What changed in Management’s Discussion and Analysis?
Read the current filingPrevious report: 10-Q
Period ended 2024-07-31; filed 2024-09-05.
0001558370-24-012611
Item 2. MANAGEMENT’S DISCUSSION AND ANALYSIS OF FINANCIAL CONDITION AND RESULTS OF OPERATIONSCurrent report: 10-Q
Period ended 2024-10-31; filed 2024-12-05.
0001558370-24-016050
Item 2. MANAGEMENT’S DISCUSSION AND ANALYSIS OF FINANCIAL CONDITION AND RESULTS OF OPERATIONSThe baseline is this issuer’s latest earlier reporting period of the same form that was filed before the current report. A previous 10-Q is a different quarter, not a year-over-year comparison. Amendments are excluded.
Compared 147 previous paragraphs and 153 current paragraphs.
63 unchanged; 75 reworded; 7 added; 6 removed; 3 previous and 8 current paragraphs rearranged.
Tables are not compared: 4 previous and 4 current tables excluded. Dates, whitespace, punctuation and numbering changes are ignored; changes to financial figures remain significant.
A changed paragraph is not evidence that risk increased or decreased. An unchanged paragraph does not establish that risk stayed the same.
Added paragraphs (7)
Current report
Growing Power Demand
Current report
One prominent driver of this surge in energy demand is the rapid rise of data centers, which are expanding to support the growing adoption of artificial intelligence technologies. These facilities require substantial amounts of electricity to power advanced computing infrastructure, positioning them as a major contributor to future electricity demand. Technology companies with artificial intelligence ambitions have begun exploring deals to bring more power to the grid in order to secure long-term power contracts to address their significant electricity demand. Additionally, the accelerating shift toward electric vehicles (“EVs”) is reshaping the transportation landscape. As more drivers transition to EVs, the need for electricity to power charging networks will grow significantly, further straining grid capacity. Finally, the trend of onshoring manufacturing facilities is adding to the demand for electricity. Companies relocating production to the U.S. to enhance supply chain resilience are increasing the energy requirements of industrial operations. Combined, these factors underscore a growing imperative for the U.S. energy sector to adapt to rising electricity demands in the coming decades.
Current report
In November 2023, Texas voters approved the $5 billion Texas Energy Fund (“TEF”) to enhance grid reliability and incentivize new dispatchable power generation projects, with a significant focus on natural gas-fired power plants. Shortly thereafter, the Public Utility Commission of Texas selected 17 natural gas-fired generation projects, totaling nearly 10 GW, to advance through a due diligence review, representing $5.4 billion in potential state-backed loans. If all projects proceed, initial disbursements are anticipated by the end of 2025, and the TEF could expand to $10 billion under a proposal from Governor Greg Abbott.
Current report
energy project owners to the extent that was expected. Furthermore, the IRA may face challenges from the new administration.
Current report
During his campaign and subsequent to his election, President-elect Trump has indicated his intent to impose heavy tariffs on imports from several nations, including Mexico, Canada, and China. These measures aim to address broader policy goals but could introduce supply chain inefficiencies, challenge current trade agreements with certain nations, and affect the cost and availability of materials critical to project execution.
Current report
The gross profit percentages of corresponding revenues for the power industry services, industrial construction services and the telecommunications infrastructure services segments were 11.1%, 11.8% and 29.4%, respectively, for the quarter ended October 31, 2023.
Current report
The gross profit percentages of corresponding revenues for the power industry services, industrial construction services and the telecommunications infrastructure services segments were 14.0%, 12.8% and 25.1%, respectively, for the nine months ended October 31, 2023.
Removed paragraphs (6)
Previous report
expected by a certain future date, typically 10 to 30 years out. These aspirational goals may increase the risk of a new power plant becoming a stranded asset before the end of its useful economic life, a risk that potential equity capital providers may be unwilling to take. Lenders, who have become more wary of funding fossil-fuel ventures as environmental, social and governance ideals influence financing decisions, may be generally unwilling to provide capital for energy projects to increase the domestic production and transmission of oil and natural gas. In addition, insurance underwriters may require oil and gas industry clients to implement plans to reduce methane emissions, and will not provide insurance coverage for oil and gas projects in government-protected conservation areas that do not allow for sustainable use.
Previous report
The surge in renewable energy is propelled by significant factors, including reductions in solar and onshore wind costs between 2009 and 2023, driven primarily by technological advancements. The EIA indicated that for 2024, of the approximately 62.8 gigawatts of new utility-scale electric-generating capacity that is planned to be added to U.S. power grids, approximately 71% will come from solar and wind facilities. However, challenges persist, notably in offshore wind sectors facing cost overruns and supply chain issues, resulting in major offshore wind projects being delayed or cancelled.
Previous report
In July 2024, President Biden signed legislation that attempts to streamline the permitting process for new reactor designs and reduce fees for companies seeking to license advanced reactor technologies. The deployment of small modular reactors could mean lower construction and electricity costs through the use of simpler power plant designs, standardized components and passive safety measures. Such plants could be built in less time than larger plants, utilize less space and represent a viable choice for reliable power to offset the intermittencies of renewable power sources. The increase by the U.S. in its use of nuclear power for electricity generation could have unfavorable effects on the demand for new natural gas-fired and additional renewable energy facilities in the future, but the increase could provide balance-of-plant construction opportunities for GPS.
Previous report
Capacity Auctions
Previous report
The gross profit percentages of corresponding revenues for the power industry services, industrial construction services and the telecommunications infrastructure services segments were 17.3%, 14.3% and 25.0%, respectively, for the quarter ended July 31, 2023.
Previous report
The gross profit percentages of corresponding revenues for the power industry services, industrial construction services and the telecommunications infrastructure services segments were 16.0%, 13.4% and 22.5%, respectively, for the six months ended July 31, 2023.
Reworded paragraphs (75)
Previous wording
The following discussion summarizes the financial position of Argan, Inc. and its subsidiaries as of July 31, 2024, and the results of their operations for the three and six month periods ended July 31, 2024 and 2023, and should be read in conjunction with (i) the unaudited condensed consolidated financial statements and notes thereto included elsewhere in this Quarterly Report on Form 10-Q and (ii) the consolidated financial statements and accompanying notes included in our Annual Report on Form 10-K for Fiscal 2024 that was filed with the SEC on April 11, 2024 (the “Annual Report”).
Current wording
The following discussion summarizes the financial position of Argan, Inc. and its subsidiaries as of October 31, 2024, and the results of their operations for the three and nine month periods ended October 31, 2024 and 2023, and should be read in conjunction with (i) the unaudited condensed consolidated financial statements and notes thereto included elsewhere in this Quarterly Report on Form 10-Q and (ii) the consolidated financial statements and accompanying notes included in our Annual Report on Form 10-K for Fiscal 2024 that was filed with the SEC on April 11, 2024 (the “Annual Report”).
Previous wording
The Company is primarily a construction firm that conducts operations through its wholly-owned subsidiaries, GPS, APC, TRC and SMC. Through GPS and APC, we provide a full range of engineering, procurement, construction, commissioning, maintenance, project development and technical consulting services to the power generation market for a wide range of customers, including independent power project owners, public utilities, power plant heavy equipment suppliers and other commercial firms with significant power requirements in the U.S., Ireland and the U.K. GPS and APC represent our power industry services reportable segment. Through TRC, the industrial construction services reportable segment provides primarily on-site services that support new plant construction and additions, maintenance turnarounds, shutdowns and emergency mobilizations for industrial plants primarily located in the Southeast region of the U.S. and that may include the fabrication, delivery and installation of steel components such as piping systems and pressure vessels. Through SMC, which conducts business as SMC Infrastructure Solutions, the telecommunications infrastructure services segment provides project management, construction, installation and maintenance services to commercial, local government and federal government customers primarily in the Mid-Atlantic region of the U.S.
Current wording
The Company is primarily a construction firm that conducts operations through its wholly-owned subsidiaries, GPS, APC, TRC and SMC. Through GPS and APC, we provide a full range of engineering, procurement, construction, commissioning, maintenance, project development and technical consulting services to the power generation market for a wide range of customers, including independent power project owners, public utilities, power plant equipment suppliers and other commercial firms with significant power requirements in the U.S., Ireland and the U.K. GPS and APC represent our power industry services reportable segment. Through TRC, the industrial construction services reportable segment provides primarily on-site services that support new plant construction and additions, maintenance turnarounds, shutdowns and emergency mobilizations for industrial plants primarily located in the Southeast region of the U.S. and that may include the fabrication, delivery and installation of steel components such as piping systems and pressure vessels. Through SMC, which conducts business as SMC Infrastructure Solutions, the telecommunications infrastructure services segment provides project management, construction, installation and maintenance services to commercial, local government and federal government customers primarily in the Mid-Atlantic region of the U.S.
Previous wording
At July 31, 2024, our consolidated project backlog amount of $1.0 billion consisted substantially of the projects of the power industry services reporting segment. The comparable consolidated backlog amount as of January 31, 2024 was $0.8 billion. Our reported amount of project backlog at a point in time represents the total value of projects awarded to us that we consider to be firm as of that date less the amounts of revenues recognized to date on the corresponding projects.
Current wording
At October 31, 2024 and January 31, 2024, our consolidated project backlog amounts were each $0.8 billion, which consisted substantially of the projects of the power industry services reporting segment. Our reported amount of project backlog at a point in time represents the total value of projects awarded to us that we consider to be firm as of that date less the amounts of revenues recognized to date on the corresponding projects.
Previous wording
Typically, we include the total value of EPC services and other major construction contracts in project backlog upon receiving a notice to proceed from the project owner. When provided with a limited notice to proceed (“LNTP”), we usually record only the value of the contract related to the LNTP initially. Nevertheless, the inclusion of contract values in project backlog may require management judgement based on the facts and circumstances.
Current wording
Typically, we include the total value of EPC services and other major construction contracts in project backlog upon receiving a notice to proceed from the project owner. When provided with a limited notice to proceed (“LNTP”), we usually add only the value of the contract related to the LNTP initially. Nevertheless, the inclusion of contract values in project backlog may require management judgement based on the facts and circumstances.
Previous wording
We are committed to the construction of state-of-the-art, natural gas-fired power plants, as important elements of our country’s electricity-generation mix now and in the future. This represents our core business. In addition, we have been directing meaningful business development efforts to winning projects primarily for the erection of utility-scale solar fields, but also wind farms, hydrogen-based energy projects, battery energy storage projects, and other industrial projects in order to diversify the sources of revenues. At July 31, 2024, approximately 55.0% of our project backlog related to renewable energy projects. For the three and six months ended July 31, 2024, the amounts of revenues earned by us and associated with renewable energy projects were 40.6% and 35.7%, respectively, of corresponding revenues for the power industry services segment. We have successfully completed alternative energy projects in the past and we have renewed efforts to obtain new work in sectors of the power market that will complement our natural gas-fired EPC services projects going forward.
Current wording
We are committed to the construction of state-of-the-art, natural gas-fired power plants, as important elements of our country’s electricity-generation mix now and in the future. This represents our core business. In addition, we have been directing meaningful business development efforts to winning EPC services projects for primarily utility-scale solar fields, but also wind farms, hydrogen-based energy projects, battery energy storage projects, and other industrial projects in order to diversify the sources of revenues. At October 31, 2024, approximately 60.0% of our project backlog related to renewable energy projects. For the three and nine months ended October 31, 2024, the amounts of revenues earned by us and associated with renewable energy projects were 42.7% and 38.7%, respectively, of corresponding revenues for the power industry services segment. We have successfully completed alternative energy projects in the past and we have renewed efforts to obtain new work in sectors of the power market that will complement our natural gas-fired EPC services projects going forward.
Previous wording
In October 2022, GPS added to project backlog the EPC services contract value of the Trumbull Energy Center, a 950 MW natural gas-fired power plant now under construction in Lordstown, Ohio (the “Trumbull Energy Center”). We received the full notice to proceed (“FNTP”) from the project owner, Clean Energy Future-Trumbull, LLC, in November 2022. This combined cycle power station will consist of two Siemens Energy SGT6-8000H gas-fired, high efficiency, combustion turbines with two heat recovery steam generators and a single steam turbine. Project completion is scheduled for early in the year ending January 31, 2027.
Current wording
In October 2022, GPS added to project backlog the EPC services contract value of the Trumbull Energy Center, a 950 MW natural gas-fired power plant now under construction in Lordstown, Ohio (the “Trumbull Energy Center”). We received the full notice to proceed (“FNTP”) from the project owner, Clean Energy Future-Trumbull, LLC, in November 2022. This combined cycle power station will consist of two Siemens Energy SGT6-8000H gas-fired, high efficiency, combustion turbines with two heat recovery steam generators and a single steam turbine. Project completion is scheduled for the last quarter of Fiscal 2026.
Previous wording
In August 2023, GPS executed LNTPs with a customer for three solar and battery projects in Illinois (the “Midwest Solar and Battery Projects”). Under the LNTPs, GPS commenced early engineering and design activities as well as procurement of major equipment for construction of state-of-the-art solar energy and battery energy storage facilities. Between January and early May 2024, GPS received FNTPs on all three of the solar and battery projects. The three projects will cumulatively represent 160 MW of electrical power and 22 MW of energy storage. For these projects, completion is expected in the last quarter of Fiscal 2025 through the first half of the fiscal year ending January 31, 2026.
Current wording
In August 2023, GPS executed LNTPs with a customer for three solar and battery projects in Illinois (the “Midwest Solar and Battery Projects”). Under the LNTPs, GPS commenced early engineering and design activities as well as procurement of major equipment for construction of state-of-the-art solar energy and battery energy storage facilities. Between January and early May 2024, GPS received FNTPs on all three of the solar and battery projects. The three projects will cumulatively represent 160 MW of electrical power and 22 MW of energy storage. For these projects, completion is expected in the last quarter of Fiscal 2025 through the first half of Fiscal 2026.
Previous wording
In June 2024, GPS entered into a subcontract and received FNTP with the installation of five 90 MW gas turbines for the dedicated supply of power to a liquified natural gas (“LNG”) facility in Louisiana. This project, led by GPS, will be a collaboration with TRC and APC. Project completion is scheduled for early in the year ending January 31, 2026.
Current wording
In June 2024, GPS entered into a subcontract and received FNTP for the installation of five 90 MW gas turbines for the dedicated supply of power to a liquified natural gas (“LNG”) facility in Louisiana. This project, led by GPS, is a collaboration with TRC and APC. Project completion is scheduled for Fiscal 2026.
Previous wording
In May 2022, APC entered into engineering and construction services contracts with the ESB to construct three 65 MW aero-derivative gas turbine flexible generation power plants in and around the city of Dublin, Ireland (“ESB FlexGen Peaker Plants”). Two of the power plants, the Poolbeg and Ringsend FlexGen Power Plants, are located on the Poolbeg Peninsula, and the Corduff FlexGen Power Plant is located in nearby Goddamendy. All three projects cleared the applicable capacity auction in Fiscal 2023 and are expected to operate intermittently during peak periods of electricity demand and as back-up supply options when renewable electricity generation is limited. The completion of each power facility is expected to occur in the second half of Fiscal 2025.
Current wording
In May 2022, APC entered into engineering and construction services contracts with the ESB to construct three 65 MW aero-derivative gas turbine flexible generation power plants in and around the city of Dublin, Ireland (“ESB FlexGen Peaker Plants”). Two of the power plants, the Poolbeg and Ringsend FlexGen Power Plants, are located on the Poolbeg Peninsula, and the Corduff FlexGen Power Plant is located in nearby Goddamendy. All three projects cleared the applicable capacity auction in Fiscal 2023 and are expected to operate intermittently during peak periods of electricity demand and as back-up supply options when renewable electricity generation is limited. Substantial completion of each power facility occurred during the quarter ended October 31, 2024.
Previous wording
In October 2021 and pursuant to the Kilroot Project, APC was contracted to construct a 2 x 330 MW natural gas-fired power plant in Carrickfergus that is near Belfast, Northern Ireland, in an existing structure that was initially designed to enclose coal-fired units.
Current wording
In October 2021 and pursuant to the Kilroot Project, APC was contracted to construct a 2 x 330 MW natural gas-fired power plant in Carrickfergus that is near Belfast, Northern Ireland, in an existing structure that was initially designed to enclose coal-fired power plant units.
Previous wording
As previously disclosed, there have been a number of challenges related to the Kilroot Project that adversely impacted our ability to execute as expected, including supply chain delays, material changes to the project, the COVID-19 omicron outbreak, the war in Ukraine and extreme weather. In addition, unresolved variations and claims disrupted the execution of the project and harmed the cash flow of this project.
Current wording
As previously disclosed, there were a number of challenges related to the Kilroot Project that adversely impacted our ability to execute as expected, including supply chain delays, material changes to the project, the COVID-19 omicron outbreak, the war in Ukraine and extreme weather. In addition, unresolved variations and claims disrupted the execution and harmed the cash flow of this project.
Previous wording
APC provided 14 days’ notice to terminate as a result of project owner breaches of the contract. Those breaches were not resolved during that 14-day period, as a result of which the contract terminated on May 3, 2024. Subsequently, the project owner made a draw for the full amount of a $9.2 million irrevocable letter of credit, or on-demand performance bond, issued by the Company’s bank. This amount is now part of the open and disputed claims related to this project because APC and the Company believe the project owner initiated the draw without cause and, therefore, the amount should be refunded. The amount is included in accounts receivable as of July 31, 2024. We have recognized the estimated contract loss related to the Kilroot Project in the amount of approximately $12.8 million, of which $2.8 million was recorded during the six-month period ended July 31, 2024 and the remainder recorded in the prior fiscal year. APC has significant unresolved contract variations and claims for extensions of time, among other issues, related to the Kilroot Project. The project owner has asserted counterclaims that APC disputes. APC will continue to pursue all of its rights under the contract, and will do so through legal means if necessary.
Current wording
APC provided 14 days’ notice to terminate as a result of project owner breaches of the contract. Those breaches were not resolved during that 14-day period, as a result of which the contract terminated on May 3, 2024. Subsequently, the project owner made a draw for the full amount of a $9.2 million irrevocable letter of credit, or on-demand performance bond, issued by the Company’s bank. This amount is now part of the open and disputed claims related to this project because APC and the Company believe the project owner initiated the draw without cause and, therefore, the amount should be refunded. This amount is included in accounts receivable as of October 31, 2024.
Previous wording
As of July 31, 2024, TRC’s project backlog was approximately $92 million as compared to $128 million on January 31, 2024. For the six months ended July 31, 2024 and 2023, TRC generated $93.3 million and $63.1 million in revenues, respectively. The increase in revenues for the current year from the comparative period highlights the results of our successful business development efforts with both new and recurring clients during Fiscal 2023 and Fiscal 2022, particularly in securing larger industrial field service construction projects. Despite the decrease in the amount of TRC’s project backlog during the current year, we are encouraged by the number and size of opportunities in our project pipeline, and we expect the TRC project backlog will increase next year.
Current wording
As of October 31, 2024, TRC’s project backlog was approximately $66.4 million as compared to $127.5 million on January 31, 2024. For the nine months ended October 31, 2024 and 2023, TRC generated $134.7 million and $101.5 million in revenues, respectively. The increase in revenues for the current year from the comparative prior period highlights the results of our successful business development efforts with both new and recurring clients during Fiscal 2023 and Fiscal 2022, particularly in securing larger industrial field service construction projects. Despite the decrease in the amount of TRC’s project backlog during the current year, we are encouraged by the number and size of opportunities in our project pipeline, and we expect the TRC project backlog will increase next year.
Previous wording
In the reference case of its most recently published Annual Energy Outlook released in March 2023 (as would be customary, the U.S. Energy Information Administration (the “EIA”) did not publish a report in early 2024), the EIA projects that economic growth paired with increasing electrification in end-user sectors will result in notable growth of electricity demand in the U.S. through 2050. Declining capital costs for solar panels, wind turbines and battery storage, as well as government subsidies like those included in the Inflation Reduction Act of 2022 (the “IRA”), will result in renewables becoming increasingly cost effective compared with the alternatives when the costs of building new power capacity are considered. Renewables are increasingly meeting power demand through 2050 as they become more competitive with natural gas, coal and nuclear power.
Current wording
Since 2007, total annual U.S. electricity demand has fluctuated, where eight of the years during that period experienced year-over-year decreases in energy consumption. However, U.S. electricity demand has since reached its highest level in two decades, reflecting a surge in consumption driven by emerging technologies and economic shifts. In the reference case of its most recently published Annual Energy Outlook released in March 2023 (as would be customary, the U.S. Energy Information Administration (the “EIA”) did not publish a report in early 2024), the EIA projected that economic growth paired with increasing electrification in end-user sectors would result in notable growth of electricity demand in the U.S. through 2050.
Previous wording
The overall growth of our power business has been substantially based on the number of combined cycle gas-fired power plants built by us, as many coal-fired plants have been shut down in the U.S. In 2010, coal-fired power plants accounted for about 45% of net electricity generation in the U.S. For 2023, coal fueled approximately 17% of net electricity generation. It has been reported that the average age of the active plants in the coal-fired fleet approximates 45 years old with an average life span of 50 years; the last coal-fired power plant built in the U.S. was constructed in 2015. On the other hand, natural-gas fired power plants provided approximately 42% of the electricity generated by utility-scale power plants in the U.S. in 2023, representing an increase of 70% in the amount of electrical power generated by natural gas-fired power plants, which provided approximately 24% of net electricity generation in 2010.
Current wording
The overall growth of our power business has been substantially based on the number of combined cycle gas-fired power plants built by us, as many coal-fired plants have been shut down in the U.S. In 2010, coal-fired power plants accounted for about 45% of net electricity generation in the U.S. For 2023, coal fueled approximately 17% of net electricity generation. It has been reported that the average age of the active plants in the coal-fired fleet approximates 45 years old with an average life span of 50 years; the last coal-fired power plant built in the U.S. was constructed in 2015. On the other hand, natural-gas fired power plants provided approximately 42% of the electricity generated by utility-scale power plants in the U.S. in 2023, representing an increase of 70% in the amount of electrical power generated by natural gas-fired power plants since 2010. Natural gas-fired power plants provided approximately 24% of net electricity generation in 2010.
Previous wording
There exist headwinds confronting a significant resurgence in the pace of planning new developments of gas-fired power plants. Various cities, counties and states have adopted clean energy and carbon-free goals or objectives with achievement
Current wording
There exist certain headwinds confronting a significant resurgence in the pace of planning new developments of gas-fired power plants. Persistent supply chain constraints, which delay critical equipment delivery, and interconnect challenges that complicate grid integration delay project timelines and strain project financing. In addition, various cities, counties and states have adopted clean energy and carbon-free goals or objectives with achievement expected by a certain future date, typically 10 to 30 years out.
Previous wording
The net amount of electricity generation in the U.S. provided by utility-scale solar photovoltaic and wind facilities continues to rise. Together, such power facilities provided approximately 12%, 13% and 15% of the net amount of electricity generated by utility-scale power facilities in 2021, 2022 and 2023, respectively. The EIA projects that new photovoltaic solar and wind capacity will continue to be added to the utility-scale power fleet in the U.S. at a brisk pace, attributable to declines in costs of renewable power plants and power storage, an increase in the scale of energy storage capacity (i.e., battery farms and other energy storage technologies), the availability of valuable tax credits, and the overall political commitment to renewable energy.
Current wording
The net amount of electricity generation in the U.S. provided by utility-scale solar photovoltaic and wind facilities continues to rise. Together, such power facilities provided approximately 12%, 13% and 15% of the net amount of electricity generated by utility-scale power facilities in 2021, 2022 and 2023, respectively. The EIA projected that new photovoltaic solar and wind capacity will continue to be added to the utility-scale power fleet in the U.S. at a brisk pace, attributable to declines in costs of renewable power plants and power storage, an increase in the scale of energy storage capacity (i.e., battery farms and other energy storage technologies), the availability of valuable tax credits, and the overall political commitment to renewable energy.
Previous wording
Over the last several decades, the number of operating nuclear reactors has declined. At the end of April 2024, the U.S. had 94 operating commercial nuclear reactors at 54 nuclear power plants in 28 states. The average age of these nuclear reactors is approximately 42 years old with most plants authorized to operate for another 20 years. Only four nuclear reactors have entered into commercial operation in the last thirty years, the most recent being the Vogtle Units 3 and 4, which entered into commercial operations in July 2023 and April 2024, respectively. Suffering significant cost overruns—more than twice the initial estimates—and substantial delays, the Vogtle units have caused the industry to shift focus to smaller, more economical designs.
Current wording
Over the last several decades, the number of operating nuclear reactors has declined. Only four nuclear reactors have entered into commercial operation in the last thirty years, the most recent being the Vogtle Units 3 and 4, located in Georgia, which entered into commercial operations in July 2023 and April 2024, respectively. Suffering significant cost overruns—more than twice the initial estimates—and substantial delays, the Vogtle units have caused the industry to shift focus to smaller, more economical designs. The deployment of small modular reactors could mean lower construction and electricity costs through the use of simpler power plant designs, standardized components and passive safety measures.
Previous wording
In August 2022, President Biden signed the IRA, a climate and healthcare bill that funds hundreds of billions of dollars in tax subsidies intended to combat climate change among other measures. However, it appears that receipt of the majority of the tax subsidies will be conditioned on the extent that taxpayers “buy American” and/or pay prevailing wages, among other requirements. Existing supply chains and skilled labor pools may lack the capacity to meet the demand that the incentives are intended to create. Therefore, the subsidies may not provide the intended economic incentives to renewable and other energy project owners.
Current wording
In August 2022, President Biden signed the IRA, a climate and healthcare bill that funds hundreds of billions of dollars in tax subsidies intended to combat climate change among other measures. However, it appears that receipt of the majority of the tax subsidies will be conditioned on the extent that taxpayers “buy American” and/or pay prevailing wages, among other requirements. Existing supply chains and skilled labor pools may lack the capacity to meet the demand that the incentives are intended to create. Therefore, the subsidies may not provide the economic incentives to renewable and other
Previous wording
In May 2023, the Biden administration proposed new rules for the Environmental Protection Agency (the “EPA”) that are intended to drastically reduce greenhouse gases from coal- and gas-fired power plants that officials admit will cost such plants billions of dollars to comply fully by 2042. The proposed rules provide plant owners flexibility to select methods for achieving emission reduction targets, which may include adopting carbon-capture technology or incorporating cleaner fuels like hydrogen. However, the technological readiness of carbon capture and hydrogen blending is still debated among industry leaders, citing concerns over commercial viability and compliance feasibility. Additionally, environmental groups and landowners have challenged plans to erect pipelines intended to transfer carbon emissions to storage locations. In April 2024, the EPA issued final rules that require coal-fired power plants that are expected to operate beyond 2039 to reduce their carbon emissions by 90% prior to 2032. For new gas-fired power plants, the rules require a sliding scale of carbon capture up to 90% based on the operational load of the individual power plant. Rules for existing natural gas power plants have been delayed until 2025 in response to concern that such rules could affect grid reliability.
Current wording
In May 2023, the Biden administration proposed new rules for the Environmental Protection Agency (the “EPA”) that are intended to drastically reduce greenhouse gases from coal- and gas-fired power plants that officials admit will cost such plants billions of dollars to comply fully by 2042. In April 2024, the EPA issued final rules that require coal-fired power plants that are expected to operate beyond 2039 to reduce their carbon emissions by 90% prior to 2032. For new gas-fired power plants, the rules require a sliding scale of carbon capture up to 90% based on the operational load of the individual power plant. Rules for existing natural gas power plants have been delayed until 2025 in response to concern that such rules could affect grid reliability. More recently, President-elect Trump has expressed strong opposition to the EPA’s emissions-regulating rules and has pledged to abolish them.
Previous wording
In June 2023, President Biden signed a bill that raised the debt ceiling, which also included reforms for certain elements of the permitting process for energy projects. The bill imposes certain timelines for federal agencies to review and to approve elements of major energy projects and includes provisions designating a single agency to take the lead on the environmental review process. Such streamlining of the current permitting process for energy generating facilities could ease certain constraints on the power industry. The legislation also provided an approval of the Appalachian natural gas pipeline.
Current wording
In June 2023, President Biden signed a bill that raised the debt ceiling, which also included reforms for certain elements of the permitting process for energy projects. The bill imposes certain timelines for federal agencies to review and to approve elements of major energy projects and includes provisions designating a single agency to take the lead on the environmental review process. Such streamlining of the current permitting process for energy generating facilities could ease certain constraints on the power industry.
Previous wording
Throughout the U.S., the risk of electricity shortages grows as the retirement of traditional power plants outpaces their replacement by renewable energy and battery storage. Electric-grid operators are warning that power-generating capacity is struggling to keep up with demand. The challenge is that solar and wind farms do not produce electricity at all times, and they need large batteries to store their output for later use.
Current wording
Throughout the U.S., the risk of electricity shortages grows as the retirement of traditional power plants outpaces their replacement by renewable energy. Electric-grid operators are warning that power-generating capacity is struggling to keep up with demand. The challenge is that solar and wind farms do not produce electricity at all times, and they need large batteries to store their output for later use.
Previous wording
PJM Interconnection LLC (“PJM”) published a study in February 2023 that supported the growing concern that the reliability of power grids is being eroded by the rush to renewable power. The study indicates that the growth rate of electricity demand in the PJM footprint is likely to increase from electrification (i.e., shifts to electric-powered automobiles, electric appliances, etc.) coupled with the proliferation of high-demand data centers in the region. Coal-fired and old gas-fired power generation facilities are being retired at a rapid pace, possibly creating the risk that such retirements may outpace the construction of new power-generating facilities as PJM’s interconnection queue includes primarily intermittent and limited-duration renewable energy resources (see the discussion in the Capacity Auctions section below). Given the operating characteristics of these types of facilities and the weather, PJM will need multiple megawatts of renewable power and accompanying battery storage, and improvements in the transmission network, to replace a single megawatt of thermal generation.
Current wording
PJM Interconnection LLC (“PJM”) published a study in February 2023 that supported the growing concern that the reliability of power grids is being eroded by the rush to renewable power. The study indicates that the growth rate of electricity demand in the PJM footprint is likely to increase from electrification (i.e., shifts to electric-powered automobiles, electric appliances, etc.) coupled with the proliferation of high-demand data centers in the region. Thermal power generation facilities are being retired at a rapid pace, creating the risk that such retirements may outpace the construction of new power-generating facilities as PJM’s interconnection queue includes primarily intermittent and limited-duration renewable energy resources. Given the operating characteristics of renewable energy facilities and the weather, PJM will need multiple megawatts of renewable power and accompanying battery storage, and improvements in the transmission network, to replace a single megawatt of retired thermal generation.
Previous wording
Many of our recently completed and awarded EPC service contracts relate to the construction of natural gas-fired power plants located within the Mid-Atlantic geographic footprint of PJM, which operates a capacity market to ensure long-term grid reliability by securing the appropriate amount of power supply resources needed to meet predicted future energy demands in its region. Capacity payments by PJM represent meaningful portions of the revenue streams of qualifying power plants.
Current wording
Some of our recently completed and awarded EPC service contracts relate to the construction of natural gas-fired power plants located within the Mid-Atlantic geographic footprint of PJM, which operates a capacity market to ensure long-term grid reliability by securing the appropriate amount of power supply resources needed to meet forecasted energy demands in its region. Capacity payments by PJM represent meaningful portions of the revenue streams of qualifying power plants.
Previous wording
Beginning in 2021, annual capacity auctions suffered delays that, once held, resulted in lower prices than previous auctions. The results for the most recent auction that was delayed until July 2024 for the 2025/2026 delivery year, represent a reversal of the unfavorable trend. The auction resulted in a price of approximately $269.92/MW-day for most of the PJM region, whereas the previous auction produced a price of $28.92/MW-day. The significant increase in price was mainly driven by planned power generator retirements coupled with forecasted increases in peak power loads, indicating the market’s anticipation of a mismatch between the ability of the current grid to supply the growing demand for power. The next capacity auction, to be held for the 2026/2027 delivery year, is scheduled for December 2024.
Current wording
of the unfavorable trend. The auction resulted in a capacity price of approximately $269.92/MW-day for most of the PJM region, whereas the previous auction produced a capacity price of $28.92/MW-day. The significant increase in price was mainly driven by planned power generator retirements coupled with forecasted increases in peak power loads, indicating the market’s anticipation of a mismatch between the ability of the current grid to supply the growing demand for power. However, PJM’s market monitor alleged that flaws in the capacity market design inflated prices in the recent auction, allegations that PJM refutes. In response, PJM has delayed its next capacity auction, to be held for the 2026/2027 delivery year, in order to craft reforms.
Previous wording
Despite the headwinds, we believe that the lower operating costs of natural gas-fired power plants, the higher energy generating efficiencies of modern gas turbines, and the requirements for grid resiliency should sustain the demand for modern combined cycle and simple cycle gas-fired power plants in the future. We believe that the benefits of natural gas as a source of power are compelling, especially as a complement to the deployment of solar and wind powered energy sources, and that the future long-term prospects for natural gas-fired power plant construction remain generally favorable as natural gas continues to be the primary source for power generation in our country. The future availability of less carbon-intense, higher efficiency and inexpensive natural gas in the U.S. should be a significant factor in the economic assessment of future power generation capacity additions, although the pace of new opportunities emerging may be restrained and the starts of awarded EPC projects may be delayed or cancelled due to the challenges described above.
Current wording
We believe that the lower operating costs of natural gas-fired power plants, the higher energy generating efficiencies of modern gas turbines, and the requirements for grid resiliency should sustain the demand for modern combined cycle and simple cycle gas-fired power plants in the future. We believe that the benefits of natural gas as a source of power are compelling, especially as a complement to the deployment of solar and wind-powered energy sources, and that the future long-term prospects for natural gas-fired power plant construction remain favorable as natural gas continues to be the primary source for power generation in our country. The future availability of less carbon-intense, higher efficiency and inexpensive natural gas in the U.S. should be a significant factor in the economic assessment of future power generation capacity additions, although the pace of new opportunities emerging may be restrained and the starts of awarded EPC projects may be delayed or cancelled due to the challenges described above.
Previous wording
The scramble for electricity, regardless of source, caused by the Russian invasion of Ukraine may have clarified that the 100% transition to renewable energy is in the distant future and has prompted, in part, renewed interest in not only carbon capture techniques, but carbon removal technologies as well. Governments, including the U.S., are taking initial steps to boost this industry. The success of this industry could reduce the climate-change fear associated with natural gas-fired power plants. We intend to execute an “all-of-the-above” approach in pursuing the construction of future facilities that support the energy transition, which we see as a continuation of our historical commitment to building cleaner energy plants.
Current wording
The current scramble for electricity, regardless of source, may be clarifying that the 100% transition to renewable energy is in the distant future and has prompted, in part, renewed interest in not only carbon capture techniques, but carbon removal technologies as well. Governments, including the U.S., are taking initial steps to boost this industry. The success of this industry could reduce the climate-change fear associated with natural gas-fired power plants. We intend to execute an “all-of-the-above” approach in pursuing the construction of future facilities that support the energy transition, which we see as a continuation of our historical commitment to building cleaner energy plants.
Previous wording
The foregoing discussion in this “Market Outlook” has focused on the state of the domestic power market as the EPC services business of GPS historically provides the predominant portion of our revenues. However, overseas power markets may provide important new power construction opportunities for APC, especially across Ireland and the U.K.
Current wording
The foregoing discussion in this “Market Outlook” has focused on the state of the domestic power market as the EPC services business of GPS historically provides the predominant portion of our revenues. However, overseas power markets may continue to provide important new power construction opportunities for APC, especially across Ireland and the U.K.
Previous wording
Whereas in the U.K., prior to the elections in July 2024, the government had expressed support for new gas-fired power plants to offset the retirement of coal-fired plants, the retirement of aging gas plants, and the intermittency of renewable energy plants. However, with the general election in July 2024, the Labour Party, led by Prime Minister Keri Starmer, has since shifted focus toward accelerating the transition to renewable energy while still acknowledging the role of gas as a transitional fuel.
Current wording
Whereas in the U.K., prior to the elections in July 2024, the government had expressed support for new gas-fired power plants to offset the retirement of coal-fired plants, the retirement of aging gas plants, and the intermittency of renewable energy plants. However, with the general election in July 2024, the Labour Party, led by Prime Minister Keri Starmer, has shifted focus toward accelerating the transition to renewable energy while still acknowledging the role of gas as a transitional fuel.
Previous wording
APC is actively pursuing business opportunities in both the renewable and support sectors of power generation with its existing and new clients. In addition, GPS has been providing top management guidance and project management expertise to APC. APC has also provided experienced resources to GPS on several of its EPC services contracts in the U.S. More recently, APC has begun a comprehensive operational review, in collaboration with GPS, to enhance project management processes.
Current wording
APC is actively pursuing business opportunities for natural gas-fired power generation projects with its existing and new clients. GPS has been providing top management guidance and project management expertise to APC. Currently, APC is undergoing a comprehensive operational review, in collaboration with GPS, to enhance project management processes and profitability.
Previous wording
Industrial field services typically represent the majority of TRC’s annual revenues with the remaining revenues contributed by projects consisting solely of metal fabrication. The business footprint for TRC encompasses the Southeast region of the U.S. where there are many local and state governments that welcome industrial production facilities with ideal locations and with serious economic development programs and incentives. The national focus on infrastructure improvements, biotechnology advancements, energy storage and clean water have resulted in firms that are focused on these trends recently choosing TRC to participate in major construction projects in the region. Other important factors and trends include low corporate state tax rates, favorable labor migration patterns, the surface transportation infrastructure and the ready access to modern seaports.
Current wording
Industrial field services typically represent the majority of TRC’s annual revenues with the remaining revenues contributed by projects consisting solely of metal fabrication. The business footprint for TRC encompasses the Southeast region of the U.S. where there are many local and state governments that welcome industrial production facilities with ideal locations and with serious economic development programs and incentives. The national focus on infrastructure improvements, biotechnology advancements, energy storage and clean water have resulted in firms that are focused on these trends
Previous wording
construction capabilities. The Dodge Construction Starts report for 2024 forecasts that total construction in the U.S. will increase by 7% in 2024, with a 16% increase in the manufacturing category. Released in July 2024, the FMI Construction Put-in-Place Forecast for 2024 predicts that construction activity in the manufacturing sector will increase by over 21% in 2024. Despite headwinds such as material price volatility and rising labor costs, skilled labor shortages, high interest rates and tighter lending standards, it is likely that 2024 will see a boost to construction associated with manufacturing, as well as the transportation and clean energy infrastructures, as funds from three key pieces of national legislation passed in 2021 and 2022 are expected to flow into the industry. These bills include the Infrastructure and Jobs Act, the IRA and the Creating Helpful Incentives to Produce Semiconductors Act, and they appear to be sustaining high construction industry confidence for 2024 and the future beyond.
Current wording
Economic data supports our belief that TRC is ideally located in a leading manufacturing growth area of the U.S., which should continue to provide it with project opportunities going forward that will expand its business and industrial construction capabilities. Despite headwinds such as rising labor costs and skilled labor shortages, it is likely that the near-term will see a boost to construction associated with manufacturing, as well as the transportation and clean energy infrastructures, as funds from three key pieces of national legislation passed in 2021 and 2022 are expected to flow into the industry. These bills include the Infrastructure and Jobs Act, the IRA and the Creating Helpful Incentives to Produce Semiconductors Act, and they appear to be sustaining high construction industry confidence for 2024 and the future beyond.
Previous wording
Consolidated revenues for the three months ended July 31, 2024 were $227.0 million, which represented an increase of $85.7 million, or 60.6%, from consolidated revenues of $141.3 million reported for the three months ended July 31, 2023. The overall improvement in revenues was due to increases in revenues between quarters for all three of our reportable segments, as presented in the table above.
Current wording
Consolidated revenues for the three months ended October 31, 2024 were $257.0 million, which represented an increase of $93.2 million, or 56.9%, from consolidated revenues of $163.8 million reported for the three months ended October 31, 2023. The overall improvement in revenues was due to increases in revenues between quarters for our power industry services and industrial construction services segments, as presented in the table above.
Previous wording
The revenues of the power industry services segment, representing the businesses of GPS and APC, increased by 64.9%, or $68.4 million, to $173.8 million for the three months ended July 31, 2024 compared with revenues of $105.3 million for the three months ended July 31, 2023 as the quarterly construction activities increased for the Midwest Solar and Battery Projects, the Trumbull Energy Center, the 405 MW Midwest Solar Project and the Louisiana LNG Facility. The increase in revenues between quarters was partially offset by decreased construction activities associated with the Guernsey Power Station project, the Shannonbridge Power Project, the ESB FlexGen Peaker Plants and the Kilroot Project, as those projects have concluded or are nearly complete. These projects were the primary drivers of the revenues for this segment for the three-month period ended July 31, 2023. The revenues of this business segment represented approximately 76.5% of consolidated revenues for the quarter ended July 31, 2024 and 74.5% of consolidated revenues for the corresponding prior year quarter.
Current wording
The revenues of the power industry services segment, representing the businesses of GPS and APC, increased by 74.9%, or $90.8 million, to $212.1 million for the three months ended October 31, 2024 compared with revenues of $121.3 million for the three months ended October 31, 2023 as the quarterly construction activities increased for the Midwest Solar and Battery Projects, the Trumbull Energy Center, the 405 MW Midwest Solar Project and the Louisiana LNG Facility. The increase in revenues between quarters was partially offset by decreased construction activities associated with the Guernsey Power Station project, the Shannonbridge Power Project and the ESB FlexGen Peaker Plants, as those projects have concluded. The revenues of this business segment represented approximately 82.5% of consolidated revenues for the quarter ended October 31, 2024 and 74.1% of consolidated revenues for the corresponding prior year quarter.
Previous wording
The primary driver for this segment’s revenues for the three months ended July 31, 2023, were the construction of the Trumbull Energy Center, Shannonbridge Power Project, the ESB FlexGen Peaker plants and the Kilroot Project.
Current wording
The primary drivers for this segment’s revenues for the three months ended October 31, 2023, were the construction of the Shannonbridge Power Project, the Trumbull Energy Center and the ESB FlexGen Peaker Plants.
Previous wording
The revenues of our industrial construction services segment, representing the business of TRC, increased by $30.3 million, or 48.0%, to $93.3 million for the six months ended July 31, 2024 compared to revenues of $63.1 million for the six months ended July 31, 2023 as the amounts of field services increased meaningfully between periods, partially offset by decreased supporting vessel fabrication work between periods. For the six months ended July 31, 2024 and 2023, the revenues of this segment represented 24.3% and 25.7% of consolidated revenues for the corresponding periods.
Current wording
The revenues of our industrial construction services segment, representing the business of TRC, increased by $2.9 million, or 7.6%, to $41.3 million for the three months ended October 31, 2024 compared to revenues of $38.4 million for the three months ended October 31, 2023. For the three months ended October 31, 2024 and 2023, the revenues of this segment represented 16.1% and 23.5% of consolidated revenues for the corresponding periods.
Previous wording
The revenue results of this business segment, which represent the business of SMC, were $3.6 million for the three-month period ended July 31, 2024, an increase of $0.4 million, or 11.2%, from the amount of revenues earned during the three months ended July 31, 2023.
Current wording
The revenue results of this business segment, which represent the business of SMC, were $3.6 million for the three-month period ended October 31, 2024, a decrease of $0.4 million, or 11.1%, from the amount of revenues earned during the three months ended October 31, 2023.
Previous wording
With the increase in consolidated revenues for the three months ended July 31, 2024 compared with last year’s second quarter ended July 31, 2023, the consolidated cost of revenues also increased between the quarters. These costs were $195.9 million and $117.6 million for the three-month periods ended July 31, 2024 and 2023, respectively, representing an increase of approximately 66.6%.
Current wording
With the increase in consolidated revenues for the three months ended October 31, 2024 compared with last year’s third quarter ended October 31, 2023, the consolidated cost of revenues also increased between the quarters. These costs were $212.7 million and $144.5 million for the three-month periods ended October 31, 2024 and 2023, respectively, representing an increase of approximately 47.2%.
Previous wording
For the three-month period ended July 31, 2024, we reported a consolidated gross profit of approximately $31.1 million, which represented an increase from the gross profit reported for the three-month period ended July 31, 2023 in the amount of $23.7 million.
Current wording
For the three-month period ended October 31, 2024, we reported a consolidated gross profit of approximately $44.3 million, which represented an increase from the gross profit reported for the three-month period ended October 31, 2023 in the amount of $19.2 million.
Previous wording
The gross profit percentage of corresponding consolidated revenues declined to 13.7% for the three-month ended July 31, 2024, from 16.8% of corresponding consolidated revenues in the comparable prior year period. The decline in the gross profit percentage during the current period was primarily due to the changing mix of projects and contract types. The gross profit percentages of corresponding revenues for the power industry services, industrial construction services and the telecommunications infrastructure services segments were 13.5%, 13.0% and 31.4%, respectively, for the quarter ended July 31, 2024.
Current wording
The gross profit percentage of corresponding consolidated revenues increased to 17.2% for the three-month ended October 31, 2024, from 11.7% of corresponding consolidated revenues in the comparable prior year period. The increase in the gross profit percentage during the current period was primarily due to the changing mix of projects, strong execution and certain positive project closeouts. Additionally, during the three-month period ended October 31, 2023, gross profit was negatively impacted by losses recorded on the Kilroot Project, which reduced margins by approximately $10.7 million. The gross profit percentages of corresponding revenues for the power industry services, industrial construction services and the telecommunications infrastructure services segments were 18.3%, 11.1% and 26.1%, respectively, for the quarter ended October 31, 2024.
Showing the first 40 of 75 pairs. Open the source sections for the rest.
Rearranged current paragraphs (8)
Current report — wording carried from elsewhere
We have recognized an estimated contract loss related to the Kilroot Project in the amount of approximately $12.6 million, of which $2.6 million was recorded during the nine-month period ended October 31, 2024 and the remainder was recorded in the prior fiscal year. APC has significant unresolved contract variations and claims for extensions of time, among other issues, related to the Kilroot Project. The project owner has asserted counterclaims that APC disputes. APC will continue to pursue all of its rights under the contract, and will do so through legal means if necessary.
Current report — wording carried from elsewhere
Declining capital costs for solar panels, wind turbines and battery storage, as well as government subsidies like those included in the Inflation Reduction Act of 2022 (the “IRA”), were projected to result in renewables becoming increasingly cost effective compared with the alternatives when the costs of building new power capacity were considered. The EIA indicated that for 2024, of the approximately 62.8 gigawatts of new utility-scale electric-generating capacity that was planned to be added to U.S. power grids, approximately 71% was expected to come from solar and wind facilities.
Current report — wording carried from elsewhere
Beginning in 2021, annual capacity auctions suffered delays that, once held, resulted in lower prices than previous auctions. The results for the most recent auction that was delayed until July 2024 for the 2025/2026 delivery year, represent a reversal
Current report — wording carried from elsewhere
recently choosing TRC to participate in major construction projects in the region. Other important factors and trends include low state corporate tax rates, favorable labor migration patterns, the surface transportation infrastructure and the ready access to modern seaports.
Current report — wording carried from elsewhere
three months ended October 31, 2023, we reported income tax expense in the amount of approximately $6.1 million, which represented an effective tax rate of 52.9% for the period. This effective tax rate differed from the statutory federal tax rate due primarily to the unrecognized tax loss benefit of the net operating loss incurred by the subsidiary of APC located in the U.K.
Current report — wording carried from elsewhere
an effective tax rate of 36.3% for the period. This effective tax rate differed from the statutory federal tax rate due primarily to the unrecognized tax loss benefit of the net operating loss incurred by the subsidiary of APC located in the U.K.
Current report — wording carried from elsewhere
Credit Agreement. We may use the borrowing ability to cover other credit instruments issued by the Bank for our use in the ordinary course of business as defined in the New Credit Agreement. Further, on May 31, 2024, we completed the negotiation of a companion facility, in the amount of $25.0 million, pursuant to which APCL may cause the Bank’s European entity to issue letters of credit on its behalf that will be secured by a blanket parent company guarantee issued by the Company to the Bank.
Current report — wording carried from elsewhere
is included in Item 7 of Part II of our Annual Report. During the nine months ended October 31, 2024, there have been no material changes in the way we apply the critical accounting policies described therein.
Rearranged previous paragraphs (3)
Previous report — wording carried elsewhere
Economic data supports our belief that TRC is ideally located in a leading manufacturing growth area of the U.S., which should continue to provide it with project opportunities going forward that will expand its business and industrial
Previous report — wording carried elsewhere
three months ended July 31, 2023, we reported income tax expense in the amount of approximately $4.6 million, which represented an effective tax rate of 26.5% for the period.
Previous report — wording carried elsewhere
European entity to issue letters of credit on its behalf (the “Master Issuance and Indemnity Agreement”) that will be secured by a blanket parent company guarantee issued by the Company to the Bank.