What changed in Management’s Discussion and Analysis?

Read the current filing

Previous report: 10-Q

Period ended 2024-06-30; filed 2024-08-14.

0001628280-24-037219

Item 2. Management’s Discussion and Analysis of Financial Condition and Results of Operations

Current report: 10-Q

Period ended 2024-09-30; filed 2024-11-07.

0001628280-24-046336

Item 2. Management’s Discussion and Analysis of Financial Condition and Results of Operations

The baseline is this issuer’s latest earlier reporting period of the same form that was filed before the current report. A previous 10-Q is a different quarter, not a year-over-year comparison. Amendments are excluded.

Compared 145 previous paragraphs and 150 current paragraphs.

111 unchanged; 25 reworded; 11 added; 9 removed; 0 previous and 3 current paragraphs rearranged.

Tables are not compared: 3 previous and 3 current tables excluded. Dates, whitespace, punctuation and numbering changes are ignored; changes to financial figures remain significant.

A changed paragraph is not evidence that risk increased or decreased. An unchanged paragraph does not establish that risk stayed the same.

Added paragraphs (11)

Current report

We are focused on constructing and operating the Rio Grande LNG Facility safely, efficiently, on schedule, and on budget. We seek to deliver reliable, economically attractive, and sustainable energy solutions through the development and operation of liquefaction and CCS infrastructure.

Current report

As of September 2024, progress on Trains 1 through 3 is in line with the schedule under the EPC Contracts. Train 1 foundation pours continued during the third quarter with compressor foundations, and the first concrete pour was completed for Train 2. Pipe work continued to progress on Train 1. Deep soil mixing for Train 2 continued, and rebar work was completed for the Train 2 main pipe rack. Work to relocate equipment and begin deep soil mixing is underway for Train 3, and tank wall construction began on Tank 1.

Current report

Investing cash outflows for the nine months ended September 30, 2024, amounted to $1,879.6 million, compared to $1,010.4 million for the same period in 2023. The increase in 2024 was primarily driven by more extensive construction activity, as construction of Phase 1 of the Rio Grande LNG Facility did not begin until July 2023.

Current report

Financing cash inflows for the nine months ended September 30, 2024, totaled $1,937.6 million, compared to $1,446.1 million for the same period in 2023. The increase in 2024 was primarily driven by a $1,599.9 million increase in debt and equity commitment proceeds and a $438.3 million decrease in debt issuance costs paid compared to the prior year. This was partly offset by $1,282.0 million in debt repayments and the absence of common stock sales during the current period compared to the prior year.

Current report

•Derivative losses during the three months ended September 30, 2024 increased approximately $570.0 million compared to the same period in 2023 primarily due to a decrease in forward SOFR rates when compared to the prior period.

Current report

•Interest expense, net of capitalized interest during the three months ended September 30, 2024 decreased approximately $16.6 million compared to the same period in 2023 primarily due to an approximate $43.3 million increase in capitalized interest, partially offset by a $26.6 million increase in total interest costs.

Current report

•Due to the changes in derivatives losses and interest expense, net of capitalized interest described above, net income attributable to non-controlling interest during the three months ended September 30, 2024 decreased approximately $337.1 million as those activities are a component of Intermediate Holdings net income and loss.

Current report

•Derivative gains during the nine months ended September 30, 2024 decreased approximately $114.6 million compared to the same period in 2023 primarily due to a decrease in forward SOFR rates when compared to the prior period.

Current report

•Interest expense, net of capitalized interest during the nine months ended September 30, 2024 increased approximately $34.9 million compared to the same period in 2023 primarily due to an approximately $144.4 million increase in total interest costs partially offset by an increase of $109.1 million of capitalized interest.

Current report

•Loss on debt extinguishment of $47.6 million during the nine months ended September 30, 2024 due to $1,282.0 million in debt repayments compared to none in the prior year.

Current report

•Due to the changes in derivatives losses, interest expense, net of capitalized interest and loss on debt extinguishment described above, net income attributable to non-controlling interest during the nine months ended September 30, 2024 decreased approximately $143.8 million as those activities are a component of Intermediate Holdings net income and loss.
Removed paragraphs (9)

Previous report

We are focused on constructing and operating the Rio Grande LNG Facility safely, efficiently, reliably, and sustainably. We seek to provide a less carbon-intensive and more sustainable LNG through project design, responsibly sourced gas, proposed net-zero power, and our planned CCS project at the Rio Grande LNG Facility. We also seek to make additional measurable contributions toward a net-zero future by developing CCS projects to reduce greenhouse gas emissions at other industrial facilities.

Previous report

As of June 2024, progress on Trains 1 through 3 is in line with the schedule under the EPC Contracts.Train 1 deep soil mixing has been completed and foundation pours are underway, including refrigeration compressor foundations. Additionally, steel erection for Train 1 is in process, and first pipework has been placed in the Train 1 cryogenic rack. Train 2 deep soil mixing is in process, and delivery of key materials such as large bore above-ground pipe and structural steel has continued. LNG tank progress has been strong, with excavation, pile leveling, and rebar installation for Tank 1 underway and Tank 2 piling completed. The permanent water supply for the site has been full constructed and is operational.

Previous report

Investing cash outflows during the six months ended June 30, 2024 and 2023 were $1,374.3 million and $56.5 million, respectively. Investing cash outflows primarily consist of cash used in the construction of Phase 1 of the Rio Grande LNG Facility. The increase in investing cash outflows during the six months ended June 30, 2024 compared to the same period in 2023 was primarily due to a positive FID on Phase 1 of the Rio Grande LNG Facility in July 2023 which has carried into 2024.

Previous report

Financing cash inflows during the six months ended June 30, 2024 and 2023 were $1,305.7 million and $74.9 million, respectively. Financing cash inflows during the 2024 period are primarily comprised of $2,300.6 million of proceeds from borrowings under Rio Grande's credit facilities and its issuance of senior secured notes and proceeds from the receipt of equity commitments in Intermediate Holdings of $333.3 million, partially offset by debt issuance costs of $36.6 million and repayment of $1,282.0 million of debt using proceeds of the senior secured notes offering during the 2024 period. Financing cash inflows during the 2023 period were primarily comprised of the sale of Company common stock.

Previous report

Derivative gain during the three months ended June 30, 2024 of $109.1 million is primarily due to an increase in forward SOFR rates from March 31, 2024 to June 30, 2024 and cash received in derivative settlements.

Previous report

Interest expense, net of capitalized interest during the three months ended June 30, 2024 of $26.0 million represents total interest cost on debt of $63.8 million, net of capitalized interest of $37.8 million.

Previous report

Net income attributable to non-controlling interest during the three and six months ended June 30, 2024 of $34.9 million and $193.3 million, respectively, is due to the sale of equity in Intermediate Holdings in July 2023 and the non-controlling interests share of Intermediate Holdings net income.

Previous report

Derivative gain during the six months ended June 30, 2024 of $367.9 million is due to the reversal of derivative liabilities recognized at December 31, 2023, an increase in forward SOFR rates from December 31, 2023 to June 30, 2024 and cash received in derivative settlements.

Previous report

Interest expense, net of capitalized interest during the six months ended June 30, 2024 of $51.5 million represents total interest cost on debt of $117.4 million, net of capitalized interest of $65.9 million.
Reworded paragraphs (25)

Previous wording

•our reliance on third-party contractors to successfully complete the Rio Grande LNG Facility, the pipeline to supply gas to the Rio Grande LNG Facility and any CCS projects we develop;

Current wording

•our reliance on third-party contractors to successfully complete the Rio Grande LNG Facility and any CCS projects we develop;

Previous wording

•the ability to obtain or maintain governmental approvals to construct or operate the Rio Grande LNG Facility and CCS projects, including in relation to the recent decision by the D.C. Circuit Court of Appeals;

Current wording

•the ability to obtain or maintain governmental approvals to construct or operate the Rio Grande LNG Facility and CCS projects, including in relation to the August 2024 decision by the D.C. Circuit Court of Appeals;

Previous wording

NextDecade Corporation, a Delaware corporation, is a Houston-based energy company primarily engaged in construction and development activities related to the liquefaction of natural gas and sale of LNG and the capture and storage of CO 2 emissions. We are constructing a natural gas liquefaction and export facility located in the Rio Grande Valley in Brownsville, Texas (the “Rio Grande LNG Facility”), which currently has three liquefaction trains and related infrastructure under construction. The Rio Grande LNG Facility has received Federal Energy Regulatory Commission (“FERC”) approval and Department of Energy ("DOE") FTA and non-FTA authorizations for the construction of five liquefaction trains and supporting infrastructure with LNG exports totaling 27 million tonnes per annum (“MTPA”). Please see "Significant Recent Developments - Regulatory" for more information regarding our FERC permit. Liquefaction trains 1 through 3 and related infrastructure are currently under construction and liquefaction trains 4 and 5 at the Rio Grande LNG Facility are currently in development. We are also developing a planned carbon capture and storage (“CCS”) project at the Rio Grande LNG Facility and other potential CCS projects that would be located at third-party industrial facilities.

Current wording

NextDecade Corporation, a Delaware corporation, is a Houston-based energy company primarily engaged in construction and development activities related to the liquefaction of natural gas and sale of LNG and the capture and storage of CO 2 emissions. We are constructing a natural gas liquefaction and export facility located in the Rio Grande Valley in Brownsville, Texas (the “Rio Grande LNG Facility”), which currently has three liquefaction trains and related infrastructure under construction. The Rio Grande LNG Facility has received Federal Energy Regulatory Commission (“FERC”) approval and Department of Energy (“DOE”) FTA and non-FTA authorizations for the construction of five liquefaction trains and supporting infrastructure with LNG exports totaling 27 million tonnes per annum (“MTPA”). Please see "Significant Recent Developments — Regulatory" for more information regarding our FERC permit. Liquefaction trains 1 through 3 and related infrastructure are currently under construction and liquefaction trains 4 and 5 at the Rio Grande LNG Facility are currently in development. We are also developing and seeking to commercialize potential carbon capture and storage (“CCS”) projects.

Previous wording

Rio Grande has entered into long-term LNG Sale and Purchase Agreements (“SPAs”) for over 90% of the expected Phase 1 nameplate LNG production capacity, pursuant to which Rio Grande customers are generally required to pay a fixed fee with respect to the contracted volumes, irrespective of whether they cancel or suspend deliveries of LNG cargoes. These SPAs create a stable foundation of predictable, long-term cash flows to Rio Grande. We believe our SPAs are attractive to our customers for several reasons, including long-term reliable supply, volumes to support growing demand for LNG and to replace customers’ contracts with legacy LNG suppliers, diversification of supply portfolios in terms of geography, price indexation, delivery points, and/or tenor, flexibility of volumes with no destination restrictions, and compatibility of some of our customers’ ESG goals with our expected lower carbon intensity LNG and planned CCS project at the Rio Grande LNG Facility.

Current wording

Rio Grande has entered into long-term LNG Sale and Purchase Agreements (“SPAs”) for over 90% of the expected Phase 1 nameplate LNG production capacity, pursuant to which Rio Grande customers are generally required to pay a fixed fee with respect to the contracted volumes, irrespective of whether they cancel or suspend deliveries of LNG cargoes. These SPAs create a stable foundation of predictable, long-term cash flows to Rio Grande. We believe our SPAs are attractive to our customers for several reasons, including long-term reliable supply, volumes to support growing demand for LNG and to replace customers’ contracts with legacy LNG suppliers, diversification of supply portfolios in terms of geography, price indexation, delivery points, and/or tenor, flexibility of volumes with no destination restrictions, and the ability of our LNG to help our customers achieve their ESG goals.

Previous wording

Rio Grande will provide a number of services in support of producing and selling LNG from the Rio Grande LNG Facility pursuant to its SPAs, including natural gas feedstock procurement and transportation, liquefaction, and delivery of LNG to customers either at the loading dock of the Rio Grande LNG Facility or at the customer’s global delivery points via chartered vessels.

Current wording

We will provide a number of services in support of producing and selling LNG from the Rio Grande LNG Facility pursuant to its SPAs, including natural gas feedstock procurement and transportation, liquefaction, and delivery of LNG to customers either at the loading dock of the Rio Grande LNG Facility or at the customer’s global delivery points via chartered vessels.

Previous wording

•The overall project completion percentage for Trains 1 and 2 and the common facilities of the Rio Grande LNG Facility was 24.1%, which is in line with the schedule under the EPC contract. Within this project completion percentage, engineering was 66.4% complete, procurement was 45.4% complete, and construction was 3.5% complete.

Current wording

•The overall project completion percentage for Trains 1 and 2 and the common facilities of the Rio Grande LNG Facility was 30.5%, which is in line with the schedule under the EPC contract. Within this project completion percentage, engineering was 76.1% complete, procurement was 57.6% complete, and construction was 5.5% complete.

Previous wording

•The overall project completion percentage for Train 3 of the Rio Grande LNG Facility was 7.8%, based on preliminary schedules, which is also in line with the schedule under the EPC contract. Within this project completion percentage, engineering was 8.4% complete, procurement was 18.4% complete, and construction was 0.1% complete.

Current wording

•The overall project completion percentage for Train 3 of the Rio Grande LNG Facility was 9.8%, based on preliminary schedules, which is also in line with the schedule under the EPC contract. Within this project completion percentage, engineering was 17.0% complete, procurement was 21.9% complete, and construction was 0.1% complete.

Previous wording

•The Company is reviewing the Court's decision and assessing all of its options, together with the key project constituencies, including its equity partners and lenders. The Company expects to take all available legal and regulatory actions, including but not limited to, appellate actions and other strategies, to ensure that construction on Phase 1 will continue and that necessary regulatory approvals will be maintained to enable the construction of Trains 4 and 5 at the Rio Grande LNG Facility.

Current wording

•The Company expects to take all available legal and regulatory actions, including but not limited to, appellate actions and other strategies, to ensure that construction on Phase 1 will continue and that necessary regulatory approvals will be maintained to enable the FID of Trains 4 and 5 at the Rio Grande LNG Facility.

Previous wording

Bechtel has continued to make meaningful progress on procurement for Phase 1, with a focus on completing purchase orders for critical and high-value items early in the construction process. As of June 2024, Bechtel has issued approximately 92% of the total purchase orders for Trains 1 and 2 and approximately 88% of the total purchase orders for Train 3.

Current wording

Bechtel has continued to make meaningful progress on procurement for Phase 1, with a focus on completing purchase orders for critical and high-value items early in the construction process. As of September 2024, Bechtel has issued approximately 96% of the total purchase orders for Trains 1 and 2 and approximately 98% of the total purchase orders for Train 3.

Previous wording

For Phase 1 of the Rio Grande LNG Facility, Rio Grande has entered into a firm transportation agreement for capacity on the Rio Bravo Pipeline to transport natural gas feedstock to the Rio Grande LNG Facility. The Rio Bravo Pipeline will be developed by Whistler LLC, a joint venture between WhiteWater, I Squared, MPLX LP, and Enbridge, and will be constructed and operated by WhiteWater. The Rio Bravo Pipeline will provide Rio Grande access to purchase natural gas supplies in the Agua Dulce area and will connect to six regional intra and interstate pipelines, giving Rio Grande access to prolific gas production from the Permian Basin and Eagle Ford Shale and providing significant flexibility to obtain competitively priced natural gas feedstock.

Current wording

For Phase 1 of the Rio Grande LNG Facility, we have entered into a firm transportation agreement for capacity on the Rio Bravo Pipeline to transport natural gas feedstock to the Rio Grande LNG Facility. The Rio Bravo Pipeline will be developed by Whistler LLC, a joint venture between WhiteWater, I Squared, MPLX LP, and Enbridge, and will be constructed and operated by WhiteWater. The Rio Bravo Pipeline will provide access to purchase natural gas supplies in the Agua Dulce area and will connect to multiple regional intra- and interstate pipelines, giving us access to prolific gas production from the Permian Basin and Eagle Ford Shale and providing significant flexibility to obtain competitively priced natural gas feedstock.

Previous wording

The Rio Bravo Pipeline is under development and is expected to be constructed and completed prior to the start of commissioning of Train 1 at the Rio Grande LNG Facility. Rio Grande has also entered into an agreement for capacity on an interruptible basis with Enbridge’s Valley Crossing Pipeline to provide redundant natural gas transportation capacity to the Rio Grande LNG Facility for commissioning and operations.

Current wording

The Rio Bravo Pipeline is under development and is expected to be constructed and completed prior to the start of commissioning of Train 1 at the Rio Grande LNG Facility. We have also entered into an agreement for capacity on an interruptible basis with Enbridge’s Valley Crossing Pipeline to provide redundant natural gas transportation capacity to the Rio Grande LNG Facility for commissioning and operations. We have entered into and may enter into additional transportation capacity agreements over time as part of our overall gas sourcing strategy to facilitate efficient and economic delivery of natural gas to the Rio Grande LNG Facility.

Previous wording

The Company has finalized an EPC contract with Bechtel for Train 4 and related infrastructure.

Current wording

The Company has finalized an EPC contract with Bechtel for Train 4 and related infrastructure. Price validity under the EPC contract for Train 4 and related infrastructure extends through December 31, 2024.

Previous wording

On April 21, 2023, the FERC issued the order on remand (the “Remand Order”) reaffirming the order issued by FERC on November 22, 2019, authorizing the siting, construction and operation of the Rio Grande LNG Facility (the “Order”). The Remand Order reaffirmed that the Rio Grande LNG Facility is not inconsistent with the public interest under the Natural Gas Act Section 3.

Current wording

On April 21, 2023, FERC issued the order on remand (the “Remand Order”) reaffirming the order issued by FERC on November 22, 2019, authorizing the siting, construction and operation of the Rio Grande LNG Facility (the “Order”). The Remand Order reaffirmed that the Rio Grande LNG Facility is not inconsistent with the public interest under the Natural Gas Act Section 3.

Previous wording

The Remand Order was issued as a result of the decision of the U.S. Court of Appeals for the District of Columbia (the “D.C. Circuit”) dated August 3, 2021, which denied all petitions filed by parties who filed requests for re-hearing of the Order, except for two technical issues dealing with environmental justice and GHG emissions, which were remanded to the FERC for further consideration.

Current wording

The Remand Order was issued as a result of the decision of the U.S. Court of Appeals for the District of Columbia (the “D.C. Circuit”) dated August 3, 2021, which denied all petitions filed by parties who filed requests for re-hearing of the Order, except for two technical issues dealing with environmental justice and GHG emissions, which were remanded to FERC for further consideration.

Previous wording

Parties sought rehearing of the Remand Order, which FERC denied by operation of law on June 22, 2023, and subsequently issued a substantive order on the merits upholding the conclusions in the Remand Order, and its reaffirmation of the FERC Order. On August 17, 2023, parties petitioned the D.C. Circuit for review of the Remand Order. Oral arguments were held on May 17, 2024. On August 6, 2024, the D.C. Circuit issued an order vacating FERC's remand authorization of the Rio Grande LNG Facility on the grounds that the FERC should have issued a supplemental EIS during its remand process. The D.C. Circuit's decision will not be effective until the appeals process has been completed.

Current wording

Parties sought rehearing of the Remand Order, which FERC denied by operation of law on June 22, 2023, and subsequently issued a substantive order on the merits upholding the conclusions in the Remand Order, and its reaffirmation of the FERC Order. On August 17, 2023, parties petitioned the D.C. Circuit for review of the Remand Order.

Previous wording

•In August 2024, the U.S. Court of Appeals for the D.C. Circuit (the “Court”) issued an order vacating the FERC remand authorization of the Rio Grande LNG Facility on the grounds that the FERC should have issued a supplemental Environmental Impact Statement (“EIS”) during its remand process. The Court's decision will not be effective until the Court has issued its mandate, which is not expected to occur until after the appeals process has been completed.

Current wording

Oral arguments in the review of the Remand Order were held on May 17, 2024. On August 6, 2024, the D.C. Circuit issued a decision vacating FERC's reauthorization of the Rio Grande LNG Facility on the grounds that FERC should have issued a supplemental EIS during its remand process. On October 21, 2024, the Company filed a petition for rehearing and rehearing en banc with the D.C. Circuit. The D.C. Circuit's decision will not be effective until the Court has issued its mandate, which is not expected to occur until the appeals process has been completed.

Previous wording

We are reviewing the D.C. Circuit's decision and evaluating all of our options. We expect to take all available legal and regulatory actions, including but not limited to, appellate actions and other strategies, to ensure that construction on Phase 1 will continue and that necessary regulatory approvals are maintained to enable the construction of Trains 4 and 5 at the Rio Grande LNG Facility.

Current wording

We expect to take all available legal and regulatory actions, including but not limited to, appellate actions and other strategies, to ensure that construction on Phase 1 will continue and that necessary regulatory approvals are maintained to enable the FID of Trains 4 and 5 at the Rio Grande LNG Facility.

Previous wording

We are required to maintain corporate and general and administrative functions to serve our business activities described above. We are also in various stages of developing other projects, such as Train 4 and Train 5 at the Rio Grande LNG Facility, additional liquefaction expansions at the Rio Grande LNG Facility, a CCS project at the Rio Grande LNG Facilities, and potential CCS projects at third party industrial facilities.

Current wording

We are required to maintain corporate and general and administrative functions to serve our business activities described above. We are also in various stages of developing other projects, such as Train 4 and Train 5 at the Rio Grande LNG Facility, additional liquefaction expansions at the Rio Grande LNG Facility and potential CCS projects.

Previous wording

Prior to the FID on Phase 1 of the Rio Grande LNG Facility, our primary cash needs historically were funding development activities in support of the Rio Grande LNG Facility and our CCS projects, which included payments of initial direct costs of the Rio Grande site lease and expenses in support of engineering and design activities, regulatory approvals and compliance, commercial and marketing activities and corporate overhead. We spent approximately $97.7 million on such development activities year-to-date through FID on July 12, 2023, which we funded through our cash on hand and proceeds from the issuances of equity and equity-based securities. Following the FID on Phase 1 of the Rio Grande LNG Facility, costs associated with the Phase 1 EPC agreements, Rio Grande site lease, and other Phase 1 related costs are being funded by debt and equity proceeds received by Rio Grande.

Current wording

Prior to the FID on Phase 1 of the Rio Grande LNG Facility, our primary cash needs historically were funding development activities in support of the Rio Grande LNG Facility and our CCS projects, which included payments of initial direct costs of the Rio Grande site lease and expenses in support of engineering and design activities, regulatory approvals and compliance, commercial and marketing activities and corporate overhead. We spent approximately $97.7 million on such development activities year-to-date through FID on July 12, 2023, which we funded through our cash on hand and proceeds from the issuances of equity and equity-based securities. Following the FID on Phase 1 of the Rio

Previous wording

Our consolidated financial statements as of and for the three and six months ended June 30, 2024 have been prepared on the basis that we will continue as a going concern, which contemplates the realization of assets and satisfaction of liabilities in the normal course of business. Based on our balance of cash and cash equivalents of $38.1 million and available commitments under a revolving loan facility of $26.2 million at June 30, 2024, there is substantial doubt about our ability to continue as a going concern within one year after the date that our consolidated financial statements were issued. Our ability to continue as a going concern will depend on managing certain operating and overhead costs and our ability to raise capital through equity, equity-based or debt financings. The consolidated financial statements do not include any adjustments that might result from the outcome of this uncertainty, which could have a material adverse effect on our financial condition.

Current wording

Our consolidated financial statements as of and for the three and nine months ended September 30, 2024 have been prepared on the basis that we will continue as a going concern, which contemplates the realization of assets and satisfaction of liabilities in the normal course of business. Based on our balance of cash and cash equivalents of $38.2 million at September 30, 2024, there is substantial doubt about our ability to continue as a going concern within one year after the date that our consolidated financial statements were issued. Our ability to continue as a going concern will depend on managing certain operating and overhead costs and our ability to raise capital through equity, equity-based or debt financings. The consolidated financial statements do not include any adjustments that might result from the outcome of this uncertainty, which could have a material adverse effect on our financial condition.

Previous wording

Operating cash outflows during the six months ended June 30, 2024 and 2023 were $22.8 million and $41.2 million, respectively. The decrease in operating cash outflows during the six months ended June 30, 2024 compared to the six months ended June 30, 2023 was primarily due to cash received in the settlement of derivatives partially offset by an increase in employee costs and professional fees paid to consultants as we construct Phase 1 of the Rio Grande LNG Facility and continue to develop subsequent phases.

Current wording

Operating cash outflows during the nine months ended September 30, 2024, amounted to $86.7 million, compared to $52.6 million for the same period in 2023. The increase in 2024 was primarily due to an increase in employee costs and professional fees paid to consultants as we construct Phase 1 of the Rio Grande LNG Facility and continue to develop subsequent phases. These increases were partially offset by cash received in the settlement of derivatives.

Previous wording

Net loss attributable to common stockholders was $32.6 million, or $(0.13) per common share (basic and diluted) for the three months ended June 30, 2024 compared to a net loss of $127.0 million, or $(0.84) per common share (basic and diluted), for the three months ended June 30, 2023. The $94.5 million decrease in net loss was primarily a result of derivative gain, partially offset by increases in general and administrative expense, net income attributable to non-controlling interest, loss on debt extinguishment and interest expense, net of capitalized interest.

Current wording

Net loss attributable to common stockholders was $123.2 million, or $(0.47) per common share (basic and diluted) for the three months ended September 30, 2024 compared to a net income of $107.6 million, or $0.48 per common share (basic and diluted), for the three months ended September 30, 2023. The $230.8 million decrease was primarily a result of the following:

Previous wording

General and administrative expense during the three months ended June 30, 2024 increased approximately $7.1 million compared to the same period in 2023 primarily due to an increase in professional fees and employee costs, partially offset by a decrease in share-based compensation expense.

Current wording

•General and administrative expenses during the three months ended September 30, 2024 increased approximately $11.5 million compared to the same period in 2023 primarily due to an increase in professional fees and employee costs, partially offset by a decrease in share-based compensation expense.

Previous wording

Net loss attributable to common stockholders was $4.2 million, or $(0.02) per common share (basic and diluted) for the six months ended June 30, 2024 compared to a net loss of $161.1 million, or $(1.08) per common share (basic and diluted), for the six months ended June 30, 2023. The $156.9 million decrease in net loss was primarily a result of derivative gain, partially offset by increases in general and administrative expense, net income attributable to non-controlling interest, loss on debt extinguishment and interest expense, net of capitalized interest.

Current wording

Net loss attributable to common stockholders was $127.4 million, or $(0.49) per common share (basic and diluted) for the nine months ended September 30, 2024 compared to a net loss of $53.5 million, or $(0.31) per common share (basic and diluted), for the nine months ended September 30, 2023. The $73.9 million increase was primarily a result of the following:

Previous wording

General and administrative expense during the six months ended June 30, 2024 increased approximately $13.3 million compared to the same period in 2023 primarily due to an increase in professional fees and employee costs, partially offset by a decrease in share-based compensation expense.

Current wording

•General and administrative expenses during the nine months ended September 30, 2024 increased approximately $24.8 million compared to the same period in 2023 primarily due to an increase in professional fees and employee costs, partially offset by a decrease in share-based compensation expense.
Rearranged current paragraphs (3)

Current report — wording carried from elsewhere

•In August 2024, the U.S. Court of Appeals for the D.C. Circuit (the “Court”) issued a decision vacating the FERC reauthorization of the Rio Grande LNG Facility on the grounds that FERC should have issued a supplemental Environmental Impact Statement (“EIS”) during its reauthorization process. On October 21, 2024, the Company filed a petition for rehearing and rehearing en banc with the Court.

Current report — wording carried from elsewhere

•The Court's decision will not be effective until the Court has issued its mandate, which is not expected to occur until after the appeals process has been completed.

Current report — wording carried from elsewhere

Grande LNG Facility, costs associated with the Phase 1 EPC agreements, Rio Grande site lease, and other Phase 1 related costs are being funded by debt and equity proceeds received by Rio Grande.