Skip to main content

URANIUM ENERGY CORP

For the period ended Apr 30, 2024. Filed Jun 10, 2024.

View on SEC.gov

About this filing

A company's report for each of its first three quarters. The financial statements are not audited. It shows how the business has moved since the last annual report, and what management says changed.

Apr 30, 2024 · Filed Jun 10, 2024

UEC$6.92+6.8%Stored close · as of Nov 6, 2026

What changed in Management’s Discussion and Analysis?

Read the current filing

Previous report: 10-Q

Period ended 2024-01-31; filed 2024-03-11.

0001437749-24-007217

Item 2. Management’s Discussion and Analysis of Financial Condition and Results of Operations

Current report: 10-Q

Period ended 2024-04-30; filed 2024-06-10.

0001437749-24-019731

Item 2. Management’s Discussion and Analysis of Financial Condition and Results of Operations

The baseline is this issuer’s latest earlier reporting period of the same form that was filed before the current report. A previous 10-Q is a different quarter, not a year-over-year comparison. Amendments are excluded.

Compared 102 previous paragraphs and 101 current paragraphs.

54 unchanged; 43 reworded; 4 added; 5 removed; 0 previous and 0 current paragraphs rearranged.

Tables are not compared: 26 previous and 26 current tables excluded. Dates, whitespace, punctuation and numbering changes are ignored; changes to financial figures remain significant.

A changed paragraph is not evidence that risk increased or decreased. An unchanged paragraph does not establish that risk stayed the same.

Added paragraphs (4)

Current report

On January 16, 2024, we announced restarting uranium extraction at our fully permitted, and past producing, Christensen Ranch Mine ISR operation in Wyoming. The first extraction is expected during August 2024 and will be funded with existing cash on the Company’s balance sheet.

Current report

Uranium recovered from the Christensen Ranch Mine ISR Project will be processed at our Irigaray central processing plant (“CPP”). The Irigaray CPP is the hub central to our four fully permitted ISR projects located in the Powder River Basin of Wyoming, including our Christensen Ranch Mine, Reno Creek, Moore Ranch and Ludeman projects. An application to increase the licensed capacity of the Irigaray CPP from the 2.5 million pounds U 3 O 8 per year to 4.0 million pounds U 3 O 8 per year was submitted to the Wyoming Department of Environmental Quality in November 2023; and approval is expected later in 2024.

Current report

To enable a faster extraction restart, extensive preparations at the Christensen Ranch Mine wellfields and satellite processing plant were completed in 2023. This included the re-installation of equipment, re-attachment of piping and a variety of electrical testing, repairs and upgrades to the existing facilities. Since that time, additional work has progressed, including the hiring of additional operational personnel, preparation of a detailed wellfield startup plan, final preparations for plant and wellfield operations, and the installation of cased wells in two new wellfield header houses in Mine Unit 10 (Modules 10-7 and 10-8).

Current report

In the U.S., H.R. 1042, “The Prohibiting Russian Uranium Imports Act” was signed into law on May 13, 2024, goes into effect on August 11, 2024 and extends through 2040. The legislation bans Russian uranium imports but allows a U.S. Department of Energy (“DOE”) waiver process through 2027 in the event no alternative viable source of low-enriched uranium (“LEU”) is available to: (i) sustain the continued operation of a nuclear reactor or a U.S. nuclear energy company; or (ii) importation of Russian LEU is determined to be in the national interest. In a separate but related action, “The Nuclear Fuel Security Act” (“NFSA”) was enacted as part of the “National Defense Authorization Act” in December of 2023 and was designed to help rebuild the domestic nuclear fuel cycle, including uranium production, conversion and enrichment. The passage of H.R. 1042 unlocks $2.7 billion in funding under the NFSA and will be used by the DOE to acquire LEU and High Assay Low Enriched Uranium (“HALEU”) for advanced reactors. Under this program DOE will acquire LEU and HALEU with priority given to domestic sources of produced uranium, conversion and enrichment. In combination, the passage of these bills will help rebuild and restore a robust domestic fuel cycle in the U.S.
Removed paragraphs (5)

Previous report

We utilize ISR mining where possible which we believe, when compared to conventional open pit or underground mining, requires lower capital and operating expenditures with a shorter lead time to extraction and a reduced impact on the environment. We have two ISR Mines which utilize ISR mining to extract U 3 O 8 or yellowcake. We do not expect, however, to utilize ISR mining for all of our uranium projects in which case we would expect to rely on conventional open pit and/or underground mining techniques. We have one uranium mine located in the State of Texas, our Palangana Mine, which utilizes ISR mining and commenced extraction of U 3 O 8, or yellowcake, in November 2010. We have one uranium processing facility located in the State of Texas, our Hobson Processing Facility, which processes material from our ISR Mines into drums of U 3 O 8, our only sales product and source of revenue, for shipping to a third-party storage and sales facility. As at January 31, 2024, we had no uranium supply or "off-take" agreements in place. Future sales of U 3 O 8 are therefore expected to generally occur through the uranium spot market, with any fluctuations in the market price continuing to have a direct impact on our revenues and cash flows.

Previous report

On August 19, 2022, we completed the acquisition of UEX Corporation ("UEX") through a plan of arrangement (the UEX Acquisition). UEX is a Canadian uranium and cobalt exploration and development company involved with a portfolio of uranium projects. UEX’s directly-owned portfolio of projects is located in the eastern, western and northern perimeters of the Athabasca Basin in Saskatchewan, Canada, one of the world’s richest uranium regions. In addition to advancing its uranium projects through its ownership interest in a joint venture entity, UEX is currently advancing several other uranium deposits in the Athabasca Basin, which include the Paul Bay, Ken Pen and Ōrora deposits at the Christie Lake Project, the Kianna, Anne, Colette and 58B deposits at its currently 49.1%-owned Shea Creek Project, the Horseshoe and Raven deposits located on its 100%-owned Horseshoe-Raven Project and the West Bear Uranium Deposit located at its 100%-owned West Bear Project.

Previous report

On October 14, 2022, we acquired, through our subsidiary, UEC Resources (SK) Corp., Roughrider Mineral Holdings Inc., a Saskatchewan corporation and wholly-owned subsidiary of Rio Tinto Fer Et Titane Inc., which, in turn, owns all of the issued and outstanding shares of Roughrider Mineral Assets Inc., also a Saskatchewan corporation, that holds certain mineral leases totaling approximately 598 hectares in northern Saskatchewan that is commonly referred to as the “Roughrider Project” located in the Athabasca Basin in Saskatchewan, Canada.

Previous report

During the three and six months ended January 31, 2024, we continued with our strategic plan for reduced operations at our Palangana Mine, and we continued reduced operations at the Christensen Ranch Mine, to capture residual pounds of U 3 O 8 only. As a result, no uranium concentrate was extracted at our ISR Mines and processed at the Hobson and the Irigaray Processing Facilities during the period. Since the acquisition of UEX and Roughrider Mineral Holdings Inc., we have increased our exploration activities in Canada.

Previous report

Subsequent to January 31, 2024, we participated in an equity financing and acquired an additional 1,047,614 common shares of URC at a price of $3.40 per share for total consideration of $3.6 million.
Reworded paragraphs (43)

Previous wording

The following management’s discussion and analysis of the Company’s financial condition and results of operations (the“MD&A”) contain forward-looking statements that involve risks, uncertainties and assumptions including, among others, statements regarding our capital needs, business plans and expectations. * In evaluating these statements you should consider various factors, including the risks, uncertainties and assumptions set forth in reports and other documents we have filed with or furnished to the SEC and, including, without limitation, this Form 10-Q Quarterly Report for the six months ended January 31, 2024, and our Form 10-K Annual Report for the fiscal year ended July 31, 2023, including the consolidated financial statements and related notes contained therein.* * These factors, or any one of them, may cause our actual results or actions in the future to differ materially from any forward-looking statement made in this Quarterly Report.* * Refer to*“Cautionary Note Regarding*** *Forward-looking Statements” as disclosed in our Form 10-K Annual Report for the fiscal year ended July 31, 2023, and Item 1A, Risk Factors, under Part II - Other Information, of this Quarterly Report.

Current wording

The following management’s discussion and analysis of the Company’s financial condition and results of operations (the“MD&A”) contain forward-looking statements that involve risks, uncertainties and assumptions including, among others, statements regarding our capital needs, business plans and expectations. * In evaluating these statements you should consider various factors, including the risks, uncertainties and assumptions set forth in reports and other documents we have filed with or furnished to the SEC and, including, without limitation, this Form 10-Q Quarterly Report for the nine months ended April 30, 2024, and our Form 10-K Annual Report for Fiscal 2023, including the consolidated financial statements and related notes contained therein.* * These factors, or any one of them, may cause our actual results or actions in the future to differ materially from any forward-looking statement made in this Quarterly Report.* * Refer to*“Cautionary Note Regarding*** *Forward-looking Statements” as disclosed in our Form 10-K Annual Report for Fiscal 2023, and Item 1A, Risk Factors, under Part II - Other Information, of this Quarterly Report.

Previous wording

This MD&A is focused on material changes in our financial condition from July 31, 2023, our most recently completed year end, to January 31, 2024, and our results of operations for the three and six months ended January 31, 2024, and should be read in conjunction with Item 7, Management’s Discussion and Analysis of Financial Condition and Results of Operations, as contained in our Form 10-K Annual Report for Fiscal 2023.

Current wording

This MD&A is focused on material changes in our financial condition from July 31, 2023, our most recently completed year end, to April 30, 2024, and our results of operations for the three and nine months ended April 30, 2024, and should be read in conjunction with Item 7, Management’s Discussion and Analysis of Financial Condition and Results of Operations, as contained in our Form 10-K Annual Report for Fiscal 2023.

Previous wording

We are primarily engaged in uranium mining and related activities, including exploration, pre-extraction, extraction and processing, on uranium projects located in the United States, Canada and the Republic of Paraguay, as more fully described in our Form 10-K Annual Report for Fiscal 2023.

Current wording

We are engaged in uranium mining and related activities, including exploration, pre-extraction, extraction and processing, on uranium projects located in the United States, Canada and the Republic of Paraguay, as more fully described in our Form 10-K Annual Report for Fiscal 2023.

Previous wording

In Texas, our fully-licensed and 100% owned Hobson Processing Facility forms the basis for our regional operating strategy in the State of Texas, specifically the South Texas Uranium Belt where we utilize ISR mining. We utilize a “hub-and-spoke” strategy whereby the Hobson Processing Facility, which has a physical capacity to process uranium-loaded resins up to a total of two million pounds of U 3 O 8 annually and is licensed to process up to one million pounds of U 3 O 8 annually, acts as the central processing site (the “hub”) for our Palangana Mine, and future satellite uranium mining activities, such as our Burke Hollow and Goliad Projects, located within the South Texas Uranium Belt (the “spokes”).

Current wording

In Texas, our fully-licensed and 100% owned Hobson Processing Facility forms the basis for our regional operating strategy in the State of Texas, specifically the South Texas Uranium Belt where we utilize ISR mining. We utilize a “hub-and-spoke” strategy whereby the Hobson Processing Facility, which has a physical capacity to process uranium-loaded resins up to a total of two million pounds of U 3 O 8 annually and is licensed to process up to four million pounds of U 3 O 8 annually, acts as the central processing site (the “hub”) for our Palangana Mine, and future satellite uranium mining activities, such as our Burke Hollow and Goliad Projects, located within the South Texas Uranium Belt (the “spokes”).

Previous wording

On August 4, 2023, we acquired a portfolio of exploration-stage projects in the Athabasca Basin for CAD$1.5 million from Rio Tinto Exploration Canada Inc., a subsidiary of Rio Tinto Inc. With this transaction, we added an additional 44,444 acres of prospective ground in the Athabasca Basin to our existing portfolio.

Current wording

On August 4, 2023, we acquired a portfolio of exploration-stage projects in the Athabasca Basin for CA$1.5 million from Rio Tinto Exploration Canada Inc., a subsidiary of Rio Tinto Inc. With this acquisition, we added an additional 44,444 acres of prospective ground in the Athabasca Basin to our existing portfolio.

Previous wording

Our operating and strategic framework is based on expanding our uranium extraction activities, which includes advancing certain uranium projects with established mineralized materials towards uranium extraction and establishing additional mineralized materials on our existing uranium projects or through acquisition of additional uranium projects.

Current wording

Our operating and strategic framework is to become a leading low-cost North American focused uranium supplier based on expanding our uranium extraction activities, which includes advancing certain uranium projects with established mineralized materials towards uranium extraction and establishing additional mineralized materials on our existing uranium projects or through acquisition of additional uranium projects.

Previous wording

Since commencing uranium extraction at our Palangana Mine in November 2010, we have been focused primarily on our South Texas uranium mining activities. Since the completion of the U1A acquisition in December 2021 (the "U1A Acquisition"), we expanded our footprints in Wyoming with our Wyoming hub-and-spoke operations. The acquisition of UEX in August 2022 and the acquisition of Roughrider Mineral Holdings Inc. in October 2022 further expanded our footprint in Canada and, in particular, the Athabasca Basin in Saskatchewan. In the meantime, we continue to establish additional uranium mines through exploration and pre-extraction activities and direct acquisitions in both the U.S. and Paraguay, all of which require us to manage numerous challenges, risks and uncertainties inherent in our business and operations as more fully described in Item 1A. Risk Factors herein.

Current wording

With the completion of the acquisition of Uranium One Americas, Inc. in December 2021 (the “U1A Acquisition”), we expanded our footprints in Wyoming with our Wyoming hub-and-spoke operations. The acquisition of UEX in August 2022 and the acquisition of Roughrider Mineral Holdings Inc. in October 2022 further expanded our footprint in Canada and, in particular, the Athabasca Basin in Saskatchewan. In the meantime, we continue to establish additional uranium mines through exploration and pre-extraction activities and direct acquisitions in both the U.S. and Paraguay, all of which require us to manage numerous challenges, risks and uncertainties inherent in our business and operations as more fully described in Item 1A. Risk Factors herein.

Previous wording

Our operations are capital intensive, and we will require significant additional financing to continue with our exploration and pre-extraction activities and acquire additional uranium projects. Historically, we have been reliant primarily on equity financings from the sale of our common stock and, for Fiscal 2014 and Fiscal 2013, on debt financing, in order to fund our operations. We have also relied on cash flows generated from our mining activities during Fiscal 2015, Fiscal 2013 and Fiscal 2012 and have relied on cash flows generated from the sales of our purchased uranium inventories under our physical uranium program to fund our operations since Fiscal 2022. However, we have yet to achieve consistent profitability or develop consistent positive cash flow from operations. Our reliance on equity and debt financings is expected to continue for the foreseeable future, and their availability whenever such additional financing is required will be dependent on many factors beyond our control including, but not limited to, the market price of uranium, the continuing public support of nuclear power as a viable source of electricity generation, the volatility in the global financial markets affecting our stock price and the status of the worldwide economy, any one of which may cause significant challenges in our ability to access additional financing, including access to the equity and credit markets. We may also be required to seek other forms of financing, such as asset divestitures or additional joint venture arrangements, to continue advancing our uranium projects which would depend entirely on finding a suitable third party willing to enter into such an arrangement, typically involving an assignment of a percentage interest in the mineral project. However, there is no assurance that we will be successful in securing any form of additional financing when required and on terms favorable to us. Our inability to obtain additional financing would have a negative impact on our operations, including delays, curtailment or abandonment of any one or all of our uranium projects.

Current wording

Our operations are capital intensive, and we will require significant additional financing to continue with our exploration and pre-extraction activities and acquire additional uranium projects. Historically, we have been reliant primarily on equity financings from the sale of our common stock in order to fund our operations. In the last two fiscal years, we have also relied on cash flows generated from the sales of our purchased uranium inventories under our physical uranium program to fund our operations, which resulted in $57.0 million in gross profits. However, we have yet to achieve consistent profitability or develop consistent positive cash flow from operations. Our reliance on equity and debt financings is expected to continue for the foreseeable future, and their availability whenever such additional financing is required will be dependent on many factors beyond our control including, but not limited to, the market price of uranium, the continuing public support of nuclear power as a viable source of electricity generation, the volatility in the global financial markets affecting our stock price and the status of the worldwide economy, any one of which may cause significant challenges in our ability to access additional financing, including access to the equity and credit markets. We may also be required to seek other forms of financing, such as asset divestitures or additional joint venture arrangements, to continue advancing our uranium projects which would depend entirely on finding a suitable third party willing to enter into such an arrangement, typically involving an assignment of a percentage interest in the mineral project. However, there is no assurance that we will be successful in securing any form of additional financing when required and on terms favorable to us. Our inability to obtain additional financing would have a negative impact on our operations, including delays, curtailment or abandonment of any one or all of our uranium projects.

Previous wording

The Palangana Mine was our sole source to generate sales revenues from the sales of U 3 O 8 during Fiscal 2015, Fiscal 2013 and Fiscal 2012. The economic viability of our mining activities, including the expected duration and profitability of our ISR Mines, of any future satellite ISR mines, such as our Burke Hollow, Goliad, Ludeman, Antelope and Charlie Projects, and of our recently acquired traditional uranium mines in the Athabasca Basin in Saskatchewan, Canada, has many risks and uncertainties. These include, but are not limited to: (i) a significant, prolonged decrease in the market price of uranium; (ii) difficulty in marketing and/or selling uranium concentrates; (iii) significantly higher than expected capital costs to construct a mine and/or processing plant; (iv) significantly higher than expected extraction costs; (v) significantly lower than expected uranium extraction; (vi) significant delays, reductions or stoppages of uranium extraction activities; and (vii) the introduction of significantly more stringent regulatory laws and regulations. Our mining activities may change as a result of any one or more of these risks and uncertainties and there is no assurance that any ore body that we extract mineralized materials from will result in achieving and maintaining profitability and developing positive cash flow.

Current wording

The economic viability of our mining activities, including the expected duration and profitability of our ISR Mines, of any future satellite ISR mines, such as our Burke Hollow, Goliad, Ludeman, Antelope and Charlie Projects, and of our recently acquired traditional uranium mines in the Athabasca Basin in Saskatchewan, Canada, has many risks and uncertainties. These include, but are not limited to: (i) a significant, prolonged decrease in the market price of uranium; (ii) difficulty in marketing and/or selling uranium concentrates; (iii) significantly higher than expected capital costs to construct a mine and/or processing plant; (iv) significantly higher than expected extraction costs; (v) significantly lower than expected uranium extraction; (vi) significant delays, reductions or stoppages of uranium extraction activities; and (vii) the introduction of significantly more stringent regulatory laws and regulations. Our mining activities may change as a result of any one or more of these risks and uncertainties and there is no assurance that any ore body that we extract mineralized materials from will result in achieving and maintaining profitability and developing positive cash flow.

Previous wording

The uranium market is being driven by a macro demand for more electricity generation and an unprecedented global push to decarbonize electrical grids, among other factors. There is a growing realization that the highly reliable, safe, baseload power nuclear energy provides must be a part of any clean energy platform. Governments around the globe are also pursuing strategies to increase energy independence for national security interests that dovetail well with nuclear power as a key component in their energy mix.

Current wording

The uranium market is currently being driven by a macro demand for more electricity generation and an unprecedented global push to decarbonize electrical grids, among other factors. There is noteworthy demand showing substantial growth is Artificial Intelligence and the electricity needed to power Data Centers. In the U.S. demand from this source, measured by power consumption, is expected to reach 35 GWe by 2030, up from 17 GWe in 2022 (Citi Data Center Demand and Nuclear Power: February 2024). There is a growing realization that the highly reliable, safe, baseload power nuclear energy provides should be a part of any clean energy platform. Governments around the globe are also pursuing strategies to increase energy independence for national security interests that dovetail well with nuclear power as a key component in their energy mix.

Previous wording

Over the past few years, global uranium market fundamentals have improved as the market began a transition from being an inventory driven to a production driven market. The spot market bottomed out in November 2016 at about US$17.75 per pound U 3 O 8 but has since shown appreciation to US$95.00 per pound on February 29, 2024 (UxC LLC Ux U 3 O 8 Daily Price).

Current wording

Over the past few years global uranium market fundamentals have improved as the market began a transition from being an inventory driven to a production driven market. The spot market bottomed out in November 2016 at about $17.75 per pound U 3 O 8, but has since shown appreciation, reaching $107.00 per pound U 3 O 8 on February 2, 2024. During the three and nine months ended April 30, 2024, uranium prices averaged $92.80 and $81.64 per pound U 3 O 8, respectively. As at April 30, 2024, the uranium price was $90.00 per pound, representing an approximate 67% increase from April 30, 2023 when the price was $53.85 per pound U 3 O 8. The period from February 2024 through April 2024 was marked by continued volatility as the price fluctuated between $85.00 and $107.00 per pound U 3 O 8 (All price information is sourced from UxC LLC Historical Ux Daily Prices).

Previous wording

Underinvestment in mining operations over the past decade has been a major factor contributing to a structural deficit that has evolved between global uranium production and reactor requirements. Production from existing uranium mines has also been a contributing factor with some large producers reducing previously planned production. Over the next two years, the mid-case gap is projected to be more than 50 million pounds U 3 O 8 and by 2033 accumulates to a total above 400 million pounds (UxC 2023 Q4 Uranium Market Outlook). For context, the U.S. reactor fleet consumes almost 45 million pounds per year (U.S. Energy Information Administration, June 13, 2023 - Uranium Marketing Annual Report). The current gap is being filled with secondary market sources, including finite inventory that has been declining and is projected to decline further in coming years. Secondary supply is also likely to be further reduced with western enrichers reversing operations from underfeeding to overfeeding that requires more uranium to increase the production of enrichment services. As secondary supplies continue to diminish, and as existing mines deplete resources, new production will be needed to meet existing and future utility demand. The timeline for new mining projects can be 10 years or longer and will require prices high enough to stimulate new mining investments.

Current wording

Underinvestment in uranium mining operations over the past decade has been a major factor contributing to a structural deficit between global production and uranium requirements. Reduced production from existing uranium mines has also been a contributing factor with some large producers cutting back and or unable to reach previously planned production levels. In 2024 and 2025 the mid-case gap between production and requirements is projected to be more than 66 million pounds U 3 O 8, and by 2034 accumulates to a total above 400 million pounds U 3 O 8 (UxC 2024 Q1 Uranium Market Outlook). For context, the U.S. reactor fleet consumes about 45 million pounds U 3 O 8 per year (U.S. Energy Information Administration, June 13, 2023 - Uranium Marketing Annual Report). The current gap is being filled with secondary market sources, including finite inventory that has been declining and is projected to decline further in coming years. Secondary supply is also likely to be further reduced with western enrichers reversing operations from underfeeding to overfeeding that requires more uranium to increase the production of enrichment services. As secondary supplies continue to diminish, and as existing mines deplete resources, new production will be needed to meet existing and future utility demand. The timeline for new mining projects can be 10 years or longer and will require prices high enough to stimulate new mining investments.

Previous wording

Since 2022, uranium supply has become more complicated due to Russia's invasion of Ukraine with their state-controlled company, Rosatom, being a significant supplier of nuclear fuel around the globe. Economic sanctions, transportation restrictions, pending legislation and buyer avoidance of Russian fuel is causing a fundamental change to the nuclear fuel markets. Additionally, the 2023 coup in Niger has underscored jurisdictional risk with that country accounting for about 5% of global uranium production and about 25% of European Union supply in 2022 (World Nuclear Association “WNA” - Uranium in Niger August 2023 / Reuters - France and EU August 2023). U.S. and European utilities are shifting more focus to security of supply with production from areas of low geopolitical risk. In addition, legislation is in process to help shore up the U.S. nuclear fuel supply chain with appropriations and banning Russian uranium. While not completely finalized, it is anticipated that the related legislation and funding will eventually pass in the U.S. Congress and be signed into law

Current wording

Since 2022, uranium supply has become more complicated due to Russia's invasion of Ukraine with its State Atomic Energy Corporation, Rosatom, being a significant supplier of nuclear fuel around the globe. Economic sanctions, transportation restrictions and recent U.S. legislation banning the importation of Russian nuclear fuel is causing a fundamental change to the nuclear fuel markets. Additionally, the 2023 coup in Niger, and the new government’s demand for the U.S. and France to vacate the country, has underscored jurisdictional risk with that country accounting for about 5% of global uranium production and about 25% of European Union supply in 2022 (World Nuclear Association - Uranium in Niger May 7, 2024 / Reuters – “Russian troops enter base housing US military in Niger, US official says” - May 3, 2024 and “Niger has not banned uranium exports to France and EU” - August 18, 2023). U.S. and European utilities are shifting more focus to security of supply with production from areas of low geopolitical risk.

Previous wording

On the demand side of the equation, the global nuclear energy industry continues robust growth, with 66 new reactors connected to the grid from 2014 through 2023 with another 62 reactors under construction (International Atomic Energy Association Power Reactor Information System “PRIS” and WNA February 2023). During 2023, five new reactors were connected to the grid, two have restarted after suspended operations (Takahama 1&2) and five reactors were permanently shut down (PRIS). Total nuclear generating capacity at the beginning of 2024 stands at 392 GWe (WNA). At COP28, 22 countries, including the U.S., Canada, France, Japan and the United Kingdom, signed a declaration to triple nuclear energy by 2050, further supporting additional growth for the nuclear industry and uranium demand.

Current wording

On the demand side of the equation, the global nuclear energy industry continues robust growth, with 70 new reactors connected to the grid from 2014 through April of 2024, and with another 59 reactors under construction. So far in 2024, four new reactors have been connected to the grid, and one reactor has been permanently shut down (International Atomic Energy Association Power Reactor Information System - May 28, 2024). Total nuclear generating capacity for the world’s 440 operable reactors as of May 7, 2024 stands at 396 GWe (World Nuclear Association). At COP28 United Nations Climate Change Conference, 22 countries, including the U.S., Canada, France, Japan and the United Kingdom, signed a declaration to triple nuclear energy by 2050, further supporting additional growth for the nuclear industry and uranium demand.

Previous wording

Additional upside market pressure is also occurring as utilities continue their return to a longer-term contracting cycle to replace expiring contracts. Cumulative uncommitted demand through 2033 totals ~817 million pounds (UxC Uranium Market Overview Q4 2023). Increasing demand is also evident from financial entities and various producers continuing to purchase significant quantities of drummed uranium inventory, further removing near term supply and adding to the strong fundamentals supporting the uranium market.

Current wording

Additional upside market pressure is also occurring as utilities continue their return to a longer-term contracting cycle to replace expiring contracts. Cumulative uncommitted demand through 2034 totals approximately 926 million pounds U 3 O 8 (UxC Uranium Market Overview Q1 2024). Increasing demand is also evident from financial entities and various producers continuing to purchase significant quantities of drummed uranium inventory, further removing near term supply and adding to the strong fundamentals supporting the uranium market.

Previous wording

For the three and six months ended January 31, 2024, we recorded sales and service revenue of $116 and $224 and realized gross profit of $19 and $37, respectively, from toll processing services. We did not sell purchased uranium inventory to date in Fiscal 2024. For the three and six months ended January 31, 2023, we recorded sales and service revenue of $47,931 and $105,223 and realized gross profit of $14,570 and $28,428, respectively, from sales of purchased uranium inventory and toll processing services.

Current wording

For the three and nine months ended April 30, 2024, we recorded sales and service revenue of $Nil and $224, and realized gross profit of $Nil and $37, respectively, from toll processing services. We did not sell purchased uranium inventory to date in Fiscal 2024. For the three and nine months ended April 30, 2023, we recorded sales and service revenue of $20,217 and $125,440 and realized gross profit of $6,219 and $34,647, respectively, from sales of purchased uranium inventory and toll processing services.

Previous wording

For the three and six months ended January 31, 2024, we recorded a net income of $2,250 ($0.01 per share) and $5,571 ($0.01 per share), and losses from operations of $12,119 and $23,504, respectively. During the three and six months ended January 31, 2023, we recorded net income of $10,892 ($0.03 per share) and $7,136 ($0.02 per share) and income from operations of $5,088 and $8,681, respectively.

Current wording

For the three and nine months ended April 30, 2024, we recorded a net loss of $19,677 ($0.05 per share) and $14,106 ($0.04 per share), and losses from operations of $13,841 and $37,345, respectively. During the three and nine months ended April 30, 2023, we recorded net loss of $10,960 ($0.03 per share) and $3,824 ($0.01 per share) and loss from operations of $3,484 and income from operations of $5,197, respectively.

Previous wording

During the three and six months ended January 31, 2024, as part of our Physical Uranium Program, we purchased 995,000 pounds of uranium concentrates with a total cost of $57,003. As of January 31, 2023, the carrying value of our uranium concentrate inventories was $63,019 (July 31, 2023: $5,801).

Current wording

During the three and nine months ended April 30, 2024, as part of our Physical Uranium Program, we purchased 995,000 pounds of uranium concentrates with a total cost of $57,003. As of April 30, 2024, the carrying value of our uranium concentrate inventories was $63,019 (July 31, 2023: $5,801).

Previous wording

For the three and six months ended January 31, 2024, we recorded revenue from toll processing services of $116 and $224, respectively, which was generated from processing uranium resins.

Current wording

For the three and nine months ended April 30, 2024, we recorded revenue from toll processing services of $Nil and $224, respectively, which was generated from processing uranium resins.

Previous wording

During the three and six months ended January 31, 2024, exploration expenditures, such as drilling and preliminary economic assessments, were primarily spent on the following projects:

Current wording

During the three and nine months ended April 30, 2024, exploration expenditures, such as drilling and preliminary economic assessments, were primarily spent on the following projects:

Previous wording

During the three and six months ended January 31, 2024, production readiness expenditures were primarily spent on the following projects:

Current wording

During the three and nine months ended April 30, 2024, extraction readiness expenditures were primarily spent on the following projects:

Previous wording

During the three and six months ended January 31, 2024, property maintenance expenditures were primarily spent on the following projects:

Current wording

During the three and nine months ended April 30, 2024, property maintenance expenditures were primarily spent on the following projects:

Previous wording

During the three and six months ended January 31, 2024, general and administrative expenses ("G&A") totaled $4,895 and $10,095, respectively, compared to $4,829 and $10,551 for the three and six months ended January 31, 2023. G&A expenses were comprised of the following:

Current wording

During the three and nine months ended April 30, 2024, general and administrative expenses (“G&A”) totaled $4,219 and $14,314, respectively, compared to $3,745 and $14,296 for the three and nine months ended April 30, 2023. G&A expenses were comprised of the following:

Previous wording

During the three and six months ended January 31, 2024 and 2023, we recorded a gain on dilution of ownership interest in URC as a result of URC issuing more shares from its equity financing and exercises of warrants and/or stock options. On October 17, 2023, we participated in URC’s equity financing, which increased our ownership in URC from 15,000,000 shares to 16,930,750 shares. As at January 31, 2024, we had 15.0% of equity interest in URC compared to 14.9% at July 31, 2023.

Current wording

During the three and nine months ended April 30, 2024 and 2023, we recorded a gain on dilution of ownership interest in URC as a result of URC issuing more shares from its equity financing and exercises of warrants and/or stock options. On October 17, 2023 and February 9, 2024, we participated in URC’s equity financings, which increased our ownership in URC from 15,000,000 shares to 16,930,750 shares and to 17,978,364 shares, respectively. As at April 30, 2024, we had a 14.9% of equity interest in URC compared to 14.9% as at July 31, 2023.

Previous wording

During the three and six months ended January 31, 2024, we recorded a share of URC’s income of $559 and $1,877, respectively. During the three and six months ended January 31, 2024, we also recorded a share of JCU's loss of $377 and $656, respectively.

Current wording

During the three and nine months ended April 30, 2024, we recorded a share of URC’s income of $520 and $2,397, respectively. During the three and nine months ended April 30, 2024, we also recorded a share of JCU’s losses of $416 and $1,072, respectively.

Previous wording

As at January 31, 2024, our investments in certain equity securities were revalued using the market values at period end, which resulted in an unrealized gain of $20,076 and $37,389 on revaluation of equity securities, respectively, for the three and six months ended January 31, 2024.

Current wording

As at April 30, 2024, our investments in certain equity securities were revalued using the market values at period end, which resulted in an unrealized loss of $13,804 and gain of $23,585 on revaluation of equity securities, respectively, for the three and nine months ended April 30, 2024.

Previous wording

In connection with the UEX Acquisition, we issued Replacement Warrants, which are accounted for as derivative liabilities as the exercise prices of the UEX warrants are denominated in Canadian dollars, which differs from the functional currency of the Company. As at January 31, 2024, the Replacement Warrants were revalued, which resulted in a loss of $(5,062) and $(11,963), respectively, for the three and six months ended January 31, 2024. Changes in fair value of derivative liabilities were primarily due to changes in our share price. During the three and six months ended January 31, 2023, we recorded a gain on revaluation of derivative liabilities of $1,726 and a loss of $(899), respectively.

Current wording

In connection with the UEX Acquisition, we issued Replacement Warrants, which are accounted for as derivative liabilities as the exercise prices of the UEX warrants are denominated in Canadian dollars which differs from the functional currency of the Company. As at April 30, 2024, the Replacement Warrants were revalued, which resulted in a gain of $2,071 and a loss of $9,892, respectively, for the three and nine months ended April 30, 2024. Changes in fair value of derivative liabilities were primarily due to changes in our share price. During the three and nine months ended April 30, 2023, we recorded a gain on revaluation of derivative liabilities of $5,550 and $4,651, respectively.

Previous wording

During the six months ended January 31, 2024, we received net proceeds of $131,162 from our ATM Offerings and from exercises of stock options and share purchase warrants.

Current wording

During the nine months ended April 30, 2024, we received net proceeds of $160,239 from our ATM Offerings and from exercises of stock options and share purchase warrants.

Previous wording

Subsequent to January 31, 2024, we received additional cash proceeds of $13,390 under our ATM Offerings.

Current wording

Subsequent to April 30, 2024, we received additional cash proceeds of $12,824 under our ATM Offerings.

Previous wording

We have a history of operating losses resulting in an accumulated deficit balance since inception. Although we recorded net income in the six months ended January 31, 2024 and 2023, we recorded net losses in Fiscal 2023 and all prior years, and we had an accumulated deficit balance of $284,109 as at January 31, 2024. Furthermore, we may not achieve and maintain profitability or develop positive cash flow from our operations in the near term.

Current wording

We have a history of operating losses resulting in an accumulated deficit balance since inception. We recorded net losses in Fiscal 2023 and in all prior years, and we had an accumulated deficit balance of $303,786 as at April 30, 2024. Furthermore, we may not achieve and maintain profitability or develop positive cash flow from our operations in the near term.

Previous wording

We hold mineral rights in the States of Arizona, New Mexico, Texas and Wyoming, in Canada and in the Republic of Paraguay, with annual land-related payments totaling $4.1 million to maintain these rights in good standing.

Current wording

We hold mineral rights in the States of Arizona, New Mexico, Texas and Wyoming, in Canada and in the Republic of Paraguay, with annual land-related payments totaling $4.8 million to maintain these rights in good standing.

Previous wording

During the three and six months ended January 31, 2024, we issued 10,418,029 and 21,188,029 shares of the Company’s common stock under our ATM Offerings for net cash proceeds of $73,238 and $129,508, respectively.

Current wording

During the three and nine months ended April 30, 2024, we issued 3,396,370 and 24,584,399 shares of the Company’s common stock under our ATM Offerings for net cash proceeds of $25,543 and $155,050, respectively.

Previous wording

During the three and six months ended January 31, 2024, we received cash proceeds totaling $737 from the exercise of share purchase warrants and cash advances of $517 for warrants to be exercised in the future period.

Current wording

During the three and nine months ended April 30, 2024, we received cash proceeds totaling $3,771 and $4,508, respectively, from the exercise of share purchase warrants.

Previous wording

During the three and six months ended January 31, 2024, we received cash proceeds totaling $137 and $400, respectively, from the exercise of stock options.

Current wording

During the three and nine months ended April 30, 2024, we received cash proceeds totaling $281 and $681, respectively, from the exercise of stock options.

Previous wording

Subsequent to January 31, 2024, we issued a further 1,700,000 shares of the Company’s common stock under our ATM Offerings for net cash proceeds of $13,390.

Current wording

Subsequent to April 30, 2024, we issued a further 1,791,300 shares of the Company’s common stock under our ATM Offerings for net cash proceeds of $12,824.

Previous wording

During the six months ended January 31, 2024, net cash used in operating activities was $81,410, of which $57,194 was from the purchases of uranium concentrate inventory. During the six months ended January 31, 2023, net cash provided by operating activities was $53,571, of which $45,533 was for the change of uranium concentrate inventory. Other significant operating expenditures included mineral property expenditures and G&A expenses.

Current wording

During the nine months ended April 30, 2024, net cash used in operating activities was $93,871, of which $57,179 was from the purchases of uranium concentrate inventory. During the nine months ended April 30, 2023, net cash provided by operating activities was $43,778, of which $39,933 was for the change in uranium concentrate inventory. Other significant operating expenditures included mineral property expenditures and G&A expenses.

Previous wording

During the six months ended January 31, 2024, net cash provided by financing activities totaled $130,287, comprised primarily of net proceeds from equity financings. During the six months ended January 31, 2023, net cash provided by financing activities totaled $54,019, comprised primarily of net proceeds from equity financings.

Current wording

During the nine months ended April 30, 2024, net cash provided by financing activities totaled $159,292, comprised primarily of net proceeds from equity financings. During the nine months ended April 30, 2023, net cash provided by financing activities totaled $64,640, comprised primarily of net proceeds from equity financings.

Previous wording

During the six months ended January 31, 2024, net cash used in investing activities totaled $12,189, comprised of cash used in the acquisition of the Henday, Milliken and Carswell Projects of $1,334, a capital contribution to JCU of $1,645, cash used to purchase of an additional interest in URC of $5,676, cash used in investment in equity securities of $5,548, proceeds from sale of equity securities of $3,008 and cash used for investment in mineral properties and the purchase of equipment of $2,328. During the six months ended January 31, 2023, net cash used in investing activities totaled $107,385, comprised of net cash of $1,984 received from the UEX Acquisition, offset by cash used in the Roughrider Acquisition of $82,117, a capital contribution to JCU of $588, cash used in investment in equity securities of $26,328 and cash used for investment in mineral properties and the purchase of property, plant and equipment of $338.

Current wording

During the nine months ended April 30, 2024, net cash used in investing activities totaled $23,282, comprised of cash used in the acquisition of the Henday, Milliken and Carswell Projects of $1,334, a capital contribution to JCU of $2,388, cash used to purchase an additional interest in URC of $9,238, cash used in investment in equity securities of $12,115, proceeds from sale of equity securities of $3,008 and cash used for investment in mineral properties and the purchase of equipment of $2,557. During the nine months ended April 30, 2023, net cash used in investing activities totaled $123,333, comprised of cash used in the Roughrider Acquisition of $82,117, a capital contribution to JCU of $595, cash used in investment in equity securities of $42,219, cash used for investment in mineral properties and the purchase of equipment of $388 and net cash of $1,984 received from the UEX Acquisition.

Previous wording

As of January 31, 2024, we had in-the-money stock options outstanding representing 6,649,539 shares at a weighted-average exercise price of $2.01 per share, and in-the-money share purchase warrants outstanding representing 3,554,810 shares at a weighted-average exercise price of $3.38 per share. As of January 31, 2024, outstanding in-the-money stock options and warrants represented a total 10,204,349 shares issuable for gross proceeds of approximately $25.4 million should these stock options and warrants be exercised in full on a cash basis. The exercise of stock options and warrants is at the discretion of their respective holders and, accordingly, there is no assurance that any of the stock options or warrants will be exercised in the future.

Current wording

As of April 30, 2024, we had in-the-money stock options outstanding representing 6,249,671 shares at a weighted-average exercise price of $2.07 per share, and in-the-money share purchase warrants outstanding representing 2,404,116 shares at a weighted-average exercise price of $3.38 per share. As of April 30, 2024, outstanding in-the-money stock options and warrants represented a total 8,653,787 shares issuable for gross proceeds of approximately $21.1 million should these stock options and warrants be exercised in full on a cash basis. The exercise of stock options and warrants is at the discretion of their respective holders and, accordingly, there is no assurance that any of the stock options or warrants will be exercised in the future.

Previous wording

During the three and six months ended January 31, 2024, we incurred $12 and $43, respectively, in exploration expenditures on behalf of JCU. As at January 31, 2024, the amount receivable from JCU totaled $8 (July 31, 2023: $201).

Current wording

During the three and nine months ended April 30, 2024, we incurred $11 and $54, respectively, in exploration expenditures on behalf of JCU. As at April 30, 2024, the amount receivable from JCU totaled $3 (July 31, 2023: $201).