Jeanne Shaheen and Todd Young alongside U.S. Representatives Rob Wittman and John Moolenaar, introduced new bipartisan, bicameral legislation to support domestic supply chains for critical minerals to meet national and economic security needs through the creation of a new Strategic Resilience Reserve (SRR). This announcement along with President Donald Trump’s signing the proclamation on January 14, 2026 to also address national security threats posed by imports of processed critical minerals and their derivative products, shows a coordinated policy push toward strengthening the U.S. critical mineral security.

Previous report

•During the three months ended March 31, 2026, the U.S. Nuclear Regulatory Commission (NRC) formally announced a major agency-wide reorganization to streamline decision making, consolidate functions, and align with national goals for a more efficient licensing and deployment of safe and innovative nuclear technology. The agency will reorganize around three core business lines, new reactors, operating reactors, and nuclear materials and waste.

Previous report

•In January 2026, U.S based tech company Meta signed deals with existing and new nuclear power providers to supply up to 6.6 giga watt of nuclear power by 2035. Meta stated the deals will provide ongoing collaboration with electric utility companies and power providers to meet the electricity demand for data centers it intends to bring online and will create in the next decade.

Previous report

•U.S. energy company Vistra has entered into 20-year power purchase agreement to provide more than 2,600 mega watts of zero-carbon energy from a combination of three different Vistra nuclear power plants to support Meta's operations. Meta said its deal with Vistra involves more than 2.1 giga watts of power from Vistra’s Beaver Valley Nuclear Power Plant in the state of Pennsylvania and its Perry and David-Besse Nuclear Power Plants in Ohio, in addition to uprates at the Ohio plants. Meta's purchases under the agreements will begin in late 2026, with additional capacity added to the grid through 2034, when the full 2,609 mega watts of power will be online.

Previous report

•On January 26, 2026, U.S. nuclear fuel supplier Centrus Energy, along with the state of Tennessee, announced the planned expansion in the state, transitioning its Oak Ridge facility to a "high-rate manufacturing plant." As part of the expansion, Centrus plans to invest more than $560 million in Anderson County, Tennessee over the next several years to support the investment in the production of thousands of advanced centrifuges.

Previous report

•U.S. based nuclear services company, Energy Solutions has submitted a notice of intent to the U.S. Nuclear Regulatory Commission confirming plans to apply for a “major licensing action” for new nuclear generation at the shuttered Kewaunee Power Station in the state of Wisconsin.

Previous report

•U.S. based Solstice Advanced Materials announced plans to expand uranium conversion production at its Metropolis Works Facility, in the state of Illinois, the sole United States uranium conversion facility. The additional production will bring the plant capacity to 10,000 tonnes of uranium fluorine.

Previous report

•For the first time in a decade, the NRC has approved the construction of a new commercial nuclear reactor—Unit 1 at TerraPower’s Kemmerer Power Station in the state of Wyoming.

Previous report

•Centrus Energy and Palantir Technologies Inc. have announced a partnership that will apply Palantir's artificial intelligence software to Centrus' expansion of its uranium enrichment capacity in the state of Ohio.

Previous report

•Arizona Public Service has officially notified the NRC of its intent to renew the operating licenses for all three units at its Palo Verde Generating Station in Arizona, which could extend operations from the mid-2040s through the mid-2060s.

Previous report

•On March 14, 2026, GE Vernova and Hitachi, Ltd. have entered a Memorandum of Understanding (MoU) to explore opportunities to deploy the BWRX-300 small modular reactor in Southeast Asia.

Previous report

•Japan announced that it is scrapping the safety screening for two reactors at the Hamaoka Nuclear Power Plant in central Japan, after plant operator Chubu Electric Power Co. was found to have fabricated data about earthquake risks.

Previous report

Total measured and indicated mineral resources 30.94 million lbs U 3 O 8

Previous report

Total inferred mineral resources 20.54 million lbs U 3 O 8

Previous report

The Company’s strategy over the next three years is centered around two of its fully licensed Texas CPPs: Rosita and Alta Mesa. The CPPs located at the Rosita and Alta Mesa projects are designed for processing feed resin from relocatable satellite IX plants employed at various deposits within several hundreds of miles of each plant. The Rosita CPP was the starting point for the Company’s Texas extraction strategy. The Rosita CPP facility is in partial standby while feeding solution from active groundwater reclamation. Rosita is located approximately 60 miles from Corpus Christi, Texas and has an 800,000-pound U 3 O 8 per year processing capacity.

Previous report

In February 2023, the Company acquired 100% of the Alta Mesa Uranium Project and the Mesteña Grande Uranium Project from Energy Fuels Inc., for $120 million. The Company’s fully licensed Alta Mesa CPP is located approximately 100 miles southwest of Corpus Christi, Texas, and has a production capacity of 1.5 million pounds of U 3 O 8 per year through its IX system located at the plant. The facility has elution, precipitation, drying, and packaging capacity for 2.0 million pounds of U 3 O 8 per year. This plant is designed to accept direct production feed to the IX columns in the plant and concurrently accept loaded resin from satellite locations, once the resin transfer system has been installed and permitted. The Alta Mesa Project includes existing and near-term Production Area Authorization (“PAA”), including fully permitted and authorized PAA-6 and PAA-7. The Mesteña Grande Uranium Project has additional inferred mineral resource areas that will require significant additional exploration drilling. In total, the Alta Mesa Uranium Project combined with the Mesteña Grande Uranium Project encompasses mineral leases on over 200,000 acres of private land.

Previous report

In June 2024, the Company announced the successful startup of uranium extraction operations at the Alta Mesa Project. The initial ramp-up was a progressive process to advance and continue increased uranium extraction via direct feed to the Alta Mesa CPP. Final installation of PAA-7 was fully completed during the three months ended March 31, 2026 and extraction is continuing from this wellfield. The second IX circuit at the Alta Mesa CPP was brought online in early 2025 and extraction continues through both IX circuits

Previous report

In 2025, the Company announced new uranium discoveries made in areas in or near existing wellfields. These discoveries have been made as a result of a major ongoing re-analysis of thousands of historic drill holes that began in April 2025 across the Alta Mesa ISR Uranium Project. This more granular and detailed evaluation has identified uranium mineralized roll fronts. Follow up delineation drilling by the Company has identified new areas of mineralization which will require additional permitting prior to uranium extraction.

Previous report

This additional roll front uranium mineralization has been discovered in close proximity to known and already exploited roll fronts. One of these new roll fronts has progressed to the point that monitor wells have now been installed and completed. Installation of the extraction wells and infrastructure are ongoing and expected to be online as soon as permitting is completed. Mineralized roll fronts have also been found overlying the past productive mineralization in PAA-4 with at least two new roll fronts discovered to date. This newly discovered mineralization lies at a depth of 320 to 345 feet, almost 200 feet above the previously exploited roll front. This shallow mineralization makes for shorter drill times with less footage required, less cement and shorter casing intervals resulting in significant cost savings in delineation and extraction versus deeper mineralization. Monitor wells have also been installed in this wellfield which will be designated as PAA-8. Permitting activities are continuing as well as delineation drilling activity. This granular re-analysis of previous drill data is expected to continue through 2026.

Previous report

The Kingsville Dome CPP will require refurbishment and licensing prior to commencement of operations.

Previous report

The Company has an experienced technical team with years of experience in ISR operations in Texas, Wyoming, and Nebraska supporting and managing our operations. We have been able to utilize our experience to self-execute the refurbishment of the Rosita and Alta Mesa CPPs, along with the design, construction and installation of infrastructure for three wellfields and two satellite IX facilities over a period of three years.

Previous report

Each of the Company’s production facilities maintain several permits and licenses in order to manage the current operations. For the Company’s operating locations, permits and licenses remain current and in effect. In specific cases, some of those permits and licenses are in renewal, and for some expansion activities, new permits or amendments will be necessary. All of our South Texas facility ISR and underground injection operations are regulated by the TCEQ and the Radioactive Material Licenses (“RMLs”) for Rosita and Alta Mesa are issued by the TCEQ under the NRC Agreement State Program that assures that a mature and consistent regulatory process is in place to provide more certainty regarding regulatory approvals.

Previous report

Currently, at Alta Mesa, the RML and the Class III UIC Area Permit are in timely renewal and under technical review by the TCEQ, but those do not affect current activities. At Upper Spring Creek, the TCEQ has issued the Class III UIC Area Permit, and the agency has approved the expansion of the Rosita RML to incorporate the Upper Spring Creek wellfield and satellite IX facility into the current license activities. Construction of the satellite and wellfield at Upper Spring Creek is near completion. Remaining permits needed to begin operations are the PAA and the Class I Waste Disposal Well permit, both of which are under review by the TCEQ as of March 31, 2026.

Previous report

In addition to the Company’s operations in South Texas, it is also developing pipeline projects in other states. The advanced stage Dewey Burdock Uranium Project in South Dakota has demonstrated ISR resources, including a 2024 S-K 1300 Technical Report Summary and Canadian National Instrument 43-101 Technical Report and Preliminary Economic Analysis. The project has its source material license from the NRC and its underground injection permits and aquifer exemption from the EPA. In April 2024, the Company submitted its application to renew the ten-year-old Source Material License, SUA-1600. The NRC has confirmed that the Dewey Burdock Source Material License is in timely renewal. The underground injection permits were appealed to the EPA’s Environmental Appeals Board (“EAB”) and the aquifer exemption was appealed to the 8th Circuit Court of Appeals. On September 16, 2025, the Company announced that the EAB denied in full a petition for review filed by the Oglala Sioux Tribe, Black Hills Clean Water Alliance, and NDN Collective against the EPA’s issuance of Class III and Class V UIC permits for the Dewey Burdock Project in South Dakota.

Previous report

In September 2025, the Company announced the Dewey Burdock Project had been approved for inclusion in the Fast-41 Program by the Permitting Council. This is a component of the implementation of President Trump’s Executive Order on Immediate Measures to Increase American Mineral Production. The Dewey Burdock Project received its Source and Byproduct Materials License in 2014, from the NRC, now under timely renewal, and will work with the NRC as the lead agency for federal permitting. The Company’s objective is to advance the Dewey Burdock Project into development and operation utilizing the ISR uranium extraction process.

Previous report

Under the Executive Order, the Permitting Council identifies priority infrastructure and critical mineral projects to receive accelerated permitting review. The addition of the first South Dakota ISR project supports the domestic uranium production focus of the United States. This focus enables the development of essential clean energy, extracted through environmentally responsible ISR technology, to provide affordable, reliable domestic energy.

Previous report

The Gas Hills Project is an advanced uranium project located in central Wyoming, approximately 60 miles west of Casper. Our Gas Hills Project is located in the historic Gas Hills Uranium District in the brownfield area of previous extensive production.

Previous report

In 2024, we disclosed that the Company initiated exploration drilling on the Dewey Terrace Project area. The near term goal of this drilling is designed to not only define the extent of the Dewey Terrace project mineralization but also determine its eastern extent and potential to connect with our Dewey Burdock deposit just across the state line in South Dakota.
Reworded paragraphs (34)

Previous wording

enCore Energy Corp., America’s Clean Energy Company™, was incorporated on October 30, 2009, under the Laws of British Columbia and is a reporting issuer in all of the provinces and territories of Canada. As of January 1, 2025, the Company ceased to be a “foreign private issuer” and has become a “domestic issuer” within the meanings under the Exchange Act. As a result, the Company must comply with the filing deadlines and disclosure obligations of a domestic issuer and non-accelerated filer as set forth in the Exchange Act. This classification impacts the timing of our periodic filings, internal control assessments, and other regulatory requirements. The Company’s common shares are listed on Nasdaq Capital Market LLC (“Nasdaq”) and the TSX Venture Exchange (“TSX-V”) under the trading symbol EU.

Current wording

enCore Energy Corp., America’s Clean Energy Company™, was incorporated on October 30, 2009, under the Laws of British Columbia and is a reporting issuer in all of the provinces and territories of Canada. As of January 1, 2025, the Company ceased to be a “foreign private issuer” and has become a “domestic issuer” within the meanings under the Exchange Act. As a result, the Company must comply with the filing deadlines and disclosure obligations of a domestic issuer and non-accelerated filer as set forth in the Exchange Act. This classification impacts the timing of our periodic filings, internal control assessments, and other regulatory requirements. The Company’s common shares are listed on the Nasdaq Capital Market LLC (“Nasdaq”) and the TSX Venture Exchange (“TSX-V”) under the trading symbol EU.

Previous wording

The Company is focused on extracting domestic uranium within the United States. The Company utilizes only proven ISR technology to provide necessary fuel for the generation of clean, reliable, and carbon-free nuclear energy. In 2023, the Company commenced uranium extraction in South Texas. The Company’s strategy is to build uranium extraction capacity by developing and placing into operation a series of uranium extraction facilities in South Texas, followed by a future pipeline of exploration projects in South Dakota and Wyoming, becoming a leading supplier of domestic uranium to fuel a growing demand for clean energy generation using nuclear power.

Current wording

The Company is focused on extracting domestic uranium within the United States. The Company utilizes proven in-situ recovery (“ISR”) technology to produce uranium for use in the generation of reliable, carbon-free nuclear energy. In 2023, the Company commenced uranium extraction in South Texas. The Company’s strategy is to build uranium extraction capacity by developing and placing into operation a series of uranium extraction facilities in South Texas, followed by a future pipeline of exploration projects in South Dakota and Wyoming, becoming a leading supplier of domestic uranium to fuel a growing demand for clean energy generation using nuclear power.

Previous wording

The primary use of uranium is to fuel nuclear power plants for the generation of carbon and emission free electricity. According to the World Nuclear Association (“WNA”), as of April 2026, there were 438 operable nuclear reactors world-wide, which required approximately 178 to 180 million pounds of U 3 O 8 annually at full operation. According to data from TradeTech LLC (“TradeTech”), the world continues to require more uranium than it produces from primary extraction. The gap between demand and primary supply is being filled by stockpiled inventories and secondary supplies, which the Company believes have dwindled significantly in recent years.

Current wording

The primary use of uranium is to fuel nuclear power plants for the generation of carbon and emission free electricity. According to the World Nuclear Association, as of April 2026, there were 438 operable nuclear reactors world-wide, which required approximately 178 to 180 million pounds of U 3 O 8 annually at full operation. According to data from TradeTech LLC, the world continues to require more uranium than it produces from primary extraction. The gap between demand and primary supply is being filled by stockpiled inventories and secondary supplies, which the Company believes have dwindled significantly in recent years.

Previous wording

Expanding the current reactor fleet to meet the levels of electrical generating capacity remains a significant challenge to the nuclear industry. To meet those goals, the global industry must protect existing capacity, and there have been multiple public pronouncements from several countries, including the United States to protect existing nuclear generating capacity. In the United States, as a result of clean energy credits granted by several states and the production tax credit for nuclear power provided in the Inflation Reduction Act of 2022, several nuclear utilities have announced operating life extensions and capacity expansions within their existing operating fleet. Also, the industry has seen an unprecedented trend in reactor recommissioning. In the United States, where just a few years ago reactors were being shut down prematurely, nuclear plants such as Palisades, Three Mile Island, and Duane Arnold are positioned to re-enter service.

Current wording

Expanding the current reactor fleet to meet anticipated future levels of electrical generating capacity required remains a significant challenge to the nuclear industry. To meet those goals, the global industry must protect existing capacity, and there have been multiple public pronouncements from several countries, including the United States, to protect existing nuclear generating capacity. In the United States, as a result of clean energy credits granted by several states and the production tax credit for nuclear power provided in the Inflation Reduction Act of 2022, several nuclear utilities have announced operating life extensions and capacity expansions within their existing operating fleet. Also, the industry has seen an unprecedented trend in reactor recommissioning. In the United States, where just a few years ago reactors were being shut down prematurely, nuclear plants such as Palisades, Three Mile Island (“Crane Clean Energy Center”), and Duane Arnold are positioned to re-enter service.

Previous wording

During the three months ended March 31, 2026, the Company completed uranium sales totaling 270,000 pounds of U 3 O 8, not including converter and transaction costs, for an average sales price of $67.78 per pound of U 3 O 8.

Current wording

During the six months ended June 30, 2026, the Company completed uranium sales totaling 485,000 pounds of U 3 O 8, not including converter and transaction costs, for an average sales price of $70.10 per pound of U 3 O 8.

Previous wording

enCore’s uranium sales strategy provides a base level of projected income from sales contracts while preserving a significant ability to realize opportunities when strong short-term market fundamentals are present.

Current wording

The Company’s uranium sales strategy provides a base level of projected income from sales contracts.

Previous wording

The Company has been able to use improving uranium market conditions to create a balanced uranium sales agreement portfolio, to provide multiple pricing structures to support future market changes and support production plans. As of March 31, 2026, we have executed fourteen uranium sales agreements to supply uranium to nuclear power plants in the United States and one legacy uranium sales agreement with a uranium trading company. enCore’s uranium sales agreement portfolio is a mix of market related pricing, hybrid base price and market related pricing, base escalated pricing, and fixed prices. Of enCore’s fourteen current uranium sales agreements, two are market-related with no floors or ceilings and eight are market related that typically retain exposure to spot pricing, while including minimum floor and maximum ceiling prices, some of which are adjusted upwards periodically for inflation. Minimum floor prices are set at levels that provide the Company with a comfortable margin over its expected costs of operations in Texas while still allowing the Company to participate in anticipated escalations of the price of uranium. The Company will continue to assess opportunities to secure future sales agreements that will support its continued project and production growth strategies. The Company is committed to honoring all sales commitments.

Current wording

The Company has been able to use improving uranium market conditions to create a balanced uranium sales agreement portfolio, providing multiple pricing structures to support future market changes and extraction plans. As of June 30, 2026, we have executed fourteen uranium sales agreements to supply uranium to nuclear power plants in the United States and one legacy uranium sales agreement with a uranium trading company. enCore’s uranium sales agreement portfolio is a mix of market related pricing, hybrid base price and market related pricing, base escalated pricing, and fixed prices. The Company has fourteen current uranium sales agreements, two are market-related with no floors or ceilings and eight are market related that typically retain exposure to spot pricing, while including minimum floor and maximum ceiling prices, some of which are adjusted upwards periodically for inflation. Minimum floor prices are set at levels that provide the Company with a comfortable margin over its expected costs of operations in Texas while still allowing the Company to participate in anticipated escalations of the price of uranium. The remaining agreements are fixed or a hybrid of both, fixed and market. The Company will continue to assess opportunities to secure future sales agreements that will support its continued project and extraction growth strategies. The Company is committed to honoring all sales commitments.

Previous wording

Our website is located at www.encoreuranium.com. From time to time, we may use our website as a distribution channel for ongoing updates for the company and material company information.

Current wording

Our website is www.encoreuranium.com. From time to time, we may use our website as a distribution channel for ongoing updates for the company and material company information.

Previous wording

enCore controls key mineral properties within the United States, in Texas, South Dakota, Wyoming and New Mexico. Our plants’ operations are designed and permitted to process uranium from a mix of satellite plants and primary sources within south Texas.

Current wording

enCore controls key mineral properties within the United States, primarily in Texas, South Dakota and Wyoming. Our current Central Processing Plants’ (“CPP”) operations are designed and permitted to process uranium from a mix of satellite ion exchange (“IX”) plants and primary sources within south Texas.

Previous wording

The South Texas Integrated ISR Project is an Exploration Stage Property, as defined by S-K 1300, which consists of five project areas: the Rosita Central Processing Plant (“Rosita CPP”), Butler Ranch Uranium ISR Project (“Butler Ranch”), Upper Spring Creek - Brevard Area ISR Uranium Project (“USC – Brevard or Brevard”), Upper Spring Creek - Brown Area ISR Uranium Project (“USC – Brown or Brown”), and Rosita South Cadena ISR Project (“RS – Cadena or Cadena”).

Current wording

The South Texas Integrated ISR Project is an Exploration Stage Property, as defined by S-K 1300, which consists of five project areas: the Rosita Central Processing Plant (“Rosita CPP”), Butler Ranch Uranium ISR Project, Upper Spring Creek - Brevard Area ISR Uranium Project, Upper Spring Creek - Brown Area ISR Uranium Project inclusive of the Brown and adjacent properties (“USC – Brown or Brown”), and Rosita South Cadena ISR Project. The Company owns 100% interest in the South Texas Integrated ISR Project which is located on over 7,074 acres of private land in the state of Texas.

Previous wording

The Alta Mesa Uranium Project (“Alta Mesa”) is an Exploration Stage Property, as defined by S-K 1300, and is a fully licensed and constructed ISR project and central processing facility, located on over 4,597 acres of private land in the state of Texas.

Current wording

The Alta Mesa Uranium Project (“Alta Mesa”) is an Exploration Stage Property, as defined by S-K 1300, and is a fully licensed and constructed ISR project and CPP, located on over 4,597 acres of private land in the state of Texas. The Company’s ownership interest is aligned with the current Joint Venture agreement providing for ownership of 70% of the Alta Mesa project.

Previous wording

The Mesteña Grande Uranium Project (“Mesteña Grande”) is an Exploration Stage Property, as defined by S-K 1300, located in Brooks and Jim Hogg Counties, Texas and is on land located adjacent to, and to the south, north, and west of the Alta Mesa Uranium Project. The Company owns a 100% interest in the Mesteña Grande project. The property consists of over 200,000 mostly contiguous acres over an approximate area of 35 miles in a north-south direction by 30 miles in an east-west direction.

Current wording

The Mesteña Grande Uranium Project (“Mesteña Grande”) is an Exploration Stage Property, as defined by S-K 1300, located in Brooks and Jim Hogg Counties, Texas and is on land located adjacent to, and to the south, north, and west of

Previous wording

The Dewey Burdock Project is an Exploration Stage Property, as defined by S-K 1300, located in southwest South Dakota and is part of the northwestern extension of the Edgemont Uranium Mining District. The Company owns 100% interest in the Dewey Burdock Project. The project includes federal claims, private mineral rights and private surface rights controlling the entire area within the licensed project permit boundary as well as surrounding areas. The Company currently controls approximately 16,962 acres of net mineral rights and 12,613 acres of surface rights.

Current wording

The Dewey Burdock Project is an Exploration Stage Property, as defined by S-K 1300, located in southwest South Dakota and is part of the northwestern extension of the Edgemont Uranium Mining District. The Company owns a 100% interest in the Dewey Burdock Project. The project includes federal claims, private mineral rights and private surface rights controlling the entire area within the licensed project permit boundary as well as surrounding areas. The Company currently controls approximately 16,962 acres of net mineral rights and 12,613 acres of surface rights.

Previous wording

The Gas Hills Project, as defined by S-K 1300, is an Exploration Stage Property located in Wyoming. The Company owns a 100% interest in the Gas Hills Project located in the historic Gas Hills Uranium District 45 miles east of Riverton, Wyoming. The Gas Hills Project consists of approximately 1,280 surface acres and 12,960 net mineral acres of unpatented lode claims, a State of Wyoming mineral lease, and private mineral leases, within a brownfield site which has experienced extensive uranium development including extraction and mill site production.

Current wording

The Gas Hills Project, as defined by S-K 1300, is an Exploration Stage Property located in Wyoming. The Company owns a 100% interest in the Gas Hills Project located in the historic Gas Hills Uranium District 45 miles east of Riverton, Wyoming. The Gas Hills Project consists of approximately 1,280 surface acres and 12,960 net mineral acres of unpatented lode claims, a State of Wyoming mineral lease, and private mineral leases, all within a brownfield site which has experienced extensive uranium development.

Previous wording

Exploration activities are currently being conducted on properties located adjacent to, and to the east of, the Alta Mesa mine site as part of our Alta Mesa East exploration project. The Alta Mesa East prospect consists of 5,900 acres of private, trust-owned mineral lease with approximately 4,897 acres of individual surface leases.

Current wording

Exploration activities are currently being conducted on properties located adjacent to, and to the east of, the Alta Mesa mine site as part of our Alta Mesa East exploration project which began in November 2025. The Alta Mesa East prospect consists of 5,900 acres of private, trust-owned mineral leases with approximately 4,897 acres of individual surface leases.

Previous wording

The Company’s exploration plan utilizes wide-spaced (800-1600 feet) drill spacing for regional assessment, and closer-spaced drillholes (400-500 feet) with closer offsets in areas of discovered mineralization. Uranium mineralization has been discovered within five primary sands beneath the site. Drilling is expected to continue throughout 2026 and beyond. Completed drilling results, geologic interpretation, and mineral resource assessments are pending.

Current wording

The Company’s exploration plan utilizes wide-spaced (800-1600 feet) drill spacing for regional assessment and closer-spaced drillholes (400-500 feet) with even closer offsets in areas of discovered mineralization. Uranium mineralization has been discovered within five primary sands beneath the site. Exploration drilling is expected to continue throughout 2026. Ongoing drilling results continue to advance the geologic model and mineral resource assessment.

Previous wording

The Company is focused on extracting uranium in the United States and delivering that uranium to customers. The Company currently utilizes only the proven ISR technology to provide necessary fuel for the generation of clean, reliable, and carbon-free nuclear energy.

Current wording

The Company is focused on extracting domestic uranium within the United States. The Company utilizes proven ISR technology to produce uranium for use in the generation of reliable, carbon-free nuclear energy.

Previous wording

enCore owns 3 of the 11 licensed and constructed CPPs in the United States. The Company has several key mineral resource projects in other jurisdictions within the United States. Our S-K 1300 compliant resources are listed below:

Current wording

enCore owns 4 of the 13 constructed and existing ISR production-facilities in the United States. The Company has several key mineral resource projects in other jurisdictions within the United States. Our S-K 1300 compliant resources are listed below:

Previous wording

•Revenue - Revenue from uranium sales for the three months ended March 31, 2026, was $18,301 compared to revenue of $18,239 for the three months ended March 31, 2025, an increase of $62 or 0%. Revenue recognized for the three months ended March 31, 2026 was consistent with the same period in 2025, as an approximately 7% decrease in sales volume was largely offset by an approximately 8% increase in sales prices. The realized sales prices per pound of uranium for the three months ended March 31, 2026 and 2025 were $67.78 and $62.89, respectively, and included the contractual sales price less sales-related costs. The realized sale price per pound increase is dictated by the market for uranium, which is a commodity.

Current wording

•Revenue - Revenue from uranium sales for the three months ended June 30, 2026, was $15,696 compared to revenue of $3,664 for the three months ended June 30, 2025, an increase of $12,032 or 328%. Revenue recognized for the three months ended June 30, 2026, was driven by the increased sales volume of 155,000 pounds and a 20% increase in sales price. The realized sales prices per pound of uranium for the three months ended June 30, 2026 and 2025, were $73.00 and $61.07, respectively, and included the contractual sales price less sales-related costs. The realized sale price per pound increase is dictated by the market for uranium, which is a commodity.

Previous wording

•Cost of Sales - Costs applicable to uranium sales were $18,365 for the three months ended March 31, 2026, related to the completed sale of 270,000 pounds of uranium at a weighted average cost of $68.02 per pound compared to uranium costs of $18,262 for the sale of 290,000 pounds at a weighted average cost of $62.97 per pound for the three months ended March 31, 2025. The increase in costs was the result of more sales placed of purchased uranium at a higher price versus extracted uranium at a lower market price. The Company’s weighted average cost components include the cost of purchased uranium and uranium from extraction. See Costs of U 3 O 8 Sold table below for more information.

Current wording

•Cost of Sales - Costs applicable to uranium sales were $18,272 for the three months ended June 30, 2026, related to the completed sale of 215,000 pounds of uranium at a weighted average cost of $84.99 per pound compared to uranium costs of $2,534 for the sale of 60,000 pounds at a weighted average cost of $42.23 per pound for the three months ended June 30, 2025. The increase in costs was the result of more sales of purchased uranium at a higher price versus extracted uranium at a lower price. The Company’s weighted average cost components include the cost of purchased uranium and uranium from extraction. See Costs of U 3 O 8 Sold table below for more information.

Previous wording

•Interest income - Interest income for the three months ended March 31, 2026, and March 31, 2025, was $386 and $279, respectively. The increase was primarily driven by the increase in cash held in brokerage and bank accounts.

Current wording

•Interest income - Interest income for the three months ended June 30, 2026 and June 30, 2025, was $272 and $201, respectively. The increase was primarily driven by the increase in cash held in brokerage and bank accounts.

Previous wording

•Interest expense - Interest expense for the three months ended March 31, 2026 and March 31, 2025, was $1,815 and $346, respectively. The increase is primarily driven by the interest expense related to the new Convertible Senior Notes. See Note 15 - Debt for more information.

Current wording

•Interest expense - Interest expense for the three months ended June 30, 2026 and June 30, 2025, was $1,819 and $240, respectively. The increase is primarily driven by the interest expense related to the new Convertible Senior Notes. See Note 15 - Debt for more information.

Previous wording

•Loss on marketable securities, unrealized - The Company recognized a loss of $10,048 on the fair value of marketable securities, unrealized for the three months ended March 31, 2026, compared to a loss of $9,876 for the three months ended March 31, 2025. Unrealized losses for the three months ended March 31, 2026 and 2025 are due to unfavorable market conditions for the respective periods.

Current wording

•Gain/Loss on marketable securities, unrealized - The Company recognized a loss of $15,870 on the fair value of marketable securities, unrealized for the three months ended June 30, 2026, compared to a gain of $2,810 for the three months ended June 30, 2025. Unrealized losses for the three months ended June 30, 2026, are due to unfavorable market conditions.

Previous wording

•Gain on marketable securities, realized - The Company recognized a gain of $3,840 on the fair value of marketable securities, realized for the three months ended March 31, 2026, as a result of the sale of common shares compared to no gain on marketable securities for the three months ended March 31, 2025.

Current wording

•Gain on marketable securities, realized - The Company recognized a gain of $2,298 on the fair value of marketable securities, realized for the three months ended June 30, 2026, as a result of the sale of common shares compared to a gain on marketable securities of $7,671 for the three months ended June 30, 2025.

Previous wording

•Operating expenses - Operating expenses include selling, general and administrative and stock compensation expense. Operating expenses for the three months ended March 31, 2026, were $10,021 as compared to $15,603 for the three months ended March 31, 2025. This decrease primarily reflects the gain on sale of mineral properties as a result of the sale of NM Energy Canada’s mineral properties and intangible assets in 2026 offset by increased activity levels the Company is experiencing in 2026. The increased activity levels is driven primarily by the increased drilling at Alta Mesa and Upper Spring Creek.

Current wording

•Operating expenses - Operating expenses include selling, general and administrative, mineral property expenditures, depreciation, depletion, amortization, and stock compensation, and are impacted by gains recognized on the sale of mineral property expenditures. Operating expenses for the six months ended June 30, 2026, were $16,897 as compared to $36,011 for the six months ended June 30, 2025. This decrease primarily reflects the gain on sale of mineral properties as a result of the sale of NM Energy Canada’s mineral properties and intangible assets in 2026, offset by increased activity levels the Company is experiencing in 2026. The increased activity levels are driven primarily by the increased drilling at Alta Mesa and Upper Spring Creek.

Previous wording

The table below presents total cost of extracted pounds and uranium costs per extracted pound during the reporting period. Total cost of extracted pounds is the cost of sales less the cost of sales of purchased goods, which includes the aggregate purchase price of uranium sourced from purchased uranium. Uranium cost per extracted pound is the total cost of extracted pounds divided by the pounds of uranium extracted during the period. Total cost of extracted pounds and uranium costs per extracted pound, includes the allocation of cash and non-cash costs

Current wording

The table below presents total cost of extracted pounds and uranium costs per extracted pound during the reporting period. Total cost of extracted pounds is the cost of sales less the cost of sales of purchased goods, which includes the aggregate purchase price of purchased uranium. Uranium cost per extracted pound is the total cost of extracted pounds divided by the pounds of uranium extracted during the period. Total cost of extracted pounds and uranium costs per extracted pound, includes the allocation of cash and non-cash costs.

Previous wording

During thethree months ended March 31, 2026, the Company continued its uranium extraction activities at Alta Mesa.

Current wording

During thesix months ended June 30, 2026, the Company continued its uranium extraction activities at Alta Mesa.

Previous wording

Our short-term cash requirements are primarily driven by exploration and development activities aimed at advancing properties for uranium extraction. We expect to meet our short-term cash requirements generally through existing working capital. As of March 31, 2026, and December 31, 2025, the Company had cash and cash equivalentsof $41,562 and$52,403, respectively, and working capital, of$121,466 and$96,134, respectively.

Current wording

Our short-term cash requirements are primarily driven by exploration and development activities aimed at advancing properties for uranium extraction. We expect to meet our short-term cash requirements generally through existing working capital. As of June 30, 2026 and December 31, 2025, the Company had cash and cash equivalentsof $21,811 and$52,403, respectively, and working capital of$87,045 and$96,134, respectively.

Previous wording

On August 22, 2025, we issued $115,000 aggregate principal amount of the Convertible Senior Notes. The Convertible Senior Notes bear an annual interest of 5.5%, payable semiannually in arrears and the Notes mature on August 15, 2030.

Current wording

On August 22, 2025, we issued $115,000 of the aggregate principal amount of the Convertible Senior Notes. The Convertible Senior Notes bear an annual interest of 5.5%, payable semiannually in arrears and the Notes mature on August 15, 2030.

Previous wording

The proceeds were used, among other things, to pay down and terminate the Uranium Loan.

Current wording

The proceeds were used, among other things, to pay down and terminate the Uranium Loan Agreement with Boss. See Note 15 - Debt for more information.

Previous wording

The following table reflects cash flow activities for the three months ended March 31, 2026 and 2025:

Current wording

The following table reflects cash flow activities for the six months ended June 30, 2026 and 2025:

Previous wording

Net cash used in operating activities decreased by $13,691 to cash used of $21,426, for the three months ended March 31, 2026, compared to cash used in operating activities of $7,735 for the three months ended March 31, 2025. This is largely driven by an increase in inventories and prepaid expenses during the three months ended March 31, 2026 compared to the same period in 2025.

Current wording

Net cash used in operating activities increased by $24,873 from $17,629 for the six months ended June 30, 2025 to $42,502 for the six months ended June 30, 2026. This was largely driven by an increase in inventory and prepaid expenses during the six months ended June 30, 2026 compared to the same period in 2025.

Previous wording

Net cash used in investing activities increased by $1,739, to $5,971, for the three months ended March 31, 2026, compared to $7,710 for the three months ended March 31, 2025. This was largely driven by an increase in exploration costs related to mineral properties and the net purchase and sale of marketable securities in 2026.

Current wording

Net cash used in investing activities increased by $9,371, to $11,486, for the six months ended June 30, 2026, compared to $2,115 for the six months ended June 30, 2025. This was largely driven by an increase in exploration costs related to mineral properties and the net purchase of marketable securities in 2026.

Previous wording

Net cash provided by financing activities increased by $12,525, to cash provided of $17,947 for the three months ended March 31, 2026, compared to cash provided by financing activities of $5,422 for the three months ended March 31, 2025. This was largely driven by the proceeds received from the exercise of warrants during the three months ended March 31, 2026.

Current wording

Net cash provided by financing activities increased by $11,396 to $17,947 for the six months ended June 30, 2026, compared to cash provided by financing activities of $6,551 for the six months ended June 30, 2025. This was largely driven by the proceeds received from the exercise of warrants during the six months ended June 30, 2026.
Rearranged current paragraphs (10)

Current report — wording carried from elsewhere

South Texas Integrated ISR Project (Rosita CPP)

Current report — wording carried from elsewhere

•Operating expenses - Operating expenses include selling, general and administrative, mineral property expenditures, depreciation, depletion, amortization, and stock compensation expense. Operating expenses for the three months ended June 30, 2026, were $26,919 as compared to $20,407 for the three months ended June 30, 2025. This increase was primarily driven by the increased stock compensation expense and an increase in activity levels the Company is experiencing in 2026 from increased drilling at Alta Mesa and Upper Spring Creek.

Current report — wording carried from elsewhere

The following table summarizes the results of operations for the six months ended June 30, 2026 and 2025:

Current report — wording carried from elsewhere

The following table sets forth selected operating data and financial metrics for uranium sales for the six months ended June 30, 2026, and 2025.

Current report — wording carried from elsewhere

•Revenue - Revenue from uranium sales for the six months ended June 30, 2026, was $33,997 compared to revenue of $21,904 for the six months ended June 30, 2025, an increase of $12,093 or 55%. The increase in revenue for the six months ended June 30, 2026, was driven by an increase in volumes sold of, 135,000 pounds or 39%. The realized sales prices per pound of uranium for the six months ended June 30, 2026 and 2025 were $70.10 and $62.58, respectively, and included the contractual sales price less sales-related costs. The realized sale price per pound increase is dictated by the market for uranium, which is a commodity.

Current report — wording carried from elsewhere

•Cost of Sales - Costs applicable to uranium sales were $36,637 for the six months ended June 30, 2026, related to the completed sale of 485,000 pounds of uranium at a weighted average cost of $75.54 per pound compared to uranium costs of $20,796 for the sale of 350,000 pounds at a weighted average cost of $59.42 per pound for the six months ended June 30, 2025. The increase in costs was the result of more purchased uranium at a higher price versus extracted uranium at a lower price. The Company’s weighted average cost components include both the cost of purchased uranium and uranium produced from extraction. See Costs of U 3 O 8 Sold table below for more information.

Current report — wording carried from elsewhere

•Interest income - Interest income for the six months ended June 30, 2026 and June 30, 2025, was $658 and $480, respectively. The increase was primarily driven by the increase in cash held in brokerage and bank accounts.

Current report — wording carried from elsewhere

•Interest expense - Interest expense for the six months ended June 30, 2026 and June 30, 2025, was $3,634 and $586, respectively. The increase is primarily driven by the interest expense related to the new Convertible Senior Notes. See Note 15 - Debt for more information.

Current report — wording carried from elsewhere

•Loss on marketable securities, unrealized - The Company recognized a loss of $25,918 on the fair value of marketable securities, unrealized for the six months ended June 30, 2026, compared to a loss of $7,066 for the six months ended June 30, 2025. Unrealized losses for the six months ended June 30, 2026 and 2025, are due to unfavorable market conditions.

Current report — wording carried from elsewhere

•Gain on marketable securities, realized - The Company recognized a gain of $6,137 on the fair value of marketable securities, realized for the six months ended June 30, 2026, as a result of the sale of common shares compared to a gain of $7,671 on marketable securities for the six months ended June 30, 2025.