POWERBANK Corp

For the period ended Jun 30, 2024. Filed Oct 1, 2024.

View on SEC.gov

About this filing

The yearly report of certain Canadian companies, filed under a joint US and Canadian system. It is the main yearly account these companies give US investors, largely as filed in Canada.

FY2024 · Filed Oct 1, 2024

Use the contents to explore the available documents and sections.

PBK$0.13-7.2%Stored close · as of Nov 6, 2026
See the whole filing, with its images and exhibits
Contents

EX-99.5 · ● Projects under development

Projects under development

NameLocationSize (MWDC)TimelineMilestoneExpected Cost ($)Cost Incurred ($)Sources of FundingCurrent Status
261 TownshipAlberta, Canada4.2June 2024NTP800,000155,697Equity financing, working capitalPhase 1 construction started in July 2024.Interconnection for Phase 2 is being prepared to submit after the interconnection agreement is executed for phase 1 with Fortis.
HardieNew York, USA7.0December 2024NTP1,355,0001,207,453Equity financing, working capitalThe project received interconnection approval and is in the final stage of permitting process.
6882 Rice Road (East Bloomfield)New York, USA5.2December 2024NTP2,580,000128,471Equity financing, working capitalThe project received interconnection approval and is in the final stage of permitting process.
SUNYNew York, USA28.0December 2025Completion of interconnection studies, engineering and permitting, along with interconnection deposit, and procurement bid application fee900,000170,975Equity financing, working capitalThe Company is preparing an interconnection request to New York Independent System Operator under the new cluster study rules. The interconnection window was open on August 1st, 2024. The company signed a lease agreement with the landowner in 2022. It has also qualified to submit a Proposal under NYSERDA’s RESRFP22-1 for Renewable Energy Credits (RECs).
NS ProjectsNova Scotia, Canada31.0December 2025NTP900,000180,292.85Equity financing, working capitalThe company is preparing the application package for the Community Solar Program.
Black CreekNew York, USA3.2December 2025NTP700,00024,188Equity financing, working capitalThe project is under interconnection study
Orleans ProjectsNew York, USA30December 2024NTP9,150,00057,048Equity financing, working capitalThe project is under interconnection study.
Oak OrchardNew York, USA7June 2025NTP1,900,00027,982Equity financing, working capitalThe project is under interconnection study.
BoyleNew York, USA5.4June 2025NTP1,150,00014,567Equity financing, working capitalThe project is under interconnection study
CamillusNew York USA3.15September 2024NTP1,700,0002,169,644Equity financing, working capitalThe project received interconnection approval and is in the final stage of permitting process.