Existing projects
The Company classifies its existing projects as those that are currently in the construction phase.
| Name | Location | Size | Timeline | Milestone | Current Status |
|---|---|---|---|---|---|
| (MWdc solar MW AC/MWh BESS) | |||||
| Camillus | New York, USA | 3.1 | Q1 FY2027 | Mechanical Completion | EPC project. Construction started in Q4 FY2025. Owned by Solar Advocate. PTO estimated for 1Q 2027. |
| Hardie Rd | New York, USA | 6.9 | Q2 FY2027 | Under Construction | EPC project. Construction started in Q4 FY2025. Owned by Qcells. |
| Rice Road | New York, USA | 6.4 | Q2 FY2027 | Under Construction | EPC project. Construction started in Q4 FY2025. Owned by Qcells. |