A company's yearly report to the SEC, with audited financial statements. It is the fullest account a company gives of its business, its finances and the risks it sees.

FY2024 · Filed Feb 28, 2025

NEXT$5.80-0.9%Stored close · as of Nov 6, 2026

What changed in Risk Factors?

Read the current filing

Previous report: 10-K

Period ended 2023-12-31; filed 2024-03-11.

0001628280-24-010236

Item 1A. Risk Factors

Current report: 10-K

Period ended 2024-12-31; filed 2025-02-28.

0001628280-25-008841

Item 1A. Risk Factors

The baseline is this issuer’s latest earlier reporting period of the same form that was filed before the current report. A previous 10-Q is a different quarter, not a year-over-year comparison. Amendments are excluded.

Compared 263 previous paragraphs and 267 current paragraphs.

232 unchanged; 23 reworded; 11 added; 6 removed; 2 previous and 1 current paragraphs rearranged.

Tables are not compared: 0 previous and 0 current tables excluded. Dates, whitespace, punctuation and numbering changes are ignored; changes to financial figures remain significant.

A changed paragraph is not evidence that risk increased or decreased. An unchanged paragraph does not establish that risk stayed the same.

Added paragraphs (11)

Current report

Tariffs issued by the United States government could have an adverse effect on our future operations.

Current report

The United States government recently has announced or imposed broad-ranging tariffs. Other countries have announced or imposed counter-tariffs on U.S.-produced items. If these tariffs or counter-tariffs were to take effect and we were unable to pass through the additional costs to us, we could experience materially lower margins, lost sales, and an overall adverse effect on our future results of operations.

Current report

We will be dependent on third-party contractors for the successful completion of the Rio Grande LNG Facility, CCS projects and related infrastructure, and any failure by our contractors to perform their contractual obligations could have a material adverse impact on our projects.

Current report

We may not be successful in developing or constructing all of our proposed expansion projects.

Current report

We may not be able to successfully develop or construct some of our proposed expansion trains at the Rio Grande LNG Facility, whether due to lack of commercial interest, inability to obtain financing, inability to obtain adequate supply of materials and equipment to complete construction of our projects, inability to obtain necessary regulatory approvals (including as a result of political factors, environmental concerns or public opposition) or otherwise. Our ability to develop additional liquefaction facilities will also depend on the availability and pricing of LNG and natural gas in North America and other places around the world. If we are unable or unwilling to develop and construct additional expansion trains, our prospects for growth will be limited.

Current report

The decision by the D.C. Circuit Court of Appeals could impact Rio Grande’s ability to complete Phase 1, the cost to complete Phase 1, the timing of the completion of Phase 1, our ability to take a final investment decision on Trains 4 and 5, our ability to develop additional expansion trains at the Rio Grande LNG Facility, and our ability to achieve expected investment returns.

Current report

Financial Condition and Results of Operations—Overview of Business and Significant Developments—Significant Recent Events—Regulatory,” on August 6, 2024, the D.C. Circuit Court of Appeals vacated the FERC reauthorization for the siting, construction and operation of the Rio Grande LNG Facility. We intend to pursue available legal remedies against judicial challenges and are engaged in active resolution of the requisite issues to ensure that the affected permit remains in effect; however, there is no guarantee as to how long any agency proceedings and judicial challenges will take to resolve, whether there will be any delays in construction activities or whether Rio Grande will ultimately succeed in maintaining the permit in its issued form or in a suitable replacement form. These uncertainties could cause Phase 1 at the Rio Grande LNG Facility to be subject to increased costs, adverse impacts to completion timing, or adverse impacts to the ability to complete construction of Phase 1. This could adversely affect the ability for Rio Grande and its owners, including us, to successfully implement our business strategy or achieve expected returns. Similarly, these uncertainties could impact the timing of, and our ability to develop and take a final investment decision on, any expansion trains at the Rio Grande LNG Facility. In addition, the bank credit facilities obtained by Rio Grande to finance a substantial portion of Phase 1 costs require maintenance of material governmental approvals. To the extent Rio Grande becomes unable to satisfy such requirement as set forth in the credit agreements or reach other accommodations with its lenders, its ability to continue borrowing under such credit facilities could be negatively impacted, which in turn could adversely affect our business, financial condition, results of operations and liquidity.

Current report

Further, in the first few days of his second term in office, President Trump issued a series of executive orders signaling a shift in environmental and energy policy, which could result in significant regulatory changes in the future. For instance, President Trump issued executive orders which revoked prior executive orders and initiatives related to environmental justice and clean energy. While the extent of the Trump Administration's changes to the environmental regulatory landscape in the United States is unknown at this time, it is possible that additional changes in the future could impact our operations.

Current report

The 2024 Warrants were issued on December 31, 2024 in two equal tranches and are exercisable at any time before December 31, 2029 for an aggregate of approximately 7.2 million shares of Company common stock, with the first tranche exercisable at $7.15 per share and the second tranche exercisable at $9.30 per share.

Current report

We could also incur additional costs and require additional resources to monitor, report, and comply with various ESG practices and current or emerging regulatory requirements, including with respect to climate change and sustainability. Further, we are currently assessing the potential impacts of the adopted or proposed laws, as well as other sustainability and climate-related disclosure obligations and evolving legal and regulatory requirements, to which we may be subject. Enhanced sustainability and climate-related disclosure requirements could lead to reputational or other harm to our relationships with regulators, employees, customers, investors or other stakeholders.

Current report

Finally, as of January 31, 2025, the Trump Administration had issued a series of executive orders that signal a shift in the United States' energy and climate change policy. Among other directives, such executive orders: (i) direct federal agencies to identify and exercise emergency authorities to facilitate conventional energy production, transportation, and refining, and call for the use of emergency regulations to expedite energy infrastructure projects; (ii) promote energy exploration and production on federal lands and waters; (iii) mandate a review of existing regulations that may burden domestic energy development; and (iv) pause the disbursement of funds appropriated through the Inflation Reduction Act and the Infrastructure Investment and Jobs Act.
Removed paragraphs (6)

Previous report

We have incurred operating losses since our inception and management expects operating losses and negative cash flows to continue for the foreseeable future and, as a result, we will require additional capital to fund our operations and execute our business plan. As of December 31, 2023, the Company had $38.2 million in cash and cash equivalents, which may not be sufficient to fund the Company's planned operations through one year after the date the consolidated financial statements are issued. Accordingly, there is substantial doubt about the Company's ability to continue as a going concern. The analysis used to determine the Company's ability to continue as a going concern does not include cash sources outside of the Company's direct control that management expects to be available within the next twelve months.

Previous report

Our ability to continue as a going concern is dependent upon our ability to obtain sufficient funding through additional debt or equity financing and to manage operating and overhead costs. There can be no assurance that we will be able to raise sufficient capital on acceptable or favorable terms to the Company, or at all.

Previous report

The Rio Grande LNG Facility’s operations will be substantially dependent on the development and operation of the Pipeline by Enbridge and its affiliates.

Previous report

In October 2020, we announced that we have developed proprietary CCS processes, which we intend to deploy at the Rio Grande LNG Facility to significantly reduce its expected CO 2 emissions. However, the Rio Grande LNG Facility CCS project may ultimately be unsuccessful or, even if successful, may not satisfy the demands or expectations of certain members of the investing community focused on ESG matters.

Previous report

The COVID-19 pandemic has resulted in significant disruption globally. Actions taken by various governmental authorities, individuals and companies around the world to prevent the spread of COVID-19 have restricted travel, business operations, and the overall level of individual movement and in-person interaction across the globe. Furthermore, the impact of the pandemic, including its effect on the demand for natural gas, led to significant global economic contraction generally and in our industry in particular. Prospects for the development and financing of the Rio Grande LNG Facility are based in part on factors including global economic conditions that have been, and are likely to continue to be, adversely affected by the COVID-19 pandemic.

Previous report

The COVID-19 pandemic has caused us to modify our business practices, including by restricting employee travel, requiring employees to work remotely and cancelling physical participation in meetings, events and conferences, and we may take further actions as may be required by government authorities or that we determine are in the best interests of our employees, customers and business partners. There is no certainty that such measures will be sufficient to mitigate the risks posed by COVID-19 or otherwise be satisfactory to government authorities. If a number of our employees were to contract COVID-19 at the same time, our operations could be adversely affected.
Reworded paragraphs (23)

Previous wording

A breach of the covenants and other restrictions in any of Rio Grande’s indebtedness could result in an event of default thereunder. Such a default may allow the holders of such indebtedness to accelerate the related indebtedness which may result in foreclosure on Rio Grande’s assets.

Current wording

A breach of the covenants and other restrictions in any of Rio Grande’s indebtedness could result in an event of default thereunder. Such a default may allow the holders of such indebtedness to accelerate the related indebtedness which may result in foreclosure on Rio Grande’s assets or equity interests in Rio Grande.

Previous wording

Additionally, NextDecade LLC has entered into a credit agreement (the “NextDecade Credit Agreement”) that provides for a $50 million revolving loan facility. The NextDecade Credit Agreement includes covenants that, among other things, limit the ability of NextDecade LLC to incur additional indebtedness, make certain investments or pay dividends or distributions on equity interests or subordinated indebtedness or purchase, redeem, or retire equity interests, sell or transfer assets, incur liens or dissolve, liquidate, consolidate, merge. Upon the occurrence and continuation of an event of default under the NextDecade Credit Agreement (and after all applicable cure periods have elapsed), the required lenders may, by notice to NextDecade LLC accelerate the loans thereunder, suspend or terminate all outstanding loan commitments under the NextDecade Credit Agreement and exercise remedies in respect of the collateral.

Current wording

Our wholly owned subsidiary, Rio Grande LNG Super Holdings, LLC ("Super Holdings"), has entered into a credit agreement (the "Corporate Credit Agreement") that provides for a $175 million senior secured loan. The Corporate Credit Agreement includes covenants that, among other things, limit the ability of Super Holdings to incur additional indebtedness, make certain investments or pay dividends or distributions on equity interests or subordinated indebtedness or purchase, redeem, or retire equity interests, sell or transfer assets, incur liens or dissolve, liquidate, consolidate, merge. Upon the occurrence and continuation of an event of default under the Corporate Credit Agreement (and after all applicable cure periods have elapsed), the majority lenders may, by notice to Super Holdings accelerate the loans thereunder, terminate any outstanding loan commitments and exercise all contractual and legal rights in relation to the collateral.

Previous wording

We currently operate parts of our business through a joint venture, Rio Grande LNG Intermediate Holdings, LLC (“Intermediate Holdings”) in which we do not have 100% ownership interest, and we may enter into additional joint ventures in the future. Joint ventures and minority investments inherently involve a lesser degree of control over business operations, thereby potentially increasing the financial, legal, operational and/or compliance risks associated with the joint venture or minority investment. For example, except for the Member Reserved Matters (as defined below), the affairs of Intermediate Holdings will otherwise be managed by a board of managers (the “Intermediate Holdings Board”). The Intermediate Holdings Board will be composed of up to four managers appointed by the NextDecade Member (the “Class A Managers”), including one Class A Manager designated by Global LNG North America Corp., a subsidiary of TotalEnergies SE, and managers appointed by members holding a minimum percentage of the Class B limited liability company interests in Intermediate Holdings (the “Class B Managers”). Approval of any matter by the Intermediate Holdings Board will require the consent of a majority of the Class A Managers voting on the matter and Class B Managers representing a majority of the Class B limited liability company interests in Intermediate Holdings voting for such matter, as applicable; provided that (i) certain specified “qualified matters,” “supermajority matters,” and “unanimous matters” are reserved to the approval of the members of Intermediate Holdings (the "Member Reserved Matters") holding a requisite percentage of the applicable classes of limited liability company interests in Intermediate Holdings, and (ii) related party transactions will be subject to approval in accordance with the procedures specified in the JV Agreement. Pursuant to the JV Agreement, the NextDecade Member will be entitled to receive up to approximately 20.8% of distributions of available cash of Intermediate Holdings to its members during operations; provided, that a majority of the Intermediate Holdings distributions to which the NextDecade Member is otherwise entitled will be paid for any distribution period only after the Financial Investors receive an agreed distribution threshold in respect of such distribution period and certain other deficit payments from prior distribution periods, if any, are made. Any such shortfall in distributions that the NextDecade Member would otherwise have been entitled to will accrue as an arrearage to be paid out in future periods in which Intermediate Holdings meets the applicable target distribution threshold for the Financial Investors. Challenges and risks presented by joint venture structures not otherwise present with respect to our wholly-owned subsidiaries and direct operations, include:

Current wording

We currently operate parts of our business through a joint venture, Rio Grande LNG Intermediate Holdings, LLC (“Intermediate Holdings”) in which we do not have 100% ownership interest, and we may enter into additional joint ventures in the future. Joint ventures and minority investments inherently involve a lesser degree of control over business operations, thereby potentially increasing the financial, legal, operational and/or compliance risks associated with the joint venture or minority investment. For example, except for the Member Reserved Matters (as defined below), the affairs of Intermediate Holdings will otherwise be managed by a board of managers (the “Intermediate Holdings Board”). The Intermediate Holdings Board will be composed of up to four managers appointed by us (the “Class A Managers”), including one Class A Manager designated by Global LNG North America Corp., a subsidiary of TotalEnergies SE, and managers appointed by members holding a minimum percentage of the Class B limited liability company interests in Intermediate Holdings (the “Class B Managers”). Approval of any matter by the Intermediate Holdings Board will require the consent of a majority of the Class A Managers voting on the matter and Class B Managers representing a majority of the Class B limited liability company interests in Intermediate Holdings voting for such matter, as applicable; provided that (i) certain specified “qualified matters,” “supermajority matters,” and “unanimous matters” are reserved to the approval of the members of Intermediate Holdings (the "Member Reserved Matters") holding a requisite percentage of the applicable classes of limited liability company interests in Intermediate Holdings, and (ii) related party transactions will be subject to approval in accordance with the procedures specified in the JV Agreement. Pursuant to the JV Agreement, we will be entitled to receive up to approximately 20.8% of distributions of available cash of Intermediate Holdings to its members during operations; provided, that a majority of the Intermediate Holdings distributions to which we are otherwise entitled will be paid for any distribution period only after the Financial Investors receive an agreed distribution threshold in respect of such distribution period and certain other deficit payments from prior distribution periods, if any, are made. Any such shortfall in distributions that we would otherwise have been entitled to will accrue as an arrearage to be paid out in future periods in which Intermediate Holdings meets the applicable target distribution threshold for the Financial Investors. Challenges and risks presented by joint venture structures not otherwise present with respect to our wholly-owned subsidiaries and direct operations, include:

Previous wording

We are not expected to generate cash flow, or even obtain revenues, from our LNG liquefaction and export activities unless and until the Rio Grande LNG Facility is operational. Additionally, we do not expect to generate cash flow from our CCS projects until we install CCS systems at the Rio Grande LNG Facility or on third-party industrial facilities. Accordingly, distributions to investors may be limited, delayed, or non-existent.

Current wording

We are not expected to generate cash flow, or even obtain revenues, from our LNG liquefaction and export activities unless and until the Rio Grande LNG Facility is operational. Additionally, we do not expect to generate cash flow from our CCS projects until such projects are installed and operational. Accordingly, distributions to investors may be limited, delayed, or non-existent.

Previous wording

The Rio Grande LNG Facility will be dependent on a pipeline owned by an affiliate of Enbridge (the “Transporter”) for the delivery of all of its natural gas. The Pipeline is currently in development and its construction will require the Transporter to secure rights-of-way along the proposed Pipeline route. It is possible that, in negotiating to secure these rights-of-way, the Transporter encounters recalcitrant landowners or competitive projects, which could result in additional time needed to secure the Pipeline route and, consequently, delays in, or abandonment of, its construction. Construction of the Pipeline could be delayed or abandoned for any of many other reasons, such as it becoming economically disadvantageous to the Transporter, a failure to obtain or maintain all necessary permits, approvals and licenses for the construction and operation, mechanical or structural failures, inadvertent damages during construction, natural disasters, or any terrorist attack, including cyberterrorism, affecting the Pipeline or the Transporter. Any such delays in the construction of the Pipeline could delay the development of the Rio Grande LNG Facility and its becoming operational.

Current wording

Commissioning and operation of the Rio Grande LNG Facility will also require the ability to deliver natural gas to the Rio Grande LNG Facility via pipelines, certain of which are under development and construction and will require securing rights-of-way along the proposed route. Negotiation to secure these rights-of-way could give rise to recalcitrant landowners or competitive projects, which could result in additional time needed to secure the route and, consequently, delays in, or abandonment of, construction. Pipeline construction could also be delayed or abandoned for any of many other reasons, such as it becoming economically disadvantageous to the owner, a failure to obtain or maintain all necessary permits, approvals and licenses for the construction and operation, mechanical or structural failures, inadvertent damages during construction, natural disasters, or any terrorist attack, including cyberterrorism. Any such delays in pipeline construction could delay the development of the Rio Grande LNG Facility and its becoming operational.

Previous wording

•failure to obtain or maintain all necessary government and third-party permits, approvals and licenses, or to comply with all the terms and conditions of those authorizations, for the construction and operation of the Rio Grande LNG Facility and CCS projects;

Current wording

•failure to obtain or maintain all necessary government and third-party permits, approvals and licenses, or to comply with all the terms and conditions of those authorizations, for the construction and operation of the Rio Grande LNG Facility and CCS projects, or litigation concerning such permits, approvals and licenses;

Previous wording

We expect our CCS projects, following successful construction and deployment, to generate revenue from a combination of sources, including fees from source facilities, government incentives and carbon credits. Government incentives include federal income tax credits under Section 45Q of the Internal Revenue Code, which currently provides a federal income tax credit per metric ton of carbon captured and permanently stored. The availability of these government incentives have a significant effect on the economics and viability of our CCS projects, and any reduction or elimination of such incentives could adversely affect the growth of our CCS business, our financial condition and our future results.

Current wording

We expect our CCS projects, following successful construction and deployment, to generate revenue from a combination of sources, including fees from source facilities, government incentives and carbon credits. Government incentives include federal income tax credits under Section 45Q of the Internal Revenue Code of 1986, as amended (the "Code"), which currently provides a federal income tax credit per metric ton of carbon captured and permanently stored. The availability of these government incentives have a significant effect on the economics and viability of our CCS projects, and any reduction or elimination of such incentives could adversely affect the growth of our CCS business, our financial condition and our future results.

Previous wording

The Rio Grande LNG Facility will be dependent on the availability of gas supply at the Agua Dulce supply area.

Current wording

The Rio Grande LNG Facility will be dependent on the availability of gas supply at the Agua Dulce Hub.

Previous wording

The Pipeline is expected to collect and transport natural gas to the Rio Grande LNG Facility. The header system at the upstream end of the Pipeline is expected to have multiple interconnects to the existing natural gas pipeline grid located in the Agua Dulce supply area (the “Agua Dulce Hub”). The Agua Dulce Hub includes deliveries from, but not limited to, ConocoPhillips' 1,100-mile South Texas intrastate and gas gathering pipeline system and ExxonMobil’s 925 MMcf/d King Ranch processing facility. As the Pipeline system interconnects are expected to be relatively close to the Agua Dulce Hub, it is expected that gas will be available for purchase in large volumes at commercially acceptable prices. Nonetheless, disruptions in upstream supply sources or increased market demand could impact the availability of gas supply to the Pipeline header system, which would result in curtailments at the Rio Grande LNG Facility.

Current wording

Rio Grande has executed agreements for transportation of natural gas to the Rio Grande LNG Facility on both a firm and interruptible basis to support commissioning and operations and provide the ability to purchase natural gas supplies at the Agua Dulce Hub, giving Rio Grande access to prolific gas production from the Permian Basin and Eagle Ford Shale and providing significant flexibility to obtain competitively priced natural gas feedstock. We expect Rio Grande to have access to multiple interconnects to the existing natural gas pipeline grid located at the Agua Dulce Hub. As the interconnects are expected to be at the Agua Dulce Hub, it is expected that gas will be available for purchase in large volumes at commercially acceptable prices. Nonetheless, disruptions in upstream supply sources or increased market demand could impact the availability of gas supply to the header system, which would result in curtailments at the Rio Grande LNG Facility.

Previous wording

Each liquefaction train for the Rio Grande LNG Facility is expected to involve the transportation on the Pipeline for liquefaction of approximately 0.9 Bcf/day of natural gas, for a total of 4.5 Bcf/day for five liquefaction trains at full build-out. Gas sales agreements for the supply of these volumes could entail negotiations with multiple parties for firm and interruptible gas supply and transportation services to the Pipeline header system, as well as pipeline interconnects and ancillary operational agreements. Delays caused by third parties in the course of negotiating agreements and constructing the required interconnects could delay the start of commercial operations for the Rio Grande LNG Facility.

Current wording

Each liquefaction train for the Rio Grande LNG Facility is expected to involve the transportation for liquefaction of approximately 0.9 Bcf/day of natural gas, for a total of 4.5 Bcf/day for five liquefaction trains at full build-out. Gas sales agreements for the supply of these volumes could entail negotiations with multiple parties for firm and interruptible gas supply and transportation services to the pipeline header system, as well as pipeline interconnects and ancillary operational agreements. Delays caused by third parties in the course of negotiating agreements and constructing the required interconnects could delay the start of commercial operations for the Rio Grande LNG Facility.

Previous wording

We are required to obtain governmental approvals and authorizations to implement our proposed business strategy, which includes the design, construction and operation of the Rio Grande LNG Facility and the export of LNG from the U.S. to foreign countries. As described above under “Business− Governmental Permits, Approvals and Authorizations,” the design, construction and operation of LNG export facilities is a highly regulated activity in the U.S., subject to a number of permitting requirements, regulatory approvals and ongoing safety and operational compliance programs. There is no guarantee that we will obtain or, once obtained, maintain these governmental authorizations, approvals and permits. While the FERC has authorized the construction and operation of the Rio Grande LNG Facility, additional approvals from FERC Staff will be required as we proceed with its construction and commissioning. Failure to obtain, or failure to obtain on a timely basis, or failure to maintain any of these governmental authorizations, approvals and permits could have a material adverse effect on our business, results of operations, financial condition and prospects.

Current wording

We are required to obtain and maintain governmental approvals and authorizations to implement our proposed business strategy, which includes the design, construction and operation of the Rio Grande LNG Facility and the export of LNG from the U.S. to foreign countries. As described above under “Business—Governmental Permits, Approvals and Authorizations,” the design, construction and operation of LNG export facilities is a highly regulated activity in the U.S., subject to a number of permitting requirements, regulatory approvals and ongoing safety and operational compliance programs, and certain of our authorizations have been challenged by project opponents and remain subject to ongoing regulatory proceedings. There is no guarantee that we will obtain or, once obtained, maintain these governmental authorizations, approvals and permits. While the FERC has authorized the construction and operation of the Rio Grande LNG Facility, it is conducting a supplemental EIS in response to action by the D.C. Circuit. Furthermore, additional approvals from FERC Staff will be required as we proceed with its construction and commissioning. Failure to obtain, or failure to obtain on a timely basis, or failure to maintain any of these governmental authorizations, approvals and permits (including potentially as a result of the D.C. Circuit's decision regarding the Remand Order or FERC's actions in response to that decision) could have a material adverse effect on our business, results of operations, financial condition and prospects.

Previous wording

In addition, some of these governmental authorizations, approvals and permits require extensive environmental review. We cannot predict or control whether our authorizations, approvals or permits will attract significant opposition or whether the permitting process will be lengthened due to complexities and appeals. Some groups have perceived, and other groups could perceive, that the proposed construction and operation of the Rio Grande LNG Facility could negatively impact the environment or cultural heritage sites. Objections from such groups could cause delays, damage to reputation and difficulties in obtaining governmental authorizations, approvals or permits or prevent the obtaining of such authorizations, approvals or permits altogether. Although the necessary authorizations, approvals and permits to construct and operate the Rio Grande LNG Facility have been obtained, such authorizations, approvals and permits may be subject to ongoing conditions imposed by regulatory agencies or may be subject to legal proceedings not involving us, which is customary for U.S. LNG projects.

Current wording

In addition, some of these governmental authorizations, approvals and permits require extensive environmental review. We cannot predict or control whether our authorizations, approvals or permits will attract significant opposition or whether the permitting process will be lengthened due to complexities and appeals. Some groups have perceived, and other groups could perceive, that the proposed construction and operation of the Rio Grande LNG Facility could negatively impact the environment or cultural heritage sites. Objections from such groups could cause delays, damage to reputation and difficulties in obtaining governmental authorizations, approvals or permits or prevent the obtaining of such authorizations, approvals or permits altogether. Although the necessary authorizations, approvals and permits to construct and operate the Rio Grande LNG Facility have been obtained, such authorizations, approvals and permits may be subject to ongoing regulatory proceedings, as well as conditions imposed by regulatory agencies, and may be subject to additional legal proceedings not involving us, which is customary for U.S. LNG projects.

Previous wording

The Tax Reform Act of 1986 (as amended) contains provisions that limit the utilization of NOL and tax credit carryforwards if there has been a change in ownership as described in Section 382 of the Internal Revenue Code (“Section 382”). Such an ownership change occurs if the aggregate stock ownership of certain stockholders, generally stockholders beneficially owning five percent or more of a corporation’s common stock, applying certain look-through and aggregation rules, increases by more than 50 percentage points over such stockholders’ lowest percentage ownership during the testing period, generally three years. Substantial changes in the Company's ownership have occurred that may limit or reduce the amount of NOL carryforwards that the Company could utilize in the future to offset taxable income. At December 31, 2023, we had federal net operating loss (“NOL”) carryforwards of approximately $260.7 million. Approximately $26.1 million of these NOL carryforwards will expire between 2034 and 2038.

Current wording

The Code contains provisions that limit the utilization of NOLs and tax credit carryforwards if there has been a change in ownership as described in Section 382 of the Code (“Section 382”). Such an ownership change occurs if the aggregate stock ownership of certain stockholders, generally stockholders beneficially owning five percent or more of a corporation’s common stock, applying certain look-through and aggregation rules, increases by more than 50 percentage points over such stockholders’ lowest percentage ownership during the testing period, generally three years. Substantial changes in the Company's ownership have occurred that may limit or reduce the amount of NOL carryforwards that the Company could utilize in the future to offset taxable income. At December 31, 2024, we had federal net operating loss (“NOL”) carryforwards of approximately $370.5 million. Approximately $26.1 million of these NOL carryforwards will expire between 2034 and 2038.

Previous wording

As of March 4, 2024, affiliates of York Capital Management, L.P., TotalEnergies SE, Valinor Capital Partners, L.P., HGC NEXT INV LLC and Ninteenth Investment Company (collectively, the “Large Stockholders”) beneficially own, in the aggregate, approximately 60% of the combined voting power of our outstanding shares of common stock. Additionally, four members of our Board of Directors are affiliated with certain of Large Stockholders. As a result, the Large Stockholders have the ability to influence the election of our directors and the outcome of corporate actions requiring stockholder approval, such as: (i) a merger or a sale of our Company, (ii) a sale of all or substantially all of our assets, and (iii) amendments to our articles of incorporation and bylaws. This concentration of voting power and control could have a significant effect in delaying, deferring or preventing an action that might otherwise be beneficial to our other stockholders and be disadvantageous to our stockholders with interests different from those entities and individuals. The Large Stockholders also have significant control over our business, policies and affairs by their affiliates serving as directors of our Company. They may also exert influence in delaying or preventing a change in control of the Company, even if such change in control would benefit the other stockholders of the Company. In addition, the significant concentration of stock ownership may adversely affect the market value of the Company’s common stock due to investors’ perception that conflicts of interest may exist or arise.

Current wording

As of February 20, 2025, affiliates of TotalEnergies SE, HGC NEXT INV LLC and Ninteenth Investment Company (collectively, the “Large Stockholders”) beneficially own, in the aggregate, approximately 45% of the combined voting power of our outstanding shares of common stock. As a result, the Large Stockholders have the ability to influence the election of our directors and the outcome of corporate actions requiring stockholder approval, such as: (i) a merger or a sale of our Company, (ii) a sale of all or substantially all of our assets, and (iii) amendments to our articles of incorporation and bylaws. This concentration of voting power and control could have a significant effect in delaying, deferring or preventing an action that might otherwise be beneficial to our other stockholders and be disadvantageous to our stockholders with interests different from those entities and individuals. Additionally, three members of our Board of Directors are affiliated with certain Large Stockholders. The Large Stockholders also have significant control over our business, policies and affairs by their affiliates serving as directors of our Company. They may also exert influence in delaying or preventing a change in control of the Company, even if such change in control would benefit the other stockholders of the Company. In addition, the significant concentration of stock ownership may adversely affect the market value of the Company’s common stock due to investors’ perception that conflicts of interest may exist or arise.

Previous wording

We issued warrants together with the issuances of our Convertible Preferred Stock (the “Common Stock Warrants”). As of December 31, 2023, the outstanding Common Stock Warrants represented the right to acquire in the aggregate a number of shares of our common stock equal to approximately 71 basis points (0.71%) of all outstanding shares of Company common stock, measured on a fully diluted basis, on the applicable exercise date with a strike price of $0.01 per share.

Current wording

We issued warrants together with the issuances of our Convertible Preferred Stock (the “2022 Warrants”) and the entry into the Corporate Credit Agreement (the “2024 Warrants” and together with the 2022 Warrants, the “Common Stock Warrants”). As of December 31, 2024, the outstanding 2022 Warrants represented the right to acquire in the aggregate a number of shares of our common stock equal to approximately 15 basis points (0.15%) of all outstanding shares of Company common stock, measured on a fully diluted basis, on the applicable exercise date with a strike price of $0.01 per share. The 2022 Warrants have a fixed three-year term that commenced on the closings of the issuances of the associated Convertible Preferred Stock. The 2022 Warrants may only be exercised by holders thereof at the expiration of such three-year term.

Previous wording

Increasing attention to environmental, social and governance matters may impact our business, financial results or stock price and climate change concerns may pose challenges to our operating model.

Current wording

Attention to sustainability and environmental, social and governance matters may impact our business, financial results or stock price and climate change concerns may pose challenges to our operating model.

Previous wording

In recent years, increasing attention has been given to corporate activities related to environmental, social and governance matters in public discourse and the investment community. A number of advocacy groups, both domestically and internationally, have campaigned for governmental and private action to promote change at public companies related to ESG matters, including through the investment and voting practices of investment advisers, public pension funds, universities and other members of the investing community. These activities include increasing attention and demands for action related to climate change, promoting the use of substitutes to fossil fuel products, and encouraging the divestment of companies in the fossil fuel industry. These activities could negatively impact negotiations with potential customers or financial counterparties, reduce demand for our products, reduce our profits, increase the potential for investigations and litigation, impair our brand and have negative impacts on the price of our common stock and access to capital markets.

Current wording

In recent years, attention has been given to sustainability and ESG commitments and other activities. A number of advocacy groups, both domestically and internationally, have campaigned for governmental and private action to promote change at public companies related to ESG matters, including through the investment and voting practices of investment advisers, public pension funds, universities and other members of the investing community. These activities include increasing attention and demands for action related to climate change, promoting the use of substitutes to fossil fuel products, and encouraging the divestment of companies in the fossil fuel industry. While there are some other governments and actors taking different approaches, these activities could negatively impact negotiations with potential customers or financial counterparties, reduce demand for our products, reduce our profits, increase the potential for investigations and litigation, impair our brand and have negative impacts on the price of our common stock and access to capital markets.

Previous wording

In addition, organizations that provide information to investors on corporate governance and related matters have developed ratings systems for evaluating companies on their approach to ESG matters. Recently, there has been an acceleration in investor demand for ESG investing opportunities, and many large institutional investors have committed to increasing the percentage of their portfolios that are allocated towards ESG-focused investments. As a result, there has been a proliferation of ESG-focused investment funds seeking ESG-oriented investment products. If we are unable to meet the ESG ratings or investment or lending criteria set by these investors and funds, we may lose investors, investors may allocate a portion of their capital away from us, our cost of capital may increase, the price of our common stock may be negatively impacted, and our reputation may also be negatively affected.

Current wording

In addition, organizations that provide information to investors on corporate governance and related matters have developed ratings systems for evaluating companies on their approach to ESG matters and informing investment and voting decisions. There has been investor demand for ESG investing opportunities, and many large institutional investors have committed to increasing the percentage of their portfolios that are allocated towards ESG-focused investments. As a result, there has been a proliferation of ESG-focused investment funds seeking ESG-oriented investment products. If we obtain an unfavorable ESG rating or if we are unable to meet the investment or lending criteria set by these investors and funds, our stock may be omitted from such ESG-oriented investment products, which may lead to investors allocating a portion of their capital away from us, our cost of capital increasing, the price of our common stock being negatively impacted, and our reputation being negatively affected.

Previous wording

Furthermore, we also could face an increased risk of climate‐related litigation suits with respect to our operations or disclosures. Claims have been made against certain energy companies alleging that greenhouse gas emissions from oil, gas and LNG operations constitute a public nuisance under federal and state law. Private individuals or public entities also could attempt to enforce environmental laws and regulations against us and could seek personal injury and property damages or other remedies. Additionally, governments and private parties are also increasingly filing suits, or initiating regulatory action, based on allegations that certain public statements regarding ESG-related matters by companies are false and misleading “greenwashing” campaigns that violate deceptive trade practices and consumer protection statutes or that climate-related disclosures made by companies are inadequate. Similar issues can also arise when aspirational statements such as net-zero or carbon neutrality targets are made without clear plans. Although we are not a party to any such climate-related or “greenwashing” litigation currently, unfavorable rulings against us in any such case brought against us in the future could significantly impact our operations and could have an adverse impact on our financial condition.

Current wording

Furthermore, we also could face an increased risk of ESG‐related litigation suits, including climate-related litigation, with respect to our operations or disclosures. Claims have been made against certain energy companies alleging that greenhouse gas emissions from oil, gas and LNG operations constitute a public nuisance under federal and state law. Private individuals or public entities also could attempt to enforce environmental laws and regulations against us and could seek personal injury and property damages or other remedies. Additionally, governments and private parties are also increasingly filing suits, or initiating regulatory action, based on allegations that certain public statements regarding ESG-related matters by companies are false and misleading “greenwashing” campaigns that violate deceptive trade practices and consumer protection statutes or that climate-related disclosures made by companies are inadequate. Similar issues can also arise when aspirational statements such as net-zero or carbon neutrality targets are made without clear plans. There has also been an increase in litigation alleging that corporate diversity, equity and inclusion programs may discriminate against certain groups. Although we are not currently a party to any such litigation currently, unfavorable rulings against us in any such case brought against us in the future could significantly impact our operations and could have an adverse impact on our financial condition.

Previous wording

The COVID-19 pandemic, Russia-Ukraine conflict, conflict in the Middle East and other sources of volatility in the energy markets may materially and adversely affect our business, financial condition, operating results, cash flow, liquidity and prospects, including our efforts to reach a final investment decision with respect to the Rio Grande LNG Facility.

Current wording

The Russia-Ukraine conflict, conflict in the Middle East and other sources of volatility in the energy markets may materially and adversely affect our business, financial condition, operating results, cash flow, liquidity and prospects, including our efforts to reach a final investment decision with respect to the Rio Grande LNG Facility.

Previous wording

A sustained disruption in the capital markets from the COVID-19 pandemic or the Russia-Ukraine conflict and hostilities in the Middle East, specifically with respect to the energy industry, could negatively impact our ability to raise capital. In the past, we have financed our operations by the issuance of equity and equity-based securities. However, we cannot predict when macro-economic disruption stemming from COVID-19 or outbreaks of variants of the virus or geopolitical uncertainty may occur. This macro-economic disruption may disrupt our ability to raise additional capital to finance our operations in the future, which could materially and adversely affect our business, financial condition and prospects, and could ultimately cause our business to fail.

Current wording

A sustained disruption in the capital markets from the Russia-Ukraine conflict and hostilities in the Middle East, specifically with respect to the energy industry, could negatively impact our ability to raise capital. In the past, we have financed our operations by the issuance of equity and equity-based securities. However, we cannot predict when macro-economic disruption stemming from geopolitical uncertainty may occur. This macro-economic disruption may disrupt our ability to raise additional capital to finance our operations in the future, which could materially and adversely affect our business, financial condition and prospects, and could ultimately cause our business to fail.

Previous wording

The COVID-19 pandemic and Russia-Ukraine conflict may also have the effect of heightening many of the other risks described in this Annual Report on Form 10-K, such as risks related to the development of the CCS projects and the Rio Grande LNG Facility, including postponement in making a positive FID on the Rio Grande LNG Facility, doing business in foreign countries, obtaining governmental approvals, and exported LNG remaining a competitive source of energy for international markets, global demand for and price of natural gas, and fluctuation in the price of our common stock.

Current wording

The Russia-Ukraine conflict may also have the effect of heightening many of the other risks described in this Annual Report on Form 10-K, such as risks related to the development of the CCS projects and the Rio Grande LNG Facility, including postponement in making a positive FID on the Rio Grande LNG Facility, doing business in foreign countries, obtaining governmental approvals, and exported LNG remaining a competitive source of energy for international markets, global demand for and price of natural gas, and fluctuation in the price of our common stock.

Previous wording

The extent to which COVID-19 ultimately impacts our business, results of operations and financial condition depends on future developments, which are uncertain and cannot be predicted, including, but not limited to, the duration and spread of COVID-19, its severity, the actions to contain COVID-19 or treat its impact, and how quickly and to what extent normal economic and operating conditions can resume. Additionally, the ultimate outcome of Russia’s invasion of Ukraine, including resulting tensions among the United States, North Atlantic Treaty Organization and Russia, disruption to the production and supply of natural gas throughout Europe, cyberwarfare and economic instability, could impact our operations or disrupt our ability to access the capital markets. The duration of the impact of the COVID-19 pandemic, the Russia-Ukraine conflict and hostilities in the Middle East is uncertain, and we may continue to experience materially adverse impacts to our business as a result of their global economic impact, including any recession that has occurred or may occur in the future, and lasting effects on the price of natural gas.

Current wording

The ultimate outcome of Russia’s invasion of Ukraine, including resulting tensions among the United States, North Atlantic Treaty Organization and Russia, disruption to the production and supply of natural gas throughout Europe, cyberwarfare and economic instability, could impact our operations or disrupt our ability to access the capital markets. The duration of the impact of the Russia-Ukraine conflict and hostilities in the Middle East is uncertain, and we may continue to experience materially adverse impacts to our business as a result of their global economic impact, including any recession that has occurred or may occur in the future, and lasting effects on the price of natural gas.
Rearranged current paragraphs (1)

Current report — wording carried from elsewhere

We are required to obtain and maintain governmental approvals and authorizations to implement our proposed business strategy, which includes the design, construction and operation of the Rio Grande LNG Facility and the export of LNG from the U.S. to foreign countries. As described in more detail in “Management’s Discussion and Analysis of
Rearranged previous paragraphs (2)

Previous report — wording carried elsewhere

We will be dependent on third-party contractors for the successful completion of the Rio Grande LNG Facility and CCS projects, and these contractors may be unable to complete the Rio Grande LNG Facility or CCS projects or may build a non-conforming Rio Grande LNG Facility or CCS projects.

Previous report — wording carried elsewhere

The Common Stock Warrants have a fixed three-year term that commenced on the closings of the issuances of the associated Convertible Preferred Stock. The Common Stock Warrants may only be exercised by holders of the Common Stock Warrants at the expiration of such three-year term.