NextDecade Corp

For the period ended Jun 30, 2025. Filed Aug 1, 2025.

View on SEC.gov

About this filing

A company's report for each of its first three quarters. The financial statements are not audited. It shows how the business has moved since the last annual report, and what management says changed.

Jun 30, 2025 · Filed Aug 1, 2025

NEXT$5.80-0.9%Stored close · as of Nov 6, 2026

What changed in Management’s Discussion and Analysis?

Read the current filing

Previous report: 10-Q

Period ended 2025-03-31; filed 2025-05-06.

0001628280-25-022731

Item 2. Management’s Discussion and Analysis of Financial Condition and Results of Operations

Current report: 10-Q

Period ended 2025-06-30; filed 2025-08-01.

0001612720-25-000009

Item 2. Management’s Discussion and Analysis of Financial Condition and Results of Operations

The baseline is this issuer’s latest earlier reporting period of the same form that was filed before the current report. A previous 10-Q is a different quarter, not a year-over-year comparison. Amendments are excluded.

Compared 118 previous paragraphs and 137 current paragraphs.

92 unchanged; 20 reworded; 19 added; 6 removed; 0 previous and 6 current paragraphs rearranged.

Tables are not compared: 2 previous and 2 current tables excluded. Dates, whitespace, punctuation and numbering changes are ignored; changes to financial figures remain significant.

A changed paragraph is not evidence that risk increased or decreased. An unchanged paragraph does not establish that risk stayed the same.

Added paragraphs (19)

Current report

•In May 2025, the Company announced a 20-year LNG SPA with JERA, pursuant to which JERA will purchase 2.0 MTPA of LNG from Train 5 at the Rio Grande LNG Facility for 20 years, on an FOB basis at a price indexed to Henry Hub, subject to a positive FID on Train 5.

Current report

•In June 2025, the Company finalized a pricing refresh of the Company's lump-sum, turnkey EPC contract with Bechtel for the construction of Train 4 and related infrastructure and executed a lump-sum, turnkey EPC contract with Bechtel for the construction of Train 5 and related infrastructure. Pricing validity under the Train 4 and Train 5 EPC contracts extends through September 15, 2025.

Current report

•In May 2025, the Company’s wholly-owned subsidiary Rio Grande LNG Super Holdings, LLC, entered into an amended credit agreement with the lender of its existing senior secured loan to increase the loan amount by $50 million to a total of $225 million initial principal. Incremental proceeds from the senior secured loan were disbursed at closing on May 14, 2025, and net proceeds will be used to fund working capital and general corporate purposes, including development expenses for expansion trains at the Rio Grande LNG Facility and specifically pre-FID expenses for Trains 4 and 5. Borrowings under the senior secured loan bear interest at 12.0%, with interest payable quarterly. Interest may be paid in-kind until March 31, 2027 and up to 50% in-kind thereafter. The senior secured loan matures December 31, 2030.

Current report

•In conjunction with the closing of the May 2025 amendment to the senior secured loan, the Company issued warrants that are exercisable for an aggregate of approximately 2.0 million shares of NextDecade common stock to the lender of the senior secured loan. The warrants are exercisable for five years after the amendment date. The warrants are exercisable at $9.30 per share, which represented a 30% premium to the volume weighted average price for the 30 trading-day period immediately preceding the amendment date.

Current report

•In July 2025, the FERC issued a final SEIS for the first five liquefaction trains at the Rio Grande LNG Facility. Based on its published schedule, FERC anticipates issuing a final order on the remand by November 20, 2025.

Current report

As of June 2025, progress on Trains 1 through 3 is in line with the schedule under the EPC contracts. During the second quarter 2025, the construction team continued piping fabrication, rebar installation, equipment setting and concrete placement, and structural steel erection in the areas of Trains 1, 2, and 3. The eighth wall lift was completed for Tank 1.

Current report

Across the site, Bechtel also continued installing concrete foundations, instrument air receivers, floodgates, permanent fencing, temporary facilities, and other siteworks.

Current report

The Company launched the financing process for Train 4 in June 2025 and expects to finance construction of Train 4 using a combination of debt and equity funding at the project level. The Company is in the process of entering into a term loan bank facility at Rio Grande LNG Train 4, LLC for the debt portion of the funding.

Current report

The Company expects to achieve a positive FID on Train 4 by mid-September 2025, subject to obtaining adequate financing.

Current report

The Company is also progressing Train 5 toward FID, and the commercialization process is underway for Train 5. In May 2025, the Company announced a 20-year LNG SPA with JERA for 2.0 MTPA of LNG in support of Train 5. The Company is targeting an additional 2.5 MTPA of long-term contracts to support a positive FID of Train 5.

Current report

In June 2025, the Company finalized an EPC contract with Bechtel for Train 5 and related infrastructure. Pricing validity under the EPC contract for Train 5 extends through September 15, 2025.

Current report

The Company continues to pursue financing for Train 5 and, subject to obtaining appropriate commercial support and financing, is targeting FID by mid-September 2025.

Current report

Cash used in operating activities for the six months ended June 30, 2025 increased by approximately $49.9 million compared to the same period in 2024 primarily due to higher pre-operational expenditures and working capital investments to support the commencement of operations at the Rio Grande LNG Facility.

Current report

•General and administrative expenses increased by approximately $18.1 million, principally reflecting incremental headcount additions to support the commencement of operations at the Rio Grande LNG Facility.

Current report

•Unrealized derivative gains decreased by approximately $83.9 million, primarily reflecting lower forward SOFR rates.

Current report

•Loss on debt extinguishment decreased approximately $31.0 million due to the lack of debt repayments during the current period.

Current report

•General and administrative expenses increased by approximately $30.6 million, principally reflecting incremental headcount additions to support the commencement of operations at the Rio Grande LNG Facility.

Current report

•Unrealized derivative gains decreased by approximately $511.5 million, primarily reflecting lower forward SOFR rates.

Current report

•Loss on debt extinguishment decreased approximately $38.4 million due to the lack of debt repayments during the current period.
Removed paragraphs (6)

Previous report

•In January 2025, the Company requested a pricing refresh under the August 2024 EPC contract with Bechtel for Train 4 and related infrastructure. The pricing refresh is in process and is expected to be completed in the second quarter of 2025.

Previous report

As of March 2025, progress on Trains 1 through 3 is in line with the schedule under the EPC contracts. During the first quarter 2025, the construction team continued steel assembly and progressed above-ground piping and setting of equipment in the Train 1 area. Within Train 2, foundation pours and steel assembly continued to progress. Concrete pours for Tanks 1 and 2 continued. First steel for Train 3 was placed in April 2025. Siteworks were finished for the material offload facility area to support equipment deliveries. Across the site, Bechtel also continued installing undergrounds, structures, loading berths, piling, concrete foundations, and other siteworks.

Previous report

We expect to make a positive FID and commence construction on Trains 4 and 5 and related infrastructure at the Rio Grande LNG Facility, subject to, among other things, entering into EPC contracts, entering into appropriate commercial arrangements, and obtaining adequate financing to construct each train and related infrastructure.

Previous report

The Company expects to launch the financing process for Train 4 in the second quarter of 2025 and expects to make a positive FID on Train 4 after financing arrangements are finalized.

Previous report

The Company is also progressing the development and commercialization of Train 5. TotalEnergies holds an LNG purchase option for 1.5 MTPA for Train 5, and the Rio Grande Phase 1 equity partners have options to invest in Train 5 equity which are identical to their options to participate in Train 4 equity.

Previous report

•Decrease of approximately $427.6 million in unrealized derivative losses primarily due to a decrease in forward SOFR rates
Reworded paragraphs (20)

Previous wording

NextDecade Corporation, a Delaware corporation, is a Houston-based energy company primarily engaged in construction and development activities related to the liquefaction of natural gas and sale of LNG and the capture and storage of CO 2 emissions. We are constructing and developing a natural gas liquefaction and export facility located in the Rio Grande Valley near Brownsville, Texas (the “Rio Grande LNG Facility”). The Rio Grande LNG Facility has received Federal Energy Regulatory Commission ("FERC") approval and Department of Energy ("DOE") FTA and non-FTA authorizations for the construction of up to five liquefaction trains and LNG exports totaling up to 27 million tonnes per annum ("MTPA"). The Rio Grande LNG Facility has three liquefaction trains and related infrastructure ("Phase 1") under construction, Train 4 has been commercialized and is being progressed toward a final investment decision ("FID"), and Train 5 is being commercialized. We are also developing and beginning the permitting process for expansion trains 6 through 8 at the Rio Grande LNG Facility and developing a potential carbon capture and storage ("CCS") project at the Rio Grande LNG Facility.

Current wording

NextDecade Corporation, a Delaware corporation, is a Houston-based energy company primarily engaged in construction and development activities related to the liquefaction of natural gas and sale of LNG and the capture and storage of CO 2 emissions. We are constructing and developing a natural gas liquefaction and export facility located in the Rio Grande Valley near Brownsville, Texas (the “Rio Grande LNG Facility”). The Rio Grande LNG Facility has received Federal Energy Regulatory Commission ("FERC") approval and Department of Energy ("DOE") FTA and non-FTA authorizations for the construction of up to five liquefaction trains and LNG exports totaling up to 27 million tonnes per annum ("MTPA"). The Rio Grande LNG Facility has three liquefaction trains and related infrastructure ("Phase 1") under construction, Train 4 has been commercialized and is being progressed toward a final investment decision ("FID"), and Train 5 is being commercialized and progressed toward FID. We are also developing and beginning the permitting process for expansion Trains 6 through 8 at the Rio Grande LNG Facility and developing a potential carbon capture and storage ("CCS") project at the Rio Grande LNG Facility.

Previous wording

•The overall project completion percentage for Trains 1 and 2 and the common facilities of the Rio Grande LNG Facility was 42.8%, which is in line with the schedule under the EPC contract. Within this project completion percentage, engineering was 87.9% complete, procurement was 76.3% complete, and construction was 14.1% complete.

Current wording

•The overall project completion percentage for Trains 1 and 2 and the common facilities of the Rio Grande LNG Facility was 48.3%, which is in line with the schedule under the EPC contract. Within this project completion percentage, engineering was 91.9% complete, procurement was 80.6% complete, and construction was 21.2% complete.

Previous wording

•The overall project completion percentage for Train 3 of the Rio Grande LNG Facility was 17.8%, which is also in line with the schedule under the EPC contract. Within this project completion percentage, engineering was 41.9% complete, procurement was 37.2% complete, and construction was 0.8% complete.

Current wording

•The overall project completion percentage for Train 3 of the Rio Grande LNG Facility was 22.7%, which is also in line with the schedule under the EPC contract. Within this project completion percentage, engineering was 55.7% complete, procurement was 45.5% complete, and construction was 2.2% complete.

Previous wording

◦Trains 7 and 8, with a total expected LNG production capacity of approximately 12 MTPA, are being developed on the site outside of the existing levee.

Current wording

◦The Company is evaluating multiple areas on the site for the development of Trains 7 and 8, with a total expected LNG production capacity of approximately 12 MTPA.

Previous wording

•In March 2025, the FERC issued a draft SEIS for the first five liquefaction trains at the Rio Grande LNG Facility. A final SEIS is expected in July 2025.

Current wording

•In March 2025, the FERC issued a draft SEIS for the first five liquefaction trains at the Rio Grande LNG Facility, providing for a public comment period that ended on May 19, 2025.

Previous wording

We are constructing and developing the Rio Grande LNG Facility on the north shore of the Brownsville Ship Channel in south Texas. The site is located on 984 acres of land which has been leased long-term and includes 15,000 feet of frontage on the Brownsville Ship Channel. We believe the site is advantaged due to its proximity to abundant natural gas resources in the Permian Basin and Eagle Ford Shale, access to an uncongested waterway for vessel loading, and location in a region that has historically been subject to fewer and less severe weather events relative to other locations along the U.S. Gulf Coast. The Rio Grande LNG Facility has been permitted by the FERC and authorized by the DOE to export up to 27 MTPA of LNG from up to five liquefaction trains. Please see "Significant Recent Developments - Regulatory" for more information regarding our FERC permit. Phase 1 at the Rio Grande LNG Facility is under construction, Train 4 has been commercialized and is being progressed toward FID, Train 5 is being commercialized, and we are developing and beginning the permitting process for Trains 6 through 8.

Current wording

We are constructing and developing the Rio Grande LNG Facility on the north shore of the Brownsville Ship Channel in south Texas. The site is located on approximately 1,000 acres of land, which has been leased long-term and includes 15,000 feet of frontage on the Brownsville Ship Channel. We believe the site is advantaged due to its proximity to abundant natural gas resources in the Permian Basin and Eagle Ford Shale, access to an uncongested waterway for vessel loading, and location in a region that has historically been subject to fewer and less severe weather events relative to other locations along the U.S. Gulf Coast. The Rio Grande LNG Facility has been permitted by the FERC and authorized by the DOE to export up to 27 MTPA of LNG from up to five liquefaction trains. Phase 1 at the Rio Grande LNG Facility is under construction, Train 4 has been commercialized and is being progressed toward FID, Train 5 is being commercialized and progressed toward FID, and we are developing and beginning the permitting process for Trains 6 through 8.

Previous wording

In July 2023, construction commenced on Phase 1 of the Rio Grande LNG Facility following a positive FID and the closing of project financing by Rio Grande, which owns Phase 1 of the Rio Grande LNG Facility. Construction will be completed by Bechtel under fully wrapped, lump-sum turnkey EPC contracts, and the liquefaction trains will utilize Air Products and Chemicals, Inc. (“APCI”) liquefaction technology, which is the predominant liquefaction technology utilized globally.

Current wording

In July 2023, construction commenced on Phase 1 of the Rio Grande LNG Facility following a positive FID and the closing of project financing by Rio Grande, which owns Phase 1 of the Rio Grande LNG Facility. Construction will be completed by Bechtel under fully wrapped, lump-sum turnkey EPC contracts, and the liquefaction trains will utilize Honeywell liquefaction technology, which is the predominant liquefaction technology utilized globally.

Previous wording

Rio Grande entered into fully wrapped, lump-sum turnkey contracts with Bechtel, a well-established and reputable LNG engineering and construction firm, for the engineering, procurement, and construction of Phase 1, and one of our wholly-owned subsidiaries entered into a corresponding contract in regards to Train 4 at the Rio Grande LNG Facility, under which Bechtel has generally guaranteed cost, performance, and schedule. Under the Phase 1 and Train 4 EPC contracts, Bechtel is responsible for the engineering, procurement, construction, commissioning, and startup of liquefaction trains and their respective related infrastructure.

Current wording

The Company has entered into fully wrapped, lump-sum turnkey contracts with Bechtel, a well-established and reputable LNG engineering and construction firm, for the engineering, procurement, and construction of Phase 1, Train 4, and Train 5 at the Rio Grande LNG Facility, under which Bechtel has generally guaranteed cost, performance, and schedule. Under these EPC contracts, Bechtel is responsible for the engineering, procurement, construction, commissioning, and startup of liquefaction trains and their respective related infrastructure.

Previous wording

The Company has finalized 20-year LNG SPAs totaling 4.6 MTPA of LNG with ADNOC, Aramco, and TotalEnergies in support of Train 4, and the Company believes sufficient commercial support is now in place to support a positive FID on Train 4.

Current wording

The Company has completed commercialization of Train 4 and has executed 20-year LNG SPAs totaling 4.6 MTPA of LNG with ADNOC, Aramco, and TotalEnergies in support of Train 4.

Previous wording

The Company has finalized an EPC contract with Bechtel for Train 4 and related infrastructure. In January 2025, the Company requested a pricing refresh under Train 4 EPC contract, which is in process and is expected to be completed in the second quarter of 2025.

Current wording

In June 2025, the Company finalized an EPC contract pricing refresh with Bechtel for Train 4 and related infrastructure. Pricing validity under the EPC contract for Train 4 extends through September 15, 2025.

Previous wording

The Company expects to finance construction of Train 4 utilizing a combination of debt and equity funding. The Company expects to enter into bank facilities for the debt portion of the funding. In connection with consummating the Rio Grande Phase 1 equity joint venture, the Company's equity partners each have options to invest in Train 4 equity, which, if exercised, would provide approximately 60% of the equity funding required for Train 4. Inclusive of these options, NextDecade currently expects to fund 40% of the equity commitments for Train 4, and to have an initial economic interest of 40% in Train 4, increasing to 60% after its equity partners achieve certain returns on their investments in Train 4.

Current wording

The Company began the financing process for Train 5 in the second quarter of 2025 and expects to finance construction of Train 5 using a combination of debt and equity funding at the project level. The Company expects to enter into bank facilities at Rio Grande LNG Train 5, LLC for the debt portion of the funding. Certain of the Company’s Phase 1 equity partners have options to invest in Train 5 equity, which if exercised, would provide 50% of the equity funding required for Train 5. Inclusive of these options, NextDecade currently expects to fund the balance of the equity commitments for Train 5, and to have an initial economic interest of up to 50% in Train 5, which will increase to up to 70% after its equity partners achieve certain returns on their investments in Train 5.

Previous wording

Train 6 is being developed inside the existing levee at the Rio Grande LNG Facility site and adjacent to Trains 1 through 5. The Company expects to pre-file an application with FERC for Train 6 in 2025 and a full application with FERC in early 2026. Trains 7 and 8 are being developed on the site outside of the existing levee.

Current wording

Train 6 is being developed inside the existing levee at the Rio Grande LNG Facility site and adjacent to Trains 1 through 5. The Company expects to pre-file an application with FERC for Train 6 in 2025 and a full application with FERC in early 2026. The Company is evaluating multiple areas on the site for the development of Trains 7 and 8 and expects to provide an update on the expected permitting timeline for Trains 7 and 8 in 2025.

Previous wording

In March 2025, the FERC issued a draft SEIS for the first five liquefaction trains at the Rio Grande LNG Facility. A final SEIS is expected in July 2025.

Current wording

In March 2025, the FERC issued a draft SEIS for the first five liquefaction trains at the Rio Grande LNG Facility, providing for a public comment period that ended on May 19, 2025. In July 2025, the FERC issued a final SEIS for the first five liquefaction trains at the Rio Grande LNG Facility. Based on its published schedule, FERC anticipates issuing a final order on the remand by November 20, 2025.

Previous wording

In connection with the FID on Phase 1 of the Rio Grande LNG Facility, Rio Grande obtained approximately $6.2 billion in equity capital commitments, inclusive of commitments from the NextDecade Member, entered into senior secured non-recourse bank credit facilities of $11.6 billion, consisting of $11.1 billion in construction term loans and a $500 million working capital facility, and closed a $700 million senior secured non-recourse private notes offering. Rio Grande expects to utilize these capital resources to fund the total cost of Phase 1, which is currently estimated at $18.0 billion and consists of EPC costs, owner’s costs and contingencies, dredging for the Brazos Island Harbor Channel Improvement Project, conservation of more than 4,000 acres of wetland and wildlife habitat area and installation of utilities, and interest during construction and other financing costs.

Current wording

In connection with the FID on Phase 1 of the Rio Grande LNG Facility, Rio Grande obtained approximately $6.2 billion in equity capital commitments, inclusive of commitments from NextDecade, entered into senior secured non-recourse bank credit facilities of $11.6 billion, consisting of $11.1 billion in construction term loans and a $500 million working capital facility, and closed a $700 million senior secured non-recourse private notes offering. Rio Grande expects to utilize these capital resources to fund the total cost of Phase 1, which is currently estimated at $18.0 billion and consists of EPC costs, owner’s costs and contingencies, dredging for the Brazos Island Harbor Channel Improvement Project, conservation of more than 4,000 acres of wetland and wildlife habitat area and installation of utilities, and interest during construction and other financing costs. Rio Grande has refinanced a total of over $1.85 billion of the original $11.1 billion Rio Grande term loan facilities into senior secured notes and loans since July 2023.

Previous wording

Our current capital resources consist of approximately $130.9 million of cash and cash equivalents as of March 31, 2025.

Current wording

Our current capital resources consist of approximately $158.5 million of cash and cash equivalents as of June 30, 2025.

Previous wording

Cash used in operating activities for the three months ended March 31, 2025 increased by approximately $40.0 million compared to the same period in 2024 primarily due to the timing of required interest payments.

Current wording

Cash used in investing activities for the six months ended June 30, 2025 increased by approximately $157.0 million compared to the same period in 2024 primarily due to increased expenditures associated with the Rio Grande LNG Facility.

Previous wording

Cash provided by financing activities for the three months ended March 31, 2025 increased by approximately $75.2 million compared to the same period in 2024 primarily due to debt repayments of $176.0 million associated with refinancing activity during the prior period partially offset by a decrease in debt proceeds of approximately $123.9 million.

Current wording

Cash provided by financing activities for the six months ended June 30, 2025 increased by approximately $362.6 million compared to the same period in 2024. This was driven by an increase of approximately $79.3 million uptick in equity commitment receipts and the absence of approximately $1.3 billion of debt repayments in the current period. These increases were partially offset by a $1.0 billion reduction in debt proceeds.

Previous wording

Net loss attributable to common stockholders was approximately $88.8 million, for the three months ended March 31, 2025 compared to net income of $28.3 million during the same period in 2024. The $117.2 million decrease was primarily a result of the following:

Current wording

Net loss attributable to common stockholders was approximately $60.9 million, for the three months ended June 30, 2025 compared to net loss of $32.6 million during the same period in 2024. The $28.3 million increase was primarily a result of the following:

Previous wording

•Due to the changes in derivatives losses, net income attributable to non-controlling interest during the three months ended March 31, 2025 decreased approximately $314.9 million as those activities are a component of Intermediate Holdings net income and loss.

Current wording

•Due to the above changes, net income attributable to non-controlling interest during the three months ended June 30, 2025 decreased approximately $44.6 million as those activities are a component of Intermediate Holdings net income and loss.
Rearranged current paragraphs (6)

Current report — wording carried from elsewhere

The Company's Phase 1 equity partners each have options to invest in Train 4 equity which, if exercised, would provide 60% of the equity funding required for Train 4. The Company expects the Phase 1 equity partners to exercise their options to participate in Train 4 equity.

Current report — wording carried from elsewhere

NextDecade currently expects to fund 40% of the equity commitments for Train 4, and to have an initial economic interest of 40% in Train 4, which will increase to 60% after its equity partners achieve certain returns on their investments in Train 4. The Company is in the process of financing its equity capital for Train 4.

Current report — wording carried from elsewhere

Final Investment Decision on Train 5

Current report — wording carried from elsewhere

In April 2025, Rio Grande elected to terminate $250 million of commitments under its working capital facility due to a decrease in expected requirements for credit support during construction, which reduced the outstanding commitments under the working capital facility to $250 million.

Current report — wording carried from elsewhere

Net loss attributable to common stockholders was approximately $149.7 million, for the six months ended June 30, 2025 compared to net loss of $4.2 million during the same period in 2024. The $145.4 million increase was primarily a result of the following:

Current report — wording carried from elsewhere

•Due to the above changes, net income attributable to non-controlling interest during the six months ended June 30, 2025 decreased approximately $359.5 million as those activities are a component of Intermediate Holdings net income and loss.