STRATEGIC DEVELOPMENTS
We continue to plan, develop, and hold or seek development rights for unique properties primarily in Ward Village, The Woodlands, Bridgeland, Summerlin, Columbia, and Teravalis. We continue to execute our strategic plans for developing several of these assets with construction either actively underway or pending. Strategic Developments are transferred into our Operating Assets segment when the asset is placed in service.
The following table summarizes our Strategic Developments projects under construction as of December 31, 2025:
| $ in thousands | Asset Type | Location | Size (a) | Total Estimated Cost (b) | Estimated Completion | Estimated Stabilization Date |
|---|---|---|---|---|---|---|
| Strategic Developments Under Construction | ||||||
| Bridgeland | ||||||
| Memorial Hermann Medical Office | Office | Cypress, TX | 50,895 sq ft | $23,661 | Q2 2026 | 2029 |
| The Woodlands | ||||||
| 7 Waterway (c) | Office | The Woodlands, TX | 186,369 sq ft | 39,181 | Q2 2026 | 2029 |
| Condominiums | ||||||
| Under Construction | ||||||
| Kalae | Condominium | Honolulu, HI | 329 units / 2,000 sq ft | 623,745 | 2028 | N/A |
| The Park Ward Village | Condominium | Honolulu, HI | 545 units / 26,800 sq ft | 613,807 | Q2 2026 | N/A |
| The Ritz-Carlton Residences | Condominium | The Woodlands, TX | 111 units / 5,800 sq ft | 369,465 | 2027 | N/A |
| Completed and Sold Out | ||||||
| ‘A‘ali‘i | Condominium | Honolulu, HI | 750 units / 11,175 sq ft | 390,138 | Completed | N/A |
| Ae`o | Condominium | Honolulu, HI | 465 units / 70,800 sq ft | 430,086 | Completed | N/A |
| Anaha | Condominium | Honolulu, HI | 317 units / 16,048 sq ft | 403,796 | Completed | N/A |
| Ke Kilohana | Condominium | Honolulu, HI | 423 units / 28,386 sq ft | 217,318 | Completed | N/A |
| Kō'ula | Condominium | Honolulu, HI | 565 units / 36,995 sq ft | 481,302 | Completed | N/A |
| Ulana Ward Village (d) | Condominium | Honolulu, HI | 696 units / 32,100 sq ft | 402,914 | Completed | N/A |
| Victoria Place | Condominium | Honolulu, HI | 349 units | 539,017 | Completed | N/A |
| Waiea | Condominium | Honolulu, HI | 177 units / 7,716 sq ft | 542,631 | Completed | N/A |
(a)For condominium units and multifamily assets, square feet represents ground floor retail space whereas units represents residential units for sale or rent.
(b)As of December 31, 2025, total estimated cost remaining to be spent on these properties was $857.9 million, of which $180.9 million is expected to be funded by HHH with the remaining cost to be funded with existing construction loans and condominium buyer deposits.
(c)The Company acquired this office property in the second quarter of 2025 for $16.3 million, and commenced a redevelopment project in the third quarter of 2025. Total estimated cost for 7 Waterway is inclusive of acquisition, closing, redevelopment, and tenant lease-up costs.
(d)The Company completed construction at Ulana in November 2025. However, landlord work is still ongoing for the retail section of the property as of December 31, 2025. The retail space is expected to be placed in service as leases are executed.
| PROPERTIES | Table of ContentsIndex to Financial Statements |
|---|
The following table summarizes future Strategic Developments projects as of December 31, 2025:
| Location | Size | |
| Future Strategic Developments Rights or Pending Construction | ||
|---|---|---|
| The Woodlands | ||
| 2000 Woodlands Parkway (a) | The Woodlands, TX | 7,900 sq ft |
| Ward Village | ||
| ‘Ilima (b) | Honolulu, HI | 148 units / 5,000 sq ft |
| The Launiu (c) | Honolulu, HI | 485 units / 10,000 sq ft |
| Melia (b) | Honolulu, HI | 220 units / 6,000 sq ft |
| Other | ||
| West End Alexandria (d) | Alexandria, VA | 41 acres |
| Commercial Land | ||
| Columbia | ||
| Columbia Commercial Land (e) | Columbia, MD | 99 acres |
| Merriweather District (e)(f) | Columbia, MD | 26 acres |
| Ward Village | ||
| Ward Commercial Land (e) | Honolulu, HI | 6 acres |
(a)2000 Woodlands Parkway was transferred to Strategic Developments in 2023. The Company expects to execute a new lease in 2026, and transfer the property back to Operating Assets.
(b)We launched pre-sales for these condominiums in June 2025, and as of December 31, 2025 we have entered into contracts for 51% of the total units at ‘Ilima and 65% of the total units at Melia.
(c)As of December 31, 2025, we have entered into contracts for 346 units at The Launiu, representing 71% of total units. Construction is expected to begin in early 2026.
(d)Represents acreage owned through a joint venture.
(e)Represents land acquired or transferred to the Strategic Developments segment for future development, excluding acreage related to assets that are now in service in our Operating Assets segment or related to completed or under construction condominium towers.
(f)Includes acreage from the Lakefront District development that is now considered a part of Merriweather District following rebranding efforts for the area.