A company's yearly report to the SEC, with audited financial statements. It is the fullest account a company gives of its business, its finances and the risks it sees.
FY2025 · Filed Feb 17, 2026
What changed in Management’s Discussion and Analysis?
Read the current filingPrevious report: 10-K
Period ended 2024-12-31; filed 2025-02-14.
0000072741-25-000007
Item 7. Management’s Discussion and Analysis of Financial Condition and Results of OperationsCurrent report: 10-K
Period ended 2025-12-31; filed 2026-02-17.
0001628280-26-008461
Item 7. Management’s Discussion and Analysis of Financial Condition and Results of OperationsThe baseline is this issuer’s latest earlier reporting period of the same form that was filed before the current report. A previous 10-Q is a different quarter, not a year-over-year comparison. Amendments are excluded.
Compared 298 previous paragraphs and 309 current paragraphs.
119 unchanged; 111 reworded; 74 added; 66 removed; 2 previous and 5 current paragraphs rearranged.
Tables are not compared: 24 previous and 28 current tables excluded. Dates, whitespace, punctuation and numbering changes are ignored; changes to financial figures remain significant.
A changed paragraph is not evidence that risk increased or decreased. An unchanged paragraph does not establish that risk stayed the same.
Added paragraphs (74)
Current report
Regulatory Developments:
Current report
•On July 25, 2025, the NHPUC issued its decision in the PSNH distribution rate case and approved a permanent rate increase of $100.7 million, effective August 1, 2025, inclusive of the temporary rate increase that went into effect in August 2024. The order established an authorized regulatory ROE of 9.5 percent with a 50 percent common equity ratio for PSNH’s capital structure. The NHPUC approved an alternative regulatory framework that authorizes formulaic annual revenue adjustments on August 1st of 2026, 2027 and 2028.
Current report
•On November 3, 2025, EGMA, NSTAR Electric, and the Massachusetts Office of the Attorney General reached a joint settlement agreement that resolved outstanding issues in multiple open Pension Adjustment Mechanism (PAM) dockets and open Resiliency Tree Work (RTW) dockets at NSTAR Electric and allows recovery of transaction and integration costs related to Eversource’s acquisition of EGMA. The settlement agreement was approved by the DPU on December 1, 2025. The settlement resulted in a net pre-tax benefit to earnings of $64.8 million on the Eversource income statement in the fourth quarter of 2025.
Current report
•On November 5, 2025, PURA issued a final decision in the Yankee Gas distribution rate case that included a distribution rate increase of $95.7 million, which excluded a previously recorded non-firm margin rate credit of $13.5 million to be refunded annually over three years, effective November 1, 2025. The final decision also established an authorized net regulatory ROE of 9.32 percent and a 53 percent common equity ratio for Yankee Gas’ capital structure. Yankee Gas filed motions to request PURA reconsider the disallowances of certain capitalized overhead costs, certain computational errors, and other issues identified in its final decision. A final decision on the reconsideration is expected from PURA by March 15, 2026.
Current report
•On November 19, 2025, PURA denied an application to approve the sale of the Aquarion Water Company, finding that the transaction did not meet managerial suitability and responsibility requirements due to concerns with governance and oversight structure over Aquarion and its consumer advocate. On January 15, 2026, the Connecticut Superior Court issued a decision on the appeal of PURA’s denial, sustaining the appeal and remanding back to PURA. A final decision is expected by PURA on March 25, 2026.
Current report
•On December 30, 2025, NSTAR Gas and the Massachusetts Office of the Attorney General reached a joint settlement agreement that allowed for the reinstatement of a rate base reset of $45.0 million increase to base distribution rates effective January 1, 2026 and for continuation of NSTAR Gas’ PBR program through November 1, 2030. The settlement agreement also required NSTAR Gas to provide credits to customers and a concession to the Office of the Attorney General, among other items. The DPU approved the settlement agreement on January 16, 2026. The settlement agreement resulted in a pre-tax charge to earnings of $12.2 million in the fourth quarter of 2025.
Current report
•On January 30, 2026, the New Hampshire Department of Energy filed a notice of appeal with the New Hampshire Supreme Court challenging certain aspects of the PSNH distribution rate case decision approved by the NHPUC on July 25, 2025, including the alternative regulatory framework and the revenue requirement. On February 6, 2026, the Office of the Consumer Advocate filed a notice of cross-appeal challenging other aspects of the rate case decision. Eversource is currently evaluating the appeals.
Current report
The impact of higher shares outstanding resulted in $0.17 earnings per share dilution in 2025, as compared to 2024.
Current report
Eversource Parent and Other Companies: Eversource parent and other companies’ losses decreased $425.8 million in 2025, as compared to 2024, due primarily to an after-tax charge of $524.0 million recorded in 2024 resulting from the sale of Eversource parent’s offshore wind investments, as compared to an aggregate net after-tax charge of $75.0 million recorded in 2025 resulting from an increase to the offshore wind contingent liability, net of tax benefits associated with the tax losses on the sales of its offshore wind investments.
Current report
Excluding these charges, Eversource parent and other companies losses increased $23.2 million due to higher interest expense from the absence in 2025 of capitalized interest as a result of the sale of our offshore wind projects in the third quarter of 2024 and higher interest costs from short-term debt, partially offset by the allowed recovery of previously expensed acquisition-related and integration costs of EGMA as part of the joint settlement agreement approved in Massachusetts on December 1, 2025.
Current report
Offshore Wind Sale and Contingent Liability: On July 9, 2024, Eversource completed the sale of its 50 percent ownership share of Sunrise Wind to Ørsted. On September 30, 2024, Eversource completed the sale of its 50 percent ownership share in the South Fork Wind and Revolution Wind projects to GIP. Eversource recorded a contingent liability relating to expected future payments to GIP as part of the sale of the South Fork Wind and Revolution Wind projects. As part of the definitive agreement with GIP, Eversource is responsible for certain post-closing purchase price adjustments. This obligation includes an expected cost overrun sharing obligation, an expected obligation to maintain GIP’s internal rate of return, and an obligation for other future costs prior to commercial operation. Eversource recognized an aggregate after-tax loss on the sales of its offshore wind investments of $524 million, which included a net $60 million increase in income tax expense including an increase in the valuation allowance for unused capital losses, in 2024.
Current report
In the third quarter of 2025, Eversource received an updated report from GIP on the construction status of Revolution Wind, which included revised projections of total construction costs. The revised cost projections reflected known and quantifiable cost increases, including those associated with the impacts of damage to the wind turbine installation vessel, insurance costs, tariff impacts, and costs incurred as a result of the stop-work order for Revolution Wind received on August 22, 2025 from the Bureau of Ocean Energy Management that halted all offshore wind construction activities through September 22, 2025. Based on those developments, Eversource recognized a pre-tax charge of $284.0 million in the third quarter of 2025 as a result of the aggregate impact of these items to increase the liability for purchase price adjustments associated with the offshore wind projects.
Current report
Payments made in 2025 reduced the contingent liability and are reflected within investing activities on the statement of cash flows. These payments included cost overruns for the Revolution Wind project paid to GIP, insurance payments, and the purchase price adjustment payment related to the South Fork Wind project paid to GIP.
Current report
Eversource continually evaluates the contingent liability and will reassess the balance as new information becomes available. Based on most recent updates from GIP on the construction status of Revolution Wind, factoring in estimated costs incurred as a result of a second stop-work order for Revolution Wind received on December 22, 2025 and removed on January 12, 2026, revised insurance costs, and other information currently available, Eversource believes that the contingent liability balance as of December 31, 2025 is a reasonable estimate to cover this contingent liability for purchase price adjustments. As of December 31, 2025, the contingent liability totaled $448.2 million and is recorded as a current liability on Eversource’s balance sheet, based upon the timing of expected payments to GIP. The contingent liability totaled $365.0 million as of December 31, 2024.
Current report
Eversource relies on information that it receives from the project owners for the construction-related, delay-related, and insurance-related costs of Revolution Wind. Eversource uses its judgment to adjust, as needed, its expected obligations to GIP while construction of Revolution Wind is completed.
Current report
New information or future developments that arise as the construction of Revolution Wind progresses will necessitate a reassessment of the estimated liability to GIP. The Company reviews available projections of total construction costs, including the latest cost estimates and project timeline, to determine if any changes to this liability are warranted.
Current report
It is reasonably possible that as additional updated cost estimates become available, and if additional cost overruns materialize or other adverse changes in facts, regulations and circumstances occur, it could result in additional losses and increases to the offshore wind contingent liability, which could be material. The Company will continue to monitor developments and evaluate potential exposures related to this contingency and will revise its estimated liability as additional information becomes available.
Current report
Eversource recognized an aggregate, net after-tax charge of $75.0 million, or $0.20 per share, in 2025 resulting from our previous offshore wind investments. This charge consists of the pre-tax $284 million increase to the offshore wind contingent liability, offset by $209 million of tax benefits associated with tax losses on the sale of the South Fork Wind and Revolution Wind projects that Eversource expects to realize.
Current report
On November 19, 2025, PURA denied the application to approve the sale, finding that the transaction did not meet managerial suitability and responsibility requirements due to concerns with governance and oversight structure over Aquarion and its consumer advocate. On December 2, 2025, the denial was appealed to the Connecticut Superior Court. On January 15, 2026, the Court issued its decision, sustaining the appeal and remanding back to PURA, finding that PURA acted illegally in denying the application as those disputed governance elements were mandated under Connecticut law. The Court upheld that operational aspects of the consumer advocate were within PURA’s statutory authority and regulatory discretion. A final decision is expected by PURA on March 25, 2026.
Current report
Based on PURA’s November 19, 2025 denial of the sale and the uncertainty of the ultimate outcome, the Aquarion water distribution business no longer met the criteria to be classified as held for sale and its assets and liabilities were reclassified as held and used on the balance sheet as of December 31, 2025. The reclassification to held and used did not result in an adjustment to Aquarion’s carrying values.
Current report
Additionally, investments for the water distribution business are expected to total approximately $1.3 billion from 2026 through 2030.
Current report
On July 14, 2025, PURA issued proposed final decisions in the first two reopener dockets. The proposed final decision in the first reopener docket adopted a PBR framework inclusive of a multi-year rate plan with an attrition relief mechanism that uses a revenue-cap formula approach to adjust revenues based on a variety of factors including inflation, a productivity factor, a customer dividend percentage, an exogenous cost factor and a capital funding mechanism, as well as an earnings sharing mechanism and a revenue decoupling mechanism for implementation in CL&P’s next distribution rate case. The multi-year rate plan has a stay out period of four years, but certain situations, such as deteriorating financial condition, exceeding authorized return, falling interest rates, or excess storm costs, could trigger the initiation of a new rate amendment proceeding during the multi-year rate plan. The proposed final decision in the second reopener docket established reporting parameters, including the commencement of scorecards and reported metrics and the development of company specific performance incentive mechanisms. Results of scorecards and reported metrics are proposed to be reported annually to PURA, beginning March 1, 2026. Company specific performance incentive mechanisms will be implemented in CL&P’s next rate case proceeding.
Current report
On August 8, 2025, PURA issued a proposed final decision in the third reopener docket, adopting the contents and reporting process for an integrated distribution system plan (IDSP) under a PBR framework. The IDSP report will document the grid planning process for available distribution system capacity and system needs, including the development, operation, and evolution of the electrical distribution grid. The IDSP report will include CL&P’s planned investments over a four-year plan period and long-term capital investment strategy, and will be utilized by PURA in determining the amount of allowable capital additions within a multi-year rate plan included in the calculation of the capital funding mechanism adopted in the first reopener docket. The draft decision requires CL&P to submit a comprehensive IDSP filing every four years in alignment with the submittal of a rate amendment application and to also submit an annual IDSP filing to report on IDSP investments throughout the four-year period.
Current report
CL&P RAM Filing: On March 28, 2025, PURA issued an interim decision in CL&P’s Rate Adjustment Mechanisms (RAM) filing and approved rates for six RAM components, with rates effective May 1, 2025 through April 30, 2026. The rates include recovery of over- or under-collection balances as of December 31, 2024, actual costs from the prior year, and adjustments to incorporate certain known and measurable cost changes not reflected in prior year costs that CL&P will incur in 2025. On August 13, 2025, PURA issued a final decision that approved a further adjustment to the Non-Bypassable Federally Mandated Congestion Charge (NBFMCC) and System Benefits Charge (SBC) rates based on a July 1, 2025 Connecticut law that authorized the State of Connecticut to issue new general obligation bonds to reduce certain hardship costs and electric vehicle program costs recovered from customers. Proceeds from the general obligation bond funding of $107.8 million will be provided back to customers through a reduction to the NBFMCC and SBC rates. The updated NBFMCC and SBC rates are effective September 1, 2025 through April 30, 2026. These rates are included in the “Public Benefits” portion of the customer bills in Connecticut.
Current report
On September 19, 2025, CL&P received $107.8 million in general obligation bond proceeds from the State of Connecticut, which represent reimbursement of incurred costs that were previously recognized as regulatory assets on CL&P’s balance sheets. The proceeds received for the reimbursement of hardship costs and for electric vehicle charging program costs were credited against the SBC and NBFMCC regulatory deferrals on CL&P’s balance sheet as of December 31, 2025. The proceeds from the state bond funding are presented as a cash inflow in Regulatory Recoveries within operating activities on CL&P’s statement of cash flows.
Current report
Yankee Gas Distribution Rate Case: On November 12, 2024, Yankee Gas filed an application with PURA to amend its existing distribution rates for effect on November 1, 2025. Yankee Gas had subsequently amended its rate application to request approval of a distribution rate increase of $193 million. On September 22, 2025, PURA issued a proposed final (draft) decision in Yankee Gas’s distribution rate case that included a distribution rate increase of $55.6 million, effective November 1, 2025.
Current report
On November 5, 2025, PURA issued a final decision in the Yankee Gas distribution rate case that included a distribution rate increase of $82.2 million and a total distribution revenue requirement of $802.2 million, effective November 1, 2025. The approved revenue requirement includes a previously recorded rate credit of $37.4 million plus carrying charges for non-firm margin credits over three years beginning November 1, 2025. Excluding the rate credit, the distribution rate increase totaled $95.7 million. The final decision also established an authorized net regulatory ROE of 9.32 percent, adopting a 9.48 percent ROE net of certain reductions totaling 16 basis points, and a 53 percent common equity ratio for Yankee Gas’ capital structure. PURA declined to approve the multi-year performance-based rate making plan that would adjust rates annually as proposed by Yankee Gas. PURA also implemented an annual cap on contemporaneous cost recovery of aging infrastructure replacement spending in the
Current report
Distribution Integrity Management Program (DIMP) rate tracking mechanism of $139.9 million, in which spending above the annual cap will be deferred for recovery until the next distribution rate case. The final decision resulted in a net pre-tax loss to earnings of $8.5 million in the fourth quarter of 2025, primarily for the write off of certain capitalized employee compensation costs that were disallowed from rate base. Yankee Gas filed motions to request PURA reconsider the disallowances of these capitalized costs, certain computational errors, and other issues identified in its final decision. On December 15, 2025, PURA issued a notice of reconsideration to reconsider the final decision. A final decision on the reconsideration is expected from PURA by March 15, 2026.
Current report
On March 28, 2024, AWC-CT filed an appeal of the March 25, 2024 Connecticut Superior Court decision to the Connecticut Appellate Court, and that appeal was subsequently transferred to the Connecticut Supreme Court. On July 9, 2025, the Connecticut Supreme Court issued a decision that overturned PURA’s disallowance of $1.5 million in water conservation program expenses, but affirmed the remaining portions of PURA’s decision that were challenged on appeal. The Connecticut Supreme Court decision also validated AWC-CT’s argument that the correct legal standard PURA must use in determining whether costs can be recovered through customer rates is the longstanding prudence standard, which evaluates the prudence of management decision-making as of the time the utility made the decision to incur costs; PURA cannot use improper hindsight analysis to evaluate prudence. On December 10, 2025, PURA revised its July 31, 2024 decision and increased AWC-CT’s approved revenue requirement by $0.3 million reflecting recovery of the $1.5 million conservation program expenses over six years.
Current report
On June 13, 2025, the DPU issued an order in the Phase II proceeding on the interim cost recovery mechanism for the ESMP, which approved the interim cost recovery mechanism with certain modifications. In the order, the DPU emphasized its attempt to balance affordability and the goals of advancing Massachusetts’ clean energy goals through proactive investments to support electrification and distributed generation. NSTAR Electric received approval for its proposed grid modernization and resiliency investments and incremental expense for a total spending cap of $139 million, reflecting an ordered reduction in capital spending on undergrounding for resiliency. In compliance with the Phase II order, a revised tariff was filed June 23, 2025, and the revised ESMP spending cap for the first term of July 1, 2025 through June 30, 2030, which included company-proposed incremental capital investment of $95 million and incremental expense of $44 million, was filed June 30, 2025. The DPU is conducting another phase of this proceeding to establish a long-term cost recovery mechanism, which is expected to be through base distribution rates.
Current report
NSTAR Gas Distribution Rates: NSTAR Gas’ PBR mechanism allows for an annual adjustment to base distribution rates for inflation and exogenous events. On June 16, 2025, NSTAR Gas submitted its annual PBR Adjustment filing for rates to be effective on November 1, 2025. On September 11, 2025, NSTAR Gas updated its filing to request approval of a $162.6 million increase to base distribution rates and a total base distribution revenue requirement of $447.7 million. The base distribution rate increase is comprised of a $10.3 million inflation-based adjustment and, in accordance with the DPU’s final decision in the 2020 NSTAR Gas rate case, a $152.3 million rate-base reset to incorporate capital additions for the period 2021 through 2024, which includes the transfer of GSEP revenues totaling $107.3 million into base rates, as well as other non-GSEP plant additions totaling $45.0 million.
Current report
On October 29, 2025, the DPU issued a decision determining that NSTAR Gas was not eligible to increase its distribution rates for the rate base reset because it did not achieve certain performance metrics under its PBR plan, and did not allow the base rate increase of $45.0 million for the incorporation of non-GSEP plant additions into base rates. The decision stated that those investments could be considered for inclusion in base distribution rates in NSTAR Gas’s next base rate proceeding. The DPU did allow NSTAR Gas to transfer its GSEP revenues through 2024 of $107.3 million for recovery through base distribution rates effective November 1, 2025. The DPU approved the base distribution rate increase of $10.3 million for the inflation-based adjustment. The DPU also approved NSTAR Gas’ mitigation proposal, in which NSTAR Gas paused recovery of the Gas System Enhancement Adjustment Factor (GSEAF) and reduced the current GSEAF to zero on November 1, 2025 in order to align this decrease with the base rate increase and to mitigate November 1, 2025 bill impacts to customers. NSTAR Gas will begin to recover the remaining 2025 GSEP revenue requirement on May 1, 2026 over 18 months. On November 4, 2025, NSTAR Gas filed a motion requesting the DPU to reconsider its decision denying the rate base reset citing legal concerns and arguing that the decision will ultimately result in higher costs for customers. NSTAR Gas also notified the DPU of its intention to file a base distribution rate case.
Current report
On December 30, 2025, NSTAR Gas and the Massachusetts Office of the Attorney General reached a joint settlement agreement that allowed for the reinstatement of the rate base reset of $45.0 million increase to base distribution rates effective January 1, 2026, for NSTAR Gas to not petition for a rate case with new rates effective December 1, 2026, and for continuation of NSTAR Gas’ PBR program through November 1, 2030. The settlement agreement also required NSTAR Gas to provide a credit to customers of $10.2 million over a ten-month period beginning January 2026 as penalty for its failure to meet three performance metrics as required for eligibility for the rate base reset, pay a $2 million concession to the Office of the Attorney General to fund customer energy assistance programs, waive recovery of certain carrying charges, delay recovery of $53 million of capital pipeline investments until the next rate case, and provide bill stabilization credit deferrals. The DPU approved the settlement agreement on January 16, 2026. The settlement agreement resulted in a pre-tax charge to earnings of $12.2 million in the fourth quarter of 2025.
Current report
NSTAR Electric and EGMA Settlement: On November 3, 2025, EGMA, NSTAR Electric, and the Massachusetts Office of the Attorney General reached a joint settlement agreement that resolved outstanding issues in multiple open Pension Adjustment Mechanism (PAM) dockets and open Resiliency Tree Work (RTW) dockets at NSTAR Electric and allows recovery of transaction and integration costs related to Eversource’s acquisition of EGMA. Certain PAM and RTW collections are being refunded to NSTAR Electric’s customers over a one-year period beginning January 1, 2026 and the transaction and integration costs of $82.3 million will be collected from EGMA customers over a ten-year period from the time of the next EGMA rate case. The settlement agreement was approved by the DPU on December 1, 2025. The settlement resulted in a net pre-tax benefit to earnings of $64.8 million on the Eversource income statement in the fourth quarter of 2025 ($82.3 million benefit at Eversource Parent and Other Companies for the allowed recovery of previously expensed acquisition-related and integration costs and $17.5 million charge at NSTAR Electric) and a net increase to regulatory assets on the Eversource balance sheet.
Current report
Massachusetts 2026 Winter Bill Relief Program: In February 2026, NSTAR Electric, NSTAR Gas and EGMA implemented a winter electric and natural gas bill relief program as required by the DPU. Under this program, in February and March 2026, residential electric customers in Massachusetts will receive an aggregate bill reduction of approximately 25 percent and residential natural gas customers will receive an aggregate bill reduction of approximately 10 percent, a portion of which will be funded by the Commonwealth of Massachusetts. The remaining bill credits will be deferred for recovery from electric customers between April and December 2026 and from natural gas customers between May and October 2026, subject to DPU approval. No carrying charges will be collected. The bill relief program results in delayed collections from customers, impacting the timing of cash flows. Proceeds of $84.1 million were received by NSTAR Electric in January 2026 and will reduce regulatory assets recorded on its balance sheet in the first quarter of 2026.
Current report
Also on June 11, 2024, PSNH filed an application with the NHPUC to request an increase in permanent base distribution rates of $181.9 million, which is inclusive of the temporary rate increase. Throughout the course of the proceeding, PSNH amended the requested revenue requirement to account for developments in the case, and arrived at a final proposed rate increase of $103 million, which primarily reflects the removal of deferred storm costs that will be addressed in a separate proceeding. On July 25, 2025, the NHPUC issued its decision on permanent rates and approved a permanent rate increase of $100.7 million, effective August 1, 2025, inclusive of the temporary rate increase referenced above. The total base distribution revenue requirement effective August 1, 2025 is $519 million. The order also established an authorized regulatory ROE of 9.5 percent with a 50 percent common equity ratio for PSNH’s capital structure.
Current report
This revenue requirement also contains an alternative regulation revenue requirement adjustment. This adjustment was part of the NHPUC’s alternative regulatory framework that the NHPUC adopted as an alternative to PSNH’s proposed performance-based regulation plan. The alternative regulatory framework authorizes formulaic annual revenue adjustments on August 1st of 2026, 2027 and 2028. PSNH is required to file its next base distribution rate case for effect in June 2029 and committed not to file its next distribution rate case until 2029. The alternative regulatory framework calculates the annual revenue adjustment using a productivity factor and an adjustment for inflation to provide PSNH with increased revenue for operations. The framework also contains an exogenous events recovery mechanism for certain unforeseen events out of PSNH’s control and exceeding a specified threshold, a performance metric, and an earnings sharing mechanism where PSNH would have to return 75 percent of all revenue back to customers that exceeds 25 basis points more than the authorized ROE of 9.5 percent. Consistent with PSNH’s proposal, lost base revenues for both net metering and energy efficiency were eliminated effective August 1, 2025.
Current report
To the extent permanent rates exceed the level of temporary rates, the difference will reconcile back to the date that the temporary rates took effect and the company recovers the difference over a twelve-month term. On August 11, 2025, PSNH filed its recoupment calculation, and on September 10, 2025, the NHPUC issued an order that the recoupment is $9.1 million and will be collected through the RRA regulatory tracking mechanism over a one-year period.
Current report
As part of the decision, unrecovered storm costs of $247 million were removed from the rate proceeding for consideration in a separate proceeding. Approval of the ultimate amount of storm costs to be recovered is subject to a separate prudency review that was filed in March of 2024 and is being considered by the NHPUC in a separate dedicated docket, which is at this time complete and awaiting the issuance of an order. Approved storm costs in excess of the amount approved in base rates will be recovered through the Regulatory Reconciliation Adjustment (RRA) regulatory tracking mechanism. The NHPUC increased the level of storm costs recovered in base rates from $12 million to $19 million.
Current report
The impact of the rate case decision resulted in a pre-tax benefit to earnings of $15.6 million at PSNH due primarily to the recoupment and the allowed recovery of other deferrals that will be recovered in the RRA. The majority of this amount was recorded as a reduction to amortization expense on PSNH’s statement of income in 2025.
Showing the first 40 of 74 passages. Open the source sections for the rest.
Removed paragraphs (66)
Previous report
Strategic Developments:
Previous report
•In the third quarter of 2024, Eversource completed the sale of its 50 percent ownership share in the Sunrise Wind project to Ørsted for adjusted proceeds of $152 million and completed the sale of its 50 percent ownership share in the South Fork Wind and Revolution Wind projects to GIP for adjusted gross proceeds of $745 million. Eversource recognized an aggregate net after-tax loss on the sales of its offshore wind investments of $524 million. Eversource recorded a contingent liability of $365 million, reflecting its estimate of the future obligations under the GIP sale terms, which include an expected cost overrun sharing obligation, expected obligation to maintain GIP’s internal rate of return, and obligation for other future costs. Eversource does not have any ongoing financial obligations associated with Sunrise Wind.
Previous report
(4)Transaction costs in 2022 primarily include costs associated with the transition of systems as a result of our purchase of the assets of Columbia Gas of Massachusetts (CMA) on October 9, 2020 and integrating the CMA assets onto Eversource’s systems.
Previous report
Eversource Parent and Other Companies: Eversource parent and other companies’ losses decreased $1.37 billion in 2024, as compared to 2023, due primarily to the loss on the sale of Eversource parent’s offshore wind investments in 2024, which resulted in an after-tax charge of $524.0 million, as compared to an impairment charge on these investments in 2023 of $1.95 billion. Results for 2023 also include a loss on the disposition of land that was initially acquired to construct the Northern Pass Transmission project and was subsequently abandoned and other charges recorded of $6.9 million. Excluding these charges, Eversource parent and other companies earnings decreased by $66.3 million due primarily to higher interest expense and the absence of a benefit in 2023 from the liquidation of Eversource parent’s equity method investment in a renewable energy fund, partially offset by the absence of a charitable contribution made in 2023 with a portion of the proceeds from the liquidation, and a lower effective tax rate.
Previous report
Eversource is currently in the process of selling its Aquarion water distribution business. For information regarding the pending sale and use of proceeds, see "Business Development and Capital Expenditures - Pending Sale of Aquarion" included in this Management's Discussion and Analysis of Financial Condition and Results of Operations.
Previous report
As a result of the CL&P long-term debt issuance in January 2025, $397.1 million of current portion of long-term debt was reclassified to Long-Term Debt on Eversource’s and CL&P’s balance sheets as of December 31, 2024.
Previous report
In June 2024, Moody’s revised the outlook from stable to negative for CL&P citing a weaker financial profile and a challenging Connecticut regulatory environment. In December 2024, S&P downgraded the ratings for Eversource parent and its subsidiaries primarily due to S&P's negative assessment of the Connecticut regulatory construct for Eversource’s Connecticut utilities. These credit ratings and outlook changes reflect higher regulatory risk in Connecticut with the regulatory construct and adverse regulatory developments, including recent rate orders and the passage of Senate Bill 7, negatively impacting the credit quality of Eversource and its subsidiaries.
Previous report
The projected capital expenditures reflect a reduction in planned capital expenditures for Connecticut’s electric and natural gas distribution businesses due to regulatory policies in Connecticut that discourage investment, including ensuring the timely recovery of costs and the ability to earn a fair return. The continuing pattern of adverse regulatory outcomes for Connecticut utilities and associated credit downgrades from our credit rating agencies necessitated a reduction to Connecticut’s electric and natural gas distribution projected capital expenditures. These capital reductions do not impact Eversource’s commitment to safety, reliability, or critical staffing structure.
Previous report
Projected capital expenditures for the water distribution business of $130 million are expected until the time of sale in late 2025 and have been factored into the water business impairment recorded as of December 31, 2024.
Previous report
Offshore Wind Business: Eversource’s previous offshore wind business included 50 percent ownership interests in each of North East Offshore and South Fork Class B Member, LLC. During 2024, Eversource sold its interest in these entities, and in doing so, sold its interests in the Revolution Wind project, the South Fork Wind project, and the Sunrise Wind project. Eversource’s current offshore wind business is now comprised only of a noncontrolling tax equity investment in South Fork Wind through a 100 percent ownership in South Fork Wind Holdings, LLC Class A interests.
Previous report
On May 25, 2023, Eversource announced that it had completed a strategic review of its offshore wind investments and determined that it would pursue the sale of its offshore wind investments. On September 7, 2023, Eversource completed the sale of its 50 percent interest in an uncommitted lease area consisting of approximately 175,000 developable acres located 25 miles off the south coast of Massachusetts to Ørsted for $625 million in an all-cash transaction.
Previous report
In September of 2023, Eversource made a $528 million investment in a tax equity interest for South Fork Wind. South Fork Wind was restructured as a tax equity investment, with Eversource purchasing 100 percent ownership of a new Class A tax equity membership interest. This investment will result in Eversource receiving cash flow benefits from investment tax credits (ITC) and other future cash flow benefits as well. As of December 31, 2024, $459 million of expected investment tax credits and other expected tax benefits were reclassified from the South Fork Wind tax equity investment balance reported in Investments in Unconsolidated Affiliates as a decrease in Accumulated Deferred Income Taxes on the Eversource balance sheet, which represented a non-cash reclassification. As a result of these investment tax credits, Eversource expects lower federal income tax payments from 2025 to 2027. As of December 31, 2024, the tax equity interest in South Fork Wind totaled $22.2 million.
Previous report
On January 24, 2024, Eversource entered into an agreement with Ørsted to sell Eversource’s 50 percent share of Sunrise Wind, subject to certain conditions and regulatory approvals. On April 18, 2024, Eversource and Ørsted executed an equity and asset purchase agreement and on July 9, 2024, Eversource completed the sale of its 50 percent ownership share of Sunrise Wind to Ørsted. In accordance with the equity and asset purchase agreement and after adjustment for a reduction in capital spending compared to forecasted amounts, adjusted proceeds totaled $152 million. Ørsted paid Eversource $118 million at the closing of the sale transaction, which was used to repay parent company debt. Remaining proceeds of $34 million will be paid after onshore construction is completed and certain other construction milestones are achieved. The remaining expected proceeds have been recorded in Other Long-Term Assets on Eversource’s balance sheet as of December 31, 2024. Eversource recorded a pre-tax gain on the sale of Sunrise Wind of $377 million in 2024. With completion of the sale, Eversource does not have any ongoing financial obligations associated with Sunrise Wind.
Previous report
On February 13, 2024, Eversource executed an agreement to sell its 50 percent interests in the South Fork Wind and Revolution Wind projects to Global Infrastructure Partners (GIP) for an initial gross purchase price of approximately $1.1 billion. The initial purchase price was subject to adjustment based on, among other things, the progress, timing and the construction cost of Revolution Wind, including changes in actual versus forecasted capital spending between signing the agreement and closing of the transaction. On September 30, 2024, Eversource completed the sale of its 50 percent ownership share in the South Fork Wind and Revolution Wind projects to GIP for adjusted gross proceeds of $745 million, which were received at closing. Adjusted gross proceeds from the sale were approximately $375 million lower than the previously estimated purchase price. This reduction reflects approximately $150 million resulting from lower capital spending between signing the agreement and closing, and approximately $225 million related to the final terms of the sale transaction, primarily due to the delay of the commercial operations date of Revolution Wind. Proceeds from the transaction were used to repay parent company debt.
Previous report
As part of the Revolution Wind and South Fork Wind sale, Eversource and GIP agreed to make certain post-closing purchase price adjustment payments, which could further impact the final purchase price. The post-closing purchase price adjustment payments include cost sharing obligations that require Eversource to share equally with GIP in GIP’s funding obligations up to an effective cap of approximately $240 million of incremental capital expenditure overruns incurred during the construction phase for Revolution Wind, after which Eversource will have responsibility for GIP’s obligations for any additional capital expenditure overruns in excess of this amount. The purchase price is also subject to post-closing adjustments as a result of final project economics, which includes Eversource’s obligation to maintain GIP’s internal rate of return through the construction period for each project as specified in the agreement. Post-closing purchase price adjustment payments will be made following the commercial operation date of Revolution Wind. South Fork Wind has achieved commercial operation, and Eversource is in the process of finalizing the construction cost post-close purchase price adjustment payment related to this project, which is not expected to be material.
Previous report
Upon the completion of both sale transactions in 2024, the total proceeds were compared to the carrying value of the investments, including an estimate of liability for post-closing adjustment payments to GIP, and Eversource recognized an aggregate, net after-tax loss on the sales of its offshore wind investments of $524 million. The aggregate, net after-tax loss is comprised of (1) the lower proceeds related to final terms of the sale transaction to GIP of approximately $225 million related to non-construction costs for the Revolution Wind and South Fork Wind projects, primarily due to a purchase price reduction of $150 million resulting from the delay of the commercial operations date of Revolution Wind, (2) recently identified forecasted construction costs as a result of a delay in the anticipated commercial operation date related to Revolution Wind of approximately $350 million, which includes an estimate for the anticipated post-closing adjustment to GIP related to Eversource’s expected cost overrun sharing obligation, and (3) approximately $326 million, which includes an estimate for the anticipated post-closing adjustment related to Eversource’s expected obligations to GIP as a result of final economics of the Revolution Wind and South Fork Wind projects and other future costs, as well as a net $60 million increase in income tax expense including an increase in the valuation allowance for unused capital losses. These losses were partially offset by the $377 million gain on the sale of Sunrise Wind.
Previous report
Upon sale, Eversource recorded a contingent liability of $365 million, reflecting its estimate of the future obligations under the GIP sale terms, which include the expected cost overrun sharing obligation, expected obligation to maintain GIP’s internal rate of return, and obligation for other future costs. The majority of this liability is expected to be settled upon the completion of the Revolution Wind project. The long-term portion of the liability of $350 million is recorded in Other Long-Term Liabilities, and $15 million is recorded in Other Current Liabilities on Eversource’s balance sheet as of December 31, 2024.
Previous report
The purchase price included the sales value related to a 40 percent level of federal investment tax credits, 10 percent of which is the energy community investment tax credit (ITC) adder included in the Inflation Reduction Act of approximately $170 million related to Revolution Wind. Although management believes the ITC adder value is realizable, there is some uncertainty at this time as to whether those ITC adders can be achieved, and management continues to evaluate the project’s qualifications and to monitor guidance issued by the United States Treasury Department. A change in the expected value or qualification of ITC adders could result in a significant loss in a future period.
Previous report
New information or future developments that arise as construction progresses and as cost estimates are reviewed and revised will require a reassessment of the estimated liability for the post-closing adjustment payments. The Company is currently aware that construction of the offshore foundations, offshore substation and turbine tower installations could result in increased cost overruns in the future. Only preliminary construction cost projections are available for these cost overruns, and there is insufficient updated information at this point in order for Eversource to change its estimate with reasonably estimable information. Eversource will continue to assess the potential exposure and adjust the liability as needed. It is expected that updated costs estimates will become available in the first half of 2025, and adverse changes in facts and circumstances could result in additional losses that could be material. The Company believes it is reasonably possible that there is an additional loss in excess of the liability recorded, but management cannot reasonably estimate a range of loss beyond the $365 million recorded at this time.
Previous report
Under the agreement with GIP, Eversource’s existing and certain additional credit support obligations for Revolution Wind are expected to roll off as the project completes construction. Under the agreement with Ørsted, Eversource’s existing credit support obligations for Sunrise Wind were either terminated or indemnified by Ørsted as a result of the sale. Eversource has entered into separate construction management agreements to manage Sunrise Wind’s and Revolution Wind’s onshore electric substation construction through completion. In this role, Eversource will be solely a service provider to Sunrise Wind and Revolution Wind.
Previous report
2023 Impairments: Equity method investments are assessed for impairment when conditions exist as of the balance sheet date that indicate that the fair value of the investment may be less than book value. Eversource continually monitors and evaluates its equity method investments to determine if there are indicators of an other-than-temporary impairment. If the decline in value is considered to be other-than-temporary, the investment is written down to its estimated fair value, which establishes a new cost basis in the investment. Impairment evaluations are based on best information available at the impairment assessment date. Subsequent declines or recoveries after the reporting date are not considered in the impairment recognized. Investments that are other-than-temporarily impaired and written down to their estimated fair value cannot subsequently be written back up for increases in estimated fair value. Impairment evaluations involve a significant degree of judgment and estimation, including identifying circumstances that indicate an impairment may exist at the equity method investment level, selecting discount rates used to determine fair values, and developing an estimate of discounted future cash flows expected from investment operations or the sale of the investment.
Previous report
During 2023, in connection with the process to divest its offshore wind business, Eversource identified indicators for impairment in both the second and fourth quarters of 2023. In each impairment assessment, Eversource evaluated its investments and determined that the carrying value of the equity method offshore wind investments exceeded the fair value of the investments and that the decline in fair value was other-than-temporary. The completion of the strategic review in the second quarter of 2023 resulted in Eversource recording a pre-tax other-than-temporary impairment charge of $401 million ($331 million after-tax) to reflect the investment at estimated fair value based on the expected sales price at that time. This established a new cost basis in the investments. Negative developments in the fourth quarter of 2023, including a lower expected sales price, additional projected construction cost increases, and the October 2023 OREC pricing denial for Sunrise Wind, resulted in Eversource conducting an impairment evaluation and recognizing an additional pre-tax other-than-temporary impairment charge of $1.77 billion ($1.62 billion after-tax) and establishing a new cost basis in the investments as of December 31, 2023. The Eversource statement of income for the year ended 2023 reflects a total pre-tax other-than-temporary impairment charge of $2.17 billion ($1.95 billion after-tax) in its offshore wind investments. The impairment charges were non-cash charges and did not impact Eversource’s cash position at the time of the impairment. Eversource’s offshore wind investments did not meet the criteria to qualify for presentation as a discontinued operation.
Previous report
The 2023 impairment evaluations involved judgments in developing the estimates and timing of the future cash flows arising from the expected sales price of Eversource’s 50 percent interest in the wind projects, including expected sales value from investment tax credit adder amounts, less estimated costs to sell, and uncertainties related to the Sunrise Wind re-bid process in New York’s offshore wind solicitation in 2024. Additional assumptions in the fourth quarter 2023 assessment included revised projected construction costs and estimated project cost overruns, management’s assumption that the Sunrise Wind project would ultimately be abandoned, estimated termination costs, salvage values of Sunrise Wind assets, and the value of the tax equity ownership interest. The assumptions used in the discounted cash flow analyses were subject to inherent uncertainties and subjectivity. All significant inputs into the impairment evaluations were Level 3 fair value measurements.
Previous report
A summary of the significant estimates and assumptions included in the 2023 impairment charges is as follows:
Previous report
A summary of the carrying value by investee and by project as of December 31, 2023 is as follows:
Previous report
During 2024, Eversource sold its interest in the North East Offshore and South Fork Class B, Member LLC equity method investments and recognized an aggregate, net after-tax loss on the sale of its offshore wind investments of $524 million.
Previous report
Capital contributions in the offshore wind investments, including the 2023 contribution for the tax equity investment in South Fork Wind, were included in Investments in Unconsolidated Affiliates on the statements of cash flows. Proceeds received from the sale of the investments in 2024, and proceeds received from the 2023 sale of the unused lease area and from an October 2023 distribution of $318 million received primarily as a result of being a 50 percent joint owner in the Class B shares of South Fork Wind which was restructured as a tax equity investment, were included in Proceeds from Unconsolidated Affiliates on the statements of cash flows.
Previous report
CL&P RAM Filing: On April 17, 2024, PURA issued an interim decision in CL&P’s Rate Adjustment Mechanisms (RAM) filing and approved rates for six RAM components, with rates effective July 1, 2024 through April 30, 2025. The rate approvals include the recovery of NBFMCC and SBC net underrecoveries as of December 31, 2023 of $264.9 million and $86.2 million, respectively, and the recovery of expected net costs of $388.5 million for the NBFMCC and $254.4 million for the SBC for the period July 1, 2024 through April 30, 2025. The NBFMCC rate adjustment is primarily driven by long-term nuclear power purchase agreements required by state policy (Millstone and Seabrook) and the SBC rate adjustment is primarily driven by costs associated with accounts receivable hardship customer protection and the new low-income discount rate effective December 2023. On August 14, 2024, PURA issued a final decision that approved a further adjustment to the NBFMCC rate to include the recovery of incurred and deferred electric vehicle program costs from 2021 through May 31, 2024 of $44.4 million and expected electric vehicle program costs from June 1, 2024 through December 31, 2024 of $24.3 million. The $44.4 million, plus $5.4 million in carrying costs, will be recovered over a 20-month period of September 1, 2024 through April 30, 2026, and the $24.3 million will be recovered over an eight-month period of September 1, 2024 through April 30, 2025. In addition, PURA approved an incremental $3.5 million of 2024 Innovative Energy Solutions program costs and $1.5 million of Connecticut Green Bank program costs over an eight-month period of September 1, 2024 through April 30, 2025. These amounts are included in the “Public Benefits” portion of the customer bills in Connecticut.
Previous report
Yankee Gas Distribution Rate Case: On November 12, 2024, Yankee Gas filed an application with PURA to amend its existing distribution rates for effect on November 1, 2025. Yankee Gas’s rate application requested approval of a distribution rate increase of $209 million, which included a base distribution rate increase of $274 million, partially offset by a reduction of $65 million in the combined Gas System Improvements and System Expansion Reconciliation rates. In addition, Yankee Gas requested approval to implement a rate credit of $37.4 million to offset the PGA rate for non-firm margin credits over one year beginning November 1, 2025. As part of the rate case, Yankee Gas proposed to implement a multi-year performance-based rate making plan with a four-year initial term from November 1, 2025 to October 31, 2029 that would adjust rates annually and includes performance metrics. A final decision by PURA is expected in October 2025.
Previous report
As a result of the State of Connecticut Superior Court’s March 2024 decision on the appeal, AWC-CT recorded the impacts of the PURA rate case decision from the effective date of the order on March 15, 2023 through December 31, 2024. The impacts primarily include a reduction to depreciation expense to reflect lower depreciation rates ordered by PURA in its final decision, partially offset by lower authorized revenues. These adjustments resulted in an after-tax benefit of $11.6 million in 2024.
Previous report
NSTAR Electric CIP Filing: On December 30, 2022, the DPU approved a provisional system planning tariff for the recovery of costs associated with a capital investment project (CIP) proposal submitted by NSTAR Electric for one of six geographic study areas in its service territory in accordance with DPU’s directives. The DPU established a new, provisional framework for planning and funding upgrades to the electric power system to foster development and interconnection of distributed energy facilities. Under the DPU program, NSTAR Electric has filed infrastructure upgrade proposals to be built within a four-year construction timeframe that allocate the costs of interconnection upgrades between the interconnecting distributed generation facility and distribution customers based on a technical analysis of capacity benefits. Payments made by the distributed generation facility will be applied against the total capital investment made by NSTAR Electric and NSTAR Electric will earn a return on the net investment. The amount allocated to distribution customers will be recovered through a reconciling mechanism, the Provisional System Planning Tariff. The DPU approved the first of these provisional system planning projects, the Marion-Fairhaven group study area, which will enable 141 MW of distributed energy resources (DER) to be interconnected at a total estimated cost of $120 million. Of the total $120 million, $66 million will be allocated to distribution customers, once the enabled distributed energy facilities capacity is fully subscribed by distributed energy facilities interconnecting customers. Additionally, NSTAR Electric will proceed with construction of approximately $54 million of transmission upgrades necessary to improve local reliability and integrate distribution energy resources in the Marion-Fairhaven area and recover the amount through local transmission rates.
Previous report
On June 4, 2024, the DPU approved four of the remaining five CIPs that were originally submitted by NSTAR Electric. These included the Plainfield-Blandford CIP, which will enable 40 MW of DER to be interconnected at a total estimated distribution investment of $37 million, the Dartmouth-Westport CIP which enables 60 MW of DER for a total distribution investment of $58 million, the Plymouth CIP which enables 380 MW of DER for a total distribution investment of $152 million and the Cape Cod CIP which enables 296 MW of DER for a total distribution investment of $170 million. Of the total $417 million for these four recently approved CIPs, $183 million will be allocated to distribution customers, once the enabled distributed energy facilities capacity is fully subscribed by distributed energy facilities interconnecting customers. Additionally, NSTAR Electric will proceed with construction of approximately $64 million of transmission upgrades necessary to improve local reliability and integrate distribution energy resources in the four CIP areas and recover the amount through local transmission rates. On January 27, 2025, NSTAR Electric filed a petition with the DPU to withdraw the sixth CIP project, Freetown, that was originally submitted.
Previous report
NSTAR Electric’s Electric Sector Modernization Plan (ESMP) Filing: On January 29, 2024, in accordance with Massachusetts state law, NSTAR Electric filed its ESMP with the DPU. The law required each electric distribution company to develop and file a comprehensive distribution system plan to proactively upgrade the distribution system (and, where applicable, the associated transmission system) to: (i) improve grid reliability, communications and resiliency; (ii) enable increased, timely adoption of renewable energy and distributed energy resources; (iii) promote energy storage and electrification technologies necessary to decarbonize the environment and economy; (iv) prepare for future climate-driven impacts on the transmission and distribution systems; (v) accommodate increased transportation electrification, increased building electrification and other potential future demands on distribution and, where applicable, the transmission system; and (vi) minimize or mitigate impacts on Massachusetts ratepayers, thereby helping the state realize its statewide greenhouse gas emissions limits and sublimits under the law. NSTAR Electric’s plan meets these requirements by providing a comprehensive view of all the investments required to build a safer, more reliable, more resilient electric distribution system to enable an affordable, equitable clean energy transition taking into account the needs of environmental justice communities. For the five-year period from 2025 through 2029, the proposed incremental distribution capital investment is $608 million and the incremental distribution expense amount is $211 million. On August 29, 2024, the DPU approved the overall ESMP for a five-year period commencing July 1, 2025.
Previous report
EGMA Distribution Rates: On November 4, 2024, EGMA submitted a revised filing for its first rate base reset for rates to be effective November 1, 2024, in accordance with an October 7, 2020 EGMA Rate Settlement Agreement approved by the DPU. The compliance filing was ordered by the DPU on October 31, 2024. The rate base reset occurring on November 1, 2024 adjusted distribution rates to account for capital additions (including the roll-in of GSEP capital additions), depreciation expense, property taxes, and return on rate base for capital additions placed into service through December 31, 2023. The total revenue requirement calculated for the first rate base reset is an increase to base distribution rates of $147.8 million, of which $34.0 million is associated with GSEP investments through December 31, 2023. Under the terms of the Rate Settlement Agreement, EGMA applied a cap on the revenue change effective November 1, 2024, and the amount in excess of the cap will be deferred for recovery through the Local Distribution Adjustment Clause (LDAC) on May 1, 2025, including carrying charges. After adjusting for the cap, the increase to base distribution rates is $85.6 million effective November 1, 2024 (of which $8.8 million is offset by a reduction in the GSEP revenue requirement and GSEP rate also taking effect on November 1, 2024 for a net distribution rate change on November 1, 2024 of $76.8 million). Base distribution rates will be increased effective November 1, 2025 to incorporate the $62.2 million remaining revenue requirement. On November 7, 2024, the DPU approved this filing.
Previous report
Future of Gas Docket: In October 2020, the DPU opened Docket “DPU 20-80 The Future of Gas” to examine the role of Massachusetts natural gas local distribution companies (LDCs) in helping to meet the state’s 2050 climate goals. In December 2023, the DPU issued an order for this docket. The DPU will consider and, in some cases, require new processes and analysis for traditional natural gas investments, which may require significant changes to the LDC planning process and business models. The DPU intends to put policies and structures in place that would protect customers as Massachusetts works to decarbonize the building sector, which may involve subsequent dockets and regulatory proceedings and potentially recasting the role of LDCs in Massachusetts. The DPU preserved customer choice for energy needs and encouraged further development of decarbonized alternatives, such as the networked geothermal systems that NSTAR Gas is piloting in Framingham, Massachusetts.
Previous report
On December 29, 2023, Eversource and other LDCs sought formal clarity from the DPU to fully understand the resulting impact to their natural gas businesses and the associated timing of any impacts. On April 2, 2024, the DPU issued an order responding to the request for clarification indicating that the LDCs shall implement the inclusion of a Non-Gas Pipeline Alternatives (NPA) analysis on all project authorizations effective immediately. Existing NPA analysis processes will be used until such time a formal stakeholder-based NPA analysis framework is established and approved by the DPU. Eversource, along with the other LDCs, have engaged a consultant to inform the development of the required NPA framework by conducting a stakeholder engagement process as mandated by the order. Another component of the order is the submission of climate compliance plans every five years beginning April 1, 2025. The climate compliance plan filings will include the NPA frameworks, along with energy transitions plans including details on the management of embedded infrastructure investments and cost recovery. Eversource along with the LDCs, have also contracted a consultant to model and investigate statewide cost recovery scenarios including under accelerated depreciation rates.
Previous report
The DPU also indicated that NSTAR Gas and EGMA are not required to provide climate compliance performance metrics in the next PBR filing, however would be expected to propose metrics at the latest in the next base distribution rate proceeding. GHG emissions reporting was not changed from the order, however, effective November of 2024, reporting requirements have changed per the MA DEP and these requirements implement registration and GHG emissions reporting requirements for companies selling and distributing heating fuels to homes and businesses in Massachusetts, including suppliers of natural gas, fuel oil, and propane, and implement a reporting requirement for fuel storage facilities.
Previous report
Eversource does not believe there is any indication of an inability to recover costs or risk of impairment of NSTAR Gas’ and EGMA’s natural gas assets at this time.
Previous report
Also on June 11, 2024, PSNH filed an application with the NHPUC to request an increase in permanent base distribution rates of $181.9 million, which is inclusive of the temporary rate increase, and proposed to take effect August 1, 2025. The temporary rates are subject to reconciliation based on the outcome of the permanent rate case back to the date when temporary rates took effect. The permanent rate increase request includes $247 million in unrecovered storm costs to be recovered over a five-year period. As part of the rate case, PSNH proposed to implement a performance-based rate making plan that would adjust rates annually over a four-year term, with a commitment to not file another rate case for at least four years. The plan includes a revenue-cap formula adjusted for inflation, a supplemental capital adjustment formula to support PSNH’s planned capital infrastructure improvements, an exogenous events recovery mechanism, performance metrics and an earnings sharing mechanism, among others. If the NHPUC approves the performance-based rate making plan as proposed, the previously established RRA and PPAM rate reconciling mechanisms and lost base revenues will be eliminated. The NHPUC is permitted up to twelve months to investigate the proposed rates and issue a final order. A decision by the NHPUC on permanent rates is expected by August 1, 2025.
Previous report
Federal: On April 10, 2024, the U.S. Environmental Protection Agency announced the final regulation setting drinking water standards for six per- and polyfluoroalkyl substances (PFAS) compounds. The regulation requires compliance under a phased approach in which systems will need to complete the initial monitoring requirements for each PFAS within three years, and when warranted, take steps to assure compliance within five years. Beginning in 2027, systems will need to report results of initial monitoring and regular monitoring and issue public notifications for any monitoring and reporting violations. Starting in 2029, systems must comply with all maximum contaminant levels (MCL) and provide public notification for MCL violations. Eversource is currently evaluating the impacts to comply with the regulation for its water business.
Showing the first 40 of 66 passages. Open the source sections for the rest.
Reworded paragraphs (111)
Previous wording
The only common equity securities that are publicly traded are common shares of Eversource. Our earnings discussion includes financial measures that are not recognized under GAAP (non-GAAP) referencing our earnings and EPS excluding losses on the sales and impairments of the offshore wind equity method investments, a loss on the pending sale of the Aquarion water distribution business, a loss on the disposition of land that was initially acquired to construct the Northern Pass Transmission project and was subsequently abandoned, and certain transaction and transition costs. EPS by business is also a non-GAAP financial measure and is calculated by dividing the Net Income Attributable to Common Shareholders of each business by the weighted average diluted Eversource common shares outstanding for the period. The earnings and EPS of each business do not represent a direct legal interest in the assets and liabilities of such business, but rather represent a direct interest in our assets and liabilities as a whole.
Current wording
The only common equity securities that are publicly traded are common shares of Eversource. Our earnings discussion includes financial measures that are not recognized under GAAP (non-GAAP) referencing our earnings and EPS excluding losses associated with our previous offshore wind investments, a loss on the pending sale of the Aquarion water distribution business, and a loss on the disposition of land that was initially acquired to construct the Northern Pass Transmission project and was subsequently abandoned. EPS by business is also a non-GAAP financial measure and is calculated by dividing the Net Income Attributable to Common Shareholders of each business by the weighted average diluted Eversource common shares outstanding for the period. The earnings and EPS of each business do not represent a direct legal interest in the assets and liabilities of such business, but rather represent a direct interest in our assets and liabilities as a whole.
Previous wording
We use these non-GAAP financial measures to evaluate and provide details of earnings results by business and to more fully compare and explain our results without including these items. This information is among the primary indicators we use as a basis for evaluating performance and planning and forecasting of future periods. We believe the impacts of the losses on the offshore wind equity method investments, the loss on the pending sale of the Aquarion water distribution business, the loss on the disposition of land associated with an abandoned project, and transaction and transition costs are not indicative of our ongoing costs and performance. We view these charges as not directly related to the ongoing operations of the business and therefore not an indicator of baseline operating performance. Due to the nature and significance of the effect of these items on Net Income Attributable to Common Shareholders and EPS, we believe that the non-GAAP presentation is a more meaningful representation of our financial performance and provides additional and useful information to readers of this report in analyzing historical and future performance of our business. These non-GAAP financial measures should not be considered as alternatives to reported Net Income Attributable to Common Shareholders or EPS determined in accordance with GAAP as indicators of operating performance.
Current wording
We use these non-GAAP financial measures to evaluate and provide details of earnings results by business and to more fully compare and explain our results without including these items. This information is among the primary indicators we use as a basis for evaluating performance and planning and forecasting of future periods. We believe the impacts of the losses associated with our previous offshore wind investments, the loss on the pending sale of the Aquarion water distribution business, and the loss on the disposition of land associated with an abandoned project are not indicative of our ongoing costs and performance. We view these charges as not directly related to the ongoing operations of the business and therefore not an indicator of baseline operating performance. Due to the nature and significance of the effect of these items on Net Income Attributable to Common Shareholders and EPS, we believe that the non-GAAP presentation is a more meaningful representation of our financial performance and provides additional and useful information to readers of this report in analyzing historical and future performance of our business. These non-GAAP financial measures should not be considered as alternatives to reported Net Income Attributable to Common Shareholders or EPS determined in accordance with GAAP as indicators of operating performance.
Previous wording
•We earned $811.7 million, or $2.27 per share, in 2024, compared with a loss of $442.2 million, or $1.26 per share, in 2023. Our 2024 results include an aggregate, net after-tax loss on the sales of our offshore wind investments of $524.0 million, or $1.47 per share, and an after-tax loss resulting from the expected sale of Aquarion of $298.3 million, or $0.83 per share. Our 2023 results included after-tax impairment charges on our offshore wind investments of $1.95 billion, or $5.58 per share. Our 2023 results also included after-tax land abandonment and other charges of $6.9 million, or $0.02 per share. Excluding these charges, our non-GAAP earnings were $1.63 billion, or $4.57 per share, in 2024, compared with non-GAAP earnings of $1.52 billion, or $4.34 per share, in 2023.
Current wording
•We earned $1.69 billion, or $4.56 per share, in 2025, compared with $811.7 million, or $2.27 per share, in 2024. Our 2025 results include an aggregate, net after-tax charge resulting from our previous offshore wind investments of $75.0 million, or $0.20 per share. Our 2024 results include an aggregate, net after-tax loss on the sale of our offshore wind investments of $524.0 million, or $1.47 per share. These 2025 and 2024 charges were recorded within Eversource Parent and Other Companies. Our 2024 results also include an after-tax loss resulting from the expected sale of Aquarion of $298.3 million, or $0.83 per share. This 2024 charge was recorded within the Water Distribution segment. Excluding these charges, our 2025 non-GAAP earnings were $1.77 billion, or $4.76 per share, and our 2024 non-GAAP earnings of $1.63 billion, or $4.57 per share.
Previous wording
•We project that we will earn within a 2025 earning guidance range of between $4.67 per share and $4.82 per share. We also project that our long-term EPS growth rate through 2029 will be in a 5 to 7 percent range, using 2024 non-GAAP EPS of $4.57 per share as the base year.
Current wording
•We project that we will earn within a 2026 earning guidance range of between $4.80 per share and $4.95 per share. We also project that our long-term EPS growth rate through 2030 will be in a 5 to 7 percent range, using 2025 non-GAAP EPS of $4.76 per share as the base year.
Previous wording
•Cash flows provided by operating activities totaled $2.16 billion in 2024, compared with $1.65 billion in 2023. Investments in property, plant and equipment totaled $4.48 billion in 2024, compared with $4.34 billion in 2023.
Current wording
•Cash flows provided by operating activities totaled $4.11 billion in 2025, compared with $2.16 billion in 2024. Investments in property, plant and equipment totaled $4.16 billion in 2025, compared with $4.48 billion in 2024.
Previous wording
•Cash totaled $26.7 million as of December 31, 2024, compared with $53.9 million as of December 31, 2023. Our available borrowing capacity under our commercial paper programs totaled $607.2 million as of December 31, 2024.
Current wording
•Cash totaled $135.4 million as of December 31, 2025, compared with $26.7 million as of December 31, 2024. Our available borrowing capacity under our commercial paper programs totaled $1.12 billion as of December 31, 2025.
Previous wording
•In 2024, we issued $4.50 billion of new long-term debt and we repaid $1.95 billion of long-term debt.
Current wording
•In 2025, we issued $2.94 billion of new long-term debt and we repaid $1.40 billion of long-term debt.
Previous wording
•In 2024, we paid dividends totaling $2.86 per common share, compared with dividends of $2.70 per common share in 2023. Our quarterly common share dividend payment was $0.715 per share in 2024, as compared to $0.675 per share in 2023. On January 29, 2025, our Board of Trustees approved a common share dividend payment of $0.7525 per share, payable on March 31, 2025 to shareholders of record as of March 4, 2025.
Current wording
•In 2025, we paid dividends totaling $3.01 per common share, compared with dividends of $2.86 per common share in 2024. Our quarterly common share dividend payment was $0.7525 per share in 2025, as compared to $0.715 per share in 2024. On January 27, 2026, our Board of Trustees approved a common share dividend payment of $0.7875 per share, payable on March 31, 2026 to shareholders of record as of March 5, 2026.
Previous wording
•We project to make capital expenditures of $24.17 billion from 2025 through 2029, of which we expect $10.22 billion to be in our electric distribution segment, $6.00 billion to be in our natural gas distribution segment, and $6.81 billion to be in our electric transmission segment. We also project to invest $1.15 billion in information technology and facilities upgrades and enhancements.
Current wording
•We project to make capital expenditures of $26.51 billion from 2026 through 2030, of which we expect $11.24 billion to be in our electric distribution segment, $6.80 billion to be in our natural gas distribution segment, and $7.24 billion to be in our electric transmission segment. We also project to invest $1.23 billion in information technology and facilities upgrades and enhancements.
Previous wording
(1)In 2024, we recorded a loss on the sales of our offshore wind equity method investments. In 2023, we recorded impairment charges resulting from the expected sales of these offshore wind investments. For further information, see "Business Development and Capital Expenditures – Offshore Wind Business" included in this Management's Discussion and Analysis of Financial Condition and Results of Operations.
Current wording
(1)In 2025, we recorded a pre-tax charge of $284 million associated with increasing our offshore wind contingent liability for expected future payments under the terms of the 2024 sale agreement with Global Infrastructure Partners (GIP) for the South Fork Wind and Revolution Wind projects, offset by expected tax benefits from the offshore wind sale of $209 million. In 2024, we recorded a pre-tax loss on the sales of our offshore wind investments of $464 million and a $60 million increase in income tax expense, resulting in an after-tax loss of $524 million. In 2023, we recorded impairment charges resulting from the expected sales of these offshore wind investments. For further information, see the "Offshore Wind Sale and Contingent Liability" section below included in this Management's Discussion and Analysis of Financial Condition and Results of Operations.
Previous wording
(2)The 2024 loss includes an impairment charge of $297 million to write down the carrying value of the water business to fair value resulting from the expected sale of Aquarion, as well as transaction costs. For further information, see "Business Development and Capital Expenditures – Pending Sale of Aquarion" included in this Management's Discussion and Analysis of Financial Condition and Results of Operations.
Current wording
(2)The 2024 loss includes an impairment charge of $297 million to write down the carrying value of the water business to fair value resulting from the expected sale of Aquarion, as well as transaction costs. For further information, see "Business Development and Capital Expenditures – Aquarion Sale Status and Regulatory Denial" included in this Management's Discussion and Analysis of Financial Condition and Results of Operations.
Previous wording
Our electric distribution segment earnings increased $23.7 million in 2024, as compared to 2023, due primarily to higher revenues from base distribution rate increases at NSTAR Electric effective January 1, 2024 and at PSNH effective August 1, 2024 and from CL&P's capital tracking mechanism due to increased electric system improvements, and an increase in interest income primarily on regulatory deferrals. Those earnings increases were partially offset by higher operations and maintenance expense primarily driven by higher employee benefit costs, higher interest expense, higher depreciation expense, the absence of a prior year benefit at PSNH related to the establishment of a new regulatory tracking mechanism that allowed for the recovery of previously incurred operating expenses associated with poles acquired on May 1, 2023, higher property tax expense, and a higher effective tax rate.
Current wording
Our electric distribution segment earnings increased $35.4 million in 2025, as compared to 2024, due primarily to higher revenues from base distribution rate increases at PSNH effective August 1, 2024 and August 1, 2025 and at NSTAR Electric effective January 1, 2025 and from CL&P's capital tracking mechanism due to increased electric system improvements. Earnings also benefited from a lower effective tax rate and the impact of the PSNH rate case decision in July 2025. Those earnings increases were partially offset by higher interest expense, higher operations and maintenance expense, higher property tax expense, higher depreciation expense, and a charge for customer credits at NSTAR Electric as a result of the joint settlement agreement approved in Massachusetts on December 1, 2025.
Previous wording
Our electric transmission segment earnings increased $81.2 million in 2024, as compared to 2023, due primarily to a higher transmission rate base as a result of our continued investment in our transmission infrastructure and the impact of the annual rate reconciliation filing with FERC, partially offset by a higher effective tax rate.
Current wording
Our electric transmission segment earnings increased $52.1 million in 2025, as compared to 2024, due primarily to a higher transmission rate base as a result of our continued investment in our transmission infrastructure and lower interest expense.
Previous wording
Our natural gas distribution segment earnings increased $66.2 million in 2024, as compared to 2023, due primarily to higher revenues from base distribution rate increases effective November 1, 2024 at EGMA and effective November 1, 2024 and November 1, 2023 at NSTAR Gas and capital tracking mechanisms due to continued investments in natural gas infrastructure. Earnings also benefited from lower operations and maintenance expense, the absence of a prior year unfavorable regulatory adjustment resulting from NSTAR Gas’ GSEP reconciliation filing, and a lower effective tax rate. Those earnings increases were partially offset by higher depreciation expense, higher interest expense, and higher property tax expense.
Current wording
Our natural gas distribution segment earnings increased $69.5 million in 2025, as compared to 2024, due primarily to higher revenues from base distribution rate increases effective November 1, 2024 and November 1, 2025 at both EGMA and NSTAR Gas, effective November 1, 2025 at Yankee Gas, and from capital tracking mechanisms due to continued investments in natural gas infrastructure. Those earnings increases were partially offset by higher operations and maintenance expense, higher depreciation expense, higher interest expense, the impact of the NSTAR Gas settlement agreement in December 2025, higher property tax expense, and the impact of the Yankee Gas rate case decision in November 2025.
Previous wording
Our water distribution segment recognized a $297 million impairment charge in 2024 as a result of writing down the carrying value of the business to fair value due to the expected sale of Aquarion. Excluding the impairment charge and transaction costs associated with the expected sale, water distribution segment earnings increased $11.5 million in 2024, as compared to 2023, due primarily to an after-tax benefit of $11.6 million recorded in 2024 to recognize the impacts of the Aquarion Water Company of Connecticut’s rate case decision from PURA. The impacts of PURA’s rate case decision on March 15, 2023 were recorded beginning in March 2024 as a result of the State of Connecticut Superior Court’s decision on the rate case appeal on March 25, 2024. The impacts primarily include a reduction to depreciation expense to reflect lower depreciation rates ordered by PURA in its final decision, partially offset by lower authorized revenues.
Current wording
Our water distribution segment recognized a $297 million impairment charge in 2024 as a result of writing down the carrying value of the business to fair value due to the expected sale of Aquarion. Excluding the 2024 impairment charge and transaction costs associated with the expected sale, water distribution segment earnings decreased $0.4 million in 2025, as compared to 2024.
Previous wording
Contingencies are evaluated using the best information available at the time the financial statements are prepared, and this assessment involves judgments and assumptions about future events. Factors that could increase the post-closing adjustment payments owed to GIP include the ultimate cost of construction and extent of cost overruns for Revolution Wind, delays in construction, which would impact the economics associated with the purchase price adjustment, and Revolution Wind’s eligibility for federal investment tax credits at a lower value than assumed and included in the purchase price.
Current wording
Contingencies are evaluated using the best information available at the time the financial statements are published, and this assessment involves judgments and assumptions about future events. Factors that could increase the obligation to GIP include construction cost overruns for Revolution Wind as well as the timing and extent of construction delays, which would impact the economics associated with the purchase price adjustment, and the eligibility for federal investment tax credits for Revolution Wind at a value lower than assumed and included in the purchase price. The purchase price of Revolution Wind included the sales value related to a 40 percent level of federal investment tax credits. A change in the expected value or qualification of investment tax credit adders could result in a significant loss in a future period.
Previous wording
Eversource, CL&P, NSTAR Electric and PSNH each uses its available capital resources to fund its respective construction expenditures, meet debt requirements, pay operating costs, including storm-related costs, pay dividends, and fund corporate obligations. Eversource's regulated companies recover their electric, natural gas and water distribution construction expenditures as the related project costs are depreciated over the life of the assets. This impacts the timing of the revenue stream designed to fully recover the total investment plus a return on the equity and debt used to finance the investments. Eversource's regulated companies spend a significant amount of cash on capital improvements and construction projects that have a long-term return on investment and recovery period. These factors have resulted in current liabilities exceeding current assets by $1.64 billion, $291.7 million and $112.0 million at Eversource, NSTAR Electric and PSNH, respectively, as of December 31, 2024.
Current wording
Eversource, CL&P, NSTAR Electric and PSNH each uses its available capital resources to fund its respective construction expenditures, meet debt requirements, pay operating costs, including storm-related costs, pay dividends, and fund corporate obligations. Eversource's regulated companies recover their electric, natural gas and water distribution construction expenditures as the related project costs are depreciated over the life of the assets. This impacts the timing of the revenue stream designed to fully recover the total investment including a return on the equity and debt used to finance the investments. Eversource's regulated companies spend a significant amount of cash on capital improvements and construction projects that have a long-term return on investment and recovery period. These factors have resulted in current liabilities exceeding current assets by $2.73 billion, $268.6 million, $9.0 million and $19.6 million at Eversource, CL&P, NSTAR Electric and PSNH, respectively, as of December 31, 2025.
Previous wording
As of December 31, 2024, $1.40 billion of Eversource's long-term debt, including $600.0 million at Eversource parent, $400.0 million at CL&P and $250.0 million at NSTAR Electric, matures within the next 12 months. Eversource, with its current credit ratings, has several options available in the financial markets to repay or refinance these maturities with the issuance of new long-term debt. Eversource, CL&P, NSTAR Electric and PSNH will reduce their short-term borrowings with operating cash flows or with the issuance of new long-term debt, determined by considering capital requirements and maintenance of Eversource's credit rating and profile.
Current wording
As of December 31, 2025, $1.39 billion of Eversource's long-term debt, including $1.00 billion at Eversource parent and $300.0 million at NSTAR Electric, matures within the next 12 months. Eversource, with its current credit ratings, has several options available in the financial markets to repay or refinance these maturities with the issuance of new long-term debt. Eversource, CL&P, NSTAR Electric and PSNH will reduce their short-term borrowings with operating cash flows or with the issuance of new long-term debt, determined by considering capital requirements and maintenance of Eversource's credit rating and profile.
Previous wording
Cash totaled $26.7 million as of December 31, 2024, compared with $53.9 million as of December 31, 2023.
Current wording
Cash totaled $135.4 million as of December 31, 2025, compared with $26.7 million as of December 31, 2024.
Previous wording
Short-Term Debt - Commercial Paper Programs and Credit Agreements: Eversource parent has a $2.00 billion commercial paper program allowing Eversource parent to issue commercial paper as a form of short-term debt. Eversource parent, CL&P, PSNH, NSTAR Gas, Yankee Gas, EGMA and Aquarion Water Company of Connecticut are parties to a five-year $2.00 billion revolving credit facility, which terminates on October 11, 2029. This revolving credit facility serves to backstop Eversource parent's $2.00 billion commercial paper program.
Current wording
Short-Term Debt - Commercial Paper Programs and Credit Agreements: Eversource parent has a $2.00 billion commercial paper program allowing Eversource parent to issue commercial paper as a form of short-term debt. Eversource parent, CL&P, PSNH, NSTAR Gas, Yankee Gas, EGMA and Aquarion Water Company of Connecticut are parties to a five-year $2.00 billion revolving credit facility. Effective October 11, 2025, the revolving credit facility’s termination date was extended for one additional year to October 11, 2030, pursuant to the extension provisions contained in the existing credit agreement. This revolving credit facility serves to backstop Eversource parent's $2.00 billion commercial paper program.
Previous wording
NSTAR Electric has a $650 million commercial paper program allowing NSTAR Electric to issue commercial paper as a form of short-term debt. NSTAR Electric is also a party to a five-year $650 million revolving credit facility, which terminates on October 11, 2029, that serves to backstop NSTAR Electric's $650 million commercial paper program.
Current wording
NSTAR Electric has a $650 million commercial paper program allowing NSTAR Electric to issue commercial paper as a form of short-term debt. NSTAR Electric is also a party to a five-year $650 million revolving credit facility. Effective October 11, 2025, the revolving credit facility’s termination date was extended for one additional year to October 11, 2030, pursuant to the extension provisions contained in the existing credit agreement. This revolving credit facility serves to backstop NSTAR Electric's $650 million commercial paper program.
Previous wording
Amounts outstanding under the commercial paper programs are included in Notes Payable and classified in current liabilities on the Eversource and NSTAR Electric balance sheets, as all borrowings are outstanding for no more than 364 days at one time. As a result of the CL&P long-term debt issuance in January 2024, $207.3 million of commercial paper borrowings under the Eversource parent commercial paper program were reclassified to Long-Term Debt on Eversource parent’s balance sheet as of December 31, 2023.
Current wording
Amounts outstanding under the commercial paper programs are included in Notes Payable and classified in current liabilities on the Eversource and NSTAR Electric balance sheets, as all borrowings are outstanding for no more than 364 days at one time.
Previous wording
Intercompany Borrowings: Eversource parent uses its available capital resources to provide loans to its subsidiaries to assist in meeting their short-term borrowing needs. Eversource parent records intercompany interest income from its loans to subsidiaries, which is eliminated in consolidation. Intercompany loans from Eversource parent to its subsidiaries are eliminated in consolidation on Eversource's balance sheets. As of December 31, 2024, there were intercompany loans from Eversource parent to CL&P of $280.0 million and to PSNH of $131.1 million. As of December 31, 2023, there were intercompany loans from Eversource parent to CL&P of $457.0 million and to PSNH of $233.0 million. Eversource parent charges interest on these intercompany loans at the same weighted-average interest rate as its commercial paper program. Intercompany loans from Eversource parent are included in Notes Payable to Eversource Parent and classified in current liabilities on the respective subsidiary's balance sheets, as these intercompany borrowings are outstanding for no more than 364 days at one time. As a result of the CL&P long-term debt issuance in January 2024, $207.3 million of CL&P’s intercompany borrowings were reclassified to Long-Term Debt on CL&P’s balance sheet as of December 31, 2023.
Current wording
Intercompany Borrowings: Eversource parent uses its available capital resources to provide loans to its subsidiaries to assist in meeting their short-term borrowing needs. Eversource parent records intercompany interest income from its loans to subsidiaries, which is eliminated in consolidation. Intercompany loans from Eversource parent to its subsidiaries are eliminated in consolidation on Eversource's balance sheets. As of December 31, 2025 and 2024, there were intercompany loans from Eversource parent to PSNH of $49.3 million and $131.1 million, respectively. As of December 31, 2024, there were intercompany loans from Eversource parent to CL&P of $280.0 million. Eversource parent charges interest on these intercompany loans at the same weighted-average interest rate as its commercial paper program. Intercompany loans from Eversource parent are included in Notes Payable to Eversource Parent and classified in current liabilities on the respective subsidiary's balance sheets, as these intercompany borrowings are outstanding for no more than 364 days at one time.
Previous wording
Availability under Long-Term Debt Issuance Authorizations: On May 1, 2024, the DPU approved NSTAR Electric’s request for authorization to issue up to $2.40 billion in long-term debt through December 31, 2026. On July 24, 2024, PURA approved CL&P’s request for authorization to issue up to $1.00 billion in long-term debt through December 31, 2025. On August 12, 2024, the DPU approved EGMA’s request for authorization to issue up to $325 million in long-term debt through December 31, 2026. On December 18, 2024, the DPU approved NSTAR Gas’ request for authorization to issue up to $475 million in long-term debt through December 31, 2027. On January 28, 2025, Yankee Gas submitted an application to PURA requesting authorization to issue up to $360 million in long-term debt through December 31, 2026. PSNH has utilized its long-term debt authorizations in place with NHPUC.
Current wording
Availability under Long-Term Debt Issuance Authorizations: On May 1, 2024, the DPU approved NSTAR Electric’s request for authorization to issue up to $2.40 billion in long-term debt through December 31, 2026. On August 12, 2024, the DPU approved EGMA’s request for authorization to issue up to $325 million in long-term debt through December 31, 2026. On December 18, 2024, the DPU approved NSTAR Gas’ request for authorization to issue up to $475 million in long-term debt through December 31, 2027. On March 26, 2025, PURA approved Yankee Gas’ request for authorization to issue up to $360 million in long-term debt through December 31, 2026. PSNH has utilized its long-term debt authorizations in place with NHPUC. CL&P has no long-term debt authorization remaining with PURA.
Previous wording
Rate Reduction Bonds: PSNH's RRB payments consist of principal and interest and are paid semi-annually. PSNH paid $43.2 million of RRB principal payments in each of 2024 and 2023, and paid $14.9 million and $16.2 million of interest payments in 2024 and 2023, respectively.
Current wording
Rate Reduction Bonds: PSNH's RRB payments consist of principal and interest and are paid semi-annually. PSNH paid $43.2 million of RRB principal payments in each of 2025 and 2024, and paid $13.4 million and $14.9 million of interest payments in 2025 and 2024, respectively.
Previous wording
Common Share Issuances: Eversource had an equity distribution agreement pursuant to which it could offer and sell up to $1.2 billion of its common shares from time to time through an “at-the-market” (ATM) equity offering program. In 2024, Eversource issued 15,740,294 common shares, which resulted in proceeds of $989.4 million, net of issuance costs. Eversource used the net proceeds received for general corporate purposes. In 2023, no shares were issued under this agreement. Eversource completed the program in October 2024.
Current wording
Common Share Issuances and Equity Distribution Agreement: On May 30, 2025, Eversource entered into an equity distribution agreement pursuant to which it may offer and sell up to $1.2 billion of its common shares from time to time through an ATM equity offering program. In 2025, Eversource issued 7,130,134 common shares, which resulted in proceeds of $465.4 million, net of issuance costs. Eversource used the net proceeds received for general corporate purposes.
Previous wording
Cash Flows: Cash flows from operating activities primarily result from the transmission and distribution of electricity, and the distribution of natural gas and water. Cash flows provided by operating activities totaled $2.16 billion in 2024, compared with $1.65 billion in 2023. Operating cash flows were favorably impacted by the timing of cash payments made on our accounts payable, a $108.8 million increase due to income tax refunds received in 2024 as compared to income tax payments made in 2023, an improvement in regulatory under-recoveries driven primarily by the timing of collections for the CL&P non-bypassable FMCC and other regulatory tracking mechanisms partially offset by the unfavorable impact in the timing of collections for energy supply costs, a $20.7 million decrease in cost of removal expenditures, a $12.4 million decrease in cash payments to vendors for storm costs, and the timing of other working capital items. The impacts of regulatory collections are included in both Regulatory Recoveries and Amortization on the statements of cash flows. These favorable impacts were partially offset by the timing of cash collections on our accounts receivable.
Current wording
Cash Flows: Cash flows from operating activities primarily result from the transmission and distribution of electricity, and the distribution of natural gas and water. Cash flows provided by operating activities totaled $4.11 billion in 2025, compared with $2.16 billion in 2024. Operating cash flows were favorably impacted by an improvement in regulatory recoveries driven primarily by the timing of collections for CL&P’s non-bypassable FMCC, CL&P’s SBC, energy efficiency costs, wholesale and retail transmission costs, and other regulatory tracking mechanisms. The CL&P non-bypassable FMCC retail rates in effect for 2025 were higher than those set in 2024 and the net Millstone and Seabrook contract cash flows were higher in 2025 as compared to 2024. These higher collections within the non-bypassable FMCC resulted in an improvement to operating cash flows of$428.2 million for the year. Higher collections from CL&P’s SBC mechanism resulted in a cash flow improvement of $113.3 million. The impacts of regulatory collections are included in both Regulatory Recoveries and Amortization on the statements of cash flows. Additionally, CL&P received general obligation bond proceeds from the State of Connecticut for the reimbursement of hardship costs and for electric vehicle charging program costs of $107.8 million in 2025, which are reflected in Regulatory Recoveries. Operating cash flows were also favorably impacted by a $321.4 million decrease in cash payments to vendors for storm costs, the timing of cash collections on our accounts receivable, the timing of cash payments made on our accounts payable, a $19.1 million decrease in cost of removal expenditures, and the timing of other working capital items. These favorable impacts were partially offset by an increase in capitalized implementation costs for cloud-based service arrangements and a $21.2 million decrease in income tax refunds received in 2025 as compared to 2024.
Previous wording
In 2024, we paid cash dividends of $1.00 billion and issued non-cash dividends of $23.5 million in the form of treasury shares, totaling dividends of $1.03 billion, or $2.86 per common share. In 2023, we paid cash dividends of $919.0 million and issued non-cash dividends of $23.4 million in the form of treasury shares, totaling dividends of $942.4 million, or $2.70 per common share. Our quarterly common share dividend payment was $0.715 per share in 2024, as compared to $0.675 per share in 2023. On January 29, 2025, our Board of Trustees approved a common share dividend payment of $0.7525 per share, payable on March 31, 2025 to shareholders of record as of March 4, 2025.
Current wording
In 2025, we paid cash dividends of $1.09 billion and issued non-cash dividends of $23.4 million in the form of treasury shares, totaling dividends of $1.12 billion, or $3.01 per common share. In 2024, we paid cash dividends of $1.00 billion and issued non-cash dividends of $23.5 million in the form of treasury shares, totaling dividends of $1.03 billion, or $2.86 per common share. Our quarterly common share dividend payment was $0.7525 per share in 2025, as compared to $0.715 per share in 2024. On January 27, 2026, our Board of Trustees approved a common share dividend payment of $0.7875 per share, payable on March 31, 2026 to shareholders of record as of March 5, 2026.
Previous wording
In 2024, CL&P, NSTAR Electric and PSNH paid $333.8 million, $643.9 million and $62.0 million, respectively, in common stock dividends to Eversource parent.
Current wording
In 2025, CL&P, NSTAR Electric and PSNH paid $430.0 million, $436.0 million and $175.0 million, respectively, in common stock dividends to Eversource parent.
Previous wording
Investments in Property, Plant and Equipment on the statements of cash flows do not include amounts incurred on capital projects but not yet paid, cost of removal, AFUDC related to equity funds, and the capitalized and deferred portions of pension and PBOP income/expense. In 2024, investments for Eversource, CL&P, NSTAR Electric, and PSNH were $4.48 billion, $978.5 million, $1.56 billion and $608.8 million, respectively. Capital expenditures were primarily for continuing projects to maintain and improve infrastructure and operations, including enhancing reliability to the transmission and distribution systems.
Current wording
Investments in Property, Plant and Equipment on the statements of cash flows do not include amounts incurred on capital projects but not yet paid, cost of removal, AFUDC related to equity funds, and the capitalized and deferred portions of pension and PBOP income/expense. In 2025, investments for Eversource, CL&P, NSTAR Electric, and PSNH were $4.16 billion, $867.8 million, $1.56 billion and $537.8 million, respectively. Capital expenditures were primarily for continuing projects to maintain and improve infrastructure and operations, including enhancing reliability to the transmission and distribution systems.
Previous wording
Our consolidated capital expenditures, including amounts incurred but not paid, cost of removal, AFUDC, and the capitalized and deferred portions of pension and PBOP income/expense (all of which are non-cash factors), totaled $4.64 billion in 2024, $4.59 billion in 2023, and $3.79 billion in 2022. These amounts included $260.5 million in 2024, $214.4 million in 2023, and $266.5 million in 2022 related to information technology and facilities upgrades and enhancements, primarily at Eversource Service and The Rocky River Realty Company.
Current wording
Our consolidated capital expenditures, including amounts incurred but not paid, cost of removal, AFUDC, and the capitalized and deferred portions of pension and PBOP income/expense (all of which are non-cash factors), totaled $4.61 billion in 2025, $4.64 billion in 2024, and $4.59 billion in 2023. These amounts included $240.2 million in 2025, $260.5 million in 2024, and $214.4 million in 2023 related to information technology and facilities upgrades and enhancements, primarily at Eversource Service and The Rocky River Realty Company.
Previous wording
Electric Transmission Business: Our consolidated electric transmission business capital expenditures decreased by $120.0 million in 2024, as compared to 2023. A summary of electric transmission capital expenditures by company is as follows:
Current wording
Electric Transmission Business: Our consolidated electric transmission business capital expenditures decreased by $118.8 million in 2025, as compared to 2024. A summary of electric transmission capital expenditures by company is as follows:
Previous wording
Greater Cambridge Energy Program: The Greater Cambridge Energy Program will construct Eversource’s first underground transmission substation in Cambridge, Massachusetts, along with associated transmission and distribution lines. The project will address the increased electric demand in the region, enhance the resiliency of the transmission system, and ensure a flexible grid to reliably serve customers. The flexibility to transmit and distribute mixed energy sources will support the decarbonization and electrification goals of both the City of Cambridge and the state of Massachusetts. The new 115/13.8-kV, 35,000 square foot substation will be located in an underground vault and includes three distribution power transformers supplying thirty-six distribution circuits. The project also includes five underground duct banks housing eight new 115-kV transmission lines. The Massachusetts Energy Facilities Siting Board approved the project on June 28, 2024. Additional required environmental permits are expected to be approved by the end of 2025, as well as a license from the MA DEP expected to be approved by the end of the second quarter of 2026. The initial in-service date for the project is June 2029, which includes two 115-kV transmission lines and the transmission portion of the substation. The first distribution circuits and substation distribution will be placed in-service by the end of 2029. The remaining transmission and distribution circuits will be placed in-service throughout 2030 and into 2031. The total project cost is approximately $1.84 billion, with $1.38 billion allocated for transmission and $460 million for distribution. As of December 31, 2024, $100.1 million has been spent on the project, with $70 million for transmission and $30.1 million for distribution.
Current wording
Greater Cambridge Energy Program: The Greater Cambridge Energy Program will construct Eversource’s first underground transmission substation in Cambridge, Massachusetts, along with associated transmission and distribution lines. The project will address the increased electric demand in the region, enhance the resiliency of the transmission system, and ensure a flexible grid to reliably serve customers. The flexibility to transmit and distribute mixed energy sources will support the decarbonization and electrification goals of both the City of Cambridge and the state of Massachusetts. The new 115/13.8-kV, 35,000 square foot substation will be located in an underground vault and includes three distribution power transformers supplying thirty-six distribution circuits. The project also includes five underground duct banks housing eight new 115-kV transmission lines. The Massachusetts Energy Facilities Siting Board approved the project on June 28, 2024. Environmental permits are acquired to support ongoing construction activities. Additional required permits for transmission line trenchless crossings, including a license from the MA DEP, are expected to be approved by the end of 2026. The initial in-service date for the project is June 2029, which includes two 115-kV transmission lines and the transmission portion of the substation. The first distribution circuits and substation distribution will be placed in-service by the end of 2029. The remaining transmission and distribution circuits will be placed in-service throughout 2030 and into 2031. The total estimated project cost is approximately $1.84 billion, with $1.38 billion allocated for transmission and $460 million for distribution. As of December 31, 2025, $200.9 million has been spent on the project, with $154.7 million for transmission and $46.2 million for distribution.
Previous wording
For the electric distribution business, basic business includes the purchase of meters, tools, vehicles, information technology, transformer replacements, equipment facilities, and the relocation of plant. Aging infrastructure relates to reliability and the replacement of overhead lines, plant substations, underground cable replacement, and equipment failures. Load growth and other includes requests for new business and capacity additions on distribution lines and substation additions and expansions.
Current wording
For the electric distribution business, basic business includes the purchase of meters, tools, vehicles, information technology, transformer replacements, equipment facilities, and the relocation of plant. Aging infrastructure relates to reliability and the replacement of overhead lines, plant substations, underground cable replacement, and equipment failures. Load growth and other includes requests for new business and capacity additions on distribution lines and substation additions and expansions. We are also focused on making strategic AI investments currently in outage discovery, maintenance management and data analytics to better maintain our system and provide value to our customers.
Previous wording
Pending Sale of Aquarion: In early 2024, Eversource initiated an exploratory assessment of the potential sale of the Aquarion water distribution business. In December 2024, final bids were received, and Eversource obtained approval from its Board of Trustees to sell the Aquarion water distribution business. On January 27, 2025, Eversource entered into a definitive agreement to sell Aquarion. Subject to certain closing adjustments, the aggregate enterprise value of the sale is approximately $2.4 billion in cash, which includes approximately $1.6 billion for the equity and $800 million of net debt that will be extinguished at closing. The sale is subject to approval by PURA, DPU and the NHPUC, as well as other approvals pursuant to the Hart-Scott-Rodino Antitrust Improvements Act as well as other customary closing conditions. The sale is expected to close in late 2025. Eversource plans to use the net proceeds from the pending sale to pay down parent company debt.
Current wording
Aquarion Sale Status and Regulatory Denial: In December 2024, Eversource obtained approval from its Board of Trustees to sell the Aquarion water distribution business. On January 27, 2025, Eversource entered into a definitive agreement to sell Aquarion to the Aquarion Water Authority (AWA), a quasi-public corporation and political subdivision of the State of Connecticut and a standalone, newly created water authority alongside the South Central Connecticut Regional Water Authority. In June 2024, a Connecticut law chartered AWA and enabled it to acquire, own and operate Aquarion as a not-for-profit water authority. Subject to certain closing adjustments, the aggregate enterprise value of the sale is approximately $2.4 billion in cash, which included approximately $1.6 billion for the equity and $800 million of net debt that will either be extinguished at closing or transferred to the buyer. The sale requires approval by PURA and the DPU, as well as other approvals pursuant to the Hart-Scott-Rodino Antitrust Improvements Act, for which the relevant waiting period has expired, as well as other customary closing conditions. Regulatory approvals in New Hampshire and Maine were received. Eversource plans to use the net proceeds from sale to pay down parent company debt.
Previous wording
In the fourth quarter of 2024, upon classifying the assets and liabilities as held for sale, Eversource concluded that the likely sale of Aquarion at a loss resulted in the requirement to test water distribution goodwill for impairment. Eversource performed an impairment test by comparing the fair value of the business to its carrying value and recorded a goodwill impairment of $297 million, as the estimated fair value of the business based on the anticipated sale was less than the carrying value. The fair value included future cash outflows of approximately $140 million of estimated income taxes as a result of the transaction. The goodwill impairment charge is presented separately within Operating Income on the Eversource statement of income for the year ended December 31, 2024.
Current wording
In the fourth quarter of 2024, upon classifying the assets and liabilities as held for sale, Eversource concluded that the likely sale of Aquarion at a loss resulted in the requirement to test water distribution goodwill for impairment. Eversource performed an impairment test by comparing the fair value of the business to its carrying value and recorded a goodwill impairment of $297 million, as the estimated fair value of the business based on the anticipated sale was less than the carrying value. The fair value included future cash outflows of approximately $140 million of estimated income taxes as a result of the transaction. The goodwill impairment charge was presented separately within Operating Income on the Eversource statement of income for the year ended December 31, 2024.
Previous wording
The FERC order included illustrative calculations for the first complaint using FERC's proposed frameworks with financial data from that complaint. Those illustrative calculations indicated that for the first complaint period, for the NETOs, which FERC concludes are of average financial risk, the preliminary just and reasonable base ROE is 10.41 percent and the preliminary incentive cap on total ROE is 13.08 percent. If the results of the illustrative calculations were included in a final FERC order for each of the complaint periods, then a 10.41 percent base ROE and a 13.08 percent incentive cap would not have a significant impact on our financial statements for all of the complaint periods. These preliminary calculations are not binding and do not represent what we believe to be the most likely outcome of a final FERC order.
Current wording
The FERC order included illustrative calculations for the first complaint using FERC's proposed frameworks with financial data from that complaint. Those illustrative calculations indicated that for the first complaint period, the preliminary just and reasonable base ROE for the NETOs, which FERC concludes are of average financial risk, is 10.41 percent and the preliminary incentive cap on total ROE is 13.08 percent. If the results of the illustrative calculations were included in a final FERC order for each of the complaint periods, then a 10.41 percent base ROE and a 13.08 percent incentive cap would not have a significant impact on our financial statements for all of the complaint periods. These preliminary calculations are not binding and do not represent what we believe to be the most likely outcome of a final FERC order.
Previous wording
On October 17, 2024, FERC issued an order on the remand of the MISO ROE proceedings. The order addressed the Court’s decision that the reintroduction of the risk-premium financial model in the ROE methodology was arbitrary and capricious by removing the risk-premium financial model from the ROE methodology. The removal of the risk-premium financial model was the only revision to FERC’s ROE methodology and resulted in a two-model approach utilizing the two-step discounted cash flow model and the capital asset pricing model. MISO was directed to provide refunds for the period November 12, 2013 to February 11, 2015 (the first MISO ROE complaint refund period) and for the period from September 28, 2016 (the date of FERC’s order on the first MISO ROE complaint) to October 17, 2024 by December 1, 2025. The order also stated that FERC does not preclude the use of the risk-premium financial model in future proceedings if the parties can demonstrate that FERC’s stated concerns around the inclusion of the model have been addressed.
Current wording
On October 17, 2024, FERC issued an order on the remand of the MISO ROE proceedings. The order addressed the Court’s decision that the reintroduction of the risk-premium financial model in the ROE methodology was arbitrary and capricious by removing the risk-premium financial model from the ROE methodology. The removal of the risk-premium financial model was the only revision to FERC’s ROE methodology and resulted in a two-model approach utilizing the two-step discounted cash flow model and the capital asset pricing model. MISO transmission owners were directed to provide refunds for the period November 12, 2013 to February 11, 2015 (the first MISO ROE complaint refund period) and for the period from September 28, 2016 (the date of FERC’s order on the first MISO ROE complaint) to October 17, 2024 by December 1, 2025. The order also stated that FERC does not preclude the use of the risk-premium financial model in future proceedings if the parties can demonstrate that FERC’s stated concerns around the inclusion of the model have been addressed. On March 25, 2025, FERC issued an order addressing arguments raised on rehearing, sustaining the result, and denying rehearing.
Previous wording
On February 4, 2025, the MISO transmission owners submitted a petition for review with the Court requesting review of the October 17, 2024 MISO ROE order on remand and a December 19, 2024 notice of denial of rehearing. The petition requests review of FERC’s decision to retroactively backdate the MISO transmission owners’ base ROE to the date of an earlier order that FERC abandoned when it issued Order No. 569, treat an underlying unlawful complaint as if it were legitimate, and order eight years of interest as part of the directed refunds.
Current wording
On February 4, 2025, the MISO transmission owners submitted a petition for review with the Court requesting review of the October 17, 2024 MISO ROE order on remand and a December 19, 2024 notice of denial of rehearing. The petition requests review of FERC’s decision to retroactively backdate the MISO transmission owners’ base ROE to the date of an earlier order that FERC abandoned when it issued Order No. 569, treat an underlying unlawful complaint as if it were legitimate, and order eight years of interest as part of the directed refunds. On August 21, 2025, the NETOs submitted a brief in support of the MISO transmission owners with the Court. Final briefs in the Court proceeding were submitted on January 26, 2026 and oral argument is scheduled for March 17, 2026.
Previous wording
A change of 10 basis points to the base ROE used to establish the reserves would impact Eversource’s after-tax earnings by an average of approximately $3 million for each of the four 15-month complaint periods. Prospectively from the date of a final FERC order implementing a new base ROE, based off of estimated 2024 rate base, a change of 10 basis points to the base ROE would impact Eversource’s future annual after-tax earnings by approximately $6 million per year, and will increase slightly over time as we continue to invest in our transmission infrastructure.
Current wording
A change of 10 basis points to the base ROE used to establish the reserves would impact Eversource’s after-tax earnings by an average of approximately $3 million for each of the four 15-month complaint periods. Prospectively from the date of a final FERC order implementing a new base ROE, based off of estimated 2025 rate base, a change of 10 basis points to the base ROE would impact Eversource’s future annual after-tax earnings by approximately $7 million per year, and will increase slightly over time as we continue to invest in our transmission infrastructure.
Showing the first 40 of 111 pairs. Open the source sections for the rest.
Rearranged current paragraphs (5)
Current report — wording carried from elsewhere
•On May 30, 2025, we entered into an equity distribution agreement pursuant to which we may offer and sell up to $1.2 billion of our common shares from time to time through an “at-the-market” (ATM) equity offering program. In 2025, we issued 7,130,134 common shares, which resulted in proceeds of$465.4 million, net of issuance costs.
Current report — wording carried from elsewhere
Base Distribution Rates: In Connecticut, PURA is required to conduct a review and investigation of the financial and operating records of each electric, natural gas and water utility serving more than seventy-five thousand customers within four years of its last general rate hearing. PURA can elect to convene a general rate hearing at an interval of less than four years unless prohibited from doing so by an agency decision or other law.
Current report — wording carried from elsewhere
Customers have the choice to purchase electricity from their Eversource electric utility or from a competitive third-party supplier. For customers who have contracted separately with these competitive suppliers, revenue is not recorded for the sale of the electricity commodity, as the utility is acting as an agent on behalf of the third-party supplier. For customers that choose to purchase electric generation from CL&P, NSTAR Electric or
Current report — wording carried from elsewhere
The decrease in energy supply procurement at CL&P was driven by lower average prices, partially offset by higher average supply-related sales volumes. The decrease in energy supply procurement at NSTAR Electric was driven by lower average prices and lower average supply-related sales volumes. The increase in energy supply procurement at PSNH was driven by higher average prices and higher average supply-related sales volumes.
Current report — wording carried from elsewhere
The variance in CL&P’s NBFMCC revenues was driven by changes in the retail NBFMCC rate. The CL&P NBFMCC rate includes the recovery of costs incurred under long-term state mandated energy purchase contracts with the Millstone and Seabrook nuclear power plants, net of the benefits received from selling this energy into the ISO-NE wholesale market. The rate changes primarily resulted from the timing of recovery of net costs associated with power purchase agreements with the Millstone and Seabrook nuclear power plants. The average NBFMCC rates are as follows:
Rearranged previous paragraphs (2)
Previous report — wording carried elsewhere
•On January 27, 2025, Eversource entered into a definitive agreement to sell Aquarion. Subject to certain closing adjustments, the aggregate enterprise value of the sale is approximately $2.4 billion in cash, which includes approximately $1.6 billion for the equity and $800 million of net debt that will be extinguished at closing. The sale is subject to regulatory and other approvals and is expected to close in late 2025. Eversource plans to use the net proceeds from the pending sale to pay down parent company debt.
Previous report — wording carried elsewhere