NexMetals Mining Corp.
For the period ended Jun 30, 2026. Filed Aug 17, 2026.
View on SEC.govAbout this filing
A company's report for each of its first three quarters. The financial statements are not audited. It shows how the business has moved since the last annual report, and what management says changed.
Jun 30, 2026 · Filed Aug 17, 2026
What changed in Management’s Discussion and Analysis?
Read the current filingPrevious report: 10-Q
Period ended 2026-03-31; filed 2026-05-13.
0001493152-26-022779
Item 2. Management’s Discussion and Analysis of Financial Condition and Results of OperationsCautionary Note Regarding Forward Looking StatementsCurrent report: 10-Q
Period ended 2026-06-30; filed 2026-08-17.
0001493152-26-038782
Item 2. Management’s Discussion and Analysis of Financial Condition and Results of OperationsCautionary Note Regarding Forward Looking StatementsThe baseline is this issuer’s latest earlier reporting period of the same form that was filed before the current report. A previous 10-Q is a different quarter, not a year-over-year comparison. Amendments are excluded.
Compared 148 previous paragraphs and 150 current paragraphs.
102 unchanged; 39 reworded; 8 added; 6 removed; 1 previous and 1 current paragraphs rearranged.
Tables are not compared: 19 previous and 21 current tables excluded. Dates, whitespace, punctuation and numbering changes are ignored; changes to financial figures remain significant.
A changed paragraph is not evidence that risk increased or decreased. An unchanged paragraph does not establish that risk stayed the same.
Added paragraphs (8)
Current report
The Company has engaged TECT Geological Consulting to develop an integrated three-dimensional geological and structural model for Selebi North and Selebi Main. The model is expected to enhance the Company’s understanding of the geological controls of mineralization across the mining license, support future resource growth and improve drill targeting of thicker, higher-grade zones, and identify potential regional exploration targets.
Current report
In June and August, the Company released the 2026 Selkirk MRE and Selkirk TRS, respectively, which incorporate the results of the Company’s historical drill core re-sampling program. Highlights of the 2026 Selkirk MRE include approximately 1.1 billion pounds of CuEq Mineral Resources in the Indicated category with 78.2 Mt grading 0.66% CuEq 1 and approximately 200 million pounds of CuEq Mineral Resources in the Inferred category with 15.1 Mt grading 0.60% CuEq 1. Selkirk has evolved into a strategically important, multi-commodity critical metals asset with the scale and development potential to drive additional value creation for shareholders.
Current report
Key drivers of the increase from the 2024 Mineral Resource Estimate (the “2024 MRE”) include: (i) significant improvement in metallurgical recoveries resulting in higher expected payabilities; (ii) inclusion of cobalt, silver and gold as payable metals, none of which were assigned value in the 2024 MRE due to limited assaying; and (iii) expanded platinum, palladium, silver, cobalt and gold datasets from the historical core resampling program, supporting an expanded mineralized envelope and larger conceptual pit shell on a Net Smelter Return basis. Further, the strip ratio was reduced to 1.02:1 from 1.65:1, among the lowest strip ratios for copper development projects globally, resulting from the inclusion of additional tonnage sitting above and adjacent to the 2024 MRE.
Current report
1 CuEq% calculated using the formula: Cu(%)+Ni(%)(85.1/91.4)+Co(%)(93.8/91.4)+Pt(g/t)(22.4/91.4) + Pd(g/t)(33.1/91.4)+Au(g/t)(68.5/91.4)+Ag(g/t)(0.8/91.4) from the Selkirk Technical Report.
Current report
The results of the soil sampling program on the prospecting licences were analyzed to highlight multi-element anomalies as well as bedrock lithology. A large mafic intrusion (2.0 kilometres x 2.5 kilometres) was outlined as well as isolated high-priority multi-element anomalies which require further follow-up.
Current report
Ongoing metallurgical flowsheet development includes additional variability tests aimed at improving recoveries and concentrate quality.
Current report
The Company will continue with additional flowsheet development testwork to further improve recoveries and concentrate quality. Regional exploration will focus on the targets generated by the soil sampling program, both on the prospecting licences and the historic data collected on the mining licence.
Current report
With the 2026 Selkirk MRE now complete, the Company is evaluating a range of strategic options for the Selkirk Mine, including potential partnerships, a spin-out, or advancement toward an economic study. With the material increase in metal inventory, substantial conversion to Indicated resources, clean concentrate quality, diversified polymetallic metal mix, and favourable open-pit mining characteristics, the Selkirk Mine is now well positioned as a meaningful contributor to the Company’s asset portfolio.
Removed paragraphs (6)
Previous report
A third U5 to A5 drill conversion kit arrived on site during the first quarter of 2026 and the A5 surface drill was mobilized on February 18, 2026. The Company has also purchased a second Marcotte deep drill which is now mobilized and drilling.
Previous report
During the first quarter of 2026, the Company received the results of its historical drill core re-sampling program, which was undertaken to obtain complete cobalt and PGE analyses in support of resource expansion and reclassification in an updated MRE. A total of 17 holes from a previous program were completed with assays announced in October 2024, while results from an initial 6 holes of the current 34-hole program were released on August 28, 2025. The assays for the remaining 28 holes were released March 19, 2026, highlights of which include 180.80 metres of 1.31% CuEq 2 in hole DSLK211. High grade footwall mineralization was also identified as an exploration target, with assays of 6.90 metres of 7.92% CuEq 2 in hole DSLK077 and 5.90 metres of 2.79% CuEq 2 in hole DSLK134.
Previous report
The results for the program have confirmed wide intervals of Cu-Ni-Co-PGE mineralization exceeding the current resource cut-off grade of 0.46% CuEq 2 outside the 2024 Selkirk Mineral Resource Estimate (“2024 Selkirk MRE”) and within the conceptual pit shell. This data will be incorporated into the updated MRE expected in the second quarter of 2026.
Previous report
Work continues on the four prospecting licences, consisting of soil sampling programs designed to follow up on historic exploration data.
Previous report
PGEs, along with gold, silver and cobalt, which were not comprehensively assayed historically, are now being evaluated, with silver and cobalt being assessed for the first time. These additional metals have the potential to provide meaningful incremental upside to overall project economics. Ongoing metallurgical flowsheet development is aimed at further improving recoveries and concentrate quality, including the evaluation of XRT pre-concentration sorting. The study results will be incorporated into an updated MRE and future economic evaluations.
Previous report
With the recent re-sampling program now complete and the receipt of LCT results, the Company will integrate these results into an updated MRE which is expected to be completed in the second quarter of 2026. In parallel, the Company will continue with additional flowsheet development testwork to further improve recoveries and concentrate quality. Soil sampling assay results on the adjoining prospecting licences will guide further work programs in 2026.
Reworded paragraphs (39)
Previous wording
This Report for NexMetals Mining Corp. contains “forward-looking information” and “forward-looking statements” within the meaning of applicable Canadian and U.S. securities laws. Forward-looking information and forward-looking statements in this Report include, but are not limited to, those relating to: the estimated timing and anticipated costs for the Company’s exploration and development activities at the Selebi Mines and Selkirk Mine for the period to September 30, 2026, including surface drilling programmes, capital expenditures, metallurgical and economic study work, and operating costs; the Company’s expected reporting on drill results; the Company’s anticipation of expansion of the Mineral Resource at the Selebi Mines through resource expansion drilling and underground development, and to complete updated Mineral Resource Estimates in the third quarter of 2026 and a Preliminary Economic Assessment in the second half of 2026; the Company’s intended metallurgical flowsheet and processing pathway, including the expectation that an on-site smelter or hydrometallurgical facility may not be required and that the Company intends to construct a new concentrator facility at the Selebi Mines; the Company’s plans to advance an updated MRE and metallurgical test work at the Selkirk Mine; the expectation that separate copper and nickel concentrates will be a viable alternative to bulk concentrate production; the expectation that negative operating cash flows will continue and that additional financing will be required to continue development of the Company’s material projects; the expectation that the proceeds from the November 2025 Financing will be sufficient to fund planned activities, including the completion of a PEA study for the Selebi Mines, and cover administrative costs into the fourth quarter of 2026; and the Company’s belief that it is well positioned in 2026 to accelerate resource growth and advance both projects toward future economic assessments. In some cases, you can identify forward-looking information by terminology such as “may,” “will,” “should,” “expects,” “plans,” “anticipates,” “believes,” “estimates,” “predicts,” “potential,” “continue” or the negative of these terms or other comparable terminology. In addition, any statements that refer to expectations, intentions, projections or other characterizations of future events or circumstances contain forward-looking information. Statements containing forward-looking information are not historical facts but instead represent management’s expectations, estimates and projections regarding future events or circumstances.
Current wording
This Report for NexMetals Mining Corp. contains “forward-looking information” and “forward-looking statements” within the meaning of applicable Canadian and U.S. securities laws. Forward-looking information and forward-looking statements in this Report include, but are not limited to, those relating to: the estimated timing and anticipated costs for the Company’s exploration and development activities at the Selebi Mines and Selkirk Mine for the period to December 31, 2026, including surface drilling programmes, capital expenditures, metallurgical and economic study work, and operating costs; the Company’s expected reporting on drill results; the Company’s anticipation of expansion of the Mineral Resource at the Selebi Mines through resource expansion drilling, and to complete an updated Mineral Resource Estimate in the third quarter of 2026 and a Preliminary Economic Assessment thereafter; the Company’s belief that drilling results to date present strong potential for significantly increased tonnage in an updated Mineral Resource Estimate at the Selebi Mines; expectations regarding improved capital efficiency resulting from the Company’s in-house drilling fleet; the Company’s intended metallurgical flowsheet and processing pathway, including the expectation that an on-site smelter or hydrometallurgical facility may not be required and that the Company intends to construct a new concentrator facility at the Selebi Mines; the Company’s plans to advance metallurgical test work and an economic study at the Selkirk Mine; the expectation that separate copper and nickel concentrates will be a viable alternative to bulk concentrate production; the expectation that negative operating cash flows will continue and that additional financing will be required to continue development of the Company’s material projects; the anticipated benefits of TECT Geological Consulting’s three-dimensional geological and structural model; the expectation that the proceeds from the November 2025 Financing will be sufficient to fund planned activities, including the completion of a PEA study for the Selebi Mines, and cover administrative costs into the fourth quarter of 2026; the Company’s intention to pursue a range of financing alternatives in advance of year-end 2026; the potential range of strategic options for the Selkirk Mine, including potential partnerships, a spin-out, or advancement toward an economic study; and the Company’s belief that it is well positioned in 2026 to accelerate resource growth and advance both projects toward future economic assessments. In some cases, you can identify forward-looking information by terminology such as “may,” “will,” “should,” “expects,” “plans,” “anticipates,” “believes,” “estimates,” “predicts,” “potential,” “continue” or the negative of these terms or other comparable terminology. In addition, any statements that refer to expectations, intentions, projections or other characterizations of future events or circumstances contain…
Excerpt shortened here; the source contains the full paragraph.
Previous wording
Forward-looking statements and forward-looking information are not guarantees of future performance and are based upon a number of estimates and assumptions of management at the date the statements are made. Such factors and assumptions may include, but are not limited to: the existing Selebi Mines MRE and the Selkirk MRE, and the assumptions regarding tonnages, grades, recoveries, and metal prices underlying those estimates, remain valid and reliable for purposes of the Company’s exploration planning; that approximately 30,000 metres of drilling at Selebi Main will generate sufficient geological data to support an updated MRE; the Company will be able to generate clean, high-grade separate copper and nickel concentrates from the Mines that meet industry-standard smelter acceptance criteria; the proceeds from the November 2025 Financing will be sufficient to fund planned activities, including the completion of a PEA study for the Selebi Mines, and cover administrative costs into the fourth quarter of 2026; the Company will be able to raise additional financing on acceptable terms to continue development beyond the current funding horizon; the Company’s interpretation of what constitutes a “compliant economic study” under the Botswana Mines and Minerals Act will be accepted by regulators; Section 42 and Section 43 applications will be submitted by December 31 2026; the Selkirk APA study phase (as extended to August 17, 2026) will be complied with, and the Company’s mining licences will remain in good standing; there will be no material changes to the Company’s current operational plans, workforce, contractor arrangements, or input costs (including fuel, power, and labour costs in Botswana); metal prices, exchange rates, and economic conditions will remain consistent with those prevailing at the date of this Report or, in the case of long-term price assumptions used in CuEq calculations, as disclosed herein.
Current wording
Forward-looking statements and forward-looking information are not guarantees of future performance and are based upon a number of estimates and assumptions of management at the date the statements are made. Such factors and assumptions may include, but are not limited to: the existing Selebi Mines MRE and the Selkirk MRE, and the assumptions regarding tonnages, grades, recoveries, and metal prices underlying those estimates, remain valid and reliable for purposes of the Company’s exploration planning; that more than 30,000 metres of drilling at Selebi Main will generate sufficient geological data to support an updated MRE; the Company will be able to generate clean, high-grade separate copper and nickel concentrates at scale from the Mines that meet industry-standard smelter acceptance criteria; the proceeds from the November 2025 Financing will be sufficient to fund planned activities, including the planned completion of a PEA study for the Selebi Mines, and cover administrative costs into the fourth quarter of 2026; the Company will be able to raise additional financing on acceptable terms to continue development beyond the current funding horizon; the Company’s interpretation of what constitutes a “compliant economic study” under the Botswana Mines and Minerals Act will be accepted by regulators; Section 42 and Section 43 applications will be submitted by December 31 2026; the Selebi APA and Selkirk APA study phases will be complied with, and the Company’s mining licences will remain in good standing; there will be no material changes to the Company’s current operational plans, workforce, contractor arrangements, or input costs (including fuel, power, and labour costs in Botswana); metal prices, exchange rates, and economic conditions will remain consistent with those prevailing at the date of this Report or, in the case of long-term price assumptions used in CuEq calculations, as disclosed herein.
Previous wording
Forward-looking statements and forward-looking information involve known and unknown risks, uncertainties and other factors that may cause our actual results, levels of activity, performance or achievements to be materially different from any future results, levels of activity, performance or achievements expressed or implied by the forward-looking statements. These risks and other factors include, without limitation, the following risk factors, which should be read in conjunction with the risks and uncertainties described in Part I, Item 1A under the heading “Risk Factors” in our Annual Report on Form 10-K for the year ended December 31, 2025, in addition to the other information included in this Quarterly Report: drilling results may not confirm the anticipated continuity, grade, or thickness of mineralization; Mineral Resource Estimates may require material downward revision; operational risks (including equipment failures, contractor underperformance, weather, and supply chain disruptions) could delay programmes and increase costs; the Company may be unable to establish Mineral Reserves; the Selebi Mines Preliminary Economic Assessment may not demonstrate economic viability given the preliminary nature of the estimates and the significant expenses required to develop the Selebi Mines; metallurgical recoveries achieved in laboratory testing may not be reproducible at commercial scale; concentrates may not meet smelter acceptance criteria at larger production volumes; further economic evaluation may demonstrate that a hydrometallurgical facility or smelter is in fact required, materially increasing capital requirements; construction of a new processing facility may be subject to permitting delays, cost overruns, or infrastructure limitations; additional financing may not be available or may not be available on favourable terms; unfavourable economic conditions or investor sentiment may impair the Company’s ability to obtain financing; changes to the operational plan may require expenditures in excess of current working capital, shortening the anticipated funding horizon; the Company’s interpretation of a “compliant economic study” under the Botswana Mines and Minerals Act may not be accepted by regulators; the Company may be unable to obtain or retain necessary permits and licences; the Selkirk APA study phase extension may not be further extended; changes to taxation or environmental laws could increase costs or preclude economic development; the Company is exposed to political, economic, and currency risks inherent in operating in Botswana; metal prices and exchange rates may differ materially from those assumed, which could render the Company’s projects uneconomical and cause actual costs and economics to differ materially from those projected; and the other risk factors stated in the Company’s other public filings available on SEDAR+ at www.sedarplus.ca and on EDGAR at www.sec.gov. Readers are cautioned that this list of risk factors should…
Excerpt shortened here; the source contains the full paragraph.
Current wording
Forward-looking statements and forward-looking information involve known and unknown risks, uncertainties and other factors that may cause our actual results, levels of activity, performance or achievements to be materially different from any future results, levels of activity, performance or achievements expressed or implied by the forward-looking statements. These risks and other factors include, without limitation, the following risk factors, which should be read in conjunction with the risks and uncertainties described in Part I, Item 1A under the heading “Risk Factors” in our Annual Report on Form 10-K for the year ended December 31, 2025, in addition to the other information included in this Quarterly Report: drilling results may not confirm the anticipated continuity, grade, or thickness of mineralization; Mineral Resource Estimates may require material downward revision; operational risks (including equipment failures, contractor underperformance and availability, weather, and supply chain disruptions) could delay programmes and increase costs; the Company may be unable to establish Mineral Reserves; the Selebi Mines Preliminary Economic Assessment may not demonstrate economic viability given the preliminary nature of the estimates and the significant expenses required to develop the Selebi Mines; metallurgical recoveries achieved in laboratory testing may not be reproducible at commercial scale; concentrates may not meet smelter acceptance criteria at larger production volumes; further economic evaluation may demonstrate that a hydrometallurgical facility or smelter is in fact required, materially increasing capital requirements; construction of a new processing facility and tailings storage facility may be subject to permitting delays, cost overruns, or infrastructure limitations; additional financing may not be available or may not be available on favourable terms; unfavourable economic conditions or investor sentiment may impair the Company’s ability to obtain financing; changes to the operational plan may require expenditures in excess of current working capital, shortening the anticipated funding horizon; the Company’s interpretation of a “compliant economic study” under the Botswana Mines and Minerals Act may not be accepted by regulators; evolving mining policies and related laws, regulations and regulatory practices in Botswana, including with respect to government or citizen participation, local ownership, in-country beneficiation or processing, fiscal terms and mineral tenure, may be adopted, interpreted, implemented or applied in a manner that increases costs, requires changes to the Company’s ownership interests or operating arrangements, delays or restricts project development, or otherwise adversely affects project economics; the Company may be unable to obtain or retain necessary permits and licences; the application for the Selkirk APA study phase extension may not be accepted by authorities; changes to taxation or enviro…
Excerpt shortened here; the source contains the full paragraph.
Previous wording
Unless otherwise indicated, all references to “$”, “C$” and “dollars” in this Report refer to Canadian dollars, references to “US$” in this Report refer to United States dollars and references to “BWP” in this Report refer to Botswanan pula. On March 31, 2026, the daily exchange rate: (i) for one United States dollar expressed in Canadian dollars was US$1.00 = C$1.3939 (or C$1.00 = US$0.7174); (ii) for one Botswanan pula expressed in Canadian dollars was BWP 1.00 = C$0.0999 (or C$1.00 = BWP 10.01); and (iii) for one Botswanan pula expressed in United States dollars was BWP 1.00 = US$0.0745 (or US$1.00 = BWP 13.42). “This quarter” or “the quarter” means the first quarter (“Q1”) of 2026.
Current wording
Unless otherwise indicated, all references to “$”, “C$” and “dollars” in this Report refer to Canadian dollars, references to “US$” in this Report refer to United States dollars and references to “BWP” in this Report refer to Botswanan pula. On June 30, 2026, the daily exchange rate: (i) for one United States dollar expressed in Canadian dollars was US$1.00 = C$1.421 (or C$1.00 = US$0.704); (ii) for one Botswanan pula expressed in Canadian dollars was BWP 1.00 = C$0.1037 (or C$1.00 = BWP 9.64); and (iii) for one Botswanan pula expressed in United States dollars was BWP 1.00 = US$0.0755 (or US$1.00 = BWP 13.25). “This quarter” or “the quarter” means the second quarter (“Q2”) of 2026.
Previous wording
This MD&A is intended to assist the reader to assess material changes in the financial condition of the Company during the quarter ended March 31, 2026, and the results of operations of the Company for the three-month periods ended March 31, 2026, and March 31, 2025. The Quarterly Financial Statements and the financial information contained in this MD&A were prepared in accordance with US GAAP and pursuant to the rules and regulations of the SEC.
Current wording
This MD&A is intended to assist the reader to assess material changes in the financial condition of the Company during the quarter ended June 30, 2026, and the results of operations of the Company for the three-month and six-months periods ended June 30, 2026, and June 30, 2025. The Quarterly Financial Statements and the financial information contained in this MD&A were prepared in accordance with US GAAP and pursuant to the rules and regulations of the SEC.
Previous wording
The information that follows relating to the Selkirk Mine is derived from, and in some instances is an extract from, the Selkirk Technical Report Summary (“Selkirk TRS”) entitled “S-K 1300 Technical Report Summary, Selkirk Nickel Project, North East District, Republic of Botswana” with an effective date of November 1, 2024, and a signature date of January 8, 2025, prepared by SLR Consulting (Canada) Ltd., prepared in compliance with the SEC’s Modernization of Property Disclosures for Mining Registrants set forth in subpart 1300 of Regulation S-K.
Current wording
The information that follows relating to the Selkirk Mine is derived from, and in some instances is an extract from, the 2026 Selkirk TRS entitled “S-K 1300 Technical Report Summary, Selkirk Nickel-Copper-PGE Project, Botswana” with an effective date of June 22, 2026, and a signature date of August 17, 2026, prepared by The MSA Group, prepared in compliance with the SEC’s Modernization of Property Disclosures for Mining Registrants set forth in subpart 1300 of Regulation S-K.
Previous wording
The qualified persons of SLR Consulting (Canada) Ltd. meet the qualifications specified under the definition of “qualified person” under Item 1300 of Regulation S-K. Portions of the following information are based on assumptions, qualifications and procedures which are not fully described herein. Reference should be made to the full text of the Selebi TRS and Selkirk TRS, which have been included as Exhibit 96.1 and 96.2 to the Company’s Annual Report on Form 10-K for the fiscal year ended December 31, 2025, respectively. In the event that we determine that any modifying factors, estimates and other scientific and technical information in the reports materially change, we may update or file a new technical report in the future. The Selebi Mines and Selkirk Mine are exploration stage properties.
Current wording
The qualified persons of SLR Consulting (Canada) Ltd. and The MSA Group, meet the qualifications specified under the definition of “qualified person” under Item 1300 of Regulation S-K. Portions of the following information are based on assumptions, qualifications and procedures which are not fully described herein. Reference should be made to the full text of the Selebi TRS and Selkirk TRS, which have been included as Exhibit 96.1 to the Company’s Annual Report on Form 10-K for the fiscal year ended December 31, 2025, and Exhibit 96.2 to this Report, respectively. In the event that we determine that any modifying factors, estimates and other scientific and technical information in the reports materially change, we may update or file a new technical report in the future. The Selebi Mines and Selkirk Mine are exploration stage properties.
Previous wording
Drilling continues to reinforce confidence in the scale and continuity of the SNUG deposit, with recent step-out results complementing previously reported thick, continuous high-grade intervals, supporting the potential to rapidly add tonnage to an updated Mineral Resource Estimate. Assays for a total of approximately 42,672 metres across 95 completed holes at Selebi North have been completed subsequent to the 2024 Selebi Mines MRE.
Current wording
Drilling continues to reinforce confidence in the scale and continuity of the Selebi North deposit, with recent step-out results complementing previously reported thick, continuous high-grade intervals, supporting the potential to rapidly add tonnage to an updated Mineral Resource Estimate. Assays for a total of approximately 42,672 metres across 95 completed holes at Selebi North have been completed subsequent to the 2024 Selebi Mines MRE.
Previous wording
During the second quarter of 2025, the Company commenced the surface drilling program targeting BHEM plates in the 2-kilometre gap zone between the Selebi North and Selebi Main deposits known as the “Hinge”. The program was designed to demonstrate the broader scale potential of the Selebi Mines and to further support the Company’s core thesis that these deposits are larger than previously recognized.
Current wording
During the second quarter of 2025, the Company commenced the surface drilling program targeting BHEM plates in the two-kilometre gap zone between the Selebi North and Selebi Main deposits. The program was designed to demonstrate the broader scale potential of the Selebi Mines and to further support the Company’s core thesis that these deposits are larger than previously recognized.
Previous wording
Initial Hinge drilling consisted of four widely spaced holes, with all holes intersecting multiple zones of mineralization, supporting potential continuous mineralization between Selebi Main and Selebi North. SMD-25-201, located down plunge of Selebi Main, intersected three zones including 3 metres of massive sulphides. BHEM results refined targeting down plunge of the existing Selebi Main resource, leading to follow-up hole SMD-25-205, which intersected 11.05 metres of 7.31% CuEq 1(3.00% Cu and 2.09% Ni), including 5.75 metres of 8.73% CuEq 1 (3.98% Cu and 2.31% Ni) located 130 metres beyond the existing Selebi Main resource within the emerging Selebi Main Flexure Zone.
Current wording
Initial drilling consisted of four widely spaced holes, with all holes intersecting multiple zones of mineralization, supporting potential continuous mineralization between Selebi Main and Selebi North. SMD-25-201, located down plunge of Selebi Main, intersected three zones including 3 metres of massive sulphides. BHEM results refined targeting down plunge of the existing Selebi Main resource, leading to follow-up hole SMD-25-205, which intersected 11.05 metres of 7.31% CuEq 1(3.00% Cu and 2.09% Ni), including 5.75 metres of 8.73% CuEq 1 (3.98% Cu and 2.31% Ni) located 130 metres beyond the existing Selebi Main resource.
Previous wording
The presence of thick, continuous massive sulphide intervals in holes spaced more than 300 metres apart supports the Company’s interpretation of a robust and laterally extensive mineralized system at Selebi Main. These results confirm that the Selebi Main mineralized system remains open well beyond current resource boundaries, highlighting strong potential to add significant tonnes in a new MRE planned for the second half of 2026.
Current wording
The presence of thick, continuous massive sulphide intervals in holes spaced 200 to 300 metres apart supports the Company’s interpretation of a robust and extensive mineralized system at Selebi Main. The mineralization characteristics of SMD-26-212-W1, SMD-25-205, and historical hole sd119 (26.1m of 8.29% CuEq 1, 3.39% Cu, 2.38% Ni: see Selebi TRS) are defining a mineralized trend exceeding one kilometre in plunge extent and confirm that the Selebi Main mineralized system remains open well beyond 2024 MRE boundaries. These results highlight the strong potential to add significant tonnes in the 2026 MRE planned for the third quarter of 2026.
Previous wording
To date, a total of 22,247 metres has been drilled as part of the surface program, comprising eight completed holes, one hole extension, four abandoned holes and four holes currently in progress.
Current wording
To date, a total of 32,458 metres has been drilled as part of the surface program, comprising twelve completed holes, one hole extension, three pre-collared holes, four abandoned holes and five holes currently in progress.
Previous wording
Operating a Company-owned drill fleet provides increased operational flexibility, cost efficiency, and scheduling control, while reducing reliance on third-party contractor availability. The Company also expects the in-house fleet to support improved capital efficiency over the longer term as drilling activity continues to scale across the Selebi Project.
Current wording
The program is being executed using five company-owned drill rigs comprising of three underground U5 drills which were converted into surface A5 drills, and two Marcotte HTM2500 drills capable of drilling to depths of 2,500 metres (NQ core). Operating a Company-owned drill fleet provides increased operational flexibility, cost efficiency, and scheduling control, while reducing reliance on third-party contractor availability. The Company also expects the in-house fleet to support improved capital efficiency over the longer term as drilling activity continues to scale across the Selebi Mines.
Previous wording
Following the completion of comprehensive technical and trade-off studies, the Company began evaluating the construction of a new processing facility at the Selebi Mines to produce concentrate for commercial sale, or, alternatively, for further refining, and does not plan to restart the existing concentrator or smelter from the original BCL operations, which were placed on care and maintenance in 2016 and remain under separate ownership. The Company is also evaluating pre-concentration using x-ray transmission technology (“XRT”) which, to date, has demonstrated the potential to reduce the amount of waste rock being sent to the processing circuit and enhance the head grade by over 15% compared to a bulk sample. By reducing the volume of waste that is directed to the processing circuit, the waste volume directed to grinding and flotation circuits could be substantially reduced, improving cost and efficiency.
Current wording
Following the completion of comprehensive technical and trade-off studies, the Company began evaluating the construction of a new processing facility at the Selebi Mines to produce concentrate for commercial sale or, alternatively, for further refining. The existing concentrator and smelter from the former BCL operations are not considered viable processing alternatives, as these facilities are under separate ownership and are subject to ongoing dismantling activities.
Previous wording
During the first quarter of 2026, the Company completed the metallurgical studiesat Blue Cost Research (“BCR”) labs. The program comprised flowsheet development, optimization and variability testing using the master Selebi Mines composite sample. Locked Cycle Tests (“LCT”) were successful in minimizing the nickel content in the copper concentrate and increasing nickel recoveries in the nickel concentrate. Preliminary LCTs achieved copper recovery of 80.6% at a grade of 29.4% copper in copper concentrate and nickel recovery of 53.0% at a grade of 10.0% nickel in nickel concentrate. Final LCTs aimed at reducing nickelin copper concentrate achieved copper recovery of 86.4% with nickel misplacement at less than 1%. Final concentrate assay results confirmed that both copper and nickel concentrates are expected to meet industry-standard smelter acceptance criteria, supporting a clear pathway to commercial sales. The concentrates exhibit very low levels of deleterious elements, all below penalty thresholds, which enhances marketability and potential offtake terms.
Current wording
During the first quarter of 2026, the Company completed the metallurgical studies at Blue Coast Research (“BCR”) labs. The program comprised flowsheet development, optimization and variability testing using the master Selebi Mines composite sample. Locked Cycle Tests (“LCTs”), which simulate full-scale plant performance, were successful in minimizing the nickel content in the copper concentrate and increasing nickel recoveries in the nickel concentrate. Preliminary LCTs achieved copper recovery of 87.0% at a grade of 27.6% copper in copper concentrate and nickel recovery of 55.9% at a grade of 10.5% nickel in nickel concentrate. Final LCTs aimed at reducing nickel in copper concentrate achieved copper recovery of 86.4% with nickel misplacement at less than 1%. Final concentrate assay results confirmed that both copper and nickel concentrates are expected to meet industry-standard smelter acceptance criteria, supporting a clear pathway to commercial sales. The concentrates exhibit very low levels of deleterious elements, expected to be below penalty thresholds, which enhances marketability and potential offtake terms.
Previous wording
The Company commenced a Preliminary Economic Assessment (“PEA”) in October 2025 for the Selebi Mines under the separate saleable concentrates scenario, the scope of which includes mine design and scheduling, process engineering, infrastructure planning, a processing facility and capital and operating cost estimation. The PEA is expected to be completed in the second half of 2026, following the completion of the new MRE. To date, the environmental documentation in support of the PEA has been completed, and engineering activities have focused on completing trade-off studies in advance of completing the new MRE.
Current wording
The Company commenced a Preliminary Economic Assessment (“PEA”) in October 2025 for the Selebi Mines under the separate saleable concentrates scenario, the scope of which includes mine design and scheduling, process engineering, infrastructure planning, a processing facility and capital and operating cost estimation. The PEA is currently targeted to be completed in the second half of 2026. To date, environmental documentation in support of the PEA has been completed, and mineral processing and metallurgical testing documentation are well advanced. Mine plan evaluations remain ongoing, reflecting, in part, the Company’s continued assessment of trade-off alternatives and the success of the ongoing surface drilling programs. The Company may further refine the scope and approach of the PEA to ensure that it appropriately reflects the evolving scale and development alternatives for the Selebi Mines.
Previous wording
During the three months ended March 31, 2026, the Company incurred $7,115,952 (three months ended March 31, 2025 - $5,944,153) in exploration and evaluation expenditures on the Selebi Mines.
Current wording
During the three and six months ended June 30, 2026, the Company incurred $9,257,727 and $16,373,679 (June 30, 2025 - $8,620,305 and $14,614,458), respectively, in exploration and evaluation expenditures on the Selebi Mines.
Previous wording
As of March 31, 2026, the Company had incurred $43,176,889 to acquire the Selebi Mines, and a further $107,028,311 in exploration and evaluation expenditures project-to-date.
Current wording
As of June 30, 2026, the Company had incurred $43,176,889 to acquire the Selebi Mines, and a further $116,286,038 in exploration and evaluation expenditures project-to-date.
Previous wording
Building on the targets identified to-date, the Company is executing on a Selebi Main resource expansion drilling program from surface using BHEM surveys to define drill targets, with approximately 30,000 metres planned to support resource expansion at Selebi Main throughout 2026. Drilling will continue to test both the Main Zone and Lower Zone, where historical drilling and BHEM modelling indicate increasing thickness and continuity down-dip and down plunge to the north. Drilling is now focused on a 200-metre spacing to allow for the expansion of the Inferred Resource, and sequencing will be guided by ongoing geophysical interpretation, allowing the Company to target conductive plates as results are received. The program is anticipated to materially expand the Inferred Resource and generate the geological data required for an updated MRE planned for the second half of 2026. Drill results are expected to be reported on a regular basis throughout 2026.
Current wording
Drilling is focused on a 200-metre spacing to allow for the expansion of the Inferred Resource, and sequencing will be guided by ongoing geophysical interpretation, allowing the Company to target conductive plates as results are received, and by the integrated three-dimensional geological and structural model. The program is anticipated to materially expand the Inferred Resource and has generated the geological data required for an updated MRE planned for the third quarter of 2026. Drill results are expected to be reported on a regular basis throughout 2026.
Previous wording
Underground development to support future infill drilling for economic studies at Selebi North was completed during the period. Key infrastructure milestones include the completion of critical ventilations, stormwater drainage works and development of the diamond drill bay. The Company will be pausing underground development works in May to prioritize resources toward expanding and extending the Selebi Main Surface Drilling Program.
Current wording
Underground development to support future infill drilling for economic studies at Selebi North was advanced in the first quarter of 2026. Key infrastructure milestones include the completion of critical ventilations, stormwater drainage works and development of a diamond drill bay. The Company paused underground development works in May to prioritize resources toward expanding and extending the Selebi Main Surface Drilling Program.
Previous wording
Results from the Selebi North Underground Resource Expansion Drilling program, ongoing results from the Selebi Main resource expansion drilling program, and BCR metallurgical test results and recovery work will be incorporated into a new MRE and PEA planned for completion in the second half of 2026.
Current wording
Results from the completed Selebi North Underground Resource Expansion Drilling program and assay results from the Selebi Main Resource Expansion Drilling program up to hole SMD-26-214, together with the BCR metallurgical test results and recovery work, will be incorporated into the 2026 MRE planned for the third quarter of 2026 and PEA currently targeted for completion in the second half of 2026.
Previous wording
2 CuEq% calculated using the formula Cu% + Ni%(55.605/53.913) + Pd g/t(22.948/53.913) + Pt g/t*(14.891/53.913) from the Selkirk Technical Report.
Current wording
1 CuEq% calculated using the formula: Cu(%)+Ni(%)(85.1/91.4)+Co(%)(93.8/91.4)+Pt(g/t)(22.4/91.4) + Pd(g/t)(33.1/91.4)+Au(g/t)(68.5/91.4)+Ag(g/t)(0.8/91.4) from the Selkirk Technical Report.
Previous wording
The key assumptions, parameters, and methods used to estimate the mineral resources are contained in the Selkirk TRS.Readers are cautioned not to assume that all or any part of an Inferred Mineral Resource exists or that, if it exists, is economically or legally mineable or that an Inferred Mineral Resource will ever be upgraded to a higher category.
Current wording
The key assumptions, parameters, and methods used to estimate the mineral resources are contained in the Selkirk TRS.Readers are cautioned not to assume that all or any part of Indicated Mineral Resources will ever be converted into Mineral Reserves as defined by S-K 1300. Readers are cautioned not to assume that all or any part of an Inferred Mineral Resource exists or that, if it exists, is economically or legally mineable or that an Inferred Mineral Resource will ever be upgraded to a higher category.
Previous wording
In July 2025, the Company commenced a 3-hole exploration program targeting untested historical Versatile Time-Domain Electromagnetic anomalies located immediately south of the Selkirk resource. The Company has completed the 3-hole exploration program, which consisted of 522 metres. Two of the three drill holes are located along the same geological horizon of the Selkirk deposit and intersected intervals of massive and disseminated sulphides. Assays for the 3-hole exploration program are pending.
Current wording
In July 2025, the Company commenced a 3-hole exploration program targeting untested historical Versatile Time-Domain Electromagnetic anomalies located immediately south of the Selkirk resource. The Company has completed the 3-hole exploration program, which consisted of 522 metres. Two of the three drill holes are located along the same geological horizon of the Selkirk deposit and intersected intervals of disseminated sulphides. Assay results indicate narrow intervals of mineralization (up to 20 metres) with grades similar to those seen at Selkirk.
Previous wording
During the quarter ended March 31, 2026, the Company incurred $586,278 (three months ended March 31, 2025 - $101,968) in exploration and evaluation expenditures on the Selkirk Mine. The Company incurred $327,109 to acquire the Selkirk Mine, and has incurred a further $8,837,191 in exploration and evaluation expenditures project-to-date as at March 31, 2026.
Current wording
During the three and six months ended June 30, 2026, the Company incurred $325,457 and $911,735 (June 30, 2025 - $1,603,705 and $1,705,673), respectively, in exploration and evaluation expenditures on the Selkirk Mine. The Company incurred $327,109 to acquire the Selkirk Mine, and has incurred a further $9,162,648 in exploration and evaluation expenditures project-to-date as at June 30, 2026.
Previous wording
As at the date of this Report, the Company has not earned revenue nor proved the economic viability of its projects. The Company’s expenses are not subject to seasonal fluctuations or general trends other than factors affecting costs such as inflation and input prices. The Company’s expenses and cash requirements will fluctuate from period to period depending on the level of activity at the projects, which may be influenced by the Company’s ability to raise capital to fund these activities. Comparisons of activity made between periods should be viewed with this in mind. The Company’s quarterly results may be affected by many factors such as timing of exploration activity, share-based compensation costs, capital raised, marketing activities and other factors that affect the Company’s exploration and evaluation activities.
Current wording
As at the date of this Report, the Company has not earned revenue nor proved the economic viability of its projects. The Company’s expenses are not subject to seasonal fluctuations or general trends other than factors affecting costs such as inflation and input prices. The Company’s expenses and cash requirements will fluctuate from period to period depending on the level of activity at the projects, which may be influenced by the Company’s ability to raise capital to fund these activities. Comparisons of activity made between periods should be viewed with this in mind. The Company’s quarterly results may be affected by many factors such as timing of exploration and study activities, share-based compensation costs, capital raised, marketing activities and other factors that affect the Company’s exploration and evaluation activities.
Previous wording
The following table summarizes the Company’s operations for the three-month periods ended March 31, 2026, and March 31, 2025:
Current wording
The following table summarizes the Company’s operations for the three- and six-month periods ended June 30, 2026, and June 30, 2025:
Previous wording
Net cash used in operating activities for the three months ended March 31, 2026, increased by $5,908,983 compared to the prior year comparable period. This increase was primarily driven by: (i) net working capital movements, including the prepayment of consumables for expansionary drilling to capture volume discounts and preferential pricing, as well as the settlement of accrued severance obligations from prior periods in the current quarter, compared to an increase in trade payables in the prior-year period as part of cash conservation measures; and (ii) an increase in general exploration expenses as the Company executed on its expansionary drilling, metallurgical flowsheet development, and other studies and evaluation work in the current year period, compared to scaled-back activities in the prior year comparable period.
Current wording
Net cash used in operating activitiesfor the six months ended June 30, 2026, decreased by $600,733 compared to the prior year comparable period. This decrease was primarily driven by a decrease in investor relations and communications expenses compared to the prior period due to strategic changes in marketing spend and the cash redemption of DSUs in the prior year period. This was partially offset by higher general exploration expenses including the advanced purchase of consumables for the Selebi Main Expansionary Drilling Program and net working capital movements, including current period settlement of accrued severance obligations from prior periods, compared to an increase in trade payables in the prior year period as part of cash conservation measures.
Previous wording
Key investing activities relate to the acquisition of property, plant and equipment. Net cash used in investing activities for the three months ended March 31, 2026, increased by $718,463 compared to the prior year comparable period. The higher spending in 2026 primarily relates to the remaining payment on a second deep drill and additional mobile and electrical equipment.
Current wording
Key investing activities relate to the acquisition of property, plant and equipment. Net cash used in investing activities decreased by $695,818 for the six months ended June 30, 2026. Spend in 2026 primarily relates to the remaining payment on a second deep drill and additional mobile and electrical equipment. During 2025, investing activities included the purchase of the Company’s first deep drill for the surface drilling programs, kits for converting two underground U5 drills into surface A5 drills, and light duty vehicles.
Previous wording
Net cash provided by financing activities for the three months ended March 31, 2026, decreased by $45,834,429 compared to the prior year comparable period. The decrease primarily reflects the closing of the Private Placement financing (as defined herein) in March 2025 for gross proceeds of $46,000,000. The Company did not execute any public or private placements during the current year period.
Current wording
Net cash provided by financing activities for the six months ended June 30, 2026, decreased by $44,111,025 compared to the prior year comparable period. The decrease primarily reflects the closing of the Private Placement financing (as defined herein) in March 2025 for gross proceeds of $46,000,000. The Company did not execute any public or private placements during the current year period.
Previous wording
As at March 31, 2026, the Company had $26,220,756 in available cash and cash equivalents (December 31, 2025 – $39,780,384), with no source of operating cash flows, nor any significant credit lines in place. As at March 31, 2026, the Company had working capital (calculated as total current assets less total current liabilities) of $26,519,278 (December 31, 2025 – $36,517,724). The decrease in working capital is a result of the use of cash in general exploration expenses and investment in drilling and other equipment.
Current wording
As at June 30, 2026, the Company had $16,956,564 in available cash and cash equivalents (December 31, 2025 – $39,780,384), with no source of operating cash flows, nor any significant credit lines in place. As at June 30, 2026, the Company had working capital (calculated as total current assets less total current liabilities) of $15,101,589 (December 31, 2025 – $36,517,724). The decrease in working capital is a result of the use of cash in general exploration expenses and investment in drilling and other equipment.
Previous wording
Based on the Company’s current operational plan, the Company has sufficient working capital to advance its currently planned activities, including the completion of a PEA for the Selebi Mines, and to fund administrative costs into the fourth quarter of 2026.
Current wording
Based on the Company’s current operational plan, the Company has sufficient working capital to advance its currently planned activities and to fund administrative costs into the fourth quarter of 2026, including the completion of a PEA for the Selebi Mines and potential economic study for the Selkirk Mine.
Previous wording
The Company continues to actively monitor its funding requirements and intends to pursue a range of financing alternatives in advance of year-end 2026 to support the continued advancement of the Selebi Mines and the Selkirk Mine toward development.
Current wording
The Company continues to actively monitor its funding requirements and is evaluating a range of financing alternatives that may include joint ventures, earn-in arrangements, royalty or stream transactions, strategic private placements or a broader offering of equity. To meet the Company’s funding requirements for the continued advancement of the Selebi Mines and the Selkirk Mine toward development, it intends to announce one or more of these transactions prior to year-end 2026. With the 2026 Selkirk MRE now complete, the Company is also evaluating additional strategic and funding optionality for the asset.
Previous wording
The ability of the Company to continue operations as a going concern is ultimately dependent upon achieving profitable operations and its ability to obtain adequate financing. The Company incurred a net loss of $10,623,437 for the three months ended March 31, 2026 (net loss of $15,228,330 for the three months ended March 31, 2025). To date, the Company has not generated profitable operations from its resource activities. It is not possible to predict whether future financing efforts will be successful or if the Company will attain a profitable level of operations. These material uncertainties cast substantial doubt about the Company’s ability to continue as a going concern. The accompanying unaudited condensed interim consolidated financial statements do not include any adjustments relating to the recoverability and classification of recorded asset amounts and classification of liabilities, and the reported expenses and comprehensive loss that might be necessary should the Company be unable to continue as a going concern. These adjustments could be material. In assessing whether a going concern assumption is appropriate, management considers all available information about the future, which is at least, but not limited to, twelve months from the date of this Report.
Current wording
The ability of the Company to continue operations as a going concern is ultimately dependent upon achieving profitable operations and its ability to obtain adequate financing. The Company incurred a net loss of $11,863,297 and $22,486,734 for the three and six months ended June 30, 2026 (June 30, 2025 - $15,088,746 and $30,317,076), respectively. To date, the Company has not generated profitable operations from its resource activities. It is not possible to predict whether future financing efforts will be successful or if the Company will attain a profitable level of operations. These material uncertainties cast substantial doubt about the Company’s ability to continue as a going concern. The accompanying unaudited condensed interim consolidated financial statements do not include any adjustments relating to the recoverability and classification of recorded asset amounts and classification of liabilities, and the reported expenses and comprehensive loss that might be necessary should the Company be unable to continue as a going concern. These adjustments could be material. In assessing whether a going concern assumption is appropriate, management considers all available information about the future, which is at least, but not limited to, twelve months from the date of this Report.
Previous wording
As of March 31, 2026, the Company had commitments for capital expenditures over the next 12 months of $nil and the following other contractual obligations and commitments:
Current wording
As of June 30, 2026, the Company had commitments for capital expenditures over the next 12 months of $75,000 and the following other contractual obligations and commitments:
Previous wording
In addition to the Selebi APA, the purchase of the Selebi Mines is also subject to a royalty agreement as well as a contingent consideration agreement with the BCL Liquidator. The royalty agreement consists of a Net Smelter Return (“NSR”) royalty of 2% on the net value of sales of concentrate or other materials with respect to production from the Selebi mining licence, of which the Company has the right to buy-back 50%. The contingent consideration agreement consists of two components: (i) a sliding scale payment of US$0.50/tonne of ore up to US$1.40/tonne of ore with respect to the discovery of new mineable deposits greater than 25 million tonnes of ore from a base case of 15.9 million tonnes, with a minimum grade of 2.5% nickel equivalent, accrued at the time of a decision to mine; and (ii) price participation of 15% on post-tax net earnings directly attributable to an increase of 25% or more in commodity prices, on a quarterly basis, for a period of seven years from the date of first shipment of concentrate or other materials.
Current wording
In addition to the Selebi APA, the purchase of the Selebi Mines is also subject to a royalty agreement as well as a contingent consideration agreement with the BCL Liquidator. The royalty agreement consists of a NSR royalty of 2% on the net value of sales of concentrate or other materials with respect to production from the Selebi mining licence, of which the Company has the right to buy-back 50%. The contingent consideration agreement consists of two components: (i) a sliding scale payment of US$0.50/tonne of ore up to US$1.40/tonne of ore with respect to the discovery of new mineable deposits greater than 25 million tonnes of ore from a base case of 15.9 million tonnes, with a minimum grade of 2.5% nickel equivalent, accrued at the time of a decision to mine; and (ii) price participation of 15% on post-tax net earnings directly attributable to an increase of 25% or more in commodity prices, on a quarterly basis, for a period of seven years from the date of first shipment of concentrate or other materials.
Previous wording
In regard to the Selkirk Mine, the purchase agreement does not provide for a purchase price or initial payment for the purchase of the assets. The Selkirk APA provides that if Selkirk were commissioned earlier than Selebi, the payment of the third Selebi instalment of US$30 million, would trigger on Selkirk’s commission date. The Selkirk APA provides for a three-year study phase originally expiring August 17, 2025, which has been extended for one year to August 17, 2026.
Current wording
The Selkirk APA does not provide for a purchase price or initial payment for the purchase of the assets. It instead provides that if Selkirk were commissioned earlier than Selebi, the payment of the third Selebi instalment of US$30 million, would trigger on Selkirk’s commission date. The Company has applied for, and is awaiting confirmation of, an extension of the Selkirk APA study phase to coincide with the expiry of the Selebi APA study phase, being December 31, 2026.
Previous wording
The Company received $2,750,000 from Cymbria for their right to participate in the Company’s right to repurchase one-half of the Selebi NSR and the entirety of the Selkirk NSR. Cymbria also has the right: (i) at any time following the date of any buyback exercise notice from PNRPL and/or PNGPL and prior to the first anniversary of sale of product, to terminate the option and receive from PNRPL and/or PNGPL a refund of the related option price paid by Cymbria; (ii) upon receipt from PNRPL and/or PNGPL of any termination, settlement or waiver of the buyback right or royalty agreement and prior to the first anniversary of sale of product, to exercise the option or terminate the option, and if terminated PNRPL and/or PNGPL shall refund the related option price paid by Cymbria; (iii) to exercise the option and compel PNRPL and/or PNGPL to exercise the buyback right at any time within the first nine months immediately following the first anniversary of sale of product and not less than 60 days prior to the date of exercise of the buyback right; and (iv) to require PNRPL and/or PNGPL to repurchase the option from Cymbria for an amount equal to the option price at any time commencing on the first anniversary of sale of product, provided PNRPL and/or PNGPL have not provided a buyback exercise notice or notice of any termination, settlement or waiver of the buyback right or royalty agreement to Cymbria.
Current wording
The Company received $2,750,000 from Cymbria for their right to participate in the Company’s right to repurchase one-half of the Selebi NSR and the entirety of the Selkirk NSR. Cymbria also has the right: (i) at any time following the date of any buyback exercise notice from PNRPL and/or PNGPL and prior to the first anniversary of sale of product, to terminate the option and receive from PNRPL and/or PNGPL a refund of the related option price paid by Cymbria; (ii) upon receipt from PNRPL and/or PNGPL of any termination, settlement or waiver of the buyback right or royalty agreement and prior to the first anniversary of sale of product, to exercise the option or terminate the option, and if terminated PNRPL and/or PNGPL shall refund the related option price paid by Cymbria; (iii) to exercise the option and compel PNRPL and/or PNGPL to exercise the buyback right at any time within the first nine months immediately following the first anniversary of sale of product upon a minimum 60 days’ notice; and (iv) to require PNRPL and/or PNGPL to repurchase the option from Cymbria for an amount equal to the option price at any time commencing on the first anniversary of sale of product, provided PNRPL and/or PNGPL have not provided a buyback exercise notice or notice of any termination, settlement or waiver of the buyback right or royalty agreement to Cymbria.
Previous wording
The Company’s exposure to interest rate risk arises from the interest rate impact on its cash and cash equivalents and debt facilities. Interest incurred on the vehicle financing and mortgage payable is based upon a variable base rate, being the lending institution’s prime lending rate, plus a fixed rate margin. Each one percentage point change in interest rates would result in a $14,677 change in annual interest expense.
Current wording
The Company’s exposure to interest rate risk arises from the interest rate impact on its cash and cash equivalents and debt facilities. Interest incurred on the vehicle financing and mortgage payable is based upon a variable base rate, being the lending institution’s prime lending rate, plus a fixed rate margin. Each one percentage point change in interest rates would result in a $14,221 change in annual interest expense.
Rearranged current paragraphs (1)
Current report — wording carried from elsewhere
Building on the targets identified to-date, the Company is executing on a Selebi Main Surface Drilling Program using BHEM surveys to define drill targets, with more than 30,000 metres planned to support resource expansion and re-classification at Selebi Main throughout 2026. Drilling will continue to test both the Main Zone and Lower Zone, where current drilling results and BHEM modelling indicate increased thicknesses down-dip of the 2024 MRE and down plunge to the north.
Rearranged previous paragraphs (1)
Previous report — wording carried elsewhere
The program is being executed using three company-owned underground U5 drills which were converted into surface A5 drills, and two Marcotte HTM2500 drills purchased by the Company capable of drilling to depths of 2,500 metres (NQ core), the second of which arrived on site on April 28, 2026.