Nouveau Monde Graphite Inc.

For the period ended Dec 31, 2024. Filed Mar 31, 2025.

View on SEC.gov

About this filing

The yearly report of certain Canadian companies, filed under a joint US and Canadian system. It is the main yearly account these companies give US investors, largely as filed in Canada.

FY2024 · Filed Mar 31, 2025

Use the contents to explore the available documents and sections.

NMG$0.84+3.9%Stored close · as of Nov 6, 2026
See the whole filing, with its images and exhibits
Contents

EX-99.3 · Projects Overview

Projects Overview

​
Matawinie Mine Project
To support the development of the Matawinie Mine, NMG plans to continue optimizing its processes, products, and operational practices to align with the technical requirements of its Anchor Customers using its Phase-1 demonstration plant; advance detailed engineering, construction planning, and procurement activities; and finalize the project financing with the various financial stakeholders engaged in the project to reach FID and launch construction of the Phase 2. A positive FID is dependent on the financing structure in light of the Updated Feasibility Study, updated financial model, the conclusions of the due diligence processes and negotiations with the various financial stakeholders, including the completion of the conditions precedent and the project-related agreements with the Anchor Customers.
Phase 1 – Matawinie Mine Demonstration Plant
​Concentrator Demonstration PlantIn operation to support product sampling and qualification to customers’ specifications.
Phase 2 – Matawinie MineMining decree obtained.Some groundworks completed; concrete-ready in preparation for launch of construction upon a positive FID. Completion and issuance of the Updated Feasibility Study reflecting advancement in engineering, technological development, project optimizations, and the financial model.Detailed engineering, construction planning, and procurement strategy advancing in parallel to project financing.
​​
Management Discussion and Analysis8
Bécancour Battery Material Plant Project
To support the development of the Bécancour Battery Material Plant, NMG plans to continue optimizing its processes, products, and operational practices to align with the technical requirements of its Anchor Customers using its Phase-1 demonstration plants; refine environmental performance and operational parameters of the chemical purification technology; advance detailed engineering, construction planning, and procurement activities; and finalize the project financing with the various financial stakeholders engaged in the project to reach FID and launch construction of the Phase 2. A positive FID is dependent on the financing structure in light of the Updated Feasibility Study, updated financial model, the conclusions of the due diligence processes and negotiations with the various financial stakeholders, including the completion of the conditions precedent and the project-related agreements with the Anchor Customers.
Phase 1 – Battery Material Demonstration Plants
​Shaping Demonstration PlantIn operation to support product sampling and qualification.
​Purification Demonstration PlantTests completed at facility in light of technology change. ​
​Coating Demonstration PlantIn operation to support product sampling and qualification.
Phase 2 – Bécancour Battery Material PlantCompletion and issuance of the Updated Feasibility Study reflecting advancement in engineering, technological development, project optimizations, and the financial model.Preliminary works initiated at the site. Engineering, construction planning, and procurement strategy advancing diligently in parallel to project financing.
Uatnan Mining Project
To support the advancement of the Uatnan Mining Project, NMG plans to continue engaging with the Innu First Nation of Pessamit to establish a collaboration model in view of advancing a feasibility study along with an environmental and social impact assessment. Additional funding will be required to support this development. The Company also aims at formalizing commercial engagement for this contemplated production.The development of the project leading to governmental authorizations is dependent on positive studies results, successful public consultation and First Nation engagement, favorable market demand, and commercial interest.
Phase 3 – Uatnan Mining ProjectPreliminary economic assessment (“2023 PEA”) completed; detailed work plan for subsequent studies ready for deployment. Assessment of potential sites for processing plants initiated.
ContentsView on SEC.gov

The text of this filing, as the company filed it with the SEC, without its images or exhibits. This is not investment advice.