NextDecade Corp

For the period ended Mar 31, 2026. Filed May 1, 2026.

View on SEC.gov

About this filing

A company's report for each of its first three quarters. The financial statements are not audited. It shows how the business has moved since the last annual report, and what management says changed.

Mar 31, 2026 · Filed May 1, 2026

NEXT$5.80-0.9%Stored close · as of Nov 6, 2026

What changed in Management’s Discussion and Analysis?

Read the current filing

Previous report: 10-Q

Period ended 2025-09-30; filed 2025-10-30.

0001612720-25-000030

Item 2. Management’s Discussion and Analysis of Financial Condition and Results of Operations

Current report: 10-Q

Period ended 2026-03-31; filed 2026-05-01.

0001612720-26-000026

Item 2. Management’s Discussion and Analysis of Financial Condition and Results of Operations

The baseline is this issuer’s latest earlier reporting period of the same form that was filed before the current report. A previous 10-Q is a different quarter, not a year-over-year comparison. Amendments are excluded.

Compared 154 previous paragraphs and 118 current paragraphs.

63 unchanged; 42 reworded; 13 added; 42 removed; 7 previous and 0 current paragraphs rearranged.

Tables are not compared: 2 previous and 2 current tables excluded. Dates, whitespace, punctuation and numbering changes are ignored; changes to financial figures remain significant.

A changed paragraph is not evidence that risk increased or decreased. An unchanged paragraph does not establish that risk stayed the same.

Added paragraphs (13)

Current report

•The overall project completion percentage for Train 4 at the Rio Grande LNG Facility was 10.6%. Within this project completion percentage, engineering was 43.6% complete, procurement was 18.8% complete, and construction was 0.5% complete.

Current report

•The overall project completion percentage for Train 5 at the Rio Grande LNG Facility was 6.8%. Within this project completion percentage, engineering was 11.7% complete, procurement was 15.3% complete, and construction was 0.0% complete.

Current report

•Early electrical commissioning of Train 1 continues, and we expect first gas into the Rio Grande LNG Facility in the second half of 2026 and first LNG production from Train 1 in the first half of 2027.

Current report

•In early 2026, we began the marketing of early cargoes that we expect to produce in 2027 and 2028 prior to the commencement of our long-term LNG Sale and Purchase Agreements (“SPAs”). In February 2026, we entered into LNG sales agreements for the sale of over 175 TBtu of LNG on a free-on-board (“FOB”) basis, with fixed liquefaction fees that are expected to achieve a cargo margin, calculated as the FOB LNG sales price less our expected costs of natural gas feedstock and fuel, of over $3.00 per MMBtu. This volume represents 33% of our expected portfolio volumes from 2027 through early 2029.

Current report

Progress on Phase 1 as of March 2026 is ahead of the guaranteed completion schedule under the EPC contracts. Train 1 continues to progress across all areas, with focus on piping, equipment installation, cable pulling, testing, and system completions, and the main cryogenic heat exchanger (“MCHE”) has been successfully installed in Train 1. Construction activities for Trains 2 and 3 are advancing, including civil works, piping, structural steel, and equipment installation, with placement of the Train 2 compressor packages underway. Welding of the inner tanks is progressing for Tanks 1 and 2, and concrete roof placement has been completed for both tanks.

Current report

Progress on Train 4 as of March 2026 is in line with the EPC contract. Early civil works are progressing on Train 4, and production piling has commenced for Tank 3. Progress on Train 5 as of March 2026 is in line with the EPC contract, and site preparation activities are underway for Train 5.

Current report

Across the site as of March 2026, construction of all permanent buildings is progressing, installation of perimeter security fencing is underway, construction activities at the gas inlet area are ongoing, dredging activities for the berths and turning basin are substantially complete, and channel deepening is nearing completion.

Current report

Cash provided by financing activities for the three months ended March 31, 2026 increased by approximately $203.9 million compared to the same period in 2025. The increase was primarily due to an increase of approximately $172.0 million in proceeds from debt issuance and an increase of approximately $33.7 million in receipts of equity commitments related primarily to construction at the Rio Grande LNG Facility, including impacts of Trains 4 and 5 which achieved positive FID in the second half of 2025.

Current report

•Derivative loss, net decreased by approximately $106.6 million primarily driven by higher forward SOFR rates, which decreased the fair-value loss on the Company’s interest rate swap portfolio, partially offset by losses on the Series A Exchange Option and Warrants with no comparable activity during the same period in 2025.
Removed paragraphs (42)

Previous report

Unless the context requires otherwise, references to “NextDecade,” “the Company,” “we,” “us,” and “our” refer to NextDecade Corporation and its consolidated subsidiaries, references to “Phase 1 LLC” refer to Rio Grande LNG, LLC, references to "Train 4 LLC" refer to Rio Grande LNG Train 4, LLC, and references to "Train 5 LLC" refer to Rio Grande LNG Train 5, LLC.

Previous report

•Progress for Train 4 included advancement on engineering drawings, issuance of purchase orders for a range of equipment and materials, and commencement of area clearing.

Previous report

◦Train 6, which has an expected LNG production capacity of approximately 6 MTPA, is being developed inside the existing levee at the site and adjacent to Trains 1 through 5. A pre-filing application with the Federal Energy Regulatory Commission ("FERC") for Train 6 is expected in 2025, and a full FERC application is expected in 2026.

Previous report

•On September 9, 2025, we announced a positive final investment decision ("FID") on Train 4 and related infrastructure at the Rio Grande LNG Facility and issued full notice to proceed ("NTP") to Bechtel Energy Inc. ("Bechtel") under the EPC contract for Train 4. Total project costs for Train 4 and related infrastructure are expected to total approximately $6.7 billion. Train 4 has an expected LNG production capacity of approximately 6 million MTPA, and guaranteed substantial completion of Train 4 is in the second half of 2030.

Previous report

•On October 16, 2025, we announced a positive FID on Train 5 and related infrastructure at the Rio Grande LNG Facility and issued full NTP to Bechtel under the EPC contract for Train 5. Total project costs for Train 5 and related infrastructure are expected to total approximately $6.7 billion. Train 5 has an expected LNG production capacity of approximately 6 million MTPA, and guaranteed substantial completion of Train 5 is in the first half of 2031.

Previous report

•In April 2025, we announced a 20-year LNG Sale and Purchase Agreement (“SPA”) with a subsidiary of Saudi Aramco (“Aramco”), pursuant to which the Aramco subsidiary will purchase 1.2 MTPA of LNG from Train 4 at the Rio Grande LNG Facility for 20 years, on a free on board (“FOB”) basis at a price indexed to Henry Hub.

Previous report

•In April 2025, we announced that TotalEnergies exercised its LNG purchase option with respect to Train 4 and the Company entered into a 20-year LNG SPA with TotalEnergies, pursuant to which TotalEnergies will purchase 1.5 MTPA of LNG from Train 4 at the Rio Grande LNG Facility for 20 years, on an FOB basis at a price indexed to Henry Hub.

Previous report

•In May 2025, we announced a 20-year LNG SPA with JERA, pursuant to which JERA will purchase 2.0 MTPA of LNG from Train 5 at the Rio Grande LNG Facility for 20 years, on an FOB basis at a price indexed to Henry Hub.

Previous report

•In June 2025, we finalized a pricing refresh of the Company's lump-sum, turnkey EPC contract with Bechtel for the construction of Train 4 and related infrastructure and executed a lump-sum, turnkey EPC contract with Bechtel for the construction of Train 5 and related infrastructure.

Previous report

•In September 2025, we announced a 20-year LNG SPA with EQT Corporation ("EQT"), pursuant to which EQT will purchase 1.5 MTPA of LNG from Train 5 at the Rio Grande LNG Facility for 20 years, on an FOB basis at a price indexed to Henry Hub.

Previous report

•In September 2025, we announced a 20-year LNG SPA with ConocoPhillips, pursuant to which ConocoPhillips will purchase 1.0 MTPA of LNG from Train 5 at the Rio Grande LNG Facility for 20 years, on an FOB basis at a price indexed to Henry Hub.

Previous report

•In May 2025, our wholly-owned subsidiary Rio Grande LNG Super Holdings, LLC, entered into an amendment to the credit agreement with the lender of its existing senior secured loan (the "Super Holdings Loan") to increase the loan amount by $50 million to a total of $225 million initial principal. Incremental proceeds from the Super Holdings Loan were disbursed at closing on May 14, 2025, and net proceeds can be used to fund working capital and general corporate purposes, including development expenses for expansion trains at the Rio Grande LNG Facility and specifically pre-FID expenses for Trains 4 and 5. Borrowings under the Super Holdings Loan bear interest at 12.0%, with interest payable quarterly. Interest may be paid in-kind until March 31, 2027 and up to 50% in-kind thereafter. The Super Holdings Loan matures December 31, 2030.

Previous report

•In conjunction with the closing of the May 2025 amendment to the Super Holdings Loan, we issued warrants that are exercisable for an aggregate of approximately 2.0 million shares of our common stock to the lender of the Super Holdings Loan. The warrants are exercisable for five years after the amendment date at $9.30 per share, which represented a 30% premium to the volume weighted average price for the 30 trading-day period immediately preceding the amendment date.

Previous report

•On September 9, 2025, in conjunction with the positive FID on Train 4 at the Rio Grande LNG Facility, we and certain of our subsidiaries closed an approximately $6.7 billion project financing for Train 4, which included the closing of:

Previous report

◦A joint venture agreement which included approximately $1.69 billion of financial commitments from Global Infrastructure Partners, a part of BlackRock ("GIP"), GIC, Mubadala Investment Company, and TotalEnergies;

Previous report

◦A commitment by the Company to invest approximately $1.13 billion in Train 4; and

Previous report

◦A senior secured, non-recourse bank credit facility of $3.85 billion with a seven year maturity.

Previous report

•On September 9, 2025, to fully fund the Company's approximately $1.13 billion equity commitments for Train 4, certain of our wholly-owned subsidiaries entered into a delayed draw, senior secured term loan bank facility of $734 million with a five year maturity (the "FinCo Loan") and term loans of $600 million with a maturity date of the earlier of eight years or the 85th day prior to the maturity date of the FinCo Loan (the "SuperFinCo Loan").

Previous report

•On October 16, 2025, in conjunction with the positive FID on Train 5 at the Rio Grande LNG Facility, we and certain of our subsidiaries closed an approximately $6.7 billion project financing for Train 5, which included the closing of:

Previous report

◦A joint venture agreement which included approximately $1.29 billion of financial commitments from GIP, GIC, and Mubadala Investment Company;

Previous report

◦A commitment by the Company to invest approximately $1.29 billion in Train 5;

Previous report

◦A senior secured, non-recourse bank credit facility of $3.59 billion with a seven year maturity; and

Previous report

◦An offering of $500 million senior secured, non-recourse private placement notes, which will bear interest at 6.56%, will be funded in multiple tranches from December 2025 through October 2026, and will amortize over a period of 20 years beginning in September 2031.

Previous report

•On October 16, 2025, to fully fund the Company's approximately $1.29 billion equity commitments for Train 5, we contributed $233 million cash to Train 5 LLC, and certain of our wholly-owned subsidiaries increased the size of the FinCo Loan by $729 million, to a total of approximately $1.46 billion, and increased the size of the SuperFinCo Loan by $600 million, to a total of $1.2 billion.

Previous report

•In October 2025, Rio Grande LNG Super Holdings, LLC, entered into a term sheet with the lender of the Super Holdings Loan to refinance $50 million of the existing loan amount and provide $50 million of incremental capital in the form of an exchangeable loan with total initial principal of $100 million (the "Exchangeable Loan"). Upon consummation of the transaction, the Exchangeable Loan would bear interest at 8%, payable in cash or in-kind at the Company's election, and would mature in October 2030. The initial principal of the Exchangeable Loan, and any amounts of interest paid in-kind, would be exchangeable into shares of Company common stock at $9.50 per share. Additionally, the interest rate on the remaining balance of the Super Holdings Loan would be amended to 13.5%.

Previous report

•In March 2025, the U.S. Court of Appeals for the D.C. Circuit (the “D.C. Circuit Court”) issued a revision to its August 2024 decision regarding the Company's FERC order, resulting in a remand without vacatur of the FERC order for the first five liquefaction trains at the Rio Grande LNG Facility. Pursuant to the remand, FERC was to consider the issue of a supplemental Environmental Impact Statement (“SEIS”) in view of several executive orders issued since January 20, 2025.

Previous report

•In July 2025, the FERC issued a final SEIS for the first five liquefaction trains at the Rio Grande LNG Facility, following a draft SEIS in March 2025.

Previous report

As of September 2025, progress on Phase 1 is ahead of schedule under the EPC contracts. During the third quarter of 2025, the construction team continued piping fabrication, rebar installation, equipment setting and concrete placement, and structural steel erection in the areas of Trains 1, 2, and 3. Roof raises were completed for the first two LNG storage tanks. Across the site, Bechtel also continued installing concrete foundations, instrument air receivers, floodgates, permanent fencing, temporary facilities, and other siteworks. In September 2025, the first compressor string and turbine for Train 1 arrived onsite.

Previous report

During September 2025, progress on Train 4 included advancement on engineering drawings, issuance of purchase orders for a range of equipment and materials, and commencement of area clearing.

Previous report

In March 2025, the D.C. Circuit Court issued a revision to its August 2024 decision regarding our FERC order, resulting in a remand without vacatur of the FERC order for the first five liquefaction trains at the Rio Grande LNG Facility. Pursuant to the remand, FERC was to consider the issue of a supplemental Environmental Impact Statement (“SEIS”) in view of several executive orders issued since January 20, 2025.

Previous report

Cash provided by financing activities for the nine months ended September 30, 2025 increased by approximately $1.4 billion compared to the same period in 2024. This was driven by an increase of approximately $217.3 million uptick in equity commitment receipts and the absence of approximately $1.3 billion of debt repayments in the current period.

Previous report

•The change in derivative (loss) gain of approximately $255.6 million was primarily driven by lower forward SOFR rates, which reduced the mark-to-market loss on the Company’s interest rate swap portfolio.

Previous report

•General and administrative expenses increased by approximately $53.1 million, principally reflecting higher share-based compensation expense recognized in connection with FID on Train 4 and incremental headcount additions to support the commencement of operations at the Rio Grande LNG Facility.

Previous report

•The change in derivative (loss) gain of approximately $255.9 million for the nine months ended September 30, 2025, was primarily driven by lower forward SOFR rates, which increased the fair-value loss on the Company’s interest rate swap portfolio.

Showing the first 40 of 42 passages. Open the source sections for the rest.

Reworded paragraphs (42)

Previous wording

We have based these forward-looking statements on assumptions and analysis made by us in light of our current expectations, perceptions about historical trends, current conditions and projections about future events and trends that we believe may affect our financial condition, results of operations, strategy, short-term and long-term business operations and objectives and financial needs.

Current wording

We have based these forward-looking statements on assumptions and analysis made by us in light of our current expectations, perceptions of historical trends, current conditions and projections about future events and trends that we believe may affect our financial condition, results of operations, strategy, short-term and long-term business operations and objectives and financial needs.

Previous wording

•our progress in the development of our liquefied natural gas (“LNG”) liquefaction and export project and any carbon capture and storage projects (“CCS projects”) we may develop and the timing of that progress;

Current wording

•our progress in the development of our natural gas liquefaction and liquefied natural gas (“LNG”) export project and any carbon capture and storage projects (“CCS projects”) we may develop and the timing of that progress;

Previous wording

•the timing and cost of the development, construction and operation of the first five liquefaction trains and related common facilities of the multi-plant integrated natural gas and liquefaction and LNG export terminal facility to be located at the Port of Brownsville in southern Texas (the “Rio Grande LNG Facility”);

Current wording

•the timing and cost of the development, construction and operation of the first five liquefaction trains and related common facilities of the multi-plant integrated natural gas liquefaction and LNG export facility to be located at the Port of Brownsville in southern Texas (the “Rio Grande LNG Facility”);

Previous wording

•the availability and frequency of cash distributions available to us from our joint ventures which own the first three trains and related common facilities ("Phase 1"), the fourth liquefaction train and related common facilities ("Train 4"), and the fifth liquefaction train and related common facilities ("Train 5") at the Rio Grande LNG Facility, respectively;

Current wording

•the availability and frequency of cash distributions available to us from the Joint Ventures, which own Phase 1, Train 4, and Train 5 of the Rio Grande LNG Facility;

Previous wording

•the ability to generate sufficient cash flow to satisfy NextDecade's or Rio Grande's significant debt service obligations or to refinance such obligations ahead of their maturity;

Current wording

•the ability to generate sufficient cash flow to satisfy our and our subsidiaries’ significant debt service obligations or to refinance such obligations ahead of their maturity;

Previous wording

•restrictions imposed by debt agreements that limit flexibility in operating the Company's business;

Current wording

•restrictions imposed by our or our subsidiaries’ debt agreements that limit flexibility in operating our business;

Previous wording

•increases in interest rates that increase the cost of servicing indebtedness;

Current wording

•increases in interest rates increasing the cost of servicing indebtedness;

Previous wording

•the accuracy of estimated costs for the Rio Grande LNG Facility and CCS projects;

Current wording

•the accuracy of estimated costs for the Rio Grande LNG Facility and any CCS projects;

Previous wording

•our ability to achieve operational characteristics of the Rio Grande LNG Facility and CCS projects, when completed, including amounts of liquefaction capacities and amount of CO 2 captured and stored, and any differences in such operational characteristics from our expectations;

Current wording

•our ability to achieve operational characteristics of the Rio Grande LNG Facility and any CCS projects, when completed, including amounts of liquefaction capacities and amount of CO 2 captured and stored, and any differences in such operational characteristics from our expectations;

Previous wording

•the development risks, operational hazards and regulatory approvals applicable to our LNG and CCS project development, construction and operation activities and those of our third-party contractors and counterparties;

Current wording

•the development risks, operational hazards, and regulatory approvals applicable to the Rio Grande LNG Facility, our LNG and any CCS project development, construction and operation activities and those of our third-party contractors and counterparties;

Previous wording

•the ability to obtain or maintain governmental approvals to construct or operate the Rio Grande LNG Facility and CCS projects;

Current wording

•the ability to obtain or maintain governmental approvals to construct or operate the Rio Grande LNG Facility and any CCS projects;

Previous wording

•global pandemics, the Russia-Ukraine conflict, conflict in the Middle East, other sources of volatility in the energy markets and their impact on our business and operating results, including any disruptions in our operations or development of the Rio Grande LNG Facility and the health and safety of our employees, and on our customers, the global economy and the demand for LNG or carbon capture;

Current wording

•global pandemics, the Russia-Ukraine conflict, the conflict in the Middle East, other sources of volatility in the energy markets and their impact on our business and operating results, including any disruptions in our operations or development of the Rio Grande LNG Facility and the health and safety of our employees, and on our customers, the global economy and the demand for LNG or carbon capture;

Previous wording

Should one or more of the foregoing risks or uncertainties materialize in a way that negatively impacts us, or should the underlying assumptions prove incorrect, our actual results may vary materially from those anticipated in our forward-looking statements, and our business, financial condition, and results of operations could be materially and adversely affected.

Current wording

Should one or more of the foregoing risks or uncertainties materialize in a way that negatively impacts us, or should the assumptions underlying our forward-looking statements prove incorrect, our actual results may vary materially from those anticipated in our forward-looking statements, and our business, financial condition, and results of operations could be materially and adversely affected.

Previous wording

The forward-looking statements contained in this Quarterly Report on Form 10-Q are made as of the date of this Quarterly Report on Form 10-Q. You should not rely upon forward-looking statements as predictions of future events. In addition, neither we nor any other person assumes responsibility for the accuracy and completeness of any of these forward-looking statements. Except as required by applicable law, we do not undertake any obligation to publicly correct or update any forward-looking statements.

Current wording

The forward-looking statements contained in this Quarterly Report on Form 10-Q are made as of the date of this Quarterly Report on Form 10-Q. You should not rely upon forward-looking statements as predictions of future events. In addition, neither we nor any other person assumes responsibility for the accuracy and completeness of any of these forward-looking statements. Except as required by applicable law, we do not undertake any obligation to publicly correct or update any forward-looking statement.

Previous wording

•The overall project completion percentage for Trains 1 and 2 and the common facilities at the Rio Grande LNG Facility was 55.9%. Within this project completion percentage, engineering was 95.0% complete, procurement was 88.8% complete, and construction was 29.8% complete.

Current wording

•The overall project completion percentage for Trains 1 and 2 and the common facilities at the Rio Grande LNG Facility was 67.8%. Within this project completion percentage, engineering was 98.4% complete, procurement was 94.3% complete, and construction was 49.4% complete.

Previous wording

•The overall project completion percentage for Train 3 at the Rio Grande LNG Facility was 33.4%. Within this project completion percentage, engineering was 70.8% complete, procurement was 67.2% complete, and construction was 4.5% complete.

Current wording

•The overall project completion percentage for Train 3 at the Rio Grande LNG Facility was 44.2%. Within this project completion percentage, engineering was 91.4% complete, procurement was 82.6% complete, and construction was 11.4% complete.

Previous wording

Basin and Eagle Ford Shale, access to an uncongested waterway for vessel loading, and location in a region that has historically been subject to fewer and less severe weather events relative to other locations along the U.S. Gulf Coast. Trains 1 through 5 at the Rio Grande LNG Facility are under construction, and we are developing and advancing the permitting process for Trains 6 through 8. There is sufficient space at the Rio Grande LNG Facility site for up to 10 liquefaction trains.

Current wording

We are constructing and developing the Rio Grande LNG Facility on the north shore of the Brownsville Ship Channel in south Texas. The site is located on approximately 1,000 acres of land, which has been leased long-term and includes 15,000 feet of frontage on the Brownsville Ship Channel. We believe the site is advantaged due to its proximity to abundant natural gas resources in the Permian Basin and Eagle Ford Shale, access to an uncongested waterway for vessel loading, and location in a region that has historically been subject to fewer and less severe weather events relative to other locations along the U.S. Gulf Coast. Trains 1 through 5 at the Rio Grande LNG Facility are under construction, and we are developing and advancing the permitting process for Trains 6 through 8. There is sufficient space at the Rio Grande LNG Facility site for up to 10 liquefaction trains.

Previous wording

Construction commenced on Phase 1 at the Rio Grande LNG Facility in July 2023, on Train 4 in September 2025, and on Train 5 in October 2025, in each case following a positive FID and the closing of project financing by the Company's subsidiaries. Construction will be completed by Bechtel under fully wrapped, lump-sum turnkey EPC contracts, and the liquefaction trains will utilize Honeywell AP-C3MRTM liquefaction technology, which is the predominant liquefaction technology utilized globally.

Current wording

Construction commenced on Phase 1 at the Rio Grande LNG Facility in July 2023, on Train 4 in September 2025, and on Train 5 in October 2025, in each case following a positive final investment decision (“FID”) and the closing of project financing by the Company’s subsidiaries. Construction will be completed by Bechtel under fully wrapped, lump-sum turnkey EPC contracts, and the liquefaction trains will utilize Honeywell AP-C3MR liquefaction technology, which is a predominant liquefaction technology utilized globally.

Previous wording

The combined scope of Phase 1, Train 4, and Train 5 includes five liquefaction trains with a total expected LNG production capacity of approximately 30 MTPA, four 180,000 cubic meter full containment LNG storage tanks, two jetty berthing structures designed to load LNG carriers up to 216,000 cubic meters in capacity, and associated site infrastructure and common facilities including feed gas pretreatment facilities, electric and water utilities, ground flares, roads, levees surrounding the entire site, and warehouses, administrative, operations control room and maintenance buildings.

Current wording

The combined scope of Phase 1, Train 4, and Train 5 includes five liquefaction trains with a total expected LNG production capacity of approximately 30 million tonnes per annum (“MTPA”), four 180,000 cubic meter full containment LNG storage tanks, two jetty berthing structures designed to load LNG carriers up to 216,000 cubic meters in capacity, and associated site infrastructure and common facilities including feed gas pretreatment facilities, electric and water utilities, ground flares, roads, levees surrounding the entire site, warehouses, and operations control room, maintenance, and administrative buildings.

Previous wording

We have entered into long-term SPAs with 14 creditworthy counterparties for aggregate volumes of approximately 25.3 MTPA of LNG from Trains 1 through 5 at the Rio Grande LNG Facility. The SPAs have a weighted average term of 19.5 years. Under these SPAs, the customers will purchase LNG from the Rio Grande LNG Facility for a price consisting of a fixed fee per MMBtu of LNG plus a variable fee per MMBtu of LNG, with the variable fees structured to cover the expected cost of natural gas plus fuel and other sourcing costs to produce LNG. In certain circumstances, customers may elect to cancel or suspend deliveries of LNG cargoes, in which case the customers would still be required to pay the fixed fee with respect to cargoes that are not delivered. A portion of the fixed fee under each SPA will be subject to annual adjustment for inflation. The SPAs and contracted volumes to be made available under the SPAs are not tied to a specific train; however, the commencement of the term of each SPA is tied to a specified train.

Current wording

We have entered into long-term LNG sale and purchase agreements (“SPAs”) with 14 creditworthy counterparties for aggregate volumes of approximately 25.3 million tonnes per annum (“MTPA”) of LNG from Trains 1 through 5 at the Rio Grande LNG Facility. The SPAs have a weighted average term of 19.5 years. Under these SPAs, the customers will purchase LNG from the Rio Grande LNG Facility for a price consisting of a fixed fee per MMBtu of LNG plus a variable fee per MMBtu of LNG, with the variable fees structured to cover the expected cost of natural gas plus fuel and other sourcing costs to produce LNG. In certain circumstances, customers may elect to cancel or suspend deliveries of LNG cargoes, in which case the customers would still be required to pay the fixed fee with respect to cargoes that are not delivered. A portion of the fixed fee under each SPA will be subject to annual adjustment for inflation. The SPAs and contracted volumes to be made available under the SPAs are not tied to a specific train; however, the commencement of the term of each SPA is tied to a specified train.

Previous wording

Each of these SPAs is currently effective, and deliveries of LNG under these SPAs will commence on the respective Date of First Commercial Delivery (“DFCD”), which is primarily tied to the substantial completion or guaranteed substantial completion dates of specific trains as defined in each SPA. In aggregate, the approximately 23.75 MTPA of Henry Hub-linked SPAs for Trains 1 through 5 have average fixed fees, unadjusted for inflation, totaling approximately $3.0 billion expected to be paid annually.

Current wording

Each of these SPAs is currently effective, and deliveries of LNG under these SPAs will commence on the respective Date of First Commercial Delivery (“DFCD”), which is primarily tied to the substantial completion or guaranteed substantial completion dates of specific trains as defined in each SPA. Of the SPAs for Trains 1 through 5, approximately 23.75 MTPA are linked to Henry Hub and have average fixed fees, unadjusted for inflation, totaling approximately $3.0 billion expected to be paid annually.

Previous wording

We expect to sell any commissioning LNG volumes and operational LNG volumes in excess of SPA volumes into the LNG market through spot, short-term, and medium-term agreements. We have entered into certain time charter agreements and expect to enter into additional time charter agreements with vessel owners to provide shipping capacity for LNG sales related to our 1.0 MTPA delivered ex-ship SPA, expected commissioning volumes, and expected portfolio volumes.

Current wording

We expect to sell any commissioning LNG volumes and operational LNG volumes in excess of SPA volumes (“portfolio volumes”) into the LNG market through spot, short-term, and medium-term agreements. We have entered into certain time charter agreements and expect to enter into additional time charter agreements with vessel owners to provide shipping capacity for LNG sales related to our 1.0 MTPA delivered ex-ship SPA, expected commissioning volumes, and expected portfolio volumes. We have also entered into certain subcharter agreements and may enter into additional subcharter agreements with third parties from time to time to manage our LNG shipping needs relative to chartered capacity.

Previous wording

We have entered into agreements for transportation of natural gas to the Rio Grande LNG Facility on both a firm and interruptible basis to support commissioning and operations and provide the ability to purchase natural gas supplies at the Agua Dulce Hub, giving us access to prolific gas production from the Permian Basin and Eagle Ford Shale and providing significant flexibility to obtain competitively priced natural gas feedstock.

Current wording

We have entered into agreements for transportation of natural gas to the Rio Grande LNG Facility on both a firm and interruptible basis to support commissioning and operations and provide the ability to purchase natural gas supplies at the Agua Dulce Hub and other physical access points, giving us access to prolific gas production from the Permian Basin, Eagle Ford Shale, and additional basins, and providing significant flexibility to obtain competitively priced natural gas feedstock.

Previous wording

Pursuant to a joint venture agreement with equity partners for ownership of Train 4 at the Rio Grande LNG Facility, we expect to receive 40% of distributions of available cash generated from Train 4 operations, which will increase to 60% when the equity partners receive a certain return on their investments in Train 4.

Current wording

Pursuant to a joint venture agreement with equity partners for ownership of Train 4 at the Rio Grande LNG Facility, we expect to receive 40% of distributions of available cash generated from Train 4 operations, which will increase to 60% when our equity partners receive a certain return on their investments in Train 4.

Previous wording

Pursuant to a joint venture agreement with equity partners for ownership of Train 5 at the Rio Grande LNG Facility, we expect to receive 50% of distributions of available cash generated from Train 5 operations, which will increase to 70% when the equity partners receive a certain return on their investments in Train 5.

Current wording

Pursuant to a joint venture agreement with equity partners for ownership of Train 5 at the Rio Grande LNG Facility, we expect to receive 50% of distributions of available cash generated from Train 5 operations, which will increase to 70% when our equity partners receive a certain return on their investments in Train 5.

Previous wording

We are developing and advancing the permitting process for additional liquefaction capacity at the Rio Grande LNG Facility site. Trains 6 through 8 are currently wholly owned by NextDecade and are cumulatively expected to increase the Company's total liquefaction capacity by approximately 18 MTPA once constructed and placed into operation.

Current wording

We are developing and advancing the permitting process for Trains 6 through 8 at the Rio Grande LNG Facility site, which are currently wholly owned by NextDecade and are cumulatively expected to increase the Company’s total liquefaction capacity by approximately 18 MTPA once constructed and placed into operation.

Previous wording

Train 6 is being developed inside the existing levee at the Rio Grande LNG Facility site and adjacent to Trains 1 through 5. The Company expects to pre-file an application with FERC for Train 6 in 2025 and a full application with FERC in 2026. The Company is evaluating multiple areas on the site for the development of Trains 7 and 8.

Current wording

Train 6 is being developed inside the existing levee at the Rio Grande LNG Facility site and adjacent to Trains 1 through 5. In November 2025, we initiated the pre-filing process with FERC for expansion at the Rio Grande LNG Facility that includes Train 6 and an additional marine berth, and we expect to file a formal application for this expansion with FERC before the end of the second quarter of 2026. We are evaluating multiple areas on the site for the development of Trains 7 and 8 and expect to advance the development of these trains throughout 2026.

Previous wording

We have obtained all major permits required to build and export LNG from the first five liquefaction trains and related infrastructure at the Rio Grande Facility, including FERC approval and Department of Energy FTA and non-FTA authorizations.

Current wording

We have obtained all major permits required to build and export LNG from the first five liquefaction trains and related infrastructure at the Rio Grande Facility, including Federal Energy Regulatory Commission (“FERC”) approval and Department of Energy FTA and non-FTA authorizations.

Previous wording

In March 2025, the FERC issued a draft SEIS for the first five liquefaction trains at the Rio Grande LNG Facility. In July 2025, the FERC issued a final SEIS for the first five liquefaction trains at the Rio Grande LNG Facility. In August 2025, the FERC issued a final order on remand reaffirming its authorization for the siting, construction, and operation of the first five liquefaction trains at the Rio Grande LNG Facility. In September 2025, a request for rehearing of the Remand Order was filed by certain intervenors and on October 30, 2025, the rehearing request was deemed denied by operation of law, rendering the Remand Order no longer appealable to FERC.

Current wording

In August 2025, the FERC issued a final order on remand (“Remand Order”) reaffirming its authorization for the siting, construction, and operation of the first five liquefaction trains at the Rio Grande LNG Facility, following the issuance of a supplemental Environmental Impact Statement (“SEIS”) in July 2025. In September 2025, certain intervenors filed a request for rehearing of the Remand Order. FERC denied that request by operation of law on October 30, 2025, and issued a substantive order on rehearing in March 2026 that reaffirmed its authorization for the first five liquefaction trains, rendering the Remand Order no longer appealable to FERC. In December 2025, the same intervenors petitioned the D.C. Circuit to review the Remand Order, and that appeal remains pending.

Previous wording

We are required to maintain corporate and general and administrative functions to serve our business activities described above, including the construction of Trains 1 through 5, the development of Trains 6 through 8, and evaluating the potential development of a CCS project at the Rio Grande LNG Facility.

Current wording

We are required to maintain corporate and general and administrative functions to serve our business activities described above, including the construction of Trains 1 through 5, the development of Trains 6 through 8, and exploring the potential development of a CCS project at the Rio Grande LNG Facility.

Previous wording

In connection with the FID on Phase 1 at the Rio Grande LNG Facility, Phase 1 LLC obtained approximately $6.2 billion in equity capital commitments, inclusive of commitments from NextDecade, entered into senior secured non-recourse bank credit facilities of $11.6 billion, consisting of $11.1 billion in construction term loans and a $500 million working capital facility, and closed a $700 million senior secured non-recourse private notes offering. Phase 1 LLC expects to utilize these capital resources to fund the total cost of Phase 1, which is currently estimated at $18.0 billion and consists of EPC costs, owner’s costs and contingencies, dredging for the Brazos Island Harbor Channel Improvement Project, conservation of more than 4,000 acres of wetland and wildlife habitat area and installation of utilities, interest during construction and other financing costs, and and including amounts spent prior to FID under limited notices to proceed. Phase 1 LLC has refinanced a total of over $1.85 billion of its original $11.1 billion term loan facilities since July 2023 through the issuance of senior secured notes and loans.

Current wording

In connection with the FID on Phase 1 at the Rio Grande LNG Facility, Phase 1 LLC obtained approximately $6.2 billion in equity capital commitments, inclusive of commitments from NextDecade, entered into senior secured non-recourse bank credit facilities of $11.6 billion, consisting of $11.1 billion in construction term loans and a $500 million working capital facility, and closed a $700 million senior secured non-recourse private notes offering. Phase 1 LLC expects to utilize these capital resources to fund the total cost of Phase 1, which is currently estimated at $18.0 billion and consists of EPC costs, owner’s costs and contingencies, dredging for the Brazos Island Harbor Channel Improvement Project, conservation of more than 4,000 acres of wetland and wildlife habitat area and installation of utilities, interest during construction and other financing costs, and including amounts spent prior to FID under limited notices to proceed. Phase 1 LLC has refinanced a total of over $1.85 billion of its original $11.1 billion term loan facilities since July 2023 through the issuance of senior secured notes and loans.

Previous wording

In connection with the FID on Train 4 at the Rio Grande LNG Facility, Train 4 LLC obtained approximately $2.8 billion in equity capital commitments, inclusive of commitments from NextDecade, and entered into a senior secured non-recourse bank credit facility of approximately $3.9 billion. Train 4 LLC expects to utilize these capital resources to fund the total cost of Train 4 and related infrastructure, which is currently estimated at $6.7 billion and consists of EPC costs, owner's costs and contingencies, interest during construction and other financing costs, and other costs, including a payment for usage of common infrastructure at the Rio Grande LNG Facility.

Current wording

In connection with the FID on Train 4 at the Rio Grande LNG Facility, Train 4 LLC obtained approximately $2.8 billion in equity capital commitments, inclusive of commitments from NextDecade, and entered into a senior secured non-recourse bank credit facility of approximately $3.8 billion. Train 4 LLC expects to utilize these capital resources to fund the total cost of Train 4 and related infrastructure, which is currently estimated at $6.7 billion and consists of EPC costs, owner’s costs and contingencies, interest during construction and other financing costs, and other costs, including a payment for usage of common infrastructure at the Rio Grande LNG Facility.

Previous wording

In connection with the FIDs of Train 4 and Train 5, we committed to make approximately $2.4 billion in equity capital contributions for Train 4 and 5 in the aggregate. At the FIDs of Train 4 and Train 5, we used the net proceeds of the Super FinCo Loans and cash on hand to fund a portion of our equity commitments for Train 4 and Train 5. We will fund the remainder of our equity commitments to Trains 4 and 5 using borrowings under the FinCo Credit Agreement.

Current wording

In connection with the FIDs of Train 4 and Train 5, we committed to make approximately $2.4 billion in equity capital contributions for Train 4 and 5 in the aggregate. At the FIDs of Train 4 and Train 5, we used the net proceeds of the Super FinCo $1.2 billion term loans and cash on hand to fund a portion of our equity commitments for Train 4 and Train 5. We expect to fund the remainder of our equity commitments to Trains 4 and 5 using borrowings under the FinCo Credit Agreement.

Previous wording

At Train 4 FID, Train 4 LLC paid NextDecade LLC, our wholly owned subsidiary and the entity that manages the construction, commissioning and operation of the Rio Grande Facility on behalf of Phase 1, Train 4 and Train 5, $98 million, representing a $48 million development fee for activities prior to FID of Train 4 and a $50 million fee for services to be rendered by NextDecade LLC in support of Train 4. Train 4 LLC will also pay NextDecade LLC an additional $50 million services fee in September 2026. At Train 5 FID, Train 5 LLC paid NextDecade LLC $117 million, representing a $17 million development fee for activities prior to FID of Train 5 and a $100 million fee for services to be rendered by NextDecade LLC in support of Train 5.

Current wording

Train 4 LLC will pay NextDecade LLC, our wholly owned subsidiary and the entity that manages the construction, commissioning, and operation of the Rio Grande LNG Facility on behalf of Phase 1, Train 4, and Train 5, a $50 million fee in September 2026 for services to be rendered by NextDecade LLC in support of Train 4.

Previous wording

We will not receive significant cash flows from liquefaction trains at the Rio Grande LNG Facility until they are operational, and the commercial operation date for the first train is expected to occur in late 2027 based on the guaranteed schedule under the EPC contracts. Any future development of liquefaction trains and any potential CCS project at the Rio Grande LNG Facility will similarly take an extended period of time to develop, construct and become operational and will require significant capital deployment.

Current wording

We will not receive significant cash flows from liquefaction trains at the Rio Grande LNG Facility until they are operational, and the commercial operation dates for Trains 1 through 5 range from late 2027 for Train 1 through the first half of 2031 for Train 5, based on the guaranteed schedule under the EPC contracts. Any future development of liquefaction trains and any potential CCS project at the Rio Grande LNG Facility will similarly take an extended period of time to develop, construct and become operational and will require significant capital deployment.

Previous wording

Cash used in operating activities for the nine months ended September 30, 2025 increased by approximately $62.1 million compared to the same period in 2024 primarily due to higher pre-operational expenditures and working capital investments to support the commencement of operations at the Rio Grande LNG Facility.

Current wording

Cash used in operating activities for the three months ended March 31, 2026 increased by approximately $42.0 million compared to the same period in 2025 primarily due to changes in working capital and increased interest payments.

Previous wording

Cash used in investing activities for the nine months ended September 30, 2025 increased by approximately $1.0 billion compared to the same period in 2024 primarily due to increased expenditures associated with construction of the Rio Grande LNG Facility.

Current wording

Cash used in investing activities for the three months ended March 31, 2026 increased by approximately $397.3 million compared to the same period in 2025 primarily due to increased expenditures associated with construction of the Rio Grande LNG Facility, including expenditures related to Trains 4 and 5, which achieved positive FID and began construction in the second half of 2025.

Previous wording

Net loss attributable to common stockholders was approximately $109.5 million, for the three months ended September 30, 2025 compared to net loss of approximately $123.2 million during the same period in 2024. The approximately $13.7 million decrease was primarily a result of the following:

Current wording

Net loss attributable to common stockholders was approximately $136.4 million for the three months ended March 31, 2026 compared to net loss of approximately $88.8 million during the same period in 2025. The approximately $47.6 million increase was primarily a result of the following:

Previous wording

•General and administrative expenses increased by approximately $22.5 million, principally reflecting higher share-based compensation expense recognized in connection with FID on Train 4 and incremental headcount additions to support the commencement of operations at the Rio Grande LNG Facility.

Current wording

•General and administrative expenses increased by approximately $5.0 million primarily due to an increase in headcount to support the commencement of operations at the Rio Grande LNG Facility.

Previous wording

•Interest expense, net increased by approximately $22.7 million primarily due to additional borrowings to construct the Rio Grande LNG Facility.

Current wording

•Interest expense increased by approximately $52.0 million primarily due to additional borrowings to construct the Rio Grande LNG Facility. This resulted in an approximate $93.5 million increase in interest on debt obligations, partially offset by a $64.4 million increase in capitalized interest.

Showing the first 40 of 42 pairs. Open the source sections for the rest.

Rearranged previous paragraphs (7)

Previous report — wording carried elsewhere

•In February 2025, we provided additional information regarding its development of additional liquefaction capacity at the Rio Grande LNG Facility beyond Trains 1 through 5. Trains 6 through 8 are currently wholly owned by NextDecade and are cumulatively expected to increase the Company's total liquefaction capacity by approximately 18 million tonnes per annum ("MTPA") once constructed and placed into operation.

Previous report — wording carried elsewhere

◦The Company is evaluating multiple areas on the site for the development of Trains 7 and 8, which have a total expected LNG production capacity of approximately 12 MTPA.

Previous report — wording carried elsewhere

•In April 2025, Phase 1 LLC elected to terminate $250 million of commitments under its working capital facility due to a decrease in expected requirements for credit support during construction, which reduced the outstanding commitments under the working capital facility to $250 million and is expected to reduce related commitment fees by approximately $2 million annually.

Previous report — wording carried elsewhere

•In August 2025, the FERC issued a final order on remand reaffirming its authorization for the siting, construction, and operation of the first five liquefaction trains at the Rio Grande LNG Facility, and as of October 30, 2025, the order is no longer appealable to FERC.

Previous report — wording carried elsewhere

We are constructing and developing the Rio Grande LNG Facility on the north shore of the Brownsville Ship Channel in south Texas. The site is located on approximately 1,000 acres of land, which has been leased long-term and includes 15,000 feet of frontage on the Brownsville Ship Channel. We believe the site is advantaged due to its proximity to abundant natural gas resources in the Permian

Previous report — wording carried elsewhere

Net loss attributable to common stockholders was approximately $259.2 million, for the nine months ended September 30, 2025 compared to net loss of approximately $127.4 million during the same period in 2024. The approximately $131.7 million increase was primarily a result of the following:

Previous report — wording carried elsewhere

•Interest expense, net increased by approximately $27.3 million primarily due to additional borrowings to construct the Rio Grande LNG Facility.