NextDecade Corp
For the period ended Sep 30, 2025. Filed Oct 30, 2025.
View on SEC.govAbout this filing
A company's report for each of its first three quarters. The financial statements are not audited. It shows how the business has moved since the last annual report, and what management says changed.
Sep 30, 2025 · Filed Oct 30, 2025
What changed in Management’s Discussion and Analysis?
Read the current filingPrevious report: 10-Q
Period ended 2025-06-30; filed 2025-08-01.
0001612720-25-000009
Item 2. Management’s Discussion and Analysis of Financial Condition and Results of OperationsCurrent report: 10-Q
Period ended 2025-09-30; filed 2025-10-30.
0001612720-25-000030
Item 2. Management’s Discussion and Analysis of Financial Condition and Results of OperationsThe baseline is this issuer’s latest earlier reporting period of the same form that was filed before the current report. A previous 10-Q is a different quarter, not a year-over-year comparison. Amendments are excluded.
Compared 137 previous paragraphs and 154 current paragraphs.
60 unchanged; 55 reworded; 38 added; 20 removed; 2 previous and 1 current paragraphs rearranged.
Tables are not compared: 2 previous and 2 current tables excluded. Dates, whitespace, punctuation and numbering changes are ignored; changes to financial figures remain significant.
A changed paragraph is not evidence that risk increased or decreased. An unchanged paragraph does not establish that risk stayed the same.
Added paragraphs (38)
Current report
Development and Construction
Current report
•Progress for Train 4 included advancement on engineering drawings, issuance of purchase orders for a range of equipment and materials, and commencement of area clearing.
Current report
•On September 9, 2025, we announced a positive final investment decision ("FID") on Train 4 and related infrastructure at the Rio Grande LNG Facility and issued full notice to proceed ("NTP") to Bechtel Energy Inc. ("Bechtel") under the EPC contract for Train 4. Total project costs for Train 4 and related infrastructure are expected to total approximately $6.7 billion. Train 4 has an expected LNG production capacity of approximately 6 million MTPA, and guaranteed substantial completion of Train 4 is in the second half of 2030.
Current report
•On October 16, 2025, we announced a positive FID on Train 5 and related infrastructure at the Rio Grande LNG Facility and issued full NTP to Bechtel under the EPC contract for Train 5. Total project costs for Train 5 and related infrastructure are expected to total approximately $6.7 billion. Train 5 has an expected LNG production capacity of approximately 6 million MTPA, and guaranteed substantial completion of Train 5 is in the first half of 2031.
Current report
•In September 2025, we announced a 20-year LNG SPA with EQT Corporation ("EQT"), pursuant to which EQT will purchase 1.5 MTPA of LNG from Train 5 at the Rio Grande LNG Facility for 20 years, on an FOB basis at a price indexed to Henry Hub.
Current report
•In September 2025, we announced a 20-year LNG SPA with ConocoPhillips, pursuant to which ConocoPhillips will purchase 1.0 MTPA of LNG from Train 5 at the Rio Grande LNG Facility for 20 years, on an FOB basis at a price indexed to Henry Hub.
Current report
•On September 9, 2025, in conjunction with the positive FID on Train 4 at the Rio Grande LNG Facility, we and certain of our subsidiaries closed an approximately $6.7 billion project financing for Train 4, which included the closing of:
Current report
◦A joint venture agreement which included approximately $1.69 billion of financial commitments from Global Infrastructure Partners, a part of BlackRock ("GIP"), GIC, Mubadala Investment Company, and TotalEnergies;
Current report
◦A commitment by the Company to invest approximately $1.13 billion in Train 4; and
Current report
◦A senior secured, non-recourse bank credit facility of $3.85 billion with a seven year maturity.
Current report
•On September 9, 2025, to fully fund the Company's approximately $1.13 billion equity commitments for Train 4, certain of our wholly-owned subsidiaries entered into a delayed draw, senior secured term loan bank facility of $734 million with a five year maturity (the "FinCo Loan") and term loans of $600 million with a maturity date of the earlier of eight years or the 85th day prior to the maturity date of the FinCo Loan (the "SuperFinCo Loan").
Current report
•On October 16, 2025, in conjunction with the positive FID on Train 5 at the Rio Grande LNG Facility, we and certain of our subsidiaries closed an approximately $6.7 billion project financing for Train 5, which included the closing of:
Current report
◦A joint venture agreement which included approximately $1.29 billion of financial commitments from GIP, GIC, and Mubadala Investment Company;
Current report
◦A commitment by the Company to invest approximately $1.29 billion in Train 5;
Current report
◦A senior secured, non-recourse bank credit facility of $3.59 billion with a seven year maturity; and
Current report
◦An offering of $500 million senior secured, non-recourse private placement notes, which will bear interest at 6.56%, will be funded in multiple tranches from December 2025 through October 2026, and will amortize over a period of 20 years beginning in September 2031.
Current report
•On October 16, 2025, to fully fund the Company's approximately $1.29 billion equity commitments for Train 5, we contributed $233 million cash to Train 5 LLC, and certain of our wholly-owned subsidiaries increased the size of the FinCo Loan by $729 million, to a total of approximately $1.46 billion, and increased the size of the SuperFinCo Loan by $600 million, to a total of $1.2 billion.
Current report
•In October 2025, Rio Grande LNG Super Holdings, LLC, entered into a term sheet with the lender of the Super Holdings Loan to refinance $50 million of the existing loan amount and provide $50 million of incremental capital in the form of an exchangeable loan with total initial principal of $100 million (the "Exchangeable Loan"). Upon consummation of the transaction, the Exchangeable Loan would bear interest at 8%, payable in cash or in-kind at the Company's election, and would mature in October 2030. The initial principal of the Exchangeable Loan, and any amounts of interest paid in-kind, would be exchangeable into shares of Company common stock at $9.50 per share. Additionally, the interest rate on the remaining balance of the Super Holdings Loan would be amended to 13.5%.
Current report
•In August 2025, the FERC issued a final order on remand reaffirming its authorization for the siting, construction, and operation of the first five liquefaction trains at the Rio Grande LNG Facility, and as of October 30, 2025, the order is no longer appealable to FERC.
Current report
During September 2025, progress on Train 4 included advancement on engineering drawings, issuance of purchase orders for a range of equipment and materials, and commencement of area clearing.
Current report
On September 9, 2025, we issued final notice to proceed to Bechtel under the EPC contract for Train 4. Total expected capital costs for Train 4 are estimated to be approximately $6.7 billion, including estimated EPC costs, owner's costs, contingencies, financing costs, and other costs, including a payment to be made at the commencement of operations to the trains in commercial operation at such date for Train 4's proportionate share of the capital costs of the common facilities it will access, net of the capital cost of any common facilities constructed under the Train 4 EPC contract.
Current report
On October 16, 2025, we issued final notice to proceed to Bechtel under the EPC contract for Train 5. Total expected capital costs for Train 5 are estimated to be approximately $6.7 billion, including estimated EPC costs, owner's costs, contingencies, financing costs, and other costs, including a payment to be made at the commencement of operations to the trains in commercial operation at such date for Train 5's proportionate share of the capital costs of the common facilities it will access, net of the capital cost of any common facilities constructed under the Train 5 EPC contract.
Current report
NextDecade Economic Interest in Trains 1 Through 5
Current report
Pursuant to a joint venture agreement with equity partners for ownership of Train 4 at the Rio Grande LNG Facility, we expect to receive 40% of distributions of available cash generated from Train 4 operations, which will increase to 60% when the equity partners receive a certain return on their investments in Train 4.
Current report
Pursuant to a joint venture agreement with equity partners for ownership of Train 5 at the Rio Grande LNG Facility, we expect to receive 50% of distributions of available cash generated from Train 5 operations, which will increase to 70% when the equity partners receive a certain return on their investments in Train 5.
Current report
There is sufficient space at the Rio Grande LNG Facility site for up to 10 liquefaction trains.
Current report
Train 4 FID Rio Grande Train 4 Financing
Current report
In connection with the FID on Train 4 at the Rio Grande LNG Facility, Train 4 LLC obtained approximately $2.8 billion in equity capital commitments, inclusive of commitments from NextDecade, and entered into a senior secured non-recourse bank credit facility of approximately $3.9 billion. Train 4 LLC expects to utilize these capital resources to fund the total cost of Train 4 and related infrastructure, which is currently estimated at $6.7 billion and consists of EPC costs, owner's costs and contingencies, interest during construction and other financing costs, and other costs, including a payment for usage of common infrastructure at the Rio Grande LNG Facility.
Current report
Train 5 FID Rio Grande Train 5 Financing
Current report
In connection with the FID on Train 5 at the Rio Grande LNG Facility, Train 5 LLC obtained approximately $2.6 billion in equity capital commitments, inclusive of commitments from NextDecade, entered into a senior secured non-recourse bank credit facility of approximately $3.6 billion, and closed a $500 million senior secured non-recourse private notes offering. Train 5 LLC expects to utilize these capital resources to fund the total cost of Train 5 and related infrastructure, which is currently estimated at $6.7 billion and consists of EPC costs, owner's costs and contingencies, interest during construction and other financing costs, and other costs, including a payment for usage of common infrastructure at the Rio Grande LNG Facility.
Current report
Following the respective FIDs of Phase 1, Train 4 and Train 5, costs associated with the EPC agreements, Rio Grande site lease, and other Phase 1, Train 4, and Train 5 related costs are being funded by debt and equity proceeds received by the Rio Grande Project Entities. Our primary corporate cash needs are capital contributions to Trains 4 and 5, development expenses for expansion projects and general and administrative expenses.
Current report
In connection with the FIDs of Train 4 and Train 5, we committed to make approximately $2.4 billion in equity capital contributions for Train 4 and 5 in the aggregate. At the FIDs of Train 4 and Train 5, we used the net proceeds of the Super FinCo Loans and cash on hand to fund a portion of our equity commitments for Train 4 and Train 5. We will fund the remainder of our equity commitments to Trains 4 and 5 using borrowings under the FinCo Credit Agreement.
Current report
At Train 4 FID, Train 4 LLC paid NextDecade LLC, our wholly owned subsidiary and the entity that manages the construction, commissioning and operation of the Rio Grande Facility on behalf of Phase 1, Train 4 and Train 5, $98 million, representing a $48 million development fee for activities prior to FID of Train 4 and a $50 million fee for services to be rendered by NextDecade LLC in support of Train 4. Train 4 LLC will also pay NextDecade LLC an additional $50 million services fee in September 2026. At Train 5 FID, Train 5 LLC paid NextDecade LLC $117 million, representing a $17 million development fee for activities prior to FID of Train 5 and a $100 million fee for services to be rendered by NextDecade LLC in support of Train 5.
Current report
•The change in derivative (loss) gain of approximately $255.6 million was primarily driven by lower forward SOFR rates, which reduced the mark-to-market loss on the Company’s interest rate swap portfolio.
Current report
•Interest expense, net increased by approximately $22.7 million primarily due to additional borrowings to construct the Rio Grande LNG Facility.
Current report
•The change in derivative (loss) gain of approximately $255.9 million for the nine months ended September 30, 2025, was primarily driven by lower forward SOFR rates, which increased the fair-value loss on the Company’s interest rate swap portfolio.
Current report
•Interest expense, net increased by approximately $27.3 million primarily due to additional borrowings to construct the Rio Grande LNG Facility.
Current report
•Due to the above changes, net loss attributable to non-controlling interest for the nine months ended September 30, 2025, increased by approximately $164.9 million, reflecting the impact of derivative losses and interest expense recognized within Phase 1 Holdings, which are consolidated in the Company’s results.
Removed paragraphs (20)
Previous report
Construction
Previous report
•In March 2025, the FERC issued a draft SEIS for the first five liquefaction trains at the Rio Grande LNG Facility, providing for a public comment period that ended on May 19, 2025.
Previous report
Liquefaction Facilities Overview
Previous report
Final Investment Decision on Train 4
Previous report
The Company has completed commercialization of Train 4 and has executed 20-year LNG SPAs totaling 4.6 MTPA of LNG with ADNOC, Aramco, and TotalEnergies in support of Train 4.
Previous report
In June 2025, the Company finalized an EPC contract pricing refresh with Bechtel for Train 4 and related infrastructure. Pricing validity under the EPC contract for Train 4 extends through September 15, 2025.
Previous report
The Company launched the financing process for Train 4 in June 2025 and expects to finance construction of Train 4 using a combination of debt and equity funding at the project level. The Company is in the process of entering into a term loan bank facility at Rio Grande LNG Train 4, LLC for the debt portion of the funding.
Previous report
The Company's Phase 1 equity partners each have options to invest in Train 4 equity which, if exercised, would provide 60% of the equity funding required for Train 4. The Company expects the Phase 1 equity partners to exercise their options to participate in Train 4 equity.
Previous report
NextDecade currently expects to fund 40% of the equity commitments for Train 4, and to have an initial economic interest of 40% in Train 4, which will increase to 60% after its equity partners achieve certain returns on their investments in Train 4. The Company is in the process of financing its equity capital for Train 4.
Previous report
The Company expects to achieve a positive FID on Train 4 by mid-September 2025, subject to obtaining adequate financing.
Previous report
Final Investment Decision on Train 5
Previous report
The Company is also progressing Train 5 toward FID, and the commercialization process is underway for Train 5. In May 2025, the Company announced a 20-year LNG SPA with JERA for 2.0 MTPA of LNG in support of Train 5. The Company is targeting an additional 2.5 MTPA of long-term contracts to support a positive FID of Train 5.
Previous report
In June 2025, the Company finalized an EPC contract with Bechtel for Train 5 and related infrastructure. Pricing validity under the EPC contract for Train 5 extends through September 15, 2025.
Previous report
The Company began the financing process for Train 5 in the second quarter of 2025 and expects to finance construction of Train 5 using a combination of debt and equity funding at the project level. The Company expects to enter into bank facilities at Rio Grande LNG Train 5, LLC for the debt portion of the funding. Certain of the Company’s Phase 1 equity partners have options to invest in Train 5 equity, which if exercised, would provide 50% of the equity funding required for Train 5. Inclusive of these options, NextDecade currently expects to fund the balance of the equity commitments for Train 5, and to have an initial economic interest of up to 50% in Train 5, which will increase to up to 70% after its equity partners achieve certain returns on their investments in Train 5.
Previous report
The Company continues to pursue financing for Train 5 and, subject to obtaining appropriate commercial support and financing, is targeting FID by mid-September 2025.
Previous report
Prior to the FID on Phase 1 of the Rio Grande LNG Facility, our primary cash needs historically were funding development activities in support of the Rio Grande LNG Facility and our CCS projects, which included payments of initial direct costs of the Rio Grande site lease and expenses in support of engineering and design activities, regulatory approvals and compliance, commercial and marketing activities and corporate overhead. Following the FID on Phase 1 of the Rio Grande LNG Facility, costs associated with the Phase 1 EPC agreements, Rio Grande site lease, and other Phase 1 related costs are being funded by debt and equity proceeds received by Rio Grande.
Previous report
Our current capital resources consist of approximately $158.5 million of cash and cash equivalents as of June 30, 2025.
Previous report
•Unrealized derivative gains decreased by approximately $83.9 million, primarily reflecting lower forward SOFR rates.
Previous report
•Unrealized derivative gains decreased by approximately $511.5 million, primarily reflecting lower forward SOFR rates.
Previous report
•Due to the above changes, net income attributable to non-controlling interest during the six months ended June 30, 2025 decreased approximately $359.5 million as those activities are a component of Intermediate Holdings net income and loss.
Reworded paragraphs (55)
Previous wording
•the timing and cost of the development, construction and operation of the first three liquefaction trains and related common facilities (“Phase 1”) of the multi-plant integrated natural gas and liquefaction and LNG export terminal facility to be located at the Port of Brownsville in southern Texas (the “Rio Grande LNG Facility”);
Current wording
•the timing and cost of the development, construction and operation of the first five liquefaction trains and related common facilities of the multi-plant integrated natural gas and liquefaction and LNG export terminal facility to be located at the Port of Brownsville in southern Texas (the “Rio Grande LNG Facility”);
Previous wording
•the availability and frequency of cash distributions available to us from our joint venture which owns Phase 1 of the Rio Grande LNG Facility;
Current wording
•the availability and frequency of cash distributions available to us from our joint ventures which own the first three trains and related common facilities ("Phase 1"), the fourth liquefaction train and related common facilities ("Train 4"), and the fifth liquefaction train and related common facilities ("Train 5") at the Rio Grande LNG Facility, respectively;
Previous wording
•the ability to generate sufficient cash flow to satisfy Rio Grande's significant debt service obligations or to refinance such obligations ahead of their maturity;
Current wording
•the ability to generate sufficient cash flow to satisfy NextDecade's or Rio Grande's significant debt service obligations or to refinance such obligations ahead of their maturity;
Previous wording
•restrictions imposed by NextDecade's or Rio Grande's debt agreements that limit flexibility in operating its business;
Current wording
•restrictions imposed by debt agreements that limit flexibility in operating the Company's business;
Previous wording
•increases in interest rates increasing the cost of servicing Rio Grande's indebtedness;
Current wording
•increases in interest rates that increase the cost of servicing indebtedness;
Previous wording
NextDecade Corporation, a Delaware corporation, is a Houston-based energy company primarily engaged in construction and development activities related to the liquefaction of natural gas and sale of LNG and the capture and storage of CO 2 emissions. We are constructing and developing a natural gas liquefaction and export facility located in the Rio Grande Valley near Brownsville, Texas (the “Rio Grande LNG Facility”). The Rio Grande LNG Facility has received Federal Energy Regulatory Commission ("FERC") approval and Department of Energy ("DOE") FTA and non-FTA authorizations for the construction of up to five liquefaction trains and LNG exports totaling up to 27 million tonnes per annum ("MTPA"). The Rio Grande LNG Facility has three liquefaction trains and related infrastructure ("Phase 1") under construction, Train 4 has been commercialized and is being progressed toward a final investment decision ("FID"), and Train 5 is being commercialized and progressed toward FID. We are also developing and beginning the permitting process for expansion Trains 6 through 8 at the Rio Grande LNG Facility and developing a potential carbon capture and storage ("CCS") project at the Rio Grande LNG Facility.
Current wording
NextDecade Corporation, a Delaware corporation, is a Houston-based energy company primarily engaged in construction and development activities related to the liquefaction of natural gas and sale of LNG. We are constructing and developing a natural gas liquefaction and export facility located in the Rio Grande Valley near Brownsville, Texas (the “Rio Grande LNG Facility”). The first five liquefaction trains and related infrastructure (together, Phase 1, Train 4, and Train 5) at the Rio Grande LNG Facility are currently under construction. We are also developing and advancing the permitting process for expansion Trains 6 through 8 and exploring a potential carbon capture and storage ("CCS") project at the Rio Grande LNG Facility.
Previous wording
We are focused on constructing and operating the Rio Grande LNG Facility safely, efficiently, on schedule, and on budget. We seek to deliver secure, economically attractive, and sustainable energy solutions through the development and operation of liquefaction and CCS infrastructure.
Current wording
We are focused on constructing and operating the Rio Grande LNG Facility safely, efficiently, on schedule, and on budget. We seek to deliver secure, affordable, and cleaner energy through the development and operation of liquefaction capacity at the Rio Grande LNG Facility.
Previous wording
Unless the context requires otherwise, references to “NextDecade,” “the Company,” “we,” “us,” and “our” refer to NextDecade Corporation and its consolidated subsidiaries, and references to “Rio Grande” refer to Rio Grande LNG, LLC and its subsidiaries.
Current wording
Unless the context requires otherwise, references to “NextDecade,” “the Company,” “we,” “us,” and “our” refer to NextDecade Corporation and its consolidated subsidiaries, references to “Phase 1 LLC” refer to Rio Grande LNG, LLC, references to "Train 4 LLC" refer to Rio Grande LNG Train 4, LLC, and references to "Train 5 LLC" refer to Rio Grande LNG Train 5, LLC.
Previous wording
•Under the engineering, procurement, and construction (“EPC”) contracts with Bechtel Energy, Inc. (“Bechtel”), Phase 1 progress is tracked for Train 1, Train 2, and the common facilities on a combined basis and Train 3 on a separate basis. As of June 2025:
Current wording
•Under the engineering, procurement, and construction (“EPC”) contracts with Bechtel Energy, Inc. (“Bechtel”), as of September 2025:
Previous wording
•The overall project completion percentage for Trains 1 and 2 and the common facilities of the Rio Grande LNG Facility was 48.3%, which is in line with the schedule under the EPC contract. Within this project completion percentage, engineering was 91.9% complete, procurement was 80.6% complete, and construction was 21.2% complete.
Current wording
•The overall project completion percentage for Trains 1 and 2 and the common facilities at the Rio Grande LNG Facility was 55.9%. Within this project completion percentage, engineering was 95.0% complete, procurement was 88.8% complete, and construction was 29.8% complete.
Previous wording
•The overall project completion percentage for Train 3 of the Rio Grande LNG Facility was 22.7%, which is also in line with the schedule under the EPC contract. Within this project completion percentage, engineering was 55.7% complete, procurement was 45.5% complete, and construction was 2.2% complete.
Current wording
•The overall project completion percentage for Train 3 at the Rio Grande LNG Facility was 33.4%. Within this project completion percentage, engineering was 70.8% complete, procurement was 67.2% complete, and construction was 4.5% complete.
Previous wording
•In February 2025, the Company provided additional information regarding its development of additional liquefaction capacity at the Rio Grande LNG Facility beyond Trains 1 through 5. Trains 6 through 8 are wholly owned by NextDecade and are cumulatively expected to increase the Company's total liquefaction capacity by approximately 18 MTPA once constructed and placed into operation.
Current wording
•In February 2025, we provided additional information regarding its development of additional liquefaction capacity at the Rio Grande LNG Facility beyond Trains 1 through 5. Trains 6 through 8 are currently wholly owned by NextDecade and are cumulatively expected to increase the Company's total liquefaction capacity by approximately 18 million tonnes per annum ("MTPA") once constructed and placed into operation.
Previous wording
◦Train 6, with expected LNG production capacity of approximately 6 MTPA, is being developed inside the existing levee at the site and adjacent to Trains 1 through 5. A pre-filing application with FERC for Train 6 is expected in 2025, and a full FERC application is expected in early 2026.
Current wording
◦Train 6, which has an expected LNG production capacity of approximately 6 MTPA, is being developed inside the existing levee at the site and adjacent to Trains 1 through 5. A pre-filing application with the Federal Energy Regulatory Commission ("FERC") for Train 6 is expected in 2025, and a full FERC application is expected in 2026.
Previous wording
◦The Company is evaluating multiple areas on the site for the development of Trains 7 and 8, with a total expected LNG production capacity of approximately 12 MTPA.
Current wording
◦The Company is evaluating multiple areas on the site for the development of Trains 7 and 8, which have a total expected LNG production capacity of approximately 12 MTPA.
Previous wording
•In April 2025, the Company announced a 20-year LNG Sale and Purchase Agreement (“SPA”) with a subsidiary of Saudi Aramco (“Aramco”), pursuant to which the Aramco subsidiary will purchase 1.2 MTPA of LNG from Train 4 at the Rio Grande LNG Facility for 20 years, on a free on board (“FOB”) basis at a price indexed to Henry Hub, subject to a positive FID on Train 4.
Current wording
•In April 2025, we announced a 20-year LNG Sale and Purchase Agreement (“SPA”) with a subsidiary of Saudi Aramco (“Aramco”), pursuant to which the Aramco subsidiary will purchase 1.2 MTPA of LNG from Train 4 at the Rio Grande LNG Facility for 20 years, on a free on board (“FOB”) basis at a price indexed to Henry Hub.
Previous wording
•In April 2025, the Company announced that TotalEnergies exercised its LNG purchase option with respect to Train 4 and the Company entered into a 20-year LNG SPA with TotalEnergies, pursuant to which TotalEnergies will purchase 1.5 MTPA of LNG from Train 4 at the Rio Grande LNG Facility for 20 years, on an FOB basis at a price indexed to Henry Hub, subject to a positive FID on Train 4. The Company believes sufficient long-term commercial support is now in place to support a positive FID on Train 4.
Current wording
•In April 2025, we announced that TotalEnergies exercised its LNG purchase option with respect to Train 4 and the Company entered into a 20-year LNG SPA with TotalEnergies, pursuant to which TotalEnergies will purchase 1.5 MTPA of LNG from Train 4 at the Rio Grande LNG Facility for 20 years, on an FOB basis at a price indexed to Henry Hub.
Previous wording
•In May 2025, the Company announced a 20-year LNG SPA with JERA, pursuant to which JERA will purchase 2.0 MTPA of LNG from Train 5 at the Rio Grande LNG Facility for 20 years, on an FOB basis at a price indexed to Henry Hub, subject to a positive FID on Train 5.
Current wording
•In May 2025, we announced a 20-year LNG SPA with JERA, pursuant to which JERA will purchase 2.0 MTPA of LNG from Train 5 at the Rio Grande LNG Facility for 20 years, on an FOB basis at a price indexed to Henry Hub.
Previous wording
•In June 2025, the Company finalized a pricing refresh of the Company's lump-sum, turnkey EPC contract with Bechtel for the construction of Train 4 and related infrastructure and executed a lump-sum, turnkey EPC contract with Bechtel for the construction of Train 5 and related infrastructure. Pricing validity under the Train 4 and Train 5 EPC contracts extends through September 15, 2025.
Current wording
•In June 2025, we finalized a pricing refresh of the Company's lump-sum, turnkey EPC contract with Bechtel for the construction of Train 4 and related infrastructure and executed a lump-sum, turnkey EPC contract with Bechtel for the construction of Train 5 and related infrastructure.
Previous wording
•In April 2025, Rio Grande LNG, LLC (“Rio Grande”) elected to terminate $250 million of commitments under its working capital facility due to a decrease in expected requirements for credit support during construction, which reduced the outstanding commitments under the working capital facility to $250 million and is expected to reduce related commitment fees by approximately $2 million annually.
Current wording
•In April 2025, Phase 1 LLC elected to terminate $250 million of commitments under its working capital facility due to a decrease in expected requirements for credit support during construction, which reduced the outstanding commitments under the working capital facility to $250 million and is expected to reduce related commitment fees by approximately $2 million annually.
Previous wording
•In May 2025, the Company’s wholly-owned subsidiary Rio Grande LNG Super Holdings, LLC, entered into an amended credit agreement with the lender of its existing senior secured loan to increase the loan amount by $50 million to a total of $225 million initial principal. Incremental proceeds from the senior secured loan were disbursed at closing on May 14, 2025, and net proceeds will be used to fund working capital and general corporate purposes, including development expenses for expansion trains at the Rio Grande LNG Facility and specifically pre-FID expenses for Trains 4 and 5. Borrowings under the senior secured loan bear interest at 12.0%, with interest payable quarterly. Interest may be paid in-kind until March 31, 2027 and up to 50% in-kind thereafter. The senior secured loan matures December 31, 2030.
Current wording
•In May 2025, our wholly-owned subsidiary Rio Grande LNG Super Holdings, LLC, entered into an amendment to the credit agreement with the lender of its existing senior secured loan (the "Super Holdings Loan") to increase the loan amount by $50 million to a total of $225 million initial principal. Incremental proceeds from the Super Holdings Loan were disbursed at closing on May 14, 2025, and net proceeds can be used to fund working capital and general corporate purposes, including development expenses for expansion trains at the Rio Grande LNG Facility and specifically pre-FID expenses for Trains 4 and 5. Borrowings under the Super Holdings Loan bear interest at 12.0%, with interest payable quarterly. Interest may be paid in-kind until March 31, 2027 and up to 50% in-kind thereafter. The Super Holdings Loan matures December 31, 2030.
Previous wording
•In conjunction with the closing of the May 2025 amendment to the senior secured loan, the Company issued warrants that are exercisable for an aggregate of approximately 2.0 million shares of NextDecade common stock to the lender of the senior secured loan. The warrants are exercisable for five years after the amendment date. The warrants are exercisable at $9.30 per share, which represented a 30% premium to the volume weighted average price for the 30 trading-day period immediately preceding the amendment date.
Current wording
•In conjunction with the closing of the May 2025 amendment to the Super Holdings Loan, we issued warrants that are exercisable for an aggregate of approximately 2.0 million shares of our common stock to the lender of the Super Holdings Loan. The warrants are exercisable for five years after the amendment date at $9.30 per share, which represented a 30% premium to the volume weighted average price for the 30 trading-day period immediately preceding the amendment date.
Previous wording
•In March 2025, the U.S. Court of Appeals for the D.C. Circuit (the “D.C. Circuit Court”) issued a revision to its August 2024 decision regarding the Company's FERC order, resulting in a remand without vacatur of the FERC order for the first five liquefaction trains at the Rio Grande LNG Facility. Pursuant to the remand, FERC is to consider the issue of a supplemental Environmental Impact Statement (“SEIS”) in view of several executive orders issued since January 20, 2025.
Current wording
•In March 2025, the U.S. Court of Appeals for the D.C. Circuit (the “D.C. Circuit Court”) issued a revision to its August 2024 decision regarding the Company's FERC order, resulting in a remand without vacatur of the FERC order for the first five liquefaction trains at the Rio Grande LNG Facility. Pursuant to the remand, FERC was to consider the issue of a supplemental Environmental Impact Statement (“SEIS”) in view of several executive orders issued since January 20, 2025.
Previous wording
•In July 2025, the FERC issued a final SEIS for the first five liquefaction trains at the Rio Grande LNG Facility. Based on its published schedule, FERC anticipates issuing a final order on the remand by November 20, 2025.
Current wording
•In July 2025, the FERC issued a final SEIS for the first five liquefaction trains at the Rio Grande LNG Facility, following a draft SEIS in March 2025.
Previous wording
Phase 1 Overview and Construction Progress
Current wording
Liquefaction Facilities Overview and Construction Progress
Previous wording
We are constructing and developing the Rio Grande LNG Facility on the north shore of the Brownsville Ship Channel in south Texas. The site is located on approximately 1,000 acres of land, which has been leased long-term and includes 15,000 feet of frontage on the Brownsville Ship Channel. We believe the site is advantaged due to its proximity to abundant natural gas resources in the Permian Basin and Eagle Ford Shale, access to an uncongested waterway for vessel loading, and location in a region that has historically been subject to fewer and less severe weather events relative to other locations along the U.S. Gulf Coast. The Rio Grande LNG Facility has been permitted by the FERC and authorized by the DOE to export up to 27 MTPA of LNG from up to five liquefaction trains. Phase 1 at the Rio Grande LNG Facility is under construction, Train 4 has been commercialized and is being progressed toward FID, Train 5 is being commercialized and progressed toward FID, and we are developing and beginning the permitting process for Trains 6 through 8.
Current wording
We are constructing and developing the Rio Grande LNG Facility on the north shore of the Brownsville Ship Channel in south Texas. The site is located on approximately 1,000 acres of land, which has been leased long-term and includes 15,000 feet of frontage on the Brownsville Ship Channel. We believe the site is advantaged due to its proximity to abundant natural gas resources in the Permian
Previous wording
In July 2023, construction commenced on Phase 1 of the Rio Grande LNG Facility following a positive FID and the closing of project financing by Rio Grande, which owns Phase 1 of the Rio Grande LNG Facility. Construction will be completed by Bechtel under fully wrapped, lump-sum turnkey EPC contracts, and the liquefaction trains will utilize Honeywell liquefaction technology, which is the predominant liquefaction technology utilized globally.
Current wording
Construction commenced on Phase 1 at the Rio Grande LNG Facility in July 2023, on Train 4 in September 2025, and on Train 5 in October 2025, in each case following a positive FID and the closing of project financing by the Company's subsidiaries. Construction will be completed by Bechtel under fully wrapped, lump-sum turnkey EPC contracts, and the liquefaction trains will utilize Honeywell AP-C3MRTM liquefaction technology, which is the predominant liquefaction technology utilized globally.
Previous wording
Phase 1 includes three liquefaction trains with a total expected LNG production capacity of approximately 18 MTPA, two 180,000 cubic meter full containment LNG storage tanks, two jetty berthing structures designed to load LNG carriers up to 216,000 cubic meters in capacity, and associated site infrastructure and common facilities including feed gas pretreatment facilities, electric and water utilities, two totally enclosed ground flares for the LNG tanks and marine facilities, two ground flares for the liquefaction trains, roads, levees surrounding the entire site, and warehouses, administrative, operations control room and maintenance buildings.
Current wording
The combined scope of Phase 1, Train 4, and Train 5 includes five liquefaction trains with a total expected LNG production capacity of approximately 30 MTPA, four 180,000 cubic meter full containment LNG storage tanks, two jetty berthing structures designed to load LNG carriers up to 216,000 cubic meters in capacity, and associated site infrastructure and common facilities including feed gas pretreatment facilities, electric and water utilities, ground flares, roads, levees surrounding the entire site, and warehouses, administrative, operations control room and maintenance buildings.
Previous wording
As of June 2025, progress on Trains 1 through 3 is in line with the schedule under the EPC contracts. During the second quarter 2025, the construction team continued piping fabrication, rebar installation, equipment setting and concrete placement, and structural steel erection in the areas of Trains 1, 2, and 3. The eighth wall lift was completed for Tank 1.
Current wording
As of September 2025, progress on Phase 1 is ahead of schedule under the EPC contracts. During the third quarter of 2025, the construction team continued piping fabrication, rebar installation, equipment setting and concrete placement, and structural steel erection in the areas of Trains 1, 2, and 3. Roof raises were completed for the first two LNG storage tanks. Across the site, Bechtel also continued installing concrete foundations, instrument air receivers, floodgates, permanent fencing, temporary facilities, and other siteworks. In September 2025, the first compressor string and turbine for Train 1 arrived onsite.
Previous wording
Phase 1 LNG Sale and Purchase Agreements
Current wording
LNG Sale and Purchase Agreements for Trains 1 Through 5
Previous wording
For Phase 1 of the Rio Grande LNG Facility, Rio Grande has entered into long-term LNG SPAs with nine creditworthy counterparties for aggregate volumes of approximately 16.2 MTPA of LNG. The SPAs have a weighted average term of 19.2 years. Under these SPAs, the customers will purchase LNG from Rio Grande for a price consisting of a fixed fee per MMBtu of LNG plus a variable fee per MMBtu of LNG, with the variable fees structured to cover the expected cost of natural gas plus fuel and other sourcing costs to produce LNG. In certain circumstances, customers may elect to cancel or suspend deliveries of LNG cargoes, in which case the customers would still be required to pay the fixed fee with respect to cargoes that are not delivered. A portion of the fixed fee under each SPA will be subject to annual adjustment for inflation. The SPAs and contracted volumes to be made available under the SPAs are not tied to a specific train; however, the commencement of the term of each SPA is tied to a specified train.
Current wording
We have entered into long-term SPAs with 14 creditworthy counterparties for aggregate volumes of approximately 25.3 MTPA of LNG from Trains 1 through 5 at the Rio Grande LNG Facility. The SPAs have a weighted average term of 19.5 years. Under these SPAs, the customers will purchase LNG from the Rio Grande LNG Facility for a price consisting of a fixed fee per MMBtu of LNG plus a variable fee per MMBtu of LNG, with the variable fees structured to cover the expected cost of natural gas plus fuel and other sourcing costs to produce LNG. In certain circumstances, customers may elect to cancel or suspend deliveries of LNG cargoes, in which case the customers would still be required to pay the fixed fee with respect to cargoes that are not delivered. A portion of the fixed fee under each SPA will be subject to annual adjustment for inflation. The SPAs and contracted volumes to be made available under the SPAs are not tied to a specific train; however, the commencement of the term of each SPA is tied to a specified train.
Previous wording
Each of these SPAs is currently effective, and deliveries of LNG under these SPAs will commence on the respective Date of First Commercial Delivery (“DFCD”), which is primarily tied to the substantial completion or guaranteed substantial completion dates of specific trains as defined in each SPA. In aggregate, approximately 14.65 MTPA of Phase 1 Henry Hub-linked SPAs have average fixed fees, unadjusted for inflation, totaling approximately $1.8 billion expected to be paid annually.
Current wording
Each of these SPAs is currently effective, and deliveries of LNG under these SPAs will commence on the respective Date of First Commercial Delivery (“DFCD”), which is primarily tied to the substantial completion or guaranteed substantial completion dates of specific trains as defined in each SPA. In aggregate, the approximately 23.75 MTPA of Henry Hub-linked SPAs for Trains 1 through 5 have average fixed fees, unadjusted for inflation, totaling approximately $3.0 billion expected to be paid annually.
Previous wording
Rio Grande expects to sell any commissioning LNG volumes and operational LNG volumes in excess of SPA volumes into the LNG market through spot, short-term, and medium-term agreements. Rio Grande has entered into certain time charter agreements and expects to enter into additional time charter agreements with vessel owners to provide shipping capacity for LNG sales related to its existing Phase 1 delivered ex-ship SPA, commissioning volumes, and expected portfolio volumes.
Current wording
We expect to sell any commissioning LNG volumes and operational LNG volumes in excess of SPA volumes into the LNG market through spot, short-term, and medium-term agreements. We have entered into certain time charter agreements and expect to enter into additional time charter agreements with vessel owners to provide shipping capacity for LNG sales related to our 1.0 MTPA delivered ex-ship SPA, expected commissioning volumes, and expected portfolio volumes.
Previous wording
The Company has entered into fully wrapped, lump-sum turnkey contracts with Bechtel, a well-established and reputable LNG engineering and construction firm, for the engineering, procurement, and construction of Phase 1, Train 4, and Train 5 at the Rio Grande LNG Facility, under which Bechtel has generally guaranteed cost, performance, and schedule. Under these EPC contracts, Bechtel is responsible for the engineering, procurement, construction, commissioning, and startup of liquefaction trains and their respective related infrastructure.
Current wording
We have entered into fully wrapped, lump-sum turnkey contracts with Bechtel, a well-established and reputable LNG engineering and construction firm, for the engineering, procurement, and construction of Phase 1, Train 4, and Train 5 at the Rio Grande LNG Facility, under which Bechtel has generally guaranteed cost, performance, and schedule. Under these EPC contracts, Bechtel is responsible for the engineering, procurement, construction, commissioning, and startup of liquefaction trains and their respective related infrastructure.
Previous wording
On July 12, 2023, Rio Grande issued final notice to proceed to Bechtel under the EPC contracts for Phase 1. Total expected capital costs for Phase 1 are estimated to be approximately $18.0 billion, including estimated EPC costs, owner’s costs, contingencies, and financing costs, and including amounts spent prior to FID under limited notices to proceed.
Current wording
On July 12, 2023, we issued final notice to proceed to Bechtel under the EPC contracts for Phase 1. Total expected capital costs for Phase 1 are estimated to be approximately $18.0 billion, including estimated EPC costs, owner’s costs, contingencies, and financing costs, and including amounts spent prior to FID under limited notices to proceed.
Previous wording
Pursuant to a joint venture agreement with equity partners for ownership of Rio Grande, we expect to receive up to approximately 20.8% of distributions of available cash generated from Phase 1 operations, provided that a majority of the cash distributions to which we are otherwise entitled will be paid for any distribution period only after our equity partners receive an agreed distribution threshold in respect of such distribution period and certain other deficit payments from prior distribution periods, if any, are made.
Current wording
Pursuant to a joint venture agreement with equity partners for ownership of Phase 1 at the Rio Grande LNG Facility, we expect to receive up to approximately 20.8% of distributions of available cash generated from Phase 1 operations, provided that a majority of the cash distributions to which we are otherwise entitled will be paid for any distribution period only after our equity partners receive an agreed distribution threshold in respect of such distribution period and certain other deficit payments from prior distribution periods, if any, are made.
Previous wording
The Company is developing and beginning the permitting process for additional liquefaction capacity at the Rio Grande LNG Facility site beyond Trains 1 through 5. Trains 6 through 8 are wholly owned by NextDecade and are cumulatively expected to increase the Company's total liquefaction capacity by approximately 18 MTPA once constructed and placed into operation.
Current wording
We are developing and advancing the permitting process for additional liquefaction capacity at the Rio Grande LNG Facility site. Trains 6 through 8 are currently wholly owned by NextDecade and are cumulatively expected to increase the Company's total liquefaction capacity by approximately 18 MTPA once constructed and placed into operation.
Previous wording
Train 6 is being developed inside the existing levee at the Rio Grande LNG Facility site and adjacent to Trains 1 through 5. The Company expects to pre-file an application with FERC for Train 6 in 2025 and a full application with FERC in early 2026. The Company is evaluating multiple areas on the site for the development of Trains 7 and 8 and expects to provide an update on the expected permitting timeline for Trains 7 and 8 in 2025.
Current wording
Train 6 is being developed inside the existing levee at the Rio Grande LNG Facility site and adjacent to Trains 1 through 5. The Company expects to pre-file an application with FERC for Train 6 in 2025 and a full application with FERC in 2026. The Company is evaluating multiple areas on the site for the development of Trains 7 and 8.
Previous wording
We have obtained all major permits required to build and export LNG from the first five liquefaction trains and related infrastructure at the Rio Grande Facility, including FERC approval and DOE FTA and non-FTA authorizations for the construction of up to five liquefaction trains and LNG exports totaling up to 27 MTPA.
Current wording
We have obtained all major permits required to build and export LNG from the first five liquefaction trains and related infrastructure at the Rio Grande Facility, including FERC approval and Department of Energy FTA and non-FTA authorizations.
Previous wording
In March 2025, the D.C. Circuit Court issued a revision to its August 2024 decision regarding our FERC order, resulting in a remand without vacatur of the FERC order for the first five liquefaction trains at the Rio Grande LNG Facility. Pursuant to the remand, FERC is to consider the issue of a supplemental Environmental Impact Statement (“SEIS”) in view of several executive orders issued since January 20, 2025.
Current wording
In March 2025, the D.C. Circuit Court issued a revision to its August 2024 decision regarding our FERC order, resulting in a remand without vacatur of the FERC order for the first five liquefaction trains at the Rio Grande LNG Facility. Pursuant to the remand, FERC was to consider the issue of a supplemental Environmental Impact Statement (“SEIS”) in view of several executive orders issued since January 20, 2025.
Previous wording
In March 2025, the FERC issued a draft SEIS for the first five liquefaction trains at the Rio Grande LNG Facility, providing for a public comment period that ended on May 19, 2025. In July 2025, the FERC issued a final SEIS for the first five liquefaction trains at the Rio Grande LNG Facility. Based on its published schedule, FERC anticipates issuing a final order on the remand by November 20, 2025.
Current wording
In March 2025, the FERC issued a draft SEIS for the first five liquefaction trains at the Rio Grande LNG Facility. In July 2025, the FERC issued a final SEIS for the first five liquefaction trains at the Rio Grande LNG Facility. In August 2025, the FERC issued a final order on remand reaffirming its authorization for the siting, construction, and operation of the first five liquefaction trains at the Rio Grande LNG Facility. In September 2025, a request for rehearing of the Remand Order was filed by certain intervenors and on October 30, 2025, the rehearing request was deemed denied by operation of law, rendering the Remand Order no longer appealable to FERC.
Showing the first 40 of 55 pairs. Open the source sections for the rest.
Rearranged current paragraphs (1)
Current report — wording carried from elsewhere
Basin and Eagle Ford Shale, access to an uncongested waterway for vessel loading, and location in a region that has historically been subject to fewer and less severe weather events relative to other locations along the U.S. Gulf Coast. Trains 1 through 5 at the Rio Grande LNG Facility are under construction, and we are developing and advancing the permitting process for Trains 6 through 8. There is sufficient space at the Rio Grande LNG Facility site for up to 10 liquefaction trains.
Rearranged previous paragraphs (2)
Previous report — wording carried elsewhere
Across the site, Bechtel also continued installing concrete foundations, instrument air receivers, floodgates, permanent fencing, temporary facilities, and other siteworks.
Previous report — wording carried elsewhere
•Loss on debt extinguishment decreased approximately $31.0 million due to the lack of debt repayments during the current period.