U.S. GOLD CORP.
For the period ended May 13, 2026. Filed May 15, 2026.
View on SEC.govAbout this filing
A notice of a major event between regular reports, such as results, a deal or a change of executives. It is often the first formal record of the news.
May 13, 2026 · Filed May 15, 2026
Use the contents to explore the available documents and sections.
Contents
EX-99 · Table 13.6: Variable Usage Equipment
Table 13.6: Variable Usage Equipment
| Equipment | Annual Hours Available (st/EH) | Productivity (st/EH) |
|---|---|---|
| Excavator | 6,013 | 1,050 |
| Loader | 6,013 | 803 |
| Haul Truck | 6,013 | 363 - 112 |
| Dozer | 5,326 | 1,000 |
| Drill | 5,326 | 1,410 |
Table 13.7: Annual Schedule of Variable Usage Equipment
| Year | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | Total |
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Loader Hours (000s) | 16.1 | 20.1 | 19.7 | 16.8 | 16.9 | 15.1 | 12.1 | 12.3 | 13.2 | 7.6 | 4.8 | 155 |
| Loader Units | 4 | 5 | 4 | 3 | 3 | 3 | 2 | 2 | 2 | 2 | 2 | 5 |
| Truck Productivity (st/EH) | 363 | 293 | 262 | 288 | 272 | 248 | 233 | 214 | 113 | 112 | 68 | 257 |
| Truck Hours Req’d 000s) | 61 | 98 | 107 | 88 | 95 | 98 | 81 | 77 | 99 | 65 | 61 | 929 |
| Truck Units | 11 | 17 | 18 | 15 | 16 | 17 | 14 | 13 | 17 | 11 | 11 | 18 |
| Dozer Hours (000s) | 24 | 37 | 37 | 37 | 37 | 37 | 37 | 37 | 32 | 32 | 21 | 371 |
| Dozer Units | 5 | 7 | 7 | 7 | 7 | 7 | 7 | 7 | 6 | 6 | 4 | 7 |
Haul truck productivity is variable and is based on a haulage model that calculates cycle times based on the location of the material mined and the destination. Cycle times and the mine schedule are used to estimate the truck hours needed to meet the schedule. The annual available hours are based on the distance and the average speed for the haulage segment, with allowances for loading, dumping, and waiting. For excavators and wheel loaders the estimated productivity is based on the calculated loading times to position and fill the selected haul trucks. Dozer productivity is based on manufacturer nomographs. Blasthole drill productivity is based on average penetration rates and blast spacing to break the scheduled rock per the detailed fragmentation provided by a blasting manufacturer. Other minor and support equipment does not have a calculated productivity, but a fixed annual usage is assigned based on similar surface mining operations. Table 13.8 shows the fleet size and scheduled hours for the fixed usage equipment.
Table 13.8: Fixed Usage Equipment
| Equipment | Hours Scheduled per Unit | Fleet Size |
|---|---|---|
| Water Truck | 5,326 | 4 |
| Motor Grader | 5,326 | 3 |
| Service/Fuel Truck | 5,326 | 2 |
| Crane Truck | 1,000 | 1 |
| Excavator | 6,013 | 1 |
| 13.10 | MINE PERSONNEL REQUIREMENTS |
Hourly mine personnel requirements for equipment operators and mechanical labor are based on the annual equipment hourly usage. Salaried based employees are specified at typical staffing levels. All hourly mine employees and supervision of all mine employees are by the mine owner. The owner also provides Site General and Administrative (Site G&A) labor, mine planning and engineering, and environmental compliance. Table 13.9 shows the total project employment over the life of the Project and subsequent tables provide mine employment (Table 13.10), tailings disposal employment (Table 13.11) and site G&A employment (Table 13.12).
| CK Gold Project S-K 1300 Technical Report | 170 | May 2026 |
|---|
Table 13.9 Mine Employment
| Year | -2 | -1 | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | Total |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Mine Employment | 7 | 29 | 180 | 251 | 255 | 233 | 241 | 244 | 224 | 220 | 207 | 138 | 100 | 255 |
| Tailings Employment | 0 | 0 | 30 | 48 | 48 | 44 | 44 | 44 | 40 | 40 | 58 | 57 | 43 | 57 |
| Mine G&A | 2 | 7 | 23 | 27 | 27 | 27 | 27 | 27 | 27 | 27 | 25 | 19 | 12 | 27 |
| Total Mine Employment | 9 | 36 | 233 | 326 | 330 | 304 | 312 | 315 | 291 | 287 | 290 | 224 | 155 | 330 |
Table 13.10 Mine Employment Detailed Breakdown
| Year | -2 | -1 | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | Total |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Loading and Hauling | 3 | 9 | 52 | 72 | 76 | 63 | 68 | 68 | 59 | 59 | 64 | 31 | 31 | 94 |
| Loading Operators | 1 | 3 | 18 | 22 | 17 | 13 | 13 | 13 | 13 | 13 | 14 | 10 | 10 | 22 |
| Hauling Operators | 2 | 6 | 34 | 50 | 59 | 50 | 55 | 55 | 46 | 46 | 50 | 21 | 21 | 59 |
| Drill and Blast | 5 | 24 | 29 | 29 | 24 | 24 | 24 | 18 | 18 | 13 | 29 | |||
| Mine Support | 2 | 3 | 43 | 60 | 60 | 60 | 60 | 60 | 60 | 60 | 50 | 44 | 32 | 60 |
| Mine Maintenance | - | 5 | 38 | 63 | 63 | 59 | 62 | 65 | 60 | 56 | 55 | 34 | 22 | 63 |
| Mine G&A | 2 | 7 | 23 | 27 | 27 | 27 | 27 | 27 | 27 | 27 | 25 | 29 | 12 | 27 |
| Mine Total | 7 | 29 | 180 | 251 | 255 | 233 | 241 | 244 | 224 | 220 | 207 | 138 | 97 | 255 |
Table 13.11 Tailings Disposal Employment
| Year | -2 | -1 | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | Total |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Hauling Operators | 0 | 0 | 13 | 21 | 21 | 17 | 17 | 17 | 13 | 13 | 26 | 30 | 26 | 30 |
| Tailing Support | 0 | 0 | 17 | 27 | 27 | 27 | 27 | 27 | 27 | 27 | 27 | 27 | 17 | 27 |
| Tailings Total | 0 | 0 | 30 | 48 | 48 | 44 | 44 | 44 | 40 | 40 | 53 | 57 | 43 | 57 |
Table 13.12 Mine G&A Employment
| Year | -2 | -1 | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | Total |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Operations Manager | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 |
| Mine General Foreman | 1 | 2 | 2 | 2 | 2 | 2 | 2 | 2 | 2 | 2 | 2 | 2 | 1 | 2 |
| Dispatch Builder | 0 | 2 | 2 | 2 | 2 | 2 | 2 | 2 | 2 | 2 | 2 | 2 | 1 | 2 |
| Dispatch Operator | 0 | 2 | 2 | 2 | 2 | 2 | 2 | 2 | 2 | 2 | 2 | 2 | 1 | 2 |
| Drill and Blast Supervisor | 8 | 9 | 9 | 9 | 9 | 9 | 9 | 9 | 9 | 4 | 4 | 9 | ||
| Mine Supervisors | 1 | 2 | 2 | 2 | 2 | 2 | 2 | 2 | 1 | 0 | 0 | 2 | ||
| Fuel Truck Operator | 3 | 4 | 4 | 4 | 4 | 4 | 4 | 4 | 4 | 4 | 2 | 4 | ||
| Mine Laborer | 4 | 5 | 5 | 5 | 5 | 5 | 5 | 5 | 4 | 4 | 2 | 5 | ||
| Mine G&A Total | 2 | 7 | 23 | 27 | 27 | 27 | 27 | 27 | 27 | 27 | 25 | 19 | 12 | 27 |
| CK Gold Project S-K 1300 Technical Report | 171 | May 2026 |
|---|
| 13.11 | MINE END OF PERIOD PROGRESSION MAPS |
End of year topographic maps showing the excavation progression are shown in Figure 13.8 to Figure 13.16.
Figure 13.8: Mine Progression – End of Year 1
Figure 13.9: Mine Progression – End of Year 2
| CK Gold Project S-K 1300 Technical Report | 172 | May 2026 |
|---|
Figure 13.10: Mine Progression – End of Year 3
Figure 13.11: Mine Progression – End of Year 4
| CK Gold Project S-K 1300 Technical Report | 173 | May 2026 |
|---|
Figure 13.12: Mine Progression – End of Year 5
Figure 13.13: Mine Progression – End of Year 6
| CK Gold Project S-K 1300 Technical Report | 174 | May 2026 |
|---|
Figure 13.14: Mine Progression – End of Year 7
Figure 13.15: Mine Progression – End of Year 8
| CK Gold Project S-K 1300 Technical Report | 175 | May 2026 |
|---|
Figure 13.16: Mine Progression – End of Year 9
| CK Gold Project S-K 1300 Technical Report | 176 | May 2026 |
|---|
The text of this filing, as the company filed it with the SEC, without its images or exhibits. This is not investment advice.