i-80 Gold Corp.

For the period ended Mar 31, 2025. Filed May 5, 2025.

View on SEC.gov

About this filing

A company's report for each of its first three quarters. The financial statements are not audited. It shows how the business has moved since the last annual report, and what management says changed.

Mar 31, 2025 · Filed May 5, 2025

IAUX$1.42+4.4%Stored close · as of Nov 6, 2026
See the whole filing, with its images and exhibits

Overview

Company Overview

i-80 Gold Corp. is a Nevada-focused growth-oriented gold and silver mining company engaged in the exploration and development, and extraction of gold and silver. The Company is the fourth largest gold mineral resource holder in the state with a pipeline of projects strategically located on Nevada's most prolific gold-producing trends. The Company's wholly owned principal assets, which are at various stages of permitting and development, include the Granite Creek property, the Ruby Hill property, the Lone Tree property, the Cove property, and the FAD property.

The Company was incorporated on November 10, 2020, under the laws of the province of British Columbia, Canada. The Company’s common shares are listed on the Toronto Stock Exchange (“TSX”) under the symbol IAU and the NYSE American (“NYSE”) under the symbol IAUX. The Company’s head office is located in Reno, Nevada, United States ("US"). The Company's corporate office is located in Toronto, Ontario, Canada.

Reference to $ or USD is to US dollars, reference to C$ or CAD is to Canadian dollars.

Operational and Financial Highlights

Three months endedMarch 31,
2025 · 2024
Revenue$000s14,0488,413
Net loss$000s(41,205)(19,700)
Loss per share$/share(0.10)(0.06)
Cash flow used in operating activities$000s(22,701)(25,223)
Cash and cash equivalents$000s13,47513,090
Exploration feet drilledft14,7627,626
Gold ounces sold1oz4,9524,061
Average realized gold price2$/oz2,8252,063

First Quarter 2025

Revenue totaled $14.0 million for the quarter compared to $8.4 million in the prior year period primarily driven by higher ounces sold at Granite Creek and a higher average realized gold price 1.

Gold sales 1 totaled 4,952 ounces at an average realized gold price 2 of $2,825 per ounce compared to gold sales 1 of 4,061 ounces at an average realized gold price 2 of $2,063 per ounce in the prior year period.

Loss per share of $0.10 for the quarter compared to a $0.06 loss per share in the prior year period primarily due to revaluation losses from the gold prepay and silver purchase agreement.

Cash used in operating activities was $22.7 million, compared to cash used in operating activities of $25.2 million in the prior year period.

Cash balance of $13.5 million as at March 31, 2025, a decrease of $5.5 million during the quarter due to cash used in operating activities partially offset by cash provided by financing activities from a private placement and the Company's at-the-market equity program ("ATM Program").

Filed preliminary economic assessments for all five gold projects as scheduled in support of the Company’s new development plan.

Completed modifications to the pumping system at Granite Creek Underground leading to improving water levels and reduced mine interruptions.

Received the Decision Record from the U.S. Bureau of Land Management for the commencement of the underground portals at Archimedes Underground.

Completed approximately 15,000 feet of underground delineation drilling at the Cove Project to enhance the certainty of the mineral resource estimate and support engineering analyses for an anticipated feasibility study.

2 This is a Non-GAAP Measure; please see “Non-GAAP Measures” section.

Executed several financing initiatives to enhance financial flexibility in support of the Company’s broader recapitalization plan, including a recently finalized working capital facility with Auramet International, Inc. for $12 million, maturing in 12 months.

Strategy Overview

On November 12, 2024 the Company announced a new development plan following a review of the strategic direction of the Company following the appointment of a new CEO and other key members to the management team. The new development plan includes the development of three underground mines, but also includes accelerating, permitting, and the development of two large oxide open pit deposits, one at Granite Creek and the other, Mineral Point, within the Ruby Hill Project area. The new development plan is viewed by the Company as the most effective strategy to generate free cash flow while progressing earlier stage projects to provide a pipeline of growth over the medium and long term. The Company also confirmed the initiation of a recapitalization plan to strengthen its balance sheet to support the new development plan. The Lone Tree Autoclave remains the centralized refractory mineral processing facility in the new development plan and management intends to continue its work towards completion of the Lone Tree Autoclave refurbishment feasibility study in the fourth quarter of 2025.

Preliminary Economic Assessments covering the Company’s five gold projects were filed in March 2025, and outline three areas of growth expenditure over the next three years to support the advancement of the Company’s development plan. These growth expenditures which are discretionary and subject to available resources, ranked from highest priority are: (i) advancing permitting activities, (ii) feasibility studies, and (iii) development work at Archimedes underground. For 2025, the growth expenditures are expected to total between $40 million to $50 million.

The Lone Tree open pit project has a variety of financial, technical, environmental and social issues to be worked through. It is expected that the project will likely remain deferred for another decade.

Recapitalization Plan

On November 12, 2024 the Company announced a new development plan following a review of the strategic direction of the Company following the appointment of a new CEO and other key members to the management team. The new development plan includes the development of three underground mines, but also includes accelerating, permitting, and the development of two large oxide open pit deposits, one at Granite Creek and the other, Mineral Point, within the Ruby Hill Project area. The new development plan is viewed by the Company as the most effective strategy to generate free cash flow while progressing earlier stage projects to provide a pipeline of growth over the medium and long term. The Company also confirmed the initiation of a recapitalization plan to strengthen its balance sheet to support the new development plan. The Lone Tree Autoclave remains the centralized refractory mineral processing facility in the new development plan and management intends to continue its work towards completion of the Lone Tree Autoclave refurbishment feasibility study in the third quarter of 2025.

The Company addressed the first phase of its recapitalization plan by entering into agreements to defer the December 2024 Gold Prepay and January 2025 Silver Purchase Agreement deliveries until March 31, 2025 and settled the deliveries on April 2, 2025 with Orion by entering into a new gold and silver prepay arrangement with National Bank of Canada with deliveries of 6,864 ounces of gold and 345,549 ounces of silver by September 30, 2025.

Management is advancing its recapitalization plan to support the Company’s development plan on several fronts, and is in active discussions with several parties regarding a number of financing options including a senior lending facility, royalty sales, non-core asset sales such as its FAD property as well as terming out the 2025 quarterly gold prepays

Management has been engaged in discussions with existing and potential new partners, and aims to complete the second phase of its refinancing plan by June 30, 2026, which coincides with the date of maturity of the Orion Convertible Loan.

Outlook

The Company expects to extract between 30,000 to 40,000 ounces 1 of gold in 2025. Granite Creek underground is expected to contribute between 20,000 to 30,000 ounces 1 of gold, and the Company’s two residual heap leach operations are expected to contribute approximately 10,000 ounces of gold in 2025.

This outlook, including expected results and targets, is subject to various risks, uncertainties and assumptions, which may impact future performance and the Company’s ability to achieve the results and targets discussed in this section. Please refer to "Cautionary Statements on Forward Looking Statements" section. The Company may, but is under no obligation to, update this outlook depending on changes in metal prices and other factors.

Financing Overview (for the three months ended March 31, 2025)

Prospectus Offering of Common Shares

On January 31, 2025, the Company closed a prospectus offering of 28.2 million common shares of the Company at a price of C$0.80 per share for aggregate gross proceeds of the Company of approximately$15.6 million (C$22.6 million).

On February 28, 2025, in connection with the prospectus offering, the Company closed a private placement of an aggregate of 1.0 million common shares to certain directors and officers of the Company at a price of C$0.80 per share for gross proceeds of approximately $0.6 million (C$0.8 million).

On February 28, 2025, the Company entered into a supplemental indenture to effect certain amendments to its convertible debenture indenture dated February 22, 2023 ("the Indenture"). The amendments provided:

the conversion price applicable to the a debenture holder’s right to elect to convert outstanding and accrued interest on the Convertible Debentures is equal to the volume weighted average price of i-80 Gold’s common shares on the TSX during the five trading days immediately preceding the date of the debenture holder’s election notice, less a discount of 15%, converted into US dollars at the Bank of Canada rate on such date;

the conversion price applicable to the Company’s right to elect to convert outstanding and accrued interest on the Convertible Debentures is equal to the greater of (x) 85% of the average closing price of the i-80 Gold common shares as measured in US dollars on the NYSE during the 10 business days immediately preceding the date of the Company’s election notice, and (y) the volume weighted average price of i-80 Gold common shares on TSX during the five trading days immediately preceding the date of the Company’s election notice, less a discount of 15%, converted into US dollars at the Bank of Canada rate on such date;

that the Company’s right to grant security against the Cove Project would rank subordinate to the security granted to the debenture holders; and

the Company with a redemption right in respect of all of the outstanding Convertible Debentures which allows the Company to redeem, in its sole discretion, all of the outstanding Convertible Debentures for cash at a 104% premium of the outstanding principal, along with accrued interest up to the redemption date.

On January 15, 2025, the Company completed the amendment and restatement of its convertible credit agreement ("A&R Convertible Credit Agreement") with an affiliate of Orion, as described herein. As a result, the conditions relating to the deferral of gold and silver deliveries, and the extension of the Orion Convertible Loan (collectively, the "Waiver Agreements") required to be completed to-date have been satisfied.

Further to the A&R Convertible Credit Agreement, Orion and i-80 Gold have extended the maturity date of the A&R Convertible Credit Agreement by six months from December 13, 2025, to June 30, 2026, and have put certain security in place to secure the Company’s obligations under the A&R Convertible Credit Agreement. Additional security against the Company’s Ruby Hill and Granite Creek projects is required to be put in place by March 31, 2025. In connection with the extension of the A&R Convertible Credit Agreement, the Company has issued to Orion 5 million common share purchase warrants (the “2025 Orion Warrants”) with an exercise price of C$1.01 and an expiry date of January 15, 2029.

In addition, i-80 Gold and Orion have agreed to enter into an offtake agreement (the “Offtake Agreement”). The Offtake Agreement has similar terms to the Company's existing offtake agreement and commences once the current offtake agreement with Deterra Royalties Limited expires at the end of December 2028.

ATM Program

During the quarter ended March 31, 2025, the Company issued 4.3 million common shares under the ATM Program for total gross proceeds of $2.5 million. As at March 27, 2025, the Company had issued a total of 26.7 million common shares under the ATM Program for total gross proceeds of $25.1 million. The ATM Program expired on March 31, 2025.

New Gold & Silver Prepay Agreement & Working Capital Facility

On March 31, 2025 the Company entered into a New Gold Prepay and Silver Purchase Agreement with National Bank under which National Bank purchased approximately 6,864 ounces of gold and 345,549 ounces of silver from the Company for delivery to National Bank by September 30, 2025 or earlier, upon an infusion of capital in line with the recapitalization plan. The proceeds of this new prepay arrangement was used to satisfy the March 31, 2025 gold and silver deliveries due to an affiliate of Orion Mine Finance under its respective Gold Prepay and Silver Purchase and sale agreements. The obligations under the prepay arrangement with National Bank are secured by the FAD project. This was funded on April 1, 2025.

Completed Preliminary Economic Assessments and Initial Assessments ("PEA") for Five Gold Projects

During the first quarter of 2025, the Company announced economic and operating highlights from preliminary economic assessments ("PEA") completed for five gold projects. These updated PEAs demonstrate the significant value of the Company's portfolio and support an updated mineral resource estimate. Technical reports for each project were filed in accordance with S-K 1300 and Item 601 of Regulation S-K in the United States and in accordance with National Instrument 43-101 Standards for Disclosure of Mineral Projects in Canada ("NI - 43-101").

Third-party Processing Agreements

The Company finalized third-party processing agreements in respect of toll milling as well as ore sales for refractory and oxide material, respectively. The Agreements remain in effect through to December 31, 2027. The Company is targeting to have the anticipated refurbishment of its Lone Tree autoclave facility complete by December 31, 2027 to allow for all material from the Company's underground mines to be processed at its autoclave facility.

Working Capital Facility

On April 29, 2025, the Company finalized a master purchase and sale agreement with Auramet International, Inc., for the prepayment of sulfide material, totaling $12.0 million and $11.6 million net proceeds.

ContentsView on SEC.gov

The text of this filing, as the company filed it with the SEC, without its images or exhibits. This is not investment advice.