LIGHTBRIDGE Corp
For the period ended Dec 31, 2025. Filed Feb 26, 2026.
View on SEC.govAbout this filing
A company's yearly report to the SEC, with audited financial statements. It is the fullest account a company gives of its business, its finances and the risks it sees.
FY2025 · Filed Feb 26, 2026
What changed in Management’s Discussion and Analysis?
Read the current filingPrevious report: 10-K
Period ended 2024-12-31; filed 2025-03-03.
0001477932-25-001404
Item 7. Management’s Discussion and Analysis of Financial Condition and Results of OperationsCurrent report: 10-K
Period ended 2025-12-31; filed 2026-02-26.
0001477932-26-001076
Item 7. Management’s Discussion and Analysis of Financial Condition and Results of OperationsThe baseline is this issuer’s latest earlier reporting period of the same form that was filed before the current report. A previous 10-Q is a different quarter, not a year-over-year comparison. Amendments are excluded.
Compared 109 previous paragraphs and 94 current paragraphs.
23 unchanged; 26 reworded; 42 added; 58 removed; 2 previous and 3 current paragraphs rearranged.
Tables are not compared: 7 previous and 7 current tables excluded. Dates, whitespace, punctuation and numbering changes are ignored; changes to financial figures remain significant.
A changed paragraph is not evidence that risk increased or decreased. An unchanged paragraph does not establish that risk stayed the same.
Added paragraphs (42)
Current report
Memorandum of Understanding with Oklo, Inc.
Current report
In January 2025, we signed a MOU with Oklo to: (1) conduct a preliminary evaluation of feasibility of co-locating a Lightbridge Commercial-scale Fuel Fabrication Facility at Oklo’s proposed commercial fuel fabrication facility; (2) explore opportunities for collaboration on reprocessing and recycling of spent uranium zirconium fuel; and (3) explore any other areas of collaboration that may be of mutual interest. We believe there may be some potential synergies in co-locating our expandable fuel facility at Oklo’s proposed site. We also believe that recycling and reprocessing spent uranium-zirconium fuel may represent another area of potential synergies.
Current report
Master Services Agreement with Amentum Technology Inc.
Current report
In December 2025, the Company entered into a MSA with Amentum relating to the performance of activities by Amentum in support of the co-location feasibility study under the MOU with Oklo, as well as other activities as the Company and Amentum may agree from time to time. In January 2026, we entered into a statement of work under our MSA with Amentum pursuant to which we expect to incur approximately $0.4 million in costs during 2026 related to the Oklo co-location feasibility study.
Current report
Memorandum of Understanding and Collaborative Agreement for Cladding Alloy Compositions
Current report
In November 2025, Lightbridge entered into an MOU and a separate Collaboration Agreement with a U.S. manufacturer specializing in advanced specialty metals to support the research and development of cladding alloy compositions for potential use as cladding materials for Lightbridge Fuel™. Under the MOU, the parties agreed to pursue a phased technical evaluation program beginning with alloy development, melting, processing, and characterization activities (Phase 1). The Collaboration Agreement governs the conduct of Phase 1 research and provides a framework for developing future project plans. Lightbridge expects to incur approximately $0.3 million in Phase 1 costs in 2026, which will be expensed as incurred and included in research and development expenses.
Current report
During 2025, previous task statements under both the SPPA and CRADA were modified to increase potential amounts payable to BEA. The duration of the umbrella SPPA was also extended from 7 to 12 years, and the performance period of the umbrella CRADA was extended from September 27, 2029 to September 27, 2032. In the fourth quarter of 2025, the Company and BEA entered into several new project task statements under the SPPA for BEA to provide technical consultation on drafting a fuel qualification plan, post-irradiation examination of fuel specimens, and code development for safety analysis and fuel performance modeling.
Current report
After accounting for all modifications and new project task statements, cash payments from the Company to BEA under both CRADA and SPPA are estimated at approximately $19.5 million on a cost reimbursable basis over the performance periods. During 2025, we expensed $2.9 million of costs reimbursable to BEA, resulting in cumulative expenses of $5.4 million recorded to date and $14.1 million remaining in future cost reimbursements, if and when incurred by BEA.
Current report
Purchase of High-Performance Computer for Fuel Modeling
Current report
During the fourth quarter of 2025, the Company completed the purchase of a HPC. The HPC is specifically configured for advanced nuclear modeling and requires specialized software and environmental conditions and provides a significant expansion of computational capability necessary for us to continue developing and simulating the viability of our nuclear fuel technology. To support the HPC, the Company also entered into agreements with additional vendors to provide co-location services, hardware/software management services, and additional nuclear simulation software. Costs for the HPC and related services and software are expensed as incurred and included in research and development expenses. Such items totaled approximately $2.0 million for the year ended December 31, 2025.
Current report
Software Code Development Agreements
Current report
In October 2025, we entered into an Agreement for Safety Analysis Codes and Services for Lightbridge Fuel Designs with NAS, a provider of nuclear engineering analysis software. Under the agreement, NAS will perform code-development, benchmarking, and modeling services to support the creation of Lightbridge’s proprietary fuel-safety analysis methods and the adaptation of industry-standard computer codes for the Lightbridge Fuel™ helical-cruciform metallic U-Zr design. The estimated completion window is between October 2026 through January 2027. The total contract value is approximately $0.8 million, with milestone-based payments. The resulting software and analysis models will be owned by Lightbridge and are expected to strengthen Lightbridge’s internal capability to perform reactor safety analyses in support of future regulatory submissions and commercial fuel demonstrations.
Current report
In December 2025, we also entered into an agreement with Studsvik Scandpower, a provider of nuclear fuel management software, to develop a transport methodology based on their existing software that will model the Lightbridge Fuel™ concept variant. We would need to separately purchase a license to this updated software after it has been developed to meet Lightbridge’s specifications. The total contract value for development of the code is approximately $0.3 million, payable upon the completion of work, expected in mid-2026.
Current report
Costs for software code development are expensed as incurred and included in research and development expenses. However, work on these arrangements is in the preliminary stages or has not yet begun, and no expenses were incurred during the year ended December 31, 2025.
Current report
Critical Heat Flux Test Program
Current report
In February 2026, we entered into an initial engineering contract and statement of work with an organization providing specialized experimental services to assess the thermal and hydraulic (TH) performance of Lightbridge Fuel™ for use in water-cooled reactors. The experimental program will be carried out in phases and include: the design and fabrication of an electrically heated fuel simulator and its acceptance testing, nine-rod PWR critical heat flux tests, with an option for the Company to also choose to conduct nine-rod BWR critical power tests, a full scale TH test program to support the U.S. licensing of Lightbridge Fuel™ in commercial PWRs, and an option for the Company to also choose to conduct a full scale TH thermal test program to support the U.S. licensing of Lightbridge Fuel™ in commercial BWRs. Phase 1 work includes prototype fuel simulator design, fabrication, and acceptance testing and is estimated to take one year to complete and cost approximately $0.5 million.
Current report
As noted under Part I. Item 1.Business, we engaged RATEN ICN in Romania to perform an engineering study to assess the compatibility and suitability of Lightbridge Fuel™ for use in CANDU reactors. The findings from this engineering study will play an important role in guiding future economic evaluations and navigating potential regulatory licensing-related issues for potential use of Lightbridge Fuel™ in CANDU reactors. In August 2025, we entered into the 2025 RATEN ICN Agreement to evaluate conducting irradiation test(s) for several Lightbridge Fuel™ rodlets. The 2025 RATEN ICN Agreement provides for two phases: in Phase 1, RATEN ICN was to conduct scoping studies to develop preliminary experiment designs, evaluate infrastructure and equipment needs, and obtain cost and schedule estimates for potential new driver fuel, and in Phase 2, if the results of Phase 1 were acceptable to Lightbridge, RATEN ICN would implement refurbishments, procure equipment and driver fuel as needed, finalize experiment design, fabricate and operate the test assembly, and complete post-irradiation examination. Lightbridge would be responsible for supplying experimental fuel rodlets for use in the irradiation tests. The Phase 1 work was completed as of December 31, 2025. The Company is currently evaluating the results of the Phase 1 work. No decision has been made about the Phase 2 scope as of the date hereof.
Current report
Commercialization Outlook and Key Drivers of Timing
Current report
Known Long-Term Industry Constraints and Uncertainties
Current report
While our current research and development activities are not dependent on the commercial availability of HALEU in metallic form, the future commercialization of Lightbridge Fuel™ will require the establishment of a commercial-scale supply and fabrication capabilities. These matters and others are discussed further under Part I. Item 1A.Risk Factors—”Risks Related to Our Business and to the Commercialization of Lightbridge Fuel™—Dependence on the Future Availability of Cost-Competitive Metallic HALEU and Commercial-Scale Fuel Fabrication Infrastructure” of this Annual Report on Form 10-K.
Current report
Research and Development
Current report
R&D expenses increased by $4.6 million for the year ended December 31, 2025, as compared to the year ended December 31, 2024. The increase was primarily due to a:
Current report
For the years ended December 31, 2025 and 2024, external R&D services accounted for approximately 32% and 49% of total R&D expense. We expect to significantly increase our R&D spend in the near future as we focus on fuel fabrication development, irradiation testing programs, and our collaboration with the DOE at INL. We also expect to hire additional engineers to support these efforts and to further develop our software modeling and simulation capabilities for Lightbridge Fuel™.
Current report
Interest Income
Current report
Overview – Funding Requirements
Current report
We assess our liquidity based on our ability to fund the cash requirements of our R&D activities, G&A expenses, contractual obligations, and other operating needs. Based on our current level of operating expenses and our available cash resources, we believe we have sufficient liquidity to fund our operations and meet our anticipated cash requirements for at least the next 12 months from the date of this filing. Our longer-term liquidity will depend on our ability to obtain additional financing, as our existing capital resources are not expected to be sufficient to fund our operations, research and development activities, and commercialization efforts beyond the next several years.
Current report
Short-Term Liquidity and Capital Resources
Current report
We believe that our existing cash and cash equivalents of $201.9 million as of December 31, 2025, together with any additional sources such as cash flows from potential financing and proceeds from our at-the-market (ATM) equity offering program will be sufficient to meet our working capital and capital expenditure requirements for at least the next 12 months from the date of this filing. However, due to the uncertainties inherent in our research and development programs and the broader industry environment, we are unable to reliably estimate our total cash requirements over the full R&D development period or beyond the next 12 months. We expect our expenditures to increase over time as we advance the development and potential commercialization of our Lightbridge Fuel™. We do not anticipate any material incoming cash flows from operations in the near term, and we expect to continue funding our business primarily through our ATM or other equity offerings.
Current report
Long-Term Liquidity and Capital Requirements
Current report
We expect that significant additional capital will be required over multiple years to advance Lightbridge Fuel™ through development and toward commercial deployment. The amount and timing of future funding needs will depend on technical progress, regulatory requirements, facility design decisions, partnering arrangements, and the availability of government support. At this stage, we cannot reliably estimate the total funding required to reach commercial deployment. We currently intend to fund these activities through a mix of equity financing, strategic partnerships, and potential government grants or awards.
Current report
The actual amount and timing of future capital requirements will depend on several factors, including:
Current report
There is inherent uncertainty in forecasting future expenditures, and actual costs may vary materially from current estimates.
Current report
Sources of Liquidity
Current report
ATM Equity Offering Program
Current report
On May 23, 2025, the Company filed a shelf registration statement on Form S-3 (File No. 333-287563), which was declared effective on June 4, 2025. On June 5, 2025, the Company entered into an Open Market Sale Agreement with Jefferies (the Jefferies ATM Agreement) to offer and sell the Company’s common stock from time to time in one or more ATM offerings, and also filed a prospectus supplement to the base prospectus forming a part of the Company’s shelf registration statement registering $75.0 million of common stock for sale under the Jefferies ATM Agreement. On September 26, 2025, we filed a prospectus supplement pursuant to which we may issue and sell from time to time up to an additional $75.0 million of common stock under the Jefferies ATM Agreement.
Current report
On November 28, 2025, we filed an automatic shelf registration statement on Form S-3 ASR (File No. 333-291837), which included a new prospectus supplement (the November 2025 Prospectus Supplement) pursuant to which we may issue and sell from time to time an additional $150.0 million of our shares of common stock under the Jefferies ATM Agreement.
Current report
During 2025, we sold approximately $144.4 million under the Jefferies ATM Agreement, receiving net proceeds (less sales commissions and expenses) of $139.6 million. As of December 31, 2025, approximately $142.1 million of our common stock remained available for issuance and sale pursuant to the November 2025 Prospectus Supplement.
Current report
Liquidity Outlook and Risks
Current report
Although we expect our ATM offerings to remain our primary source of working capital in 2026, there are inherent uncertainties associated with our ability to continue raising capital through an ATM program. These uncertainties include potential declines in our stock price, fluctuations in our stock trading volume, adverse overall stock market conditions, or regulatory changes that could limit our access to capital under the current ATM arrangement. In addition, the issuance of additional shares through the ATM program may result in significant dilution to existing stockholders, and the potential for such dilution could negatively impact the market price of our common stock. There can be no assurance that ATM financing will remain available to us on acceptable terms, or at all, when needed until the commercialization of our fuel.
Current report
Contractual and Other Obligations
Showing the first 40 of 42 passages. Open the source sections for the rest.
Removed paragraphs (58)
Previous report
This MD&A consists of the following sections:
Previous report
When used in this Annual Report on Form 10-K, the terms “Lightbridge”, the “Company”, “we”, “our”, and “us” refer to Lightbridge Corporation together with its wholly-owned subsidiaries Lightbridge International Holding LLC and Thorium Power Inc. Lightbridge’s principal executive offices are located at 11710 Plaza America Drive, Suite 2000, Reston, Virginia, 20190, USA.
Previous report
Technology industry companies believe that nuclear energy can offer a strategic, sustainable, and reliable solution for powering data centers. Advances in reactor technology, combined with growing corporate and governmental support for clean energy, can position nuclear power as a cornerstone of future energy strategies for data-intensive industries. We believe that by integrating nuclear power, the data center sector can achieve operational efficiency, energy security, and sustainability. We believe uses of our fuel could include providing additional power via power uprates of existing reactors, which may be willing to pay a premium for reliable, clean, and sustainable baseload electricity. Oil and gas producing companies are investing in low-emission energy technologies to reduce fossil fuel emissions from oil and gas production. Advances in nuclear reactor and fuel technology can position nuclear power as a key energy source for this purpose.
Previous report
Emerging nuclear technologies include small modular reactors (SMRs), which are now in the development and licensing phases. We expect that Lightbridge Fuel™ can provide water-cooled SMRs with the same benefits our technology brings to large reactors, with such benefits being even more meaningful to the economic case for deployment of SMRs, including potential load following capability when included on a virtually zero-carbon electric grid with renewable energy sources. We expect Lightbridge Fuel™ to enable power uprates in SMRs.
Previous report
We have built a significant portfolio of patents, and we anticipate testing our nuclear fuel through third-party vendors and others, including the United States Department of Energy’s (DOE) national laboratories. Currently, we are performing the majority of our R&D activities within and in collaboration with the DOE’s national laboratories.
Previous report
We anticipate that the initial phase of work under the two agreements that has been released will culminate in casting and extrusion of unclad fuel material samples using enriched uranium supplied by the DOE that will subsequently be inserted for irradiation testing in the Advanced Test Reactor (ATR) at INL. The initial phase of work aims to generate irradiation performance data for Lightbridge’s delta-phase uranium-zirconium alloy relating to various thermophysical properties. The data will support fuel performance modeling and regulatory licensing efforts for commercial deployment of Lightbridge Fuel™. We use a rolling wave planning approach for project management purposes on the released scopes of work. It is an iterative planning technique in which the work to be accomplished in the near term is planned in detail, while work further in the future is planned at a higher level. As such, periodic revisions to the scope and/or cost estimates are anticipated.
Previous report
We anticipate that subsequent phases of work under the two umbrella agreements that have not yet been released may include post-irradiation examination of the irradiated fuel material coupons, loop irradiation testing in the ATR, and post-irradiation examination of one or more uranium-zirconium fuel rodlets, as well as transient experiments in the Transient Reactor Test Facility at INL.
Previous report
On March 26, 2024, the Company and BEA entered into Modification No. 2 PTS under the SPPA, dated December 9, 2022, as amended on May 23, 2023, by and between the Company and BEA. Pursuant to the terms of Modification No. 2, the potential amounts payable by the Company to reimburse BEA for its expenses and employee time were increased by approximately $0.6 million, bringing the total estimated cost for the work to be performed under the “umbrella” SPPA to $1.7 million.
Previous report
On October 24, 2024, the Company and BEA entered into Modification No. 3 PTS under the SPPA, dated December 9, 2022, as amended on May 23, 2023 and March 26, 2024, by and between the Company and BEA. Pursuant to the terms of Modification No. 3, the potential amounts payable by the Company to reimburse BEA for its expenses and employee time were increased by approximately $0.3 million, bringing the total estimated cost for the work to be performed under the “umbrella” SPPA to approximately $2.0 million.
Previous report
On January 16, 2025 the Company and BEA entered into Modification No. 3 PTS under the CRADA, dated September 27, 2022, as amended on May 22, 2023, May30, 2023, by and between the Company and BEA. Pursuant to the terms of Modification No. 3, the potential amounts payable by the Company to reimburse BEA for its expenses and employee time were increased from $2.6 million by approximately $1.6 million, bringing the total estimated cost for the work to be performed under the “umbrella” CRADA to $4.2 million. This modification also required that a $0.6 million advance payment be made, which was paid on January 16, 2025.
Previous report
After Modification No. 3, to the PTS under the CRADA and the anticipated Modification No. 4 to the PTS under the SPPA, total cash payments from the Company to BEA under both Agreements are estimated at approximately $6.5 million (excluding project contingencies) on a cost reimbursable basis over the performance periods under the initial releases.
Previous report
On October 16, 2023, we engaged Institutul de Cercetări Nucleare Pitești, a subsidiary of Regia Autonoma Tehnologii pentru Energia Nucleara (RATEN ICN) in Romania to perform an engineering study to assess the compatibility and suitability of Lightbridge Fuel™ for use in CANDU reactors. This assessment covers key areas including mechanical design, neutronics analysis, and thermal and thermal-hydraulic evaluations. The findings from this engineering study will play an important role in guiding future economic evaluations and navigating potential regulatory licensing-related issues for potential use of Lightbridge Fuel™ in CANDU reactors. On July 2, 2024, we issued a change order adding a new task to the remaining scope of this engineering study. Following the change order, the Company paid a total fee of approximately $0.2 million for this engineering study, which was completed in 2024. We anticipate performing additional studies with RATEN ICN.
Previous report
Nuclear Energy University Program Awards
Previous report
Texas A&M University (TAMU), NuScale Power, and Structural Integrity Associates are working on a 3-year study of our nuclear fuel, led by TAMU. The TAMU study is expected to be completed in 2026. In mid-2023, TAMU was awarded $1.0 million by the DOE’s Nuclear Energy University Program (NEUP) R&D Awards to conduct this study. The project entails a characterization of the performance of the Lightbridge Fuel™ Helical Cruciform advanced fuel design, which will generate sets of experimental data on friction factor, flow, and heat transfer behavior under NuScale’s SMR simulated normal and off-normal conditions.
Previous report
We previously announced the ongoing NEUP project with the Massachusetts Institute of Technology (MIT). The study led by MIT and funded by DOE relates to evaluation of accident tolerant fuels (ATFs) in various SMRs. The project aims to simulate the fuel and safety performance of Lightbridge Fuel™ for the NuScale SMR and provide scoping analysis to improve the safety and economics of water-cooled SMRs. In October 2024, MIT presented a technical paper with preliminary safety evaluation results at the TopFuel 2024 Conference in Grenoble, France. According to MIT, the results have shown promising safety and performance benefits for Lightbridge Fuel™. Compared to conventional fuel, Lightbridge Fuel™ demonstrated improved thermal-hydraulic margins, lower operating temperatures, and greater potential for power uprates, which contributes to enhancing reactor economics.
Previous report
We do not have any performance obligations with the collaboration teams working on the above-mentioned projects and will not receive any revenue or record any economic benefits from these awards.
Previous report
Future Steps Toward Our Fuel Development and Timeline For The Commercialization of Our Nuclear Fuel Assemblies
Previous report
We anticipate fuel development milestones for Lightbridge Fuel™ over the next 2-3 years will consist of the following:
Previous report
The above future steps describe our current proposed approach to deploying Lightbridge Fuel™ in CANDU and/or U.S. PWR reactors.
Previous report
Fuel Development Strategy
Previous report
Below is a brief description of each key fuel development step leading up to a lead test assembly (LTA) operation in a commercial reactor.
Previous report
Fuel Fabrication
Previous report
In the short to medium term, we expect the development of the fabrication processes for Lightbridge Fuel™ to be performed utilizing existing facilities and equipment within the DOE national laboratory complex and other facilities. Discussions are currently ongoing with the INL to perform process development activities and establish the capability to manufacture development quantities of fuel rods for irradiation testing.
Previous report
Fabrication of LTAs will require a dedicated pilot-scale fuel fabrication facility. We estimate the major scopes of work to establish a manufacturing capability for LTR/LTA could take several years to complete and require tens of millions of dollars in capital expenditures. Expanding that pilot-scale fuel fabrication facility to batch reload quantities would require a substantial additional capital investment in the manufacturing facility and equipment (in the order of hundreds of millions of dollars). These estimates assume sufficient funding availability and that the project receives prioritization by the DOE and U.S. Nuclear Regulatory Commission (NRC) to facilitate access to the required quantities of the HALEU material and timely regulatory licensing of such a facility.
Previous report
Nuclear Material/Coupon Sample Irradiation Test
Previous report
Lightbridge’s irradiation testing program includes coupon irradiation of material samples of its uranium-zirconium fuel alloy which will allow characterization of the underlying thermophysical behavior of the fuel alloy. This project is currently underway with INL, and we expect insertion of fuel material coupons in the ATR in 2026 and completion of irradiation testing to full burnup and post-irradiation examination of the fuel material coupons in approximately several years thereafter. The data obtained from this program will be a fundamental component of Lightbridge’s accelerated fuel qualification approach described below as it will be used to inform and develop the physics-based models and simulations of the fuel rod behaviors.
Previous report
Loop Irradiation Testing
Previous report
The purpose of the loop irradiation testing of Lightbridge’s metallic fuel rods is to demonstrate the performance and behavior of the fuel rods under prototypic commercial reactor operating conditions typical of PWRs at a power level and burnup accumulation higher than the fuel would experience in normal operation in a commercial power plant. This will provide a physical demonstration of the capabilities of the fuel rods to ensure reactor safety. Such testing is expected to provide information of sufficient detail to validate the performance of individual fuel rods such that their behavior in normal operating conditions of a NRC-regulated nuclear power plant would be sufficiently well understood to request a license amendment from the NRC for operation of a LTA.
Previous report
We plan on such a loop irradiation test to be performed in the ATR at INL. The ATR currently has limited irradiation loop test facilities; however, the planned installation of the new so-called “I-loops” in the coming years will increase the loop irradiation capacity of ATR for performing tests on Lightbridge Fuel™ in the desired test conditions.
Previous report
We expect the performance of the irradiation test to take three years of in-reactor time plus an additional one year for post-irradiation examination, wherein analysis of the fuel rod performance and behavior is performed, from the time when the additional test loop becomes available.
Previous report
Preparation for Lead Test Assembly Operation
Previous report
Insertion of a LTA with Lightbridge’s fuel rods in a nuclear power plant requires the power plant owner to obtain approval from the NRC based on a safety evaluation and justification that the LTA will not be detrimental to the plant’s licensed operations. This justification must address numerous technical areas (e.g., neutronics design, mechanical design, thermal hydraulic design, materials science, reactor operations, etc.) and include considerations of the performance of the LTA itself as well as its interaction with other fuel assemblies in the reactor core which may be impacted by the presence of the LTA. The safety evaluation must result in confirmation that the plant’s ability to ensure plant worker and public safety is not compromised due to the operation of the LTA. This safety justification will require cooperation between Lightbridge, the fuel manufacturer, and the power plant owner.
Previous report
With historical approaches, the development and qualification of a nuclear fuel system can take 20-30 years as the approach has been driven largely by a cycle of physical testing and design changes based on the results of those physical tests. Computer modeling and simulation has increasingly been used in support of fuel qualification efforts, but the cyclical approach continues to be the default methodology.
Previous report
Advanced nuclear fuel developers are now taking an approach that leverages significant improvements in computational capability in a methodology referred to as Accelerated Fuel Qualification (AFQ). The AFQ approach combines physics-informed modeling and simulation coupled with targeted physical testing such that the overall fuel qualification effort could be significantly reduced in terms of cost and time. Lightbridge intends to leverage the AFQ methodologies to qualify its advanced fuels.
Previous report
Along with leveraging the AFQ approach, uranium-zirconium fuel technology has the benefits of being previously demonstrated in operating icebreaker reactors and several aspects of the performance of the fuel have been demonstrated. This enables Lightbridge to begin designing a LTA and developing the necessary computer models of the fuel behavior, prior to obtaining the results of the loop irradiation testing of the fuel rod.
Previous report
Along with the irradiation testing and computer simulations, some physical testing of the fuel assembly design will be required. Lightbridge anticipates that such ‘out-of-pile’ testing to justify the LTA performance may take four years.
Previous report
We expect that the LTA design effort, development of computer modeling and simulation capabilities, and performance of the LTA safety justification may take eight years. The NRC’s review and approval of the license amendment for LTA insertion is expected to require two years after the license amendment is submitted.
Previous report
Based on these activities and time estimates, Lightbridge expects to have LTAs of its fuel ready for insertion in a commercial reactor in the 2030s.
Previous report
The above fuel development strategy is based on the following key assumptions:
Previous report
Research and Development (R&D)
Showing the first 40 of 58 passages. Open the source sections for the rest.
Reworded paragraphs (26)
Previous wording
ITEM 7. MANAGEMENT’S DISCUSSION ANDANALYSIS OF FINANCIAL CONDITION AND RESULTS OF OPERATIONS
Current wording
ITEM 7. MANAGEMENT’S DISCUSSION AND****ANALYSIS OF FINANCIAL CONDITION AND RESULTS OF OPERATIONS
Previous wording
The following Management’s Discussion and Analysis of Financial Condition and Results of Operations, or MD&A, is intended to help the reader understand Lightbridge Corporation, our operations, and our present business environment. MD&A is provided as a supplement to, and should be read in conjunction with, our Consolidated Financial Statements and the accompanying Notes thereto, which are contained in Part II. Item 8.Financial Statements and Supplementary Data of this report.
Current wording
The following Management’s Discussion and Analysis of Financial Condition and Results of Operations, or MD&A, is intended to help the reader understand Lightbridge Corporation, our operations, and our present business environment. MD&A is provided as a supplement to, and should be read in conjunction with, our Consolidated Financial Statements and the accompanying Notes thereto, which are contained in Part II. Item 8.Financial Statements and Supplementary Data of this Annual Report on Form 10-K.
Previous wording
At Lightbridge, we are developing next generation nuclear fuel for water-cooled reactors that could significantly improve the economics and safety of existing and new nuclear power plants, large and small, and enhance proliferation resistance of spent nuclear fuel while supplying clean energy to the electric grid or to “behind the meter” customers for electric power, including data centers. We believe that the world’s energy and climate needs can only be met if nuclear power’s share of the energy-generating mix grows substantially in the coming decades. We believe Lightbridge can benefit from a growing nuclear power industry, and that our nuclear fuel can help enable that growth to happen.
Current wording
At Lightbridge, we are developing next generation nuclear fuel for water-cooled reactors that could significantly improve the economics and safety of existing and new nuclear power plants and enhance proliferation resistance of spent nuclear fuel while supplying clean energy to the electric grid or to “behind the meter” customers for electric power, including data centers. We believe our metallic fuel could offer significant economic and safety benefits over traditional nuclear fuel, primarily because of the superior heat transfer properties and the resulting lower operating temperature of our all-metal fuel. Data centers will need massive, constant power that we believe nuclear power can provide. Advances in reactor technology, combined with growing corporate and governmental support for clean energy, can position nuclear power as a cornerstone of future energy strategies for data-intensive industries, which may be willing to pay a premium for reliable, clean, and sustainable baseload electricity.
Previous wording
We have obtained patent validation in key countries that we believe would have a commercial market for our fuel and will continue to seek patent validation in countries that either currently operate or are expected to build and operate a large number of nuclear power reactors compatible with our fuel technology.
Current wording
We believe our metallic fuel can be used in different types of water-cooled commercial power reactors, such as PWRs, BWRs, VVERs, CANDUs, water-cooled SMRs, and water-cooled research reactors. We have obtained patent validation in key countries that we believe would have a commercial market for our fuel and will continue to seek patent validation in countries that either currently operate or are expected to build and operate a large number of nuclear power reactors compatible with our fuel technology.
Previous wording
In December 2022, Lightbridge entered into agreements with Battelle Energy Alliance, LLC (BEA), the DOE’s operating contractor for Idaho National Laboratory (INL), to support the development of Lightbridge Fuel™. The framework agreements use an innovative structure that consists of an “umbrella” Strategic Partnership Project Agreement (SPPA) and an “umbrella” Cooperative Research and Development Agreement (CRADA), each with BEA, with an initial duration of seven years.
Current wording
As noted under Part I. Item 1.Business, we entered into agreements with BEA to support the development of Lightbridge Fuel™. The framework agreements consist of an “umbrella” SPPA and an “umbrella” CRADA, each with BEA.
Previous wording
The Company anticipates entering into additional modifications to the Project Task Statements (PTS) under the SPPA and/or CRADA with INL to expand the scope of work, including performing additional extrusions, updating the experiment design for irradiation testing of coupon samples in the ATR, as well as other potential activities. We are discussing these additional scopes and timing of work with INL to be performed under the two “umbrella” agreements with BEA; which we anticipate will increase our R&D expenses for the SPPA and/or CRADA. In late 2024, we worked with INL to re-baseline the project scope, schedule, and cost estimate at completion. As a result, the expected cost estimate at completion was increased by approximately $2.0 million. The successful execution of this project is subject to risks, including potential delays, cost overruns, regulatory challenges, and changes in funding availability, and if the project scope does increase, then the project will be successfully executed or completed. Regardless of whether further project modifications occur, INL has indicated to the Company that due to resource and manufacturing equipment constraints, INL may not be able to meet the Company’s preferred project timeline, and that the total project cost will exceed the current budget.
Current wording
The successful execution of this project is subject to risks, including potential delays, cost overruns, regulatory challenges, and changes in funding availability, and if the project scope does increase, then the project will be successfully executed or completed. Regardless of whether further project modifications occur, INL has indicated to the Company that due to resource and manufacturing equipment constraints, INL may not be able to meet the Company’s preferred project timeline, and that the total project cost will exceed the current budget.
Previous wording
The long-term milestones towards development and commercialization of nuclear fuel assemblies include, among other things, irradiating nuclear material samples and prototype fuel rods with enriched uranium in test reactors, conducting post-irradiation examination of irradiated material samples and/or prototype fuel rods, performing thermal-hydraulic experiments, performing seismic and other out-of-reactor experiments, performing advanced computer modeling and simulations to support fuel qualification, designing a lead test assembly (LTA), entering into a lead test rod/assembly agreement(s) with a host reactor(s), demonstrating the production process of lead test rods and/or lead test assemblies at a pilot-scale fuel fabrication facility and demonstrating the operation of lead test rods and/or lead test assemblies in commercial reactors.
Current wording
The long-term milestones towards development and commercialization of nuclear fuel assemblies include, among other things, irradiating nuclear material samples and prototype fuel rods with enriched uranium in test reactors, conducting post-irradiation examination of irradiated material samples and/or prototype fuel rods, performing thermal-hydraulic experiments, performing seismic and other out-of-reactor experiments, performing advanced computer modeling and simulations to support fuel qualification, designing an LTA, entering into a lead test rod/assembly agreement(s) with a host reactor(s), demonstrating the production process of our fuel including lead test rods and/or lead test assemblies at a planned LEFF and demonstrating the operation of lead test rods and/or lead test assemblies in commercial reactors.
Previous wording
There are inherent uncertainties in the cost and outcomes of the many steps needed for successful deployment of our fuel in commercial nuclear reactors, which makes it difficult to accurately predict the timing of the commercialization of our nuclear fuel technology. However, based on our best estimate and assuming adequate R&D funding levels, we expect to begin demonstration of lead test rods and/or possibly LTAs with our metallic fuel in commercial reactors in the 2030s and begin receiving purchase orders for initial fuel reload batches from utilities 15-20 years from now, with deployment of our nuclear fuel in the first reload batch in a commercial reactor taking place approximately two years thereafter. We are exploring ways of shortening this timeframe that may include securing access to expanded irradiation test loop capacity in existing or new research reactor facilities. Lightbridge aims to engage early with relevant nuclear regulators to inform our future R&D activities.
Current wording
There are inherent uncertainties in the cost and outcomes of the many steps needed for successful deployment of our fuel in commercial nuclear reactors, which makes it difficult to accurately predict the timing of the commercialization of our nuclear fuel technology. Our ultimate commercial model remains under evaluation and may evolve as our fuel development progresses, regulatory pathways are clarified, and commercial partnerships are established. However, based on our best estimate and assuming adequate R&D funding levels, we expect to begin demonstration of lead test rods and/or possibly LTAs with our metallic fuel in commercial reactors in the mid-2030s and begin receiving purchase orders for initial fuel reload batches from utilities 15 years from now, with deployment of our nuclear fuel in the first reload batch in a commercial reactor taking place approximately two years thereafter. See Part I. Item 1A.Risk Factors—”Risks Related to Our Business and to the Commercialization of Lightbridge Fuel™” of this Annual Report on Form 10-K.
Previous wording
General and administrative expenses consist mostly of compensation and related costs for personnel and facilities, stock-based compensation, finance, human resources, information technology, and fees for consulting and other professional services. Professional services are principally comprised of legal, audit, strategic advisory services, and outsourcing services.
Current wording
General and administrative expenses consist primarily of compensation and related costs for finance personnel, including stock-based compensation, and fees for professional and consulting services. Professional services are principally comprised of legal, audit, strategic advisory services, and outsourced services such as human resources and information technology.
Previous wording
General and administrative expenses increased by $1.4 million for the year ended December 31, 2024, as compared to the year ended December 31, 2023. The increase of $1.4 million was primarily due to an increase in employee compensation and employee benefits of $0.3 million, an increase in consulting fees and professional fees of $0.3 million, an increase in stock-based compensation of $0.6 million, an increase in IT expenses of $0.1 million, an increase in travel and recruitment expenses of $0.1 million, and an increase in patent expense of $0.1 million, partially offset by a decrease in insurance expense of $0.1 million.
Current wording
General and administrative expenses increased by $5.5 million for the year ended December 31, 2025, as compared to the year ended December 31, 2024. The increase was primarily due to a:
Previous wording
Total stock-based compensation included in general and administrative expenses was $1.7 million and $1.1 million for the years ended December 31, 2024 and 2023, respectively.
Current wording
Total stock-based compensation included in general and administrative expenses was $4.4 million and $1.8 million for the years ended December 31, 2025 and 2024, respectively.
Previous wording
R&D expenses consist primarily of costs associated with our CRADA and SPPA agreements with INL, employee compensation and related fringe benefits including stock-based compensation and other research and development costs for the development of our Lightbridge Fuel™.
Current wording
R&D expenses consist primarily of costs associated with our CRADA and SPPA agreements with BEA, IT expenses, employee compensation and related fringe benefits, including stock-based compensation, and other research and development costs for the development of our Lightbridge Fuel™.
Previous wording
Total stock-based compensation included in research and development expenses was $0.3 million and $0.2 million for the years ended December 31, 2024 and 2023, respectively.
Current wording
Total stock-based compensation included in research and development expenses was $1.4 million and $0.3 million for the years ended December 31, 2025 and 2024, respectively.
Previous wording
There was an increase in other income of $0.2 million due to higher cash balances over the past year, which resulted in an increase in interest income earned from the purchase of treasury bills and from our bank savings account for the year ended December 31, 2024, as compared to the year ended December 31, 2023.
Current wording
There was an increase in interest income of $2.3 million due to higher cash balances over the past year, which resulted in an increase in interest income earned from the purchase of treasury bills and from our bank savings account for the year ended December 31, 2025, as compared to the year ended December 31, 2024.
Previous wording
We incurred a pre-tax net loss for both 2024 and 2023. We reviewed all sources of income for the purpose of recognizing the deferred tax assets and concluded a full valuation allowance for 2024 and 2023 was necessary. Therefore, we did not have a provision for taxes for both years ended December 31, 2024 and 2023. Prior period ownership changes, coupled with the Company’s projections of no taxable income for the foreseeable future, will substantially limit any future benefit to be derived from our NOLs.
Current wording
We incurred a pre-tax net loss for both 2025 and 2024. We reviewed all sources of income for the purpose of recognizing the deferred tax assets and concluded a full valuation allowance for 2025 and 2024 was necessary. Therefore, we did not have a provision for income taxes for both years ended December 31, 2025 and 2024. Prior period ownership changes, coupled with the Company’s projections of no taxable income for the foreseeable future, will substantially limit any future benefit to be derived from our NOLs.
Previous wording
See Note 7. Income Taxes of the Notes to our Consolidated Financial Statements included in Part II. Item 8.Financial Statements and Supplementary Data of this Annual Report on Form 10-K for information regarding our income taxes and the limitations on the utilization and amount of our net operating loss carry-forwards.
Current wording
See Note 6.Income Taxes, to our Consolidated Financial Statements included in Part II. Item 8.Financial Statements and Supplementary Data of this Annual Report on Form 10-K for information regarding our income taxes and the limitations on the utilization and amount of our net operating loss carryforwards.
Previous wording
At December 31, 2024, we had cash and cash equivalents of $40.0 million, as compared to $28.6 million at December 31, 2023, an increase of $11.4 million. We raised net proceeds of $21.4 million from the sale of approximately 4.5 million shares of common stock during the year ended December 31, 2024. Our net cash used in operating activities for the year ended December 31, 2024, was $9.5 million and our cash flow projections indicate that we will have continued negative cash flows for the foreseeable future. We currently do not anticipate any incoming cash flows, other than the sale of common stock through our at-the-market (ATM) offering. We are not profitable, and we cannot provide any assurance that we will become profitable in the future. We will continue to incur losses because we are in the early R&D development stage of our nuclear fuel.
Current wording
At December 31, 2025, we had cash and cash equivalents of $201.9 million, as compared to $40.0 million at December 31, 2024, an increase of $161.9 million. We raised net proceeds of $176.0 million from the sale of approximately 12.6 million shares of common stock during the year ended December 31, 2025. Our net cash used in operating activities for the year ended December 31, 2025, was $14.3 million.
Previous wording
Currently, our primary source of liquidity is cash raised from our ATM facility.
Current wording
Our current primary source of liquidity is potential proceeds from our ATM equity offerings.
Previous wording
See Note 8. Stockholders’ Equity and Stock-Based Compensation of the Notes to our Consolidated Financial Statements included in Part II. Item 8.Financial Statements and Supplementary Data of this Annual Report on Form 10-K for information regarding our prior equity financings.
Current wording
See Note 7.Stockholders’ Equity, to our Consolidated Financial Statements included in Part II. Item 8.Financial Statements and Supplementary Data of this Annual Report on Form 10-K for information regarding our prior equity financings.
Previous wording
We have no debt or lines of credit, and we have financed our operations to date through the sale of our preferred stock and common stock. Management believes that public or private equity investments may be available in the future; however, adverse market conditions, in our common stock price and trading volume, as well as other factors could substantially impair our ability to raise capital in the future and continue developing our nuclear fuel.
Current wording
We currently have no debt or lines of credit and have historically funded our operations through the sale of common stock. Although management believes additional public or private equity investments may be available in the future, adverse market conditions, unfavorable stock price movements, or reduced trading volumes could substantially impair our ability to raise capital when needed.
Previous wording
On December 9, 2022, we entered into initial project task statements with BEA, the operating contractor of INL, in collaboration with the DOE, which statements set forth the initial scopes of work and funding commitments under the umbrella agreements, each dated September 27, 2022, between the Company and BEA. At December 31, 2024, we had approximately $1.7 million in project task statements to BEA relating to the research and development being conducted under the SPPA and CRADA at INL. Performance of work under these agreements may be terminated at any time by either party, without any liability, after the effective date of termination, upon giving a thirty-day written notice under the SPPA and a sixty-day written notice under the CRADA, to the other party. In the event of termination, the Company shall be responsible for BEA’s costs (including the closeout costs), through the effective date of termination, but in no event shall the Company’s cost responsibility exceed the total estimated cost stated in each PTS and any subsequent modification to the PTS.
Current wording
Other than ongoing personnel-related expenditures and vendor payments, we have limited contractual obligations. As noted under Part I. Item 1.Business, we have entered into initial project task statements with BEA, the operating contractor of INL, in collaboration with the DOE, which statements set forth the initial scopes of work and funding commitments under the SPPA and CRADA umbrella agreements. Performance of work under these agreements may be terminated at any time by either party, without any liability, after the effective date of termination, upon thirty days’ written notice under the SPPA and sixty days’ written notice under the CRADA. In the event of termination, the Company shall be responsible for BEA’s costs (including the closeout costs), through the effective date of termination, but in no event shall the Company’s cost responsibility exceed the total estimated cost stated in each project task statement and any subsequent modification to the project task statement. As of December 31, 2025, the total remaining costs reimbursable from the Company to BEA, if and when incurred, would not exceed $14.2 million.
Previous wording
The following table provides detailed information about our net cash flows for the years ended December 31, 2024 and 2023 (amounts reflected in millions):
Current wording
The following table provides detailed information about our net cash flows for the years ended December 31, 2025 and 2024 (rounded to millions):
Previous wording
Cash used in operating activities increased by $3.0 million in 2024 as compared to 2023. This increase was primarily due to increased spending on R&D, general and administrative expenses and changes in working capital, which included an increase in prepaid assets of $0.1 million, and was partially offset by an increase in accounts payable and accrued liabilities of $0.2 million.
Current wording
Cash used in operating activities increased by $4.8 million in 2025 as compared to 2024. This increase was primarily due to increased cash expenditures on R&D and general and administrative expenses, partially offset by higher interest income, reflecting increased average cash balances following equity financings and higher short-term interest rates during the period. The changes in working capital in 2025, which included an increase in prepaid expenses and other assets of $0.9 million, were partially offset by an increase in accounts payable and accrued liabilities of $0.4 million.
Previous wording
Cash provided by our ATM facility was $21.4 million (sale of approximately 4.5 million common shares) and $6.4 million (sale of approximately 1.5 million common shares) for the years 2024 and 2023, respectively. Cash used during the years 2024 and 2023 related to the payment of withholding taxes on the net share settlement of equity awards was $0.5 million and $0.2 million, respectively.
Current wording
Net cash provided by our ATM facility was $176.0 million from the sale of approximately 12.6 million common shares and $21.4 million from the sale of approximately 4.5 million common shares for the years 2025 and 2024, respectively.
Previous wording
The preparation of consolidated financial statements, in conformity with accounting principles generally accepted in the United States of America, requires management to make estimates and assumptions that affect the reported amounts of assets and liabilities and disclosure of contingent assets and liabilities at the date of the consolidated financial statements, and the reported amounts of expenses during the reporting period. Actual results could differ from those estimates. Estimates and assumptions are periodically reviewed and the effects of revisions are reflected in the consolidated financial statements in the period they are determined to be necessary. Our significant accounting policies are more fully described in Note 1. Basis of Presentation, Summary of Significant Accounting Policies, and Nature of Operations, in the Notes to the Consolidated Financial Statements included in Part II. Item 8.Financial Statements and Supplementary Data of this Annual Report on Form 10-K. There were no critical accounting estimates at December 31, 2024 and 2023.
Current wording
Estimates and assumptions are periodically reviewed and the effects of revisions are reflected in the consolidated financial statements in the period they are determined to be necessary. Our significant accounting policies are more fully described in Note 1.Basis of Presentation, Summary of Significant Accounting Policies, and Nature of Operations, to the Consolidated Financial Statements included in Part II. Item 8.Financial Statements and Supplementary Data of this Annual Report on Form 10-K.
Previous wording
Refer to Note 1. Basis of Presentation, Summary of Significant Accounting Policies, and Nature of Operations of the Notes to our Consolidated Financial Statements in Part II. Item 8.Financial Statements and Supplementary Data of this Form 10-K for a discussion of recent accounting standards and pronouncements.
Current wording
Refer to Note 1.Basis of Presentation, Summary of Significant Accounting Policies, and Nature of Operations, to our Consolidated Financial Statements in Part II. Item 8.Financial Statements and Supplementary Data of this Annual Report on Form 10-K for a discussion of recent accounting standards and pronouncements.
Rearranged current paragraphs (3)
Current report — wording carried from elsewhere
We are exploring ways of shortening this timeframe that may include securing access to expanded irradiation test loop capacity in existing or new research reactor facilities and engaging early with nuclear regulators to inform them of our future R&D and licensing activities. There can be no assurance that our efforts will result in an accelerated commercialization timeline.
Current report — wording carried from elsewhere
Cash provided by financing activities increased by $155.3 million in 2025 as compared to 2024. This increase was due to a:
Current report — wording carried from elsewhere
The preparation of our Consolidated Financial Statements, in conformity with accounting principles generally accepted in the United States of America, requires us to make estimates and assumptions that affect the reported amounts of assets and liabilities and disclosure of contingent assets and liabilities at the date of the financial statements, and the reported amounts of expenses during the reporting period. Actual results could differ from those estimates and assumptions.
Rearranged previous paragraphs (2)
Previous report — wording carried elsewhere
We believe our metallic fuel will offer significant economic and safety benefits over traditional nuclear fuel, primarily because of the superior heat transfer properties and the resulting lower operating temperature of all-metal fuel.
Previous report — wording carried elsewhere
We believe our metallic fuel can be used in different types of water-cooled commercial power reactors, such as pressurized water reactors (PWRs), boiling-water reactors (BWRs), Russian-designed water-cooled, water-moderated energetic reactors (VVERs), CANDUs, water-cooled SMRs, and water-cooled research reactors.