| Item 1. | Legal Proceedings |
|---|
At any point in time, we may be involved in various lawsuits or other legal proceedings. Such lawsuits could arise from the sale of products or services or from other matters relating to our regular business activities, compliance with various governmental regulations and requirements, or other transactions or circumstances.
EPA
We have been named as a party in the December 19, 2019 United States Environmental Protection Agency (“EPA”) Demand Letter regarding the Malta Rocket Fuel Area Superfund Site (“Site”) located in Malta and Stillwater, New York, in connection with an alleged release of hazardous materials into the environment. The EPA is seeking reimbursement of response costs from all named parties in the amount of approximately $358 thousand plus interest in connection with the investigation and disposal activities associated with the various drum caches discovered at the Site, issuance of the Explanation of Significant Differences (“ESD”) of the Site, and implementation of the work contemplated by the ESD. We consider the likelihood of a material adverse outcome with respect to this matter to be remote and do not currently anticipate that any expense or liability that we may incur as a result of this matter in the future will be material to the Company’s business or financial condition.
NYDIG
NYDIG ABL LLC, (“NYDIG”) filed a complaint against SMCB1(“Borrower”) and SMC (“Guarantor”, and together with Borrower, “NYDIG Defendants”) in Marshall Circuit Court of the Commonwealth of Kentucky on December 29, 2022 regarding a series of loans (the “NYDIG Loans”) made by NYDIG to Borrower pursuant to a Master Equipment Finance Agreement (“MEFA”) that were secured by certain assets of Borrower and guaranteed by Guarantor pursuant to a written guaranty agreement executed by Guarantor. On February 15, 2023, the Court approved an agreed order granting NYDIG’s motion for writ of possession which, among other things, ordered the NYDIG Defendants to provide NYDIG access to the collateral securing the NYDIG Loans and preserved the rights of NYDIG to pursue a deficiency judgment against the NYDIG Defendants. Also on February 15, 2023, the NYDIG Defendants filed their answer and affirmative defenses in this proceeding. On February 23, 2023, NYDIG proceeded to foreclose on all of the collateral securing the MEFA, and repossessed the collateralized assets that totaled approximately $3.4 million, of which approximately $560 thousand was first used to pay off accrued interest and penalties to date. On September 5, 2023, NYDIG provided a letter finalizing the accounting for the repossessed collateralized assets totaling proceeds of approximately $3.4 million. This included legal and other expenses associated with the sale of the assets, net a modest gain on the estimated net book value of the assets totaling $251 thousand that was expensed as a loss on disposition of assets for the year ended December 31, 2023. On December 7, 2023, NYDIG filed its Motion for Summary Judgment seeking entry of a judgment against the NYDIG Defendants in the approximate amount of $10.3 million for principal and interest and penalties. On January 12, 2024, the NYDIG Defendants filed their objection to NYDIG’s motion for summary judgment on the grounds that NYDIG failed to explain what collateral of which loan was sold and how the sale proceeds were allocated and applied to each loan. NYDIG and the NYDIG Defendants consensually resolved the motion in the form of a Stipulation and Agreed Judgment, which the Court approved on February 23, 2024.
On March 13, 2024, NYDIG served the NYDIG Defendants with a post-judgment discovery seeking information regarding the NYDIG Defendants’ assets and liabilities. Per agreement between NYDIG and the NYDIG Defendants, the deadline to respond to the discovery demands was extended to May 13, 2024 but with rolling weekly production that commenced on April 12, 2024. The NYDIG Defendants completed responding to NYDIG’s initial document requests on May 13, 2024. On September 24, 2024, NYDIG sent a letter seeking supplemental discovery from the NYDIG Defendants. The NYDIG Defendants responded seeking clarification from NYDIG regarding their supplemental requests. On November 6, 2024, NYDIG sent a second “meet and confer” letter seeking (i) the production of additional/supplemental documents from Soluna by November 20, 2024 and (ii) the deposition of a representative of the Defendants on or before December 15, 2024. The parties remain in discussions regarding the requested supplemental discovery.
Additionally, NYDIG has stated its intention to pursue SCI, the parent company of Guarantor, under a piercing of the corporate veil theory relating to NYDIG Defendants’ debts and liabilities under the loan documents. The Company intends to vigorously defend itself from NYDIG’s parent company claims. SCI denies any such liability and has filed a complaint for a declaratory judgment against NYDIG in the Eighth Judicial District Court in Clark County, Nevada on March 16, 2023, seeking a declaratory judgment as to such matter. NYDIG filed a motion to dismiss in response to SCI’s declaratory judgment complaint on April 13, 2023. SCI filed a response in opposition to NYDIG’s motion to dismiss on April 27, 2023. The court heard oral arguments on May 16, 2023. On June 22, 2023, the court issued an order granting NYDIG’s motion to dismiss, on the basis that the case was not ripe for decision, without prejudice. SCI intends to continue to vigorously defend any allegations regarding liability on account of NYDIG Defendants’ debts and liabilities to NYDIG under their loan documents and intends to refile a declaratory judgment complaint against NYDIG.
Atlas
In September 2023, Atlas Technology Group LLC (“Atlas”) filed a complaint against Soluna MC LLC, Soluna Computing, Inc., and Soluna Holdings, Inc. (collectively, the “Atlas Defendants”) in the Supreme Court of New York regarding a co-location services agreement. Atlas alleged that Soluna MC’s termination of the agreement was a breach, seeking a return of pre-paid fees of approximately $464 thousand, additional damages of at least $7.9 million, and reimbursement of legal fees. The complaint also mentioned alter ego liability and corporate veil piercing.
The Atlas Defendants filed a motion to dismiss, and on April 17, 2024, the Court dismissed three of the four counts. The remaining count was answered on May 6, 2024, with counterclaims against Atlas. The Court denied the dismissal of Soluna Computing, Inc. and Soluna Holdings, Inc. as parties, leading to an appeal filed on May 7, 2024.
On June 25, 2024, Atlas and the Atlas Defendants entered into a settlement agreement.