EX-99 · Table 13.6: Variable Usage Equipment

Table 13.6: Variable Usage Equipment

EquipmentAnnual Hours Available (st/EH)Productivity (st/EH)
Excavator6,0131,050
Loader6,013803
Haul Truck6,013363 - 112
Dozer5,3261,000
Drill5,3261,410

Table 13.7: Annual Schedule of Variable Usage Equipment

Year1234567891011Total
Loader Hours (000s)16.120.119.716.816.915.112.112.313.27.64.8155
Loader Units454333222225
Truck Productivity (st/EH)36329326228827224823321411311268257
Truck Hours Req’d 000s)61981078895988177996561929
Truck Units111718151617141317111118
Dozer Hours (000s)2437373737373737323221371
Dozer Units577777776647

Haul truck productivity is variable and is based on a haulage model that calculates cycle times based on the location of the material mined and the destination. Cycle times and the mine schedule are used to estimate the truck hours needed to meet the schedule. The annual available hours are based on the distance and the average speed for the haulage segment, with allowances for loading, dumping, and waiting. For excavators and wheel loaders the estimated productivity is based on the calculated loading times to position and fill the selected haul trucks. Dozer productivity is based on manufacturer nomographs. Blasthole drill productivity is based on average penetration rates and blast spacing to break the scheduled rock per the detailed fragmentation provided by a blasting manufacturer. Other minor and support equipment does not have a calculated productivity, but a fixed annual usage is assigned based on similar surface mining operations. Table 13.8 shows the fleet size and scheduled hours for the fixed usage equipment.

Table 13.8: Fixed Usage Equipment

EquipmentHours Scheduled per UnitFleet Size
Water Truck5,3264
Motor Grader5,3263
Service/Fuel Truck5,3262
Crane Truck1,0001
Excavator6,0131
13.10MINE PERSONNEL REQUIREMENTS

Hourly mine personnel requirements for equipment operators and mechanical labor are based on the annual equipment hourly usage. Salaried based employees are specified at typical staffing levels. All hourly mine employees and supervision of all mine employees are by the mine owner. The owner also provides Site General and Administrative (Site G&A) labor, mine planning and engineering, and environmental compliance. Table 13.9 shows the total project employment over the life of the Project and subsequent tables provide mine employment (Table 13.10), tailings disposal employment (Table 13.11) and site G&A employment (Table 13.12).

CK Gold Project S-K 1300 Technical Report170May 2026

Table 13.9 Mine Employment

Year-2-11234567891011Total
Mine Employment729180251255233241244224220207138100255
Tailings Employment00304848444444404058574357
Mine G&A27232727272727272725191227
Total Mine Employment936233326330304312315291287290224155330

Table 13.10 Mine Employment Detailed Breakdown

Year-2-11234567891011Total
Loading and Hauling39527276636868595964313194
Loading Operators13182217131313131314101022
Hauling Operators26345059505555464650212159
Drill and Blast524292924242418181329
Mine Support23436060606060606050443260
Mine Maintenance-5386363596265605655342263
Mine G&A27232727272727272725291227
Mine Total72918025125523324124422422020713897255

Table 13.11 Tailings Disposal Employment

Year-2-11234567891011Total
Hauling Operators00132121171717131326302630
Tailing Support00172727272727272727271727
Tailings Total00304848444444404053574357

Table 13.12 Mine G&A Employment

Year-2-11234567891011Total
Operations Manager11111111111111
Mine General Foreman12222222222212
Dispatch Builder02222222222212
Dispatch Operator02222222222212
Drill and Blast Supervisor899999999449
Mine Supervisors122222221002
Fuel Truck Operator344444444424
Mine Laborer455555554425
Mine G&A Total27232727272727272725191227
CK Gold Project S-K 1300 Technical Report171May 2026
13.11MINE END OF PERIOD PROGRESSION MAPS

End of year topographic maps showing the excavation progression are shown in Figure 13.8 to Figure 13.16.

Figure 13.8: Mine Progression – End of Year 1

Figure 13.9: Mine Progression – End of Year 2

CK Gold Project S-K 1300 Technical Report172May 2026

Figure 13.10: Mine Progression – End of Year 3

Figure 13.11: Mine Progression – End of Year 4

CK Gold Project S-K 1300 Technical Report173May 2026

Figure 13.12: Mine Progression – End of Year 5

Figure 13.13: Mine Progression – End of Year 6

CK Gold Project S-K 1300 Technical Report174May 2026

Figure 13.14: Mine Progression – End of Year 7

Figure 13.15: Mine Progression – End of Year 8

CK Gold Project S-K 1300 Technical Report175May 2026

Figure 13.16: Mine Progression – End of Year 9

CK Gold Project S-K 1300 Technical Report176May 2026
ContentsView on SEC.gov

The text of this filing, as the company filed it with the SEC, without its images or exhibits. This is not investment advice.