American Resources Corp
For the period ended Mar 31, 2025. Filed May 28, 2025.
View on SEC.govAbout this filing
A company's report for each of its first three quarters. The financial statements are not audited. It shows how the business has moved since the last annual report, and what management says changed.
Mar 31, 2025 · Filed May 28, 2025
What changed in Management’s Discussion and Analysis?
Read the current filingPrevious report: 10-Q
Period ended 2024-09-30; filed 2024-11-19.
0001477932-24-007457
Item 2. Management’s Discussion and Analysis of Financial Condition and Results of OperationsCurrent report: 10-Q
Period ended 2025-03-31; filed 2025-05-28.
0001477932-25-004218
Item 2. Management’s Discussion and Analysis of Financial Condition and Results of OperationsThe baseline is this issuer’s latest earlier reporting period of the same form that was filed before the current report. A previous 10-Q is a different quarter, not a year-over-year comparison. Amendments are excluded.
Compared 105 previous paragraphs and 108 current paragraphs.
46 unchanged; 29 reworded; 31 added; 28 removed; 2 previous and 2 current paragraphs rearranged.
Tables are not compared: 4 previous and 4 current tables excluded. Dates, whitespace, punctuation and numbering changes are ignored; changes to financial figures remain significant.
A changed paragraph is not evidence that risk increased or decreased. An unchanged paragraph does not establish that risk stayed the same.
Added paragraphs (31)
Current report
Within the McCoy Elkhorn subsidiary, Carnegie 1 is deemed material under Items 1304 of Regulation S-K. The Carnegie 1 is an underground mine in the Alma and Upper Alma coal seams and located near Kimper, Kentucky. When operating, coal is mined via room-and-pillar mining methods utilizing a continuous miner with the estimated capacity to produce up to approximately 10,000 tons per month of coal. The coal is stockpiled on-site and trucked approximately 7 miles to McCoy Elkhorn’s preparation facilities. In 2023, Carnegie 1 produced approximately 67,000 tons and sold at an average of $180 per ton. The mineral mined is leased from a 3 rd party professional mineral company with lease payments based on the greater of $1.75 per ton or 6% of gross sales price.
Current report
Although currently idle, Bevins #1 and Bevins #2, as well as the rail loadout no work is required beyond routine maintenance to recommence operations. The 2017 purchase price allocated to the McCoy Elkhorn properties was approximately $95,000.
Current report
The Wayland Surface Mine is a surface waste-rock reprocessing mine in a variety of coal seams (primarily the Upper Elkhorn 1 coal seam) located near Wayland, Kentucky. When operating, coal is mined via area mining through the reprocessing of previously processed coal, and the coal is trucked approximately 22 miles to the Mill Creek Preparation Plant at Deane Mining, where it is processed and sold. The mine has an estimated capacity to produce up to approximately 15,000 tons per month of coal and started production in mid-2018 with nominal coal extracted and sold as thermal coal. Since 2022, mining operations have been idle due to the company's focus on the metallurgical and industrial markets and adverse market conditions.
Current report
Other potential customers of Knott County Coal include industrial customers, specialty customers and utilities for electricity generation, although no definitive sales have been identified yet.
Current report
The Mill Creek Preparation Plant is an 800 ton-per-hour coal preparation facility located in Deane, Kentucky. The associated Rapid Loader rail loadout is a batch-weight rail loadout with 110 car storage capacity and services by CSX Transportation in their Big Sandy and Elkhorn rate districts. The Mill Creek Preparation Plant is owned by Deane Mining, subject to certain restrictions present in the agreement between Deane Mining and the surface landowner, Land Resources & Royalties LLC. We are currently utilizing less than 10% of the available processing capacity of the Mill Creek Preparation Plant.
Current report
A**dditional Permits:
Current report
In June 2023, WCC closed on an Industrial Development Bond in the amount of $45,000,000 for the purpose of financing the development of the permits and infrastructure. As of December 31, 2024 and 2023, approximately $32,500,000 and $9,500,000 of the $36,500,000 initial project fund have been expended, respectively. Due to a delay in government approvals and the expansion of rare earth concentrations it is undeterminable as to when meaningful operations will commence and the additional capital expenditures required.
Current report
The Company acquired the Pioneer Preparation Plant as an idled facility. The purchase price allocated to the Wyoming County Coal property was approximately $22,300,000 of which approximately $22,100,000 was settled with shares of the Company’s Class A Common stock. The remaining portion was satisfied in the form of a convertible note which was converted to Company common stock in December 2020.
Current report
The two idled mining permits are for underground mines and have been actively mined in the past and being maintained as idled, pending any changes to the coal market that may warrant re-starting production. Approximate coal deposits owned and leased are 0 tons and 58,100,000 tons. The current leases contain minimum annual payments of $12,000 and production royalty payments ranging from 6% to 7% of gross sales price.
Current report
In 2022, the E4-2 mine produced approximately 106,000 tons and sold the coal at an average price of $153 per ton. During the period of ownership by the Company, 100% of the coal sold was sold as industrial stoker and PCI. Since the end of 2022, the mine has been idle due to adverse market conditions.
Current report
Both the Davidson Branch Preparation Plant and the rail loadout have been maintained should operations commence in a future period. The purchase price allocated to Perry County Resources property was approximately $1,551,000.
Current report
ERC Mining Indiana Corporation (the Gold Star Mine)
Current report
Located primarily within Greene and Sullivan Counties, Indiana, ERC Mining Indiana Corporation (“ERC”) is currently comprised of one idled underground mine (the Gold Star Mine), one idled coal preparation plant and rail loadout. ERC sold its coal in the past as thermal coal to utilities. The Company does not plan to mine the property and purchased it for monetization of infrastructure assets and to reclaim the property which has been ongoing through 2024. The Company is facilitating the full reclamation and remediation of the former mine site.
Current report
Approximate coal deposits owned and leased are 0 tons and 4,383,298 tons, respectively. All of the deposits are in reclamation.
Current report
The Gold Star Mine is an underground mine in the Indiana IV (aka the Survant) coal seam located near the town of Jasonville, Indiana. Currently idled, the Gold Star Mine has been mined in the past via room-and-pillar mining methods using continuous miners, and the coal is belted directly from the mine to the raw coal stockpile at the preparation plant less than a mile away.
Current report
Processing and Transportation:
Current report
The idled preparation plant is a 165 ton-per-hour coal preparation facility located near the underground mine portal. The rail loadout associated with the preparation plant is a rail loadout serviced by the Indiana Rail Road. The preparation plant has a coarse refuse and slurry impoundment. There was no purchase price allocated to the Gold Star property.
Current report
Permits:
Current report
ERC holds one permit that covers the Gold Star Mine, processing plant, rail loadout, and related infrastructure which are in reclamation status.
Current report
Total operating expenses decreased by $1,808,844 for the three months ending March 31, 2025 as compared to 2024. This decrease was primarily driven by lower coal production related costs due to idled mining operations, lower holding costs of $794,457 due to concentrated efforts to lower payroll costs, and professional fees of $774,460 due to the decrease in legal fees.
Current report
The increase in net other expense is primarily attributable to the net decrease in interest income of $485,630 and the net increase in interest expense of $1,089,817, compared to the three months ended March 31, 2024.
Current report
Our primary sources of liquidity are derived from existing unrestricted cash, reimbursements from bond funds and other debt and capital proceeds. With the suspension of our coal production activities beginning in 2023 and the development stage of our new ReElement and Electrified Materials businesses through 2024, our sources of revenue in 2024 were primarily limited to royalty income and coal processing fees. We anticipate our ReElement and Electrified Materials new businesses to achieve increasing revenues in 2025; however, we will continue to require cash flows from financing activities to support operations and the continued development of our new business models.
Current report
As of March 31, 2025, the company has a cash balance of $24,623 and a working deficit of $75,839,150. We expect to fund our liquidity requirements over the next 12 months primarily with cash on hand and additional debt and equity financing transactions. If future cash flows are insufficient to meet our liquidity needs or capital requirements, we may be required to rationalize our expenditures or slow down efforts to further develop our new business models. We do not have any credit lines currently available to fund our liquidity requirements. Maintaining future liquidity is subject to significant uncertainties primarily related to the generation of revenues from our new business models at levels that surpass breakeven and the ability to obtain additional debt and equity financing.
Current report
Cash Flows
Current report
Three Months Ended March 31, 2025 and 2024
Current report
The $3,291,767 decrease in cash used for operating activities was primarily due to a $365,084 decrease in net loss and a $1,523,562 increase in cash flow provided by changes in working capital offset by an decrease of $496,880 in non-cash charges.
Current report
Cash provided by investing activities for the three months ended March 31, 2025 was $741,401 compared to cash used in investing activities of $432,642 for the three months ended March 31, 2024. The change was primarily due to purchases of property and equipment, net of capitalized interest income and (expense) of $1,643,099 and proceeds from short-term investments of $582,902.
Current report
Cash provided by financing activities for the three months ended 2025 was $76,799 compared to $148,262,883 for the three months ended 2024. The change was due to proceeds from tax exempt bonds, net of $149,719,203 that was received in March 31, 2024 and no bonds issued in 2025, repayment of other financing obligation of $1,373,201, offset by proceeds from convertible promissory note of $1,450,000.
Current report
Capital Resources
Current report
We had no material commitments for capital expenditures as of March 31, 2025.
Current report
As of March 31, 2025, we had no off-balance sheet arrangements.
Removed paragraphs (28)
Previous report
The Carnegie 1 Mine is an underground mine in the Alma and Upper Alma coal seams and located near Kimper, Kentucky. In 2011, coal production from the Carnegie Mine in the Alma coal seam commenced and then subsequently the mine was idled. Production at the Carnegie Mine was reinitiated in early 2017 under Quest Energy’s ownership and is currently being mined via room-and-pillar mining methods utilizing a continuous miner. The coal is stockpiled on-site and trucked approximately 7 miles to McCoy Elkhorn’s preparation facilities. The Carnegie Mine is currently operated as a modified contractor mine, whereby McCoy Elkhorn provides the mining infrastructure and equipment for the operations and pays the contractor a fixed per-ton fee for managing the workforce, procuring the supplies, and maintaining the equipment and infrastructure in proper working order.
Previous report
Beginning in January 2020, Mine #15 and Carnegie 1 mines were idled due to the adverse market effects Covid-19 global pandemic. The Carnegie 1 mine restarted during October 2022 and the Carnegie 2 mine commenced during 2022.
Previous report
Both Bevins #1 and Bevins #2, as well as the rail loadout, are operational and any work required on any of the plants or loadouts would be routine maintenance. The allocated cost of this property at McCoy Elkhorn Coal paid by the company is $95,210.
Previous report
Currently all permitted mines are idled, in development or in reclamation.
Previous report
The Company acquired the Pioneer Preparation Plants as an idled facility, and since acquisition, no work has been performed at the facility. Both the Pioneer Preparation Plant and the rail loadout are idled and would require an undetermined amount of work and capital to bring them into operation, which is currently in the initial phases of planning and no cost estimates have been received. The allocated cost for the property at Wyoming County Coal will pay by the Company is $22,326,101 of which $22,091,688 has been paid using shares of the Company’s Class A Common stock. The remaining portion was paid in cash.
Previous report
Beginning in January 2020, The E4-2 mine was idled due to the adverse market effects Covid-19 global pandemic. The E4-2 Mine was restarted during March 2022 and idled due to regional flooding during October 2022.
Previous report
Both the Davidson Branch Preparation Plant and the rail loadout are operational, and any work required on any of the plant or loadouts would be routine maintenance. The allocated cost of for the property at Perry County Resources paid by the Company is $1,954,317.
Previous report
The Mine Act and the MINER Act, and regulations issued under these federal statutes, impose stringent health and safety standards on mining operations. The regulations that have been adopted under the Mine Act and the MINER Act are comprehensive and affect numerous aspects of mining operations, including training of mine personnel, mining procedures, roof control, ventilation, blasting, use and maintenance of mining equipment, dust and noise control, communications, emergency response procedures, and other matters. The Mine Safety and Health Administration (MSHA) regularly inspects mines to ensure compliance with regulations promulgated under the Mine Act and MINER Act.
Previous report
Due to the large number of mining permits held by the Company that have been previously mined and operated, there is a significant amount of environmental reclamation and remediation required by the Company to comply with local, state, and federal regulations for coal mining companies.
Previous report
From our inception to-date our activities have been primarily financed from the proceeds of our acquisitions, common share equity investments and loans.
Previous report
The following table summarizes the period over period changes in revenue generating operations for the three and nine months ended September 30, 2024:
Previous report
Revenue decreased by $16,120,841 for the nine months ended September 30, 2024 compared to 2023. The primary driver of the decrease was a reduction of $16,120,841 in coal sales for the three months ended September 30, 2024 as compared to 2023. Additionally, royalty income decreased by $350,627. These decreases were partially offset by an increase in metal recovery and sales of $127,355 for the three months ended September 30, 2024 compared to 2023.
Previous report
Total operating expenses increased by $835,050 for the three months ending September 30, 2024 as compared to 2023. This increase was primarily driven by general and administrative expenses of $2,216,846, professional fees of $323,114. These increases were offset by decreases Coal production and holdings costs of $299,197, production taxes and royalties of $250,216 and development expense of $1,722,803.
Previous report
Total operating expenses decreased by $9,456,053 for the nine months ending September 30, 2024 as compared to 2023. This decrease was primarily driven by a decrease in coal production and holdings costs of $5,659,000 as well as decreases in production taxes and royalties of $1,396,806, development expenses of $7,585,297 and gain on sale of equipment of $1,225,000. These decreases were partially offset by increases in general and administrative expenses of $3,268,457 and a increase in professional fees by $824,772. General and administrative expenses are primarily made up of costs related to contract labor, payroll, facility maintenance, and other standard operational expenses.
Previous report
Total other income (expenses) decreased by $357,563 for the three months ended September 30, 2024 as compared to 2023. The decrease is primarily made up of decreases in other income (expense) of $182,101 and interest expense of $253,039. These decreases were partially offset by increases in earnings from equity method investees of $72,881 and interest income of $4,696.
Previous report
Total other income (expenses) decreased by $1,230,030 for the nine months ended September 30, 2024 as compared to 2023. The decrease is primarily made up of decreases in earnings from equity method investees of $435,845, other income (expense) of $362,096 and interest expense of $521,410. These decreases were partially offset by an increase in interest income of $89,321.
Previous report
As of September 30, 2024, our available cash was $161,651,732. We expect to fund our liquidity requirements with cash on hand, future borrowings and cash flow from operations. If future cash flows are insufficient to meet our liquidity needs or capital requirements, we may reduce our mine development and/or fund a portion of our expenditures through issuance of debt or equity securities, or from other sources, such as asset sales. We do not have any credit lines currently available to fund our liquidity requirements, and currently there is uncertainty regarding our ability to execute the above strategy.
Previous report
Cash Flows from Operating Activities
Previous report
Cash used in operating activities was $16,317,031 for the nine months ended September 30, 2024, which consists of a net loss of $21,909,367, offset by adjustments to reconcile net loss to net cash of $6,415,477 and a change in our net operating assets and liabilities of $823,141 which is primarily the result of an decrease in inventories of $1,975,812, and accounts payable of $1,609,584 and an increase in accounts payable related party of $2,318,695.
Previous report
Cash used in operating activities was $15,908,173 for the nine months ended September 30, 2023, which consists of a net loss of $13,791,277 partially offset by adjustments to reconcile net loss to net cash of $4,143,169 and a change in our net operating assets and liabilities of $6,260,065, which is primarily the result of a decrease in receivables of $3,730,070, inventories of $1,719,836, prepaid expenses and other current assets of $1,131,065, accounts payable – related party of $1,102,822 offset by an increase of accounts payable of $1,849,532.
Previous report
Cash Flows from Investing Activities
Previous report
Cash used in investing activities was $1,757,837 for the nine months ended September 30, 2024, which consisted of an increase in purchase of property and equipment for $166,229, proceeds from the sale of equipment of $400,000, cash invested in a note receivable of $99,022 and proceeds from short-term investments, net of $1,191,608.
Previous report
Cash used in investing activities was $3,862,383 for the nine months ended September 30, 2023, which consisted of a decrease in purchase of property and equipment for $283,790, proceeds from short-term investments, net of $703,593 and purchase of investments, net of $4,500,000, which were partially offset by proceeds received from the sale of equipment for $1,625,000.
Previous report
Cash Flows from Financing Activities
Previous report
Cash provided by financing activities was $145,336,288 for the nine months ended September 30, 2024, which consisted of cash received from warrant conversions in the amount of $32,339, proceeds from the convertible promissory note – related party in the amount of $894,172, proceeds from the exercise of stock options of $156,900, proceeds from tax exempt bonds of $149,719,203, and proceeds received from other financing obligations of $95,592, partially offset by the repayment of other financing obligations in the amount of $5,561,918.
Previous report
Cash provided by financing activities was $45,671,490 for the nine months ended September 30, 2023, which consisted of repayment on long term debt of $1,112,850 and repayment on other financing obligations of $4,329,186, partially offset by proceeds from tax exempt bonds of $43,475,887 and proceeds received from other financing obligations of $7,637,639.
Previous report
As a public company, we will be subject to certain reporting and other compliance requirements of a publicly reporting company. We will be subject to certain costs for such compliance which private companies may not choose to make. We have identified such costs as being primarily for audits, legal services, filing expenses, financial and reporting controls and shareholder communications and estimate the cost to be approximately $35,000 monthly if the activities of our Company remain somewhat the same for the next few months. We have included such costs in our monthly cash flow needs and expect to pay such costs from a combination of cash from operations and financing activities.
Previous report
We do not have any off-balance sheet arrangements that we are required to disclose pursuant to these regulations. In the ordinary course of business, we enter into operating lease commitments, purchase commitments and other contractual obligations. These transactions are recognized in our financial statements in accordance with generally accepted accounting principles in the United States.
Reworded paragraphs (29)
Previous wording
On January 5, 2017, American Resources Corporation (ARC) executed a Share Exchange Agreement between the Company and Quest Energy Inc. (“Quest Energy”), a private company incorporated in the State of Indiana on May 2015 with offices at 12115 Visionary Way, Fishers, IN 46038, and due to the fulfillment of various conditions precedent to closing of the transaction, the control of the Company was transferred to the Quest Energy shareholders on February 7, 2017. This transaction resulted in Quest Energy becoming a wholly-owned subsidiary of ARC. Through Quest Energy, ARC was able to acquire coal mining and coal processing operations, substantially all located in eastern Kentucky and western West Virginia. On November 25, 2020, Quest Energy changed its name to American Carbon Corp. (American Carbon)
Current wording
On January 5, 2017, American Resources Corporation (ARC) executed a Share Exchange Agreement between the Company and Quest Energy Inc. (“Quest Energy”), a private company incorporated in the State of Indiana on May 2015 with offices at 12115 Visionary Way, Fishers, IN 46038, and due to the fulfillment of various conditions precedent to closing of the transaction, the control of the Company was transferred to the Quest Energy shareholders on February 7, 2017. This transaction resulted in Quest Energy becoming a wholly-owned subsidiary of ARC. Through Quest Energy, ARC was able to acquire coal mining and coal processing operations, substantially all located in eastern Kentucky and western West Virginia. On November 25, 2020, Quest Energy changed its name to American Carbon Corp. On December 27, 2024, American Carbon changed its name to American Infrastructure Corporation (American Infrastructure Corporation).
Previous wording
American Carbon currently has seven coal mining and processing operating subsidiaries: McCoy Elkhorn Coal LLC (doing business as McCoy Elkhorn Coal Company) (McCoy Elkhorn), Knott County Coal LLC (Knott County Coal), Deane Mining, LLC (Deane Mining) and Wyoming County Coal LLC (Wyoming County), Quest Processing LLC (Quest Processing), Perry County Resources (Perry County) located in eastern Kentucky and western West Virginia within the Central Appalachian coal basin, and ERC Mining Indiana Corporation (ERC) located in southwest Indiana within the Illinois coal basin. The coal deposits under control by the Company are generally comprise of metallurgical coal (used for steel making), pulverized coal injections (used in the steel making process) and high-BTU, low sulfur, low moisture bituminous coal used for a variety of uses within several industries, including industrial customers and specialty products. Since mid-2019, we have not mined or sold coal which is sold into the thermal coal markets. All production and future investment will be for the mining of metallurgical coal used in the steel and specialty markets.
Current wording
American Infrastructure Corporation currently has seven coal mining and processing operating subsidiaries: McCoy Elkhorn Coal LLC (doing business as McCoy Elkhorn Coal Company) (McCoy Elkhorn), Knott County Coal LLC (Knott County Coal), Deane Mining, LLC (Deane Mining), Wyoming County Coal LLC (Wyoming County), Perry County Resources (Perry County) located in eastern Kentucky and western West Virginia within the Central Appalachian coal basin, and ERC Mining Indiana Corporation (ERC) located in southwest Indiana within the Illinois coal basin. The coal deposits under control by the Company are generally comprise of metallurgical coal (used for steel making), pulverized coal injections (used in the steel making process) and high-BTU, low sulfur, low moisture bituminous coal used for a variety of uses within several industries, including industrial customers and specialty products.
Previous wording
Efforts to diversify revenue streams have led to the establishment of additional subsidiaries; American Metals LLC (AM) which is focused on the recovery and sale of recovered metal and steel and ReElement Technologies LLC (ReElement) which is focused on the aggregation and monetization of critical and rare earth element deposits.
Current wording
Efforts to diversify revenue streams have led to the establishment of additional subsidiaries; Electrified Materials Corporation (EMC) which is focused on the aggregation, recovery and sale of recovered metal and steel and American Rare Earth LLC (ARE) which is focused on the purification and monetization of critical and rare earth element deposits and end of life magnets and batteries. During 2024, American Rare Earth LLC changed its name to ReElement Technologies LLC (ReElement). During 2024, ReElement filed and changed from a limited liability company to a corporation. During 2025, the Company gave up majority stake in American Infrastructure, ReElements, and Electrified Materials. The Company maintained contractual and financial interests in each of these entities that provide it with the power to direct key activities and accordingly these entities continue to be consolidated as variable interest entities.
Previous wording
We have not classified, and as a result, do not have any “proven” or “probable” reserves as defined in United States Securities and Exchange Commission Industry Guide 7, and as a result, our company and its business activities are deemed to be in the exploration stage until mineral deposits are defined on our properties.
Current wording
We have not classified, and as a result, do not have any “proven” or “probable” reserves as defined in United States Securities and Exchange Commission Items 1300 through 1305 of Regulation S-K, and as a result, our company and its business activities are deemed to be in the exploration stage until mineral reserves are defined on our properties.
Previous wording
Located primarily within Pike County, Kentucky, McCoy Elkhorn is currently comprised of three mines (Mine #15) in “idle” status, and two mines in operations (Carnegie 1 and 2 Mines), two coal preparation facilities (Bevins #1 and Bevins #2), and other mines in various stages of development or reclamation. McCoy Elkhorn sells its coal to a variety of customers, both domestically and internationally, primarily to the steel making industry as a high-vol “B” coal or blended coal. The coal controlled at McCoy Elkhorn (along with our other subsidiaries) has not been classified as either “proven” or “probable” as defined in the United States Securities and Exchange Commission Items 1300 through 1305 of Regulation S-K, and as a result, do not have any “proven” or “probable” reserves under such definition and are classified as an “Exploration Stage” pursuant to Items 1300 through 1305 of Regulation S-K.
Current wording
Located primarily within Pike County, Kentucky, McCoy Elkhorn is currently comprised of three mines in “idle” status (Mine #15 and the Carnegie 1 and Carnegie 2 Mines), two coal preparation facilities (Bevins #1 and Bevins #2), and other mines and permits in various stages of development or reclamation. The address for the Bevins #1 and #2 preparation facilities is 2069 Highway 194 E Meta, KY 41501.
Previous wording
Mine #15 is an underground mine in the Millard (also known as Glamorgan) coal seam and located near Meta, Kentucky. Mine #15 is mined via room-and-pillar mining methods using continuous miners, and the coal is belted directly from the stockpile to McCoy Elkhorn’s coal preparation facility. Mine #15 is currently a “company run” mine, whereby the Company manages the workforce at the mine. The coal from Mine #15 is stockpiled at the mine site and belted directly to the Company’s nearby coal preparation facilities. Production at Mine #15 re-commenced under Quest Energy’s ownership in September 2016.
Current wording
Mine #15 is an underground mine in the Millard (also known as Glamorgan) coal seam and located near Meta, Kentucky. When operating, coal is mined via room-and-pillar mining methods using continuous miners and belted directly from the stockpile to McCoy Elkhorn’s coal preparation facility. Mine #15 has the estimated capacity to produce up to approximately 40,000 tons per month of coal. The mineral available is leased from various 3 rd party mineral holders. Coal mined from the lease requires a payment of greater of $2.50 per ton or 5% of gross sales price.
Previous wording
The Carnegie 2 Mine is an underground mine in the Alma and Upper Alma coal seams and located near Kimper, Kentucky. In 2021, mine development began and operations at the Carnegie 2 Mine started in August 2022 and is currently being mined via room-and-pillar mining methods utilizing a continuous miner. The coal is stockpiled on-site and trucked approximately 7 miles to McCoy Elkhorn’s preparation facilities. The Carnegie 2 Mine is currently a “company run” mine, whereby the Company manages the workforce at the mine and pays all expenses of the mine. The Carnegie 2. Mine has the estimated capacity to produce up to approximately 10,000 tons per month of coal.
Current wording
Carnegie 2 is also an underground mine in the Alma and Upper Alma coal seams and located near Kimper, Kentucky. When operating, coal is mined via room-and-pillar mining methods utilizing a continuous miner with the estimated capacity to produce up to approximately 10,000 tons per month of coal. The coal is stockpiled on-site and trucked approximately 7 miles to McCoy Elkhorn’s preparation facilities. In 2023, the Carnegie 2 Mine produced approximately 13,000 tons and sold at an average of $237 per ton. The mineral being mined is leased from a 3 rd party professional mineral company with lease payments based on the greater of $1.75 per ton or 6% of gross sales price.
Previous wording
The Bevins #1 Preparation Plant is an 800 ton-per hour coal preparation facility located near Meta, Kentucky, across the road from Mine #15. Bevins #1 has raw coal stockpile storage of approximately 25,000 tons and clean coal stockpile storage of 100,000 tons of coal. The Bevins #1 facility has a fine coal circuit and a stoker circuit that allows for enhance coal recovery and various coal sizing options depending on the needs of the customer. The Company acquired the Bevins Preparation Plants as idled facilities, and since acquisition, the primary work completed at the Bevins Preparation Plants by the Company includes rehabilitating the plants’ warehouse and replacing belt lines.
Current wording
The Bevins #1 Preparation Plant is an 800 ton-per hour coal preparation facility located near Meta, Kentucky, across the road from Mine #15. Bevins #1 has raw coal stockpile storage of approximately 25,000 tons and clean coal stockpile storage of 100,000 tons of coal. The Bevins #1 facility has a fine coal circuit and a stoker circuit that allows for enhance coal recovery and various coal sizing options depending on the needs of the customer.
Previous wording
The Bevins #2 Preparation Plant is on the same permit site as Bevins #1 and is a 500 ton-per-hour processing facility with fine coal recovery and a stoker circuit for coal sizing options. Bevins #2 has raw coal stockpile storage of 25,000 tons of coal and a clean coal stockpile storage of 45,000 tons of coal. We are currently utilizing less than 10% of the available processing capacity of Bevins #1 and Bevins #2.
Current wording
The Bevins #2 Preparation Plant is on the same permit site as Bevins #1 and is a 500 ton-per-hour processing facility with fine coal recovery and a stoker circuit for coal sizing options. Bevins #2 has raw coal stockpile storage of 25,000 tons of coal and a clean coal stockpile storage of 45,000 tons of coal.
Previous wording
Due to additional coal processing storage capacity at Bevins #1 and Bevins #2 Preparation Plants, McCoy Elkhorn has the ability to process, store, and load coal for other regional coal producers for an agreed-to fee.
Current wording
Due to the processing storage capacity at Bevins #1 and Bevins #2 Preparation Plants, McCoy Elkhorn has the capacity to process, store, and load coal for other regional coal producers for agreed to fees.
Previous wording
Located primarily within Knott County, Kentucky (but with additional idled permits in Leslie County, Perry County, and Breathitt County, Kentucky), Knott County Coal is comprised of 22 idled mining permits (or permits in reclamation) and permits for one preparation facility: the idled Supreme Energy Preparation Plant. The idled mining permits are either in various stages of reclamation or being maintained as idled, pending any changes to the coal market that may warrant reinitiating production. The idled mines at Knott County Coal are primarily underground mines that utilize room-and-pillar mining. The coal controlled at Deane Mining (along with our other subsidiaries) has not been classified as either “proven” or “probable” as defined in the United States Securities and Exchange Commission Items 1300 through 1305 of Regulation S-K, and as a result, do not have any “proven” or “probable” reserves under such definition and are classified as an “Exploration Stage” pursuant to Items 1300 through 1305 of Regulation S-K.
Current wording
Located primarily within Knott County, Kentucky (but with additional idled permits in Leslie County, Perry County, and Breathitt County, Kentucky), Knott County Coal is comprised of one idled mine (the Wayland Surface Mine) and 22 idled mining permits (or permits in reclamation), including the permits associated with the idled Supreme Energy Preparation Plant. The idled mining permits are either in various stages of planning, idle status or reclamation. The idled mines at are primarily underground mines that utilize room-and-pillar mining. Approximate coal deposits owned and leased are 0 tons and 3,207,000 tons, respectively. The current leases contain production royalty payments based on the greater of $1.50 per clean ton or 6% of gross sales price.
Previous wording
The idled Supreme Energy Preparation Plant is a 450 ton-per-hour coal preparation facility located in Kite, Kentucky. The Bates Branch rail loadout associated with the Supreme Energy Preparation Plant is a batch-weigh rail loadout with 110 rail car storage capacity and serviced by CSX Transportation in their Big Sandy rate district. The Supreme Energy Preparation Plant has a coarse refuse and slurry impoundment called the King Branch Impoundment.
Current wording
The idled Supreme Energy Preparation Plant is a 400 ton-per-hour coal preparation facility with a fine coal circuit located in Kite, Kentucky. The Bates Branch rail loadout associated with the Supreme Energy Preparation Plant is a batch-weigh rail loadout with 220 rail car storage capacity and serviced by CSX Transportation in their Big Sandy rate district. When operating, coarse refuse is trucked to the Kings Branch impoundment, which is approximately one mile from the Supreme Energy facility, and slurry is piped from the Supreme Energy facility to the Kings Branch impoundment.
Previous wording
The Supreme Energy Preparation Plant is owned by Knott County Coal, subject to certain restrictions present in the agreement between Knott County Coal and the surface landowner, Land Resources & Royalties LLC.
Current wording
The Supreme Energy Preparation Plant is owned by Knott County Coal, subject to certain restrictions present in the agreement between Knott County Coal and the surface landowner, Land Resources & Royalties LLC. During 2024 components of the Supreme Energy Preparation Plant have been transferred as part of the WCC development.
Previous wording
The Company acquired the Supreme Energy Preparation Plants as an idled facility, and since acquisition, no work has been performed at the facility other than minor maintenance. Both the Supreme Energy Preparation Plant and the rail loadout are idled and would require an undetermined amount of work and capital to bring them into operation. The allocated cost of the property at Knott County Coal paid by the Company is $286,046.
Current wording
The Company acquired the Supreme Energy Preparation Plants as an idled facility, and since acquisition, no work has been performed at the facility other than minor maintenance. Both the Supreme Energy Preparation Plant and the rail loadout are idled and would require an undetermined amount of work and capital to bring them into operation. The purchase price allocated of the Knott County Coal property was approximately $286,000.
Previous wording
In addition to the above mines, Knott County Coal holds 22 coal mining permits that are in development, idled or in various stages of reclamation. Any idled mines that are brought into production would require significant upfront capital investment and there is no assurance of the feasibility of any such new operations.
Current wording
In addition to the above mines, Knott County Coal holds 20 additional coal mining permits, idled or in various stages of reclamation. Any idled mines that are brought into production would require significant upfront capital investment and there is no assurance of the feasibility of any such new operations.
Previous wording
Both the Mill Creek Preparation Plant and the rail loadout are operational, and any work required on any of the plant or loadouts would be routine maintenance. The allocated cost for the property at Deane Mining paid by the Company is $1,569,641.
Current wording
Both the Mill Creek Preparation Plant and the rail loadout are operational, and any work required on any of the plant or loadouts would be routine maintenance. The allocated cost of the property at Deane Mining paid by the Company is $1,569,641.
Previous wording
Located within Wyoming County, West Virginia, Wyoming County Coal is comprised of two idled underground mining permits and the three permits associated with the idled Pioneer Preparation Plant, the Hatcher rail loadout, and Simmons Fork Refuse Impoundment. The two idled mining permits are undisturbed underground mines that are anticipated to utilize room-and-pillar mining. The coal controlled at Wyoming County Coal (along with our other subsidiaries) has not been classified as either “proven” or “probable” as defined in the United States Securities and Exchange Commission Items 1300 through 1305 of Regulation S-K, and as a result, do not have any “proven” or “probable” reserves under such definition and are classified as an “Exploration Stage” pursuant to Items 1300 through 1305 of Regulation S-K.
Current wording
Located within Wyoming County, West Virginia, Wyoming County Coal (WCC) is comprised of two idled underground mining permits and the three permits associated with the idled Pioneer Preparation Plant, the Hatcher rail loadout, and Simmons Fork Refuse Impoundment. The two idled mining permits are undisturbed underground mines that are anticipated to utilize room-and-pillar mining. Approximate coal deposits owned and leased are 5,668,00 tons and 0 tons, respectively.
Previous wording
The Company is in the initial planning phase of getting estimates on the cost to upgrade the preparation facility to a modern 350 ton per hour preparation facility, although no cost estimates have yet been received. The Company is also in the initial planning phase of getting estimates on the cost and timing of upgrading the rail load out facility to a modern batch weight load out system, although no cost estimates have yet been received.
Current wording
In connection with the Industrial Development Bond financing, the Company is in the process of upgrading and redeveloping the preparation facility to a modern 350 ton per hour preparation facility and upgrading the rail load out facility to a modern batch weight load out system.
Previous wording
Wyoming County Coal holds two coal mining permits that are in the initial planning phase and three permits associated with the idled Pioneer Preparation Plant, the Hatcher rail loadout, and Simmons Fork Refuse Impoundment. Any mine that is brought into production would require significant upfront capital investment and there is no assurance of the feasibility of any such new operations. As of the report date, the permits have not been fully transferred as they await final regulatory approval. As of the balance sheet date and report date, the West Virginia permit transfers have not yet been approved, and WCC has not substituted its reclamation surety bonds for the seller’s bond collateral. The transfer of any new permits to the Company is subject to regulatory approval. This approval is subject to the review of both unabated or uncorrected violations that are listed on the Applicator Violator List. The Company, to include several of its subsidiaries, does have unabated and/or uncorrected violations that are listed on the Applicator Violator List. Should the state regulators believe that the Company is not in the process of abating or correcting the currently outstanding issues associated with their currently held permits they may choose not to issue the Company any new permits until such issues are properly rectified.
Current wording
Wyoming County Coal holds two coal mining permits that are in the development phase including faceup and infrastructure work and three permits associated with the idled Pioneer Preparation Plant, the Hatcher rail loadout, and Simmons Fork Refuse Impoundment.
Previous wording
Located primarily within Perry County, Kentucky, Perry County Resources LLC is comprised of one “Idled” underground mine (the E4-2 mine) and one “Idled” coal processing facility called the Davidson Branch Preparation Plant, along with two additional idled underground mining permits. The two idled mining permits are for underground mines and have been actively mined in the past and being maintained as idled, pending any changes to the coal market that may warrant re-starting production. The coal controlled at Perry County Resources (along with our other subsidiaries) has not been classified as either “proven” or “probable” as defined in the United States Securities and Exchange Commission Items 1300 through 1305 of Regulation S-K, and as a result, do not have any “proven” or “probable” reserves under such definition and are classified as an “Exploration Stage” pursuant to Items 1300 through 1305 of Regulation S-K.
Current wording
Located primarily within Perry County, Kentucky, Perry County Resources LLC is comprised of one idled underground mine (the E4-2 mine) and one idled coal processing facility called the Davidson Branch Preparation Plant, along with two additional idled underground mining permits. The E4-2 mine and Davidson Branch Preparation Plan are located at 1845 KY-15 Hazard, KY 41701.
Previous wording
The E4-2 mine is an underground mine in the Elkhorn 4 (aka the Amburgy) coal seam located near the town of Hazard, Kentucky. The E4-2 mine is mined via room-and-pillar mining methods using both continuous miners and continuous haulage systems, and the coal is belted directly from the mine to the raw coal stockpile at the Davidson Branch Preparation Plant less than a mile away. The E4-2 mine is currently a “company-run” mine, whereby the Company manages the workforce at the mine and pays all expenses of the mine. The Company acquired the E4-2 mine as an active mine, and since acquisition in September 2019, the primary work at the E4-2 mine has been rehabilitation of existing infrastructure to increase the operational efficiencies of the mine, including replacing belt structure, repairing equipment, replacing underground mining infrastructure, and installing new mining infrastructure as the mine advances due to coal extraction. The E4-2 mine has the estimated capacity to produce up to approximately 80,000 tons per month of coal.
Current wording
Within the Perry County subsidiary, E4-2 mine is deemed material under Items 1304 of Regulation S-K. The E4-2 mine is an underground mine in the Elkhorn 4 (aka the Amburgy) coal seam located near the town of Hazard, Kentucky. When operating, coal is mined via room-and-pillar mining methods using both continuous miners and continuous haulage systems, and the coal is belted directly from the mine to the raw coal stockpile at the Davidson Branch Preparation Plant less than a mile away. The E4-2 mine has the estimated capacity to produce up to approximately 80,000 tons per month of coal. The mineral available is partially owned by the Company and partially leased from various mineral holders. The lease terms are the greater of $1.50 per ton or 6% of gross sales price.
Previous wording
The Davidson Branch Preparation Plant is a 1,300 ton-per-hour coal preparation facility located near Hazard, Kentucky. The associated “Bluegrass 4” rail loadout is a batch-weight rail loadout with 135 car storage capacity and services by CSX Transportation in their Hazard/Elkhorn rate district. The Davidson Branch Preparation Plant is owned by Perry County Resources. We are currently utilizing less than 10% of the available processing capacity of the Davidson Branch Preparation Plant.
Current wording
The Davidson Branch Preparation Plant is a 1,300 ton-per-hour coal preparation facility located near Hazard, Kentucky. The associated “Bluegrass 4” rail loadout is a batch-weight rail loadout with 135 car storage capacity and services by CSX Transportation in their Hazard/Elkhorn rate district. The Davidson Branch Preparation Plant is owned by Perry County Resources. With mining operations currently idle, the preparation plan is not currently operating.
Previous wording
In addition to the above mine, preparation facility, and related permits, Perry County Resources holds four additional coal mining permits that are idled or in development. Any idled mines that are brought into production would require significant upfront capital investment and there is no assurance of the feasibility of any such new operations.
Current wording
In addition to the above mine, preparation facility, and related permits, Perry County Resources had four additional coal mining permits that are idled or in development stage. Any idled mines that are brought into production would require significant upfront capital investment and there is no assurance of the feasibility of any such new operations. Three of the idled permits were sold to an unrelated entity on March 4, 2020 for $700,000 cash and $300,000 of value for equipment.
Previous wording
ARC, through its operating subsidiaries, employs a combination of company employees and contract labor to mine coal, process coal, and related functions. The Company is continually evaluating the use of company employees and contract labor to determine the optimal mix of each, given the needs of the Company. Currently, McCoy Elkhorn’s Carnegie 1 and 2 Mines and Perry’s E4-1 mine and are primarily run by contract labor, and the Company’s various coal preparation facilities are run by contract labor.
Current wording
ARC and its operating subsidiaries, employ a combination of company employees and contract labor. The Company is continually evaluating the use of company employees and contract labor to determine the optimal mix of each, given the needs of the Company.
Previous wording
The Company currently has approximately 26 direct employees. The Company is headquartered in Fishers, Indiana with four members of the Company’s executive team based at this location.
Current wording
The Company currently has approximately 23 direct employees. The Company is headquartered in Fishers, Indiana with four members of the Company’s executive team based at this location.
Previous wording
The following table summarizes our results of operations for the three and nine months ended September 30, 2024:
Current wording
The following table summarizes our results of operations for the three months ended March 31, 2025 and 2024:
Previous wording
Revenue decreased by $5,721,840 for the three months ended September 30, 2024 compared to 2023. The primary driver of the decrease was a reduction of $5,721,840 in coal sales for the three months ended September 30, 2024 as compared to 2023. The decrease was partially offset by increases in metal recovery sales and royalty income of $148,333 and $425, respectively, for the three months ended September 30, 2024 compared to 2023.
Current wording
Revenue decreased by $62,092 for the three months ended March 31, 2025 compared to 2024. The primary driver of the decrease was a reduction of $64,667 in royalty income for the three months ended March 31, 2025 as compared to 2024.
Previous wording
The following table summarizes the period over period changes in operating expenses (income) for the three and nine months ended September 30, 2024:
Current wording
The following table summarizes the period over period changes in operating expenses (income) for the three months ended March 31, 2025 and 2024:
Previous wording
The following table summarizes the period over period changes in other income (expense) for the three and nine months ended September 30, 2024:
Current wording
The following table summarizes the period over period changes in other income (expense) for the three months ended March 31, 2025 and 2024:
Rearranged current paragraphs (2)
Current report — wording carried from elsewhere
Since mid-2019, we have not mined or sold coal which is sold into the thermal coal markets. Due to adverse market conditions all mining operations are currently idled. Should mining operations commence, all production and future investment will be for the mining of metallurgical coal. The following table is presented for historical purposes.
Current report — wording carried from elsewhere
When operating, McCoy Elkhorn has historically sold its coal to a variety of customers, both domestically and internationally, primarily to the steel making industry as a high-vol “B” coal or blended coal. Due to adverse market conditions, Mine #15 was in idle status during 2023 and 2024 and the mining operations at Carnegie 1 and 2 were idled during 2023.
Rearranged previous paragraphs (2)
Previous report — wording carried elsewhere
The mineral being mined through Carnegie 1 and Carnegie 2 is leased from a 3 rd party professional mineral company. Coal mined from the lease requires a payment of greater of $1.75 per ton or 6% of gross sales price.
Previous report — wording carried elsewhere
Coal from Access Energy is processed at Deane Mining’s Mill Creek Preparation Plant, an 800 ton-per hour coal preparation facility with a batch-weight loadout and rail spur for loading coal into trains for rail shipments. The spur has storage for 110 rail cars and is serviced by CSX Transportation and is located on both CSX’s Big Sandy rate district and CSX’s Elkhorn rate district. The Mill Creek Preparation Plant has a coarse refuse and slurry impoundment called Razorblade Impoundment.