Skip to main content

Core Scientific, Inc./tx

For the period ended Dec 31, 2025. Filed Mar 2, 2026.

View on SEC.gov

About this filing

A company's yearly report to the SEC, with audited financial statements. It is the fullest account a company gives of its business, its finances and the risks it sees.

FY2025 · Filed Mar 2, 2026

CORZ$11.76+3.3%Stored close · as of Nov 6, 2026

What changed in Management’s Discussion and Analysis?

Read the current filing

Previous report: 10-K

Period ended 2024-12-31; filed 2025-02-27.

0001628280-25-008302

Item 7. Management's Discussion and Analysis of Financial Condition and Results of Operations

Current report: 10-K

Period ended 2025-12-31; filed 2026-03-02.

0001628280-26-013305

Item 7. Management's Discussion and Analysis of Financial Condition and Results of Operations

The baseline is this issuer’s latest earlier reporting period of the same form that was filed before the current report. A previous 10-Q is a different quarter, not a year-over-year comparison. Amendments are excluded.

Compared 281 previous paragraphs and 400 current paragraphs.

23 unchanged; 49 reworded; 241 added; 207 removed; 2 previous and 87 current paragraphs rearranged.

Tables are not compared: 22 previous and 17 current tables excluded. Dates, whitespace, punctuation and numbering changes are ignored; changes to financial figures remain significant.

A changed paragraph is not evidence that risk increased or decreased. An unchanged paragraph does not establish that risk stayed the same.

Added paragraphs (241)

Current report

Unless otherwise indicated, references to “2025” and “2024” in this MD&A refer to the years ended December 31, 2025

Current report

As described in Note 3 — Restatement of Previously Issued Financial Statements in Part II, Item 8 to the consolidated

Current report

financial statements included in this Annual Report, during the preparation of the consolidated financial statements for the year ended

Current report

December 31, 2025, the Company identified errors in its previously issued consolidated financial statements related to the accounting

Current report

for property, plant and equipment demolished in connection with the conversion of certain facilities from digital asset mining

Current report

operations to high-density colocation infrastructure. The Company is concurrently filing an amended Annual Report on Form 10-K/A

Current report

for the year ended December 31, 2024 and amended Quarterly Reports on Forms 10-Q/A for the quarterly periods ended March 31,

Current report

2025, June 30, 2025, and September 30, 2025. The discussion that follows presents 2024 comparative data on an as-restated basis.

Current report

purpose-built data centers that support high-density colocation services and digital asset mining for both our own account and to a

Current report

lesser extent, third-party customers. Our data centers are optimized for power-intensive, mission-critical computing workloads, with a

Current report

focus on artificial intelligence (“AI”) and other high-performance computing (“HPC”) applications.

Current report

In 2024, the Company announced its first high-density colocation contract with CoreWeave, Inc. (“CoreWeave), a provider of

Current report

high-performance computing (“HPC”) services, which subsequently had been expanded to 590 megawatts (“MW”) of leased customer

Current report

power capacity over the exercise of several contractual options. We believe leveraging our existing infrastructure for high-density

Current report

colocation services will provide more stable and predictable revenue streams, and represents substantially less risk over time than our

Current report

solutions and diversifying our customer base. This will be done as circumstances allow and in a manner designed to retain access to

Current report

electrical power under our control, maximize the value of our digital asset mining equipment to third parties, and fulfill existing

Current report

obligations to suppliers and customers. We intend to convert every megawatt in our portfolio to high-density colocation infrastructure

Current report

over the next three years. In addition to converting our existing portfolio, we are actively pursuing the acquisition of new sites,

Current report

including land and power capacity, to expand our data center footprint beyond our current facilities.

Current report

mine digital assets and manage our self-mining fleet with a focus on power expense coverage and cash generation while we convert

Current report

our data centers for alternative high-density colocation service business opportunities. We expect to increase revenue derived from

Current report

high-density colocation (“HDC”) services as capacity gets delivered to our current end customer as well as when we sign and begin

Current report

As of December 31, 2025, we operated a diversified portfolio of ten data centers across seven U.S. states, representing

Current report

approximately 1.4 gigawatts(“GW”) of gross utility power capacity, or approximately 920 megawatts (“MW”) of total leasable

Current report

customer power capacity. We continue to be in active discussions with both our existing and future potential utility providers

Current report

During 2025, total revenue decreased to$319.0 million from$510.7 million, primarily due to lower digital asset self-mining

Current report

revenue and digital asset hosted mining revenue as we shifted capital and infrastructure toward colocation, partially offset by higher

Current report

colocation revenue from incremental billable customer power capacity. Operating loss increased to$245.6 million in 2025 from

Current report

$142.1 million in 2024. Netloss was$288.6 million in 2025 and included significant non-cash items, including changes of$33.1

Current report

million in the fair value of warrants and contingent value rights. Adjusted EBITDA decreased to $29.7 million in 2025 from$157.4

Current report

On July 7, 2025, the Company entered into an Agreement and Plan of Merger(the “Merger Agreement”)with CoreWeave, Inc.

Current report

(“CoreWeave”) pursuant to which CoreWeave would acquire the Company in an all-stock transaction, subject to stockholder approval

Current report

and other customary closing conditions. On October 30, 2025, the Company terminated the Merger Agreement in accordance with its

Current report

terms following Company stockholder rejection of the terms of the Merger Agreement at a special meeting of stockholders on that

Current report

The Company incurred$21.6 million of advisory, legal, and other professional or consulting fees related to the proposed

Showing the first 40 of 241 passages. Open the source sections for the rest.

Removed paragraphs (207)

Previous report

In May 2024, we expanded our relationship with CoreWeave, Inc. (“CoreWeave”) the artificial intelligence (“AI”) hyperscaler, to provide approximately 200 megawatts (“MW”) of digital infrastructure to host CoreWeave’s HPC operations and provided CoreWeave options with respect to the Company’s existing facilities to provide approximately 500 MW of digital infrastructure on similar terms. In June and August 2024, the Company announced CoreWeave’s execution of options to secure an additional 70 MW and 112 MW, respectively, of infrastructure to host its HPC operations. In October 2024, the Company announced that CoreWeave had exercised its final option for an additional 120 MW of infrastructure.

Previous report

We had an average hourly operating power demand of approximately 572 megawatts (“MW”) for the year ended December 31, 2024. We had secured approximately 1,317 MW of contracted power capacity at our sites as of December 31, 2024. We also operate and manage one of the largest data center infrastructure asset bases among publicly listed North American miners with operational capacity of approximately 784 MW in support of our mining and HPC operations.

Previous report

Our average self-mining fleet energy efficiency for the year ended December 31, 2024 was 25.1 joules per terahash, compared to 27.9 joules per terahash for the year ended December 31, 2023. Self-mining fleet energy efficiency is a measure of our fleet’s average actual energy efficiency over the period presented.

Previous report

On February 29, 2024, the Company entered into a long-term contract with CoreWeave, Inc. (“CoreWeave”) to deliver 16 MW of infrastructure at the Company’s Austin, Texas facility. Following the commencement of operations in the Austin, Texas facility, on June 3, 2024, the Company entered into a series of long-term contracts with CoreWeave to deliver approximately 200 MW of infrastructure to host CoreWeave’s HPC operations, which will require the Company to modify multiple existing sites. The site modifications commenced in the second half of fiscal 2024 and operational status is expected to begin in the first half of fiscal 2025. On June 25, 2024, the Company announced CoreWeave’s execution of an option to secure an additional 70 MW of infrastructure to host its HPC operations. Operational status for the additional 70 MW is expected in the second half of 2025. Further, on August 6, 2024, the Company announced that CoreWeave had executed an option to secure an additional 112 MW of infrastructure to host its

Previous report

HPC operations. On October 22, 2024, the Company announced that CoreWeave had exercised its final option for an additional 120 MW of infrastructure.

Previous report

On December 5, 2024, the Company completed a private offering (the “2031 Convertible Notes Offering”) of $625.0 million aggregate principal amount of 0.00% Convertible Senior Notes due 2031 (the “2031 Convertible Notes”). The net proceeds from the 2031 Convertible Notes Offering were approximately $608.7 million, after deducting the initial purchasers’ discounts and commissions and the Company’s estimated offering expenses. The Company intends to use the net proceeds from the 2031 Convertible Notes Offering for general corporate purposes, including working capital, operating expenses, capital expenditures, acquisitions of complementary businesses or assets, or other repurchases of its securities.

Previous report

On August 19, 2024, the Company completed a private offering (the “2029 Convertible Notes Offering”) of $460.0 million aggregate principal amount of 3.00% Convertible Senior Notes due 2029 (the “2029 Convertible Notes”). The net proceeds from the 2029 Convertible Notes Offering were approximately $447.6 million, after deducting the initial purchasers’ discounts and commissions and the Company’s estimated offering expenses. The Company used approximately $62.0 million of the net proceeds from the 2029 Convertible Notes Offering to repay in full the outstanding loans under the Exit Credit Agreement, of which $0.8 million was paid for interest. Additionally, the Company used approximately $154.1 million of the net proceeds from the 2029 Convertible Notes Offering to redeem all of the outstanding Secured Notes, of which $4.1 million was paid for interest. Further, the Company paid $49.6 million to repay the BlockFi facility in full, of which $0.7 million was paid for interest, and paid $6.5 million to repay the Stonebriar facility in full, of which $0.1 million was paid for interest. The Company intends to use the remaining net proceeds from the 2029 Convertible Notes Offering for general corporate purposes, including working capital, operating expenses, capital expenditures, acquisitions of complementary businesses or assets, or other repurchases of its securities.

Previous report

For more detailed information regarding the 2031 Convertible Notes Offering and the 2029 Convertible Notes Offering conversion, refer to Note 8 — Convertible and Other Notes Payable to our consolidated financial statements in Item 8 of Part II of this Annual Report on Form 10-K.

Previous report

On April 19, 2024, the Bitcoin protocol executed its fourth planned halving, wherein the bitcoin rewards issued for each solved block declined from 6.25 bitcoin to 3.125 bitcoin, reducing the bitcoin received from bitcoin mining by 50% (excluding transaction fee rewards). As a result, revenue generated from bitcoin mining declined, adversely impacting gross profit.

Previous report

On January 15, 2024, the Company and certain of its affiliates (collectively, the “Debtors”) filed with the United States Bankruptcy Court for the Southern District of Texas (the “Bankruptcy Court”) the Fourth Amended Joint Chapter 11 Plan of Core Scientific, Inc. and its Affiliated Debtors (with Technical Modifications) (the “Plan of Reorganization”). On January 16, 2024, the Bankruptcy Court entered an order confirming the Plan of Reorganization. On January 23, 2024 (the “Effective Date”), the conditions to the effectiveness of the Plan of Reorganization were satisfied or waived and the Company emerged from bankruptcy. On January 24, 2024, the Company’s common shares began trading on the Nasdaq market under the ticker symbol CORZ.

Previous report

On the Effective Date, the obligations of the Company under the Company’s notes sold pursuant to (i) the Secured Convertible Note Purchase Agreement, dated as of April 19, 2021 (as amended, restated, amended and restated, supplemented or otherwise modified from time to time), by and among Core Scientific, Inc. (as successor of Core Scientific Holding Co.), the guarantors party thereto from time to time, U.S. Bank National Association, as note agent and collateral agent, and the purchasers of the notes issued thereunder (the “Secured Convertible Notes”), and (ii) the Convertible Note Purchase Agreement, dated as of August 20, 2021 (as amended, restated, amended and restated, supplemented or otherwise modified from time to time), by and among Core Scientific, Inc. (as successor of Core Scientific Holding Co.), the guarantors party thereto from time to time, U.S. Bank National Association, as note agent and collateral agent, and the purchasers of the notes issued thereunder (the “Other Convertible Notes,” and together with the Secured Convertible Notes, the “Convertible Notes”), replacement debtor-in-possession credit agreement, stock certificates, book entries, and any other certificate, share, note, bond, indenture, purchase right, option, warrant, or other instrument or document, directly or indirectly, evidencing or creating any indebtedness or obligation of or ownership interest in the Debtors giving rise to any claim or interest (except such certificates, notes or other instruments or documents evidencing indebtedness or obligations of, or interests in, the Debtors that are specifically reinstated pursuant to the Plan of Reorganization) were cancelled, and the duties and obligations of all parties thereto were deemed satisfied in full, canceled, released, discharged, and of no force or effect.

Previous report

On the Effective Date, Pursuant to the Plan of Reorganization

Previous report

•The Company entered into a credit and guaranty agreement (the “Exit Credit Agreement”), consisting of an $80 million first-lien credit facility with certain holders of the Company’s Convertible Notes. The Exit Credit Agreement was paid in full on August 19, 2024.

Previous report

•The Company issued $150.0 million aggregate principal amount of senior secured notes due 2028 (the “Secured Notes”) pursuant to a secured notes indenture (the “Secured Notes Indenture”). The Secured Notes were paid in full on August 19, 2024.

Previous report

•The Company issued $260.0 million aggregate principal amount of secured convertible notes due 2029 (the “New Secured Convertible Notes”) pursuant to a secured convertible notes indenture (the “New Secured Convertible Notes Indenture”). The New Secured Convertible Notes were issued to holders of the Company’s Convertible Notes. The New Secured Convertible notes were mandatorily converted as of July 10, 2024 and are no longer outstanding.

Previous report

•The Company entered into an agreement which provided for the issuance of contingent value rights (the “CVRs”) to holders of the Company’s Convertible Notes and provided for the issuance of CVRs issued to holders of allowed general unsecured claims (the GUC CVRs”). On July 1, 2024, the GUC CVR obligations were extinguished pursuant to their terms when the VWAP of the Company’s New Common Stock on Nasdaq National Market System exceeded $5.02 for 20 trading days within the applicable 30 consecutive trading day period.

Previous report

•The holders of our pre-emergence Secured Convertible Notes and Other Convertible Notes received Secured Notes Indenture, New Secured Convertible Notes Indenture, post-emergence common stock and CVRs. Certain holders of New Secured Convertible Notes also funded and received the Exit Credit Agreement.

Previous report

For more detailed information regarding our emergence from bankruptcy, refer to Notes 3 — Chapter 11 Filing and Emergence from Bankruptcy, 8 — Convertible and Other Notes Payable, 9 — Contingent Value Rights and Warrant Liabilities and 12 — Stockholders' Deficit to our consolidated financial statements in Item 8 of Part II of this Annual Report on Form 10-K.

Previous report

We own and host specialized computers (“miners”) configured for the purpose of validating transactions on multiple digital asset network blockchains (referred to as, “mining”), predominantly the Bitcoin network. Substantially all of the miners we own and host were manufactured by Bitmain Technologies Limited (“Bitmain”) and incorporate application-specific integrated circuit (“ASIC”) chips specialized to solve blocks on the bitcoin blockchains using the 256-bit secure hashing algorithm (“SHA-256”) in return for bitcoin digital asset rewards.

Previous report

We have entered into and facilitated agreements with vendors to supply mining equipment for our digital asset mining operations. The majority of our purchases are made on multi-month contracts with installment payments due in advance of scheduled deliveries. Delivery schedules have ranged from one month to 12 months. As of December 31, 2023, we had two active purchase agreements with Bitmain. The first agreement was for the acquisition of Antminer S19J XP miners with a combined exahash of 4.1 or 28,400 miners. The second agreement was for the acquisition of Antminer S21 miners with a combined exahash of 2.5 or approximately 12,900 miners. As of December 31, 2024, the Company had received all of the miners and completed all 2024 payments due on miners ordered for deployment this year.

Previous report

Activity related to our digital asset balances for the years ended December 31, 2024 and 2023, were as follows (in thousands):

Previous report

1 Reflects the impact of the Company’s adoption of Accounting Standards Update (“ASU”) 2023-08, Intangibles-Goodwill and Other-Crypto Assets (Subtopic 350-60): Accounting for and Disclosure of Crypto Assets (“ASU 2023-08”) effective January 1, 2024.

Previous report

2 As of December 31, 2024 and December 31, 2023, there was $0.9 million and $1.7 million, respectively, of digital asset receivable included in prepaid expenses and other current assets on the consolidated balance sheets.

Previous report

Miners perform computational operations in support of digital asset blockchains measured in “hash rate” or “hashes per second.” A “hash” is the computation run by mining hardware in support of the blockchain; therefore, a miner’s “hash rate” refers to the rate at which it is capable of solving such computations. The equipment originally employed for mining bitcoin used the central processing unit (“CPU”) of a computer to mine various forms of digital assets. Due to performance limitations, CPU mining was rapidly replaced by the GPU, which offers significant performance advantages over CPUs. General purpose chipsets like CPUs and GPUs have since been replaced as the standard in the mining industry by ASIC chips such as those found in the miners we and our customers use to mine bitcoin (although they continue to have uses in other industries). These ASIC chips are designed specifically to maximize the rate of hashing operations.

Previous report

In digital asset mining, hash rate is a measure of the processing speed at which a mining computer operates in its attempt to secure a specific digital asset. A participant in a blockchain network’s mining function has a hash rate equivalent to the total of all its miners seeking to mine a specific digital asset. System-wide, the total network hash rate reflects the sum total of all miners seeking to mine each specific type of digital asset. A participant’s higher total hash rate relative to the system-wide total hash rate generally results in a corresponding higher success rate in digital asset rewards over time as compared to mining participants with relatively lower total hash rates.

Previous report

However, as the relative market price for a digital asset, such as bitcoin, increases, more users are incentivized to mine for that digital asset, which increases the network’s overall hash rate. As a result, a mining participant must increase its total hash rate in order to maintain its relative possibility of solving a block on the network blockchain. Achieving greater hash rate power by deploying increasingly sophisticated miners in ever greater quantities has become one of the bitcoin mining industry’s great sources of competition. Our goal is to deploy a powerful fleet of self- and hosted-miners, while operating as energy-efficiently as possible.

Previous report

The table below provides a summary of the impact to revenue from the increase or decrease in the market price of bitcoin, difficulty and our hash rate. The impact to revenue in each scenario assumes only one driver increases or decreases and all others are held constant.

Previous report

Further affecting the industry, and particularly for the bitcoin blockchain, the digital asset reward for solving a block is subject to periodic incremental halving. Halving is a process designed to control the overall supply and reduce the risk of inflation in digital assets using a proof-of-work consensus algorithm. At a predetermined block, the mining reward is reduced by half, hence the term “halving.” A reduction in the number of bitcoins rewarded per block would result in a reduction of revenue to those mining bitcoin, barring any increase in the spot price of bitcoin or decrease in Bitcoin network hash rate or difficulty. Historically, the network hash rate has tended to decline, for a period of time, post-halving as less efficient mining servers become less profitable to operate and their operators discontinue or limit their use.

Showing the first 40 of 207 passages. Open the source sections for the rest.

Reworded paragraphs (49)

Previous wording

Unless the context otherwise requires, all references in this section to “we,” “us,” “our,” the “Company,” “Core Scientific,” or “Core” refer to Core Scientific, Inc. and its subsidiaries.

Current wording

Unless the context otherwise requires, all references in this section to “we,” “us,” “our,” the “Company,” “Core Scientific,”

Previous wording

The following Management's Discussion and Analysis of Financial Condition and Results of Operations (“MD&A”) is intended to promote understanding of the results of operations and financial condition. This MD&A is provided as a supplement to, and should be read in conjunction with, our consolidated financial statements and the accompanying Notes to Financial Statements (Part II, Item 8 of this Form 10-K). This section generally discusses the results of operations for 2024 compared to 2023. For discussion related to the results of operations and changes in consolidated financial condition for 2023 compared to 2022 refer to Part II, Item 7.—“Management's Discussion and Analysis of Financial Condition and Results of Operations” in our fiscal year 2023 Annual Report on Form 10-K, which was filed with the SEC on March 13, 2024.

Current wording

The following Management's Discussion and Analysis of Financial Condition and Results of Operations (“MD&A”) is

Previous wording

As discussed in the section titled “Cautionary Note Regarding Forward-Looking Statements,” the following discussion and analysis contains forward-looking statements that involve risks and uncertainties, as well as assumptions that, if they never materialize or prove incorrect, could cause our results to differ materially from those expressed or implied by such forward-looking statements. Factors that could cause or contribute to such differences include, but are not limited to, those identified below, and those discussed in the section titled “Risk Factors” under Part I, Item 1A in this Annual Report on Form 10-K.

Current wording

As discussed in the section titled “Cautionary Note Regarding Forward-Looking Statements,” the following discussion and

Previous wording

Core Scientific, Inc. (“we,” “us,” “our,” the “Company,” “Core Scientific,” or “Core”) is a leader in designing, building and operating digital infrastructure for high-performance computing. Since our inception in 2018, we have been a premier provider and operator of dedicated, purpose-built facilities and software solutions for digital asset mining for ourselves and our third-party customers. and in March 2024, we announced the provision of digital infrastructure colocation services to a third party engaged in high-performance computing (“HPC”).

Current wording

Core Scientific, Inc. (“we,” “us,” “our,” the “Company,” “Core Scientific,” or “Core”)designs, builds and operates large-scale

Previous wording

These new agreements leverage the Company’s existing digital infrastructure and expertise in third-party hosting solutions. We believe that using our existing infrastructure for HPC hosting operations will provide more consistent dollar-based revenue and represents substantially less risk than our traditional hosted bitcoin mining or our bitcoin self-mining operations. As a result, we intend to focus our business development and marketing efforts on expanding our HPC hosting customer base. As a result, we initiated a significant strategic transition from bitcoin mining to hosting and colocation services for customers employing hosting services for HPC workloads such as artificial intelligence-related applications.

Current wording

traditional hosted bitcoin mining or self-mining operations.

Previous wording

During 2024, we were substantially engaged in constructing, refurbishing, reallocating or converting a substantial portion of our ten facilities in Alabama (1), Georgia (2), Kentucky (1), North Carolina (1), North Dakota (1), Oklahoma (1), and Texas (3) to support artificial intelligence related workloads, primarily for our one existing HPC customer, but also to support our commitment to meeting the growing demand for HPC solutions and diversifying our revenue streams.

Current wording

We are constructing, refurbishing, reallocating or converting our ten facilities in Alabama (1), Georgia (2), Kentucky (1), North

Previous wording

Currently, the vast majority of our revenue is from mining bitcoin for our own account (‘self-mining”). We remain committed to maintaining the efficiency of our digital asset mining while capitalizing on the opportunities presented by the growing HPC hosting business.

Current wording

Currently, the vast majority of our revenue is from mining bitcoin for our own account (“self-mining”). We will continue to

Previous wording

Our total revenue was $510.7 million, $502.4 million and $640.3 million for the years ended December 31, 2024, 2023, and 2022, respectively. We generated an operating loss of $19.2 million and operating income of $9.0 million for the years ended December 31, 2024 and 2023, respectively, and an operating loss of $2.11 billion for the year ended December 31, 2022. We incurred net loss of $1.32 billion, $246.5 million and $2.15 billion for the years ended December 31, 2024, 2023 and 2022, respectively. Our adjusted earnings before interest, taxes, depreciation and amortization (“Adjusted EBITDA”) was $157.4 million, $169.5 million and $(11.6) million for the years ended December 31, 2024, 2023 and 2022, respectively. Adjusted EBITDA is a non-GAAP financial measure. See “Key Business Operating Metrics and Non-GAAP Financial Measures” below for our definition of, and additional information related to Adjusted EBITDA.

Current wording

million in 2024. Adjusted EBITDA is a non-GAAP financial measure. See “Key Business Operating Metrics and Non-GAAP

Previous wording

As a large-scale owner and operator of high-power digital infrastructure for digital asset mining and hosting services, we believe that we are well positioned to serve customers in digital asset mining and an expanding market for HPC operations. As noted in the “Business Strategy” section below, we believe that opportunities for growth exist in various applications of our data centers for third-party customers focused on cloud computing as well as machine learning and artificial intelligence, which has driven our recent expansion into providing HPC hosting services. Furthermore, we believe that the adoption and mainstream use of bitcoin and the blockchain technology on which it is based has accelerated the demand for bitcoin and other digital currencies.

Current wording

As a large-scale owner and operator of high-power digital infrastructure, we generate revenue primarily through (i) Colocation

Previous wording

We focus primarily on contracting our digital infrastructure for HPC hosting, and mining and selling bitcoin for cash, enhancing efficiencies in our operations (reducing our cost to mine). Our digital asset mining operation is focused on earning bitcoin by solving complex cryptographic algorithms to validate transactions on specific bitcoin blockchains, which is commonly referred to as “mining.” Our digital asset self-mining activity competes with myriad mining operations throughout the world to complete new blocks on the blockchain and earn the reward in the form of bitcoin.

Current wording

We focus primarily on contracting our digital infrastructure for Colocation, mining bitcoin, and enhancing efficiencies in our

Previous wording

Our data centers house bitcoin mining computers and will increasingly house graphics processing units (“GPUs”). These specialized facilities lever our specialized design and construction proficiency by employing high-density, low-cost engineering, power designs and modular construction. For digital asset mining, our proprietary thermodynamic structural design manages heat and airflow to deliver best-in-class uptime and, ultimately, increased mining rewards to us and our customers. We are allocating a significant portion of our current and future data centers to support other forms of high-value computing, such as HPC hosting operations, in connection with our short-, medium- and long-term strategic plan.

Current wording

Our data centers house bitcoin mining computers and will increasingly house specialized compute accelerators, including

Previous wording

Our business strategy is to grow our revenue and profitability by expanding our existing large-scale data center infrastructure portfolio configured for specialized computers performing specific, high-value applications such as cloud computing, machine learning and artificial intelligence, and maximizing the portion of our existing infrastructure portfolio contracted for HPC hosting. We intend to continue to strategically develop and make operational the infrastructure necessary to support our existing contractual commitments to our existing HPC customer and to support expected customer growth and additional demand by leveraging our data center expertise and capabilities. We intend to seek additional opportunities and to engage additional customers in the HPC Hosting segment to expand our business into these areas using our knowledge, expertise, existing and future infrastructure where favorable market opportunities exist.

Current wording

Our strategy is to grow our revenue and profitability by converting and expanding our large-scale data center infrastructure

Previous wording

Our strategy is focused on hyperscale cloud-based providers and enterprises, including potential customers we believe have significant data center infrastructure needs that have not yet been outsourced or will require additional data center space and power to support their growth and their increasing reliance on technology infrastructure in their operations. We believe our capabilities for serving the needs of large hyperscale providers and enterprises will continue to enable us to capitalize on the growing demand for outsourced data center facilities in our markets and in new markets where our customers are located or plan to be located in the future.

Current wording

have significant data center infrastructure needs that have not yet been outsourced or will require additional data center space and

Previous wording

We have three operating segments: “Digital Asset Self-Mining,” consisting of performing digital asset mining for our own account, “Digital Asset Hosted Mining,” consisting of providing hosting services to third parties for digital asset mining, and “HPC Hosting,” consisting of providing hosting services to third parties for GPU-based HPC hosting operations. Prior to April 1, 2024, we operated only in the Digital Asset Self-Mining and Digital Asset Hosted Mining segments.

Current wording

employing AI and HPC related workloads, “Digital Asset Self-Mining,” consisting of performing digital asset mining for our own

Previous wording

Our HPC Hosting operation segment generates revenue by providing colocation, cloud and connectivity services to customers in exchange for a fee. Our HPC Hosting operation segment provides colocation, facilities operations, security and other services to third-party HPC customers to support workloads for machine learning and artificial intelligence. As of December 31, 2024, we have operational capacity of approximately 784 MW to support of our existing and planned HPC operations.

Current wording

Our Colocation segment provides space, power, cooling, facilities operations, security and other services to third-party

Previous wording

Our Digital Asset Self-Mining operation segment generates revenue from the deployment and operation our own large fleet of miners within our owned digital infrastructure as part of a pool of users that process transactions conducted on one or more blockchain networks. In exchange for this activity, we receive digital assets in the form of bitcoin. We began digital asset mining at scale in 2018 and in 2020 became one of the largest North American providers of hosting services primarily for third-party mining customers. We had an average hourly operating power demand of approximately 572 MW for the year ended December 31, 2024.

Current wording

Our Digital Asset Self-Mining operation segment generates revenue from the deployment and operation of our own large fleet

Previous wording

Our Digital Asset Hosted Mining operation segment generates revenue through the sale of electricity-based consumption contracts for our hosting services, which are recurring in nature. Our Digital Asset Hosted Mining operation segment provides a full suite of services to our digital asset mining customers. We provide deployment, monitoring, troubleshooting, optimization and maintenance of our customers’ digital asset mining equipment and provide necessary electrical power, repair and other infrastructure services necessary for our customers to operate, maintain and efficiently mine digital assets. We do not expect to further expand our Digital Asset Hosted Mining operations in 2025 and future years.

Current wording

of services to our digital asset mining customers. We provide deployment, monitoring, troubleshooting, optimization and maintenance

Previous wording

The tables below summarize the total number of self- and hosted miners in operation as of December 31, 2024 and December 31, 2023 (miners in thousands):

Current wording

The tables below summarize the total number of self- and hosted miners in operation as of December 31, 2025 and

Previous wording

Our financial performance and continued growth depend in large part on our ability to mine for digital assets profitably and to attract customers for our digital asset hosted mining services. Increases in power costs, inability to mine digital assets efficiently and to sell digital assets at favorable prices will reduce our operating margins, impact our ability to attract customers for our services, may harm our growth prospects and could have a material adverse effect on our business, financial condition and results of operations. Over time, we have observed a positive trend in the total market capitalization of digital assets, which suggests increased adoption. However, historical trends are not indicative of future adoption, and it is possible that the adoption of digital assets and blockchain technology may slow, take longer to develop, or never be broadly adopted, which would negatively impact our business and operating results.

Current wording

inability to mine digital assets efficiently and to sell digital assets at favorable prices will reduce our operating margins and could have

Previous wording

The planned growth of our HPC data center hosting operations business, through increased investment in conversion of several of our bitcoin mining sites to HPC data center hosting sites over the next several years, should gradually reduce our overall exposure to volatility in the spot price of bitcoin as HPC begins to account for a comparatively larger percentage of our financial results. The HPC data center hosting business is characterized by implementation of long-term contracts with customers spanning several years with terms and conditions outlining and resulting in stable, predictable revenue and cash flows over each period.

Current wording

spanning 10+ years with terms and conditions resulting in stable, predictable revenue and cash flows over each period.

Previous wording

Our Digital Asset Self-Mining segment is heavily dependent on the spot price of bitcoin. The prices of digital assets, specifically bitcoin, have experienced substantial volatility, meaning that high or low prices may have little or no relationship to identifiable market forces, may be subject to rapidly changing investor sentiment, and may be influenced by factors such as technology, regulatory void or changes, fraudulent actors, manipulation, and media reporting. Bitcoin (as well as other digital assets) may have value based on various factors, including their acceptance as a means of exchange by consumers and others, scarcity, and market demand.

Current wording

Our Digital Asset Self-Mining segment is heavily dependent on the spot price of bitcoin. The prices of digital assets,

Previous wording

Bitcoin miners receive a transaction fee in the form of a portion of bitcoin for validating transactions on the Bitcoin network. The transaction fee can vary in value over time, with higher fees prioritizing certain transactions over those with lower fees. An increase in Bitcoin network transaction fees increases mining proceeds.

Current wording

strategy. Bitcoin miners also receive a transaction fee in the form of a portion of bitcoin for validating transactions on the Bitcoin

Previous wording

Our business is not only impacted by the volatility in digital asset prices, but also by increases in the competition for digital asset production. For bitcoin, this increased competition is described as the network hash rate resulting from the growth in the overall quantity and quality of miners working to solve blocks on the bitcoin blockchain, and the difficulty index associated with the secure hashing algorithm employed in solving the blocks.

Current wording

Our business is not only impacted by the volatility in digital asset prices and transaction fees, but also by increases in the

Previous wording

The increase in bitcoin’s network hash rate results in a regular increase in the cryptographic complexity associated with solving blocks on its blockchain, or its difficulty. Increased difficulty reduces the mining proceeds of the equipment proportionally and eventually requires bitcoin miners to upgrade their mining equipment to remain profitable and compete effectively with other miners. Similarly, a decline in network hash rate results in a decrease in difficulty, increasing mining proceeds.

Current wording

Increased difficulty reduces the mining proceeds of the equipment proportionally and eventually requires bitcoin miners to

Previous wording

Electricity cost is the major operating cost for the mining fleet, as well as for the hosting services provided to customers and related parties. The cost and availability of electricity are affected primarily by changes in seasonal demand, with peak demand during the summer months driving higher costs and increased curtailments to support grid operators. Severe winter weather can increase the cost of electricity and the frequency of curtailments when it results in damage to power transmission infrastructure that reduces the grid’s ability to deliver power. Geopolitical and macroeconomic factors, such as overseas military or economic conflict between states, can adversely affect electricity costs by raising the cost of power generation inputs such as natural gas. Other events out of our control can also impact electricity costs and availability. In certain power markets, financial hedging can be employed to protect buyers from the financial impact of significant increases in power prices.

Current wording

Electricity cost is the major operating cost for our mining fleet, as well as for the hosted mining services provided to customers.

Previous wording

In addition to factors underlying our mining business growth and profitability, the success of our HPC hosting business greatly depends on our ability to retain and develop opportunities with our existing customers, secure additional infrastructure and attract new customers.

Current wording

depends on our ability to retain and develop opportunities with our existing customers, secure additional infrastructure and attract new

Previous wording

Our business environment is constantly evolving. However, digital asset mining is now dominated by large-scale, industrial miners operating large dedicated facilities around the world, including sovereign nation states with vast resources who mine directly or support mining operations through their sovereign wealth funds, all of whom compete to solve new blocks, acquire new and used miners, and purchase and consume energy and supplies to build mining facilities. We face significant competition in every aspect of our business, including, but not limited to, the acquisition of new miners, the ability to raise capital, obtaining low-cost electricity, obtaining access to sites with reliable sources of high power, and evaluating new technology developments in the industry.

Current wording

and can contribute to increases in network hash rate and difficulty. We face significant competition in every aspect of our business,

Previous wording

Based on available data, we believe that an increase in the scale and sophistication of competition in the digital asset mining industry has continued to increase network hash rate, with new entrants and existing competitors increasing the number of miners mining for bitcoin.

Current wording

Based on available data, we believe that an increase in the scale and sophistication of competition in the digital asset mining

Previous wording

In HPC hosting, we compete with other providers of high-power data center capacity, such as major data center real estate investment trusts (“REITs”), developers of data centers, hyperscalers and bitcoin miners with capacity suitable for HPC hosting. This competition focuses primarily on the identification and acquisition of new, high-power sites, but also includes competition for the capital required to build or modify existing sites to support HPC hosting. Additionally, the modification of some of our data centers to accommodate HPC hosting involves the procurement of critical equipment, technologies and skilled labor, which are in high demand from other entities seeking to address the same market opportunity, thereby putting us into competition with many other organizations for those resources.

Current wording

In our Colocation operations, we compete with other providers of high-power data center capacity, such as major data center

Previous wording

In addition to our financial results, we use the following business operating metrics and non-GAAP financial measures to evaluate our business, measure our performance, identify trends affecting our business, and make strategic decisions. For a definition of these key business operating metrics, see the sections titled “Self-Mining Hash Rate,” and “Cost of Self-Mining One Bitcoin and Hash Cost,” (below), and for non-GAAP financial measures, see the section titled “Adjusted EBITDA” (below).

Current wording

In addition to our financial results, we use the following business operating metrics and non-GAAP financial measures to

Previous wording

The above items are excluded from our Adjusted EBITDA measure because these items are non-cash in nature or because the amount and timing of these items are not related to the current results of our core business operations which renders evaluation of our current performance, comparisons of performance between periods and comparisons of our current performance with our competitors less meaningful. However, you should be aware that when evaluating Adjusted EBITDA, we may incur future expenses similar to those excluded when calculating this measure. Our presentation of this measure should not be construed as an inference that its future results will be unaffected by unusual items. Further, this non-GAAP financial measure should not be considered in isolation from, or as a substitute for, financial information prepared in accordance with accounting principles generally accepted in the United States (“GAAP”). We compensate for these limitations by relying primarily on GAAP results and using Adjusted EBITDA on a supplemental basis. Our computation of Adjusted EBITDA may not be comparable to other similarly titled measures computed by other companies because not all companies calculate this measure in the same fashion. You should review the reconciliation of net loss to Adjusted EBITDA below and not rely on any single financial measure to evaluate our business.

Current wording

statements prepared in accordance with accounting principles generally accepted in the United States (“GAAP”).

Previous wording

Adjusted EBITDA is a non-GAAP financial measure defined as our net loss, adjusted to eliminate the effect of (i) interest income, interest expense, and other income (expense), net; (ii) provision for income taxes; (iii) depreciation and amortization; (iv) stock-based compensation expense; (v) Reorganization items, net; (vi) unrealized fair value adjustment on energy derivatives; (vii) change in fair value of warrant and contingent value rights; (viii) HPC organizational startup costs which are not reflective of the ongoing costs incurred after startup, (ix) post-emergence bankruptcy advisory costs incurred related to reorganization which are not reflective of the ongoing costs incurred in post-emergence operations, and (x) certain additional non-cash items that do not reflect the performance of our ongoing business operations. For additional information, including the reconciliation of net loss to Adjusted EBITDA, please refer to the table below. We believe Adjusted EBITDA is an important measure because it allows management, investors, and our Board of Directors to evaluate and compare our operating results, including our return on capital and operating efficiencies, from period-to-period by making the adjustments described above. In addition, it provides useful information to investors and others in understanding and evaluating our results of operations, as well as provides a useful measure for period-to-period comparisons of our business, as it removes the effect of net interest expense, taxes, certain non-cash items, variable charges and timing differences. Moreover, we have included Adjusted EBITDA in this Annual Report on Form 10-K because it is a key measurement used by our management internally to make operating decisions, including those related to operating expenses, evaluate performance, and perform strategic and financial planning.

Current wording

investors with Adjusted EBITDA, which is a non‑GAAP financial measure. Adjusted EBITDA is defined as our net loss, adjusted to

Previous wording

The following table presents a reconciliation of net loss to Adjusted EBITDA for the years ended December 31, 2024, 2023 and 2022, (in thousands):

Current wording

The following table presents a reconciliation of net lossto Adjusted EBITDA for theyears ended December 31, 2025 and 2024

Previous wording

The following table sets forth our selected Consolidated Statements of Operations for each of the periods indicated (in thousands).

Current wording

The following table sets forth our selected consolidated statements of operations for each of the periods indicated (in

Previous wording

•HPC hosting revenue. HPC hosting revenue is generated by licensing data center space and related services to licensees at our Austin, Texas data center. These licensing agreements and orders include lease components, nonlease components (such as power delivery, physical security, maintenance and other billable expenses), as well as noncomponent elements such as taxes. Under these contracts, customers pay fixed payments (based on electric capacity) and variable payments on a recurring basis. HPC hosting power fees are passed through to the customer without markup and are included on a gross basis in HPC hosting revenue.

Current wording

and other billable services. Power fees are passed through to customers without markup and are recognized as revenue on a gross

Previous wording

Total digital asset hosted mining revenue from customers decreased by $24.5 million or 24%, to $77.6 million for the year ended December 31, 2024, from $102.0 million for the year ended December 31, 2023. The decrease in hosted mining revenue from customers was primarily driven by the termination of contracts with several customers since 2023, due primarily to our shift to HPC hosting.

Current wording

The year over year decrease in hosted mining revenue from customers was primarily driven byour shift to our Colocation

Previous wording

•the Company’s entry into a warrant agreement and Convertible Value Rights Agreement pursuant to the Plan of Reorganization. During the year ended December 31, 2024, we incurred a $1.37 billion Change in fair value of warrant and contingent value rights due to the increase in the price of the underlying instruments driven by the increase in the Company’s stock price to $14.05 per share as of December 31, 2024, from $3.44 per share as of the Effective Date. The increase in stock price resulted in a $1.45 billion increase in the fair value of the warrant liabilities during the year ended December 31, 2024, partially offset by a $82.1 million decrease in fair value of contingent value rights; and

Previous wording

•General and administrative. General and administrative expenses include compensation, benefits, other personnel-related expenses for employees who are not part of our operating sites, research, development, sales, or marketing functions. Also included are stock-based compensation, rent, HPC organizational and site startup costs, post-emergence bankruptcy advisor fees related to the reorganization, professional fees, business insurance, auditor fees, bad debt, amortization of intangibles, franchise taxes, and bank fees. HPC organizational startup costs were primarily consulting costs that were specifically incurred preparing for and entering into the HPC hosting business, and are not expected to be incurred in the ongoing operations of the HPC hosting business. HPC site startup costs are noncapitalizable costs associated with the administration of converting and building of future HPC hosting operating sites, and include compensation and other personnel-related expenses, including stock-based compensation. Similar costs will be incurred in the future operations of the HPC hosting sites.

Previous wording

We have assessed our current and expected operating and capital expenditure requirements and our current and expected sources of liquidity, and have determined, based on our forecasted financial results and financial condition as of December 31, 2024, that our operating cash flows, existing cash balances, and continued access to debt markets will be sufficient to satisfy our cash requirements over the next twelve months and beyond.

Current wording

We have assessed our current and expected operating and capital expenditure requirements and our current and expected

Showing the first 40 of 49 pairs. Open the source sections for the rest.

Rearranged current paragraphs (87)

Current report — wording carried from elsewhere

or “Core” refer to Core Scientific, Inc. and its subsidiaries.

Current report — wording carried from elsewhere

intended to promote understanding of the results of operations and financial condition. This MD&A is provided as a supplement to,

Current report — wording carried from elsewhere

and should be read in conjunction with, our consolidated financial statements and the accompanying Notes to Financial Statements

Current report — wording carried from elsewhere

(Part II, Item 8 of this Form 10-K). This section generally discusses the results of operations for 2025 compared to 2024. For

Current report — wording carried from elsewhere

discussion related to the results of operations and changes in consolidated financial condition for 2024 compared to 2023 refer to

Current report — wording carried from elsewhere

Part II, Item 7.—“Management's Discussion and Analysis of Financial Condition and Results of Operations” in our fiscal year 2024

Current report — wording carried from elsewhere

Annual Report on Form 10-K, which was filed with the SEC on February 20, 2025.

Current report — wording carried from elsewhere

analysis contains forward-looking statements that involve risks and uncertainties, as well as assumptions that, if they never

Current report — wording carried from elsewhere

materialize or prove incorrect, could cause our results to differ materially from those expressed or implied by such forward-looking

Current report — wording carried from elsewhere

statements. Factors that could cause or contribute to such differences include, but are not limited to, those identified below, and those

Current report — wording carried from elsewhere

discussed in the section titled “Risk Factors” under Part I, Item 1A in this Annual Report on Form 10-K.

Current report — wording carried from elsewhere

Carolina (1), North Dakota (1), Oklahoma (1), and Texas (3) to support artificial intelligence related workloads, in support of our

Current report — wording carried from elsewhere

existing colocation customer, but also to support our commitment to meeting the growing demand for high-density colocation

Current report — wording carried from elsewhere

Financial Measures” below for our definition of, and additional information related to Adjusted EBITDA.

Current report — wording carried from elsewhere

graphics processing units (“GPUs”). These facilities leverage our specialized design and construction capabilities by employing high-

Current report — wording carried from elsewhere

density, innovative engineering, power designs and modular construction. For digital asset mining, our proprietary thermodynamic

Current report — wording carried from elsewhere

structural design manages heat and airflow to deliver reliable operations to us and our customers. As part of our go-forward strategy,

Current report — wording carried from elsewhere

power to support their growth and their increasing reliance on technology infrastructure in their operations.

Current report — wording carried from elsewhere

account, and “Digital Asset Hosted Mining,” consistingof providing hosting services to third parties for digital asset mining. Prior to

Current report — wording carried from elsewhere

April 1, 2024, we operated primarily in the Digital Asset Self-Mining and Digital Asset Hosted Mining segments.

Current report — wording carried from elsewhere

customers to support workloads for machine learning and artificial intelligence.

Current report — wording carried from elsewhere

of miners within our owned digital infrastructure as part of a pool of users that process transactions conducted on one or more

Current report — wording carried from elsewhere

blockchain networks. In exchange for this activity, we receive digital assets in the form of bitcoin.

Current report — wording carried from elsewhere

of our customers’ digital asset mining equipment and provide necessary electrical power, repair and other infrastructure services

Current report — wording carried from elsewhere

necessary for our customers to operate, maintain and efficiently mine digital assets. We do not currently expect to further expand our

Current report — wording carried from elsewhere

Digital Asset Hosted Mining operations in future years.

Current report — wording carried from elsewhere

specifically bitcoin, have experienced substantial volatility, meaning that high or low prices may have little or no relationship to

Current report — wording carried from elsewhere

identifiable market forces, may be subject to rapidly changing investor sentiment, and may be influenced by factors such as

Current report — wording carried from elsewhere

technology, regulatory developments and enforcement actions. Bitcoin (as well as other digital assets) may have value based on

Current report — wording carried from elsewhere

various factors, including their acceptance as a means of exchange by consumers and others, scarcity, and market demand. Changes in

Current report — wording carried from elsewhere

network. The transaction fee can vary in value over time, with higher fees prioritizing certain transactions over those with lower fees.

Current report — wording carried from elsewhere

An increase in Bitcoin network transaction fees increases mining proceeds.

Current report — wording carried from elsewhere

competition for digital asset production. For bitcoin, this increased competition is described as the network hash rate resulting from the

Current report — wording carried from elsewhere

growth in the overall quantity and quality of miners working to solve blocks on the bitcoin blockchain, and the difficulty index

Current report — wording carried from elsewhere

associated with the secure hashing algorithm employed in solving the blocks. Increases in network hash rate generally increase

Current report — wording carried from elsewhere

upgrade their mining equipment to remain profitable and compete effectively with other miners. Difficulty and network conditions are

Current report — wording carried from elsewhere

The cost and availability of electricity are affected primarily by changes in seasonal demand, with peak demand during the summer

Current report — wording carried from elsewhere

months driving higher costs and increased curtailments to support grid operators. Severe winter weather can increase the cost of

Current report — wording carried from elsewhere

electricity and the frequency of curtailments when it results in damage to power transmission infrastructure that reduces the grid’s

Current report — wording carried from elsewhere

ability to deliver power. Geopolitical and macroeconomic factors, such as overseas military or economic conflict between states, can

Showing the first 40 of 87 passages. Open the source sections for the rest.

Rearranged previous paragraphs (2)

Previous report — wording carried elsewhere

Change in fair value of digital assets

Previous report — wording carried elsewhere

Change in fair value of digital assets