Item 1. Legal Proceedings

On August 6, 2024, the D.C. Circuit issued a decision vacating FERC's reauthorization of the Rio Grande LNG Facility on the grounds that FERC should have issued a supplemental EIS during its remand process. The order was issued as the outcome of an appeal by petitioners of the Remand Order issued by FERC on April 21, 2023. The Remand Order was issued by FERC, following the D.C. Circuit's remand of FERC's original November 22, 2019 order, to reaffirm FERC's original order authorizing the siting, construction and operation of the Rio Grande LNG Facility, and reiterated that the Rio Grande LNG Facility is not inconsistent with the public interest under the Natural Gas Act Section 3.

On October 21, 2024, the Company filed a petition for rehearing and rehearing en banc with the D.C. Circuit. The D.C. Circuit's decision will not be effective until the Court has issued its mandate, which is not expected to occur until the appeals process has been completed.

We expect to take all available legal and regulatory actions, including but not limited to, appellate actions and other strategies, to ensure that construction on Phase 1 will continue and that necessary regulatory approvals are maintained to enable the FID of Trains 4 and 5 at the Rio Grande LNG Facility.