17. Commitments and Contingencies

  1. Commitments and Contingencies

KDP is occasionally subject to litigation or other legal proceedings. Reserves are recorded for specific legal proceedings when the Company determines that the likelihood of an unfavorable outcome is probable and the amount of loss can be reasonably estimated. The Company had litigation reserves of $12 million as of both December 31, 2023 and 2022. KDP has also identified certain other legal matters where we believe an unfavorable outcome is reasonably possible and/or for which no estimate of possible losses can be made. The Company does not believe that the outcome of these, or any other, pending legal matters, individually or collectively, will have a material adverse effect on the results of operations, financial condition or liquidity of KDP.

ANTITRUST LITIGATION

In February 2014, TreeHouse Foods, Inc. and certain affiliated entities filed suit against KDP’s wholly-owned subsidiary, Keurig (formerly known as Green Mountain Coffee Roasters, Inc.), in the U.S. District Court for the Southern District of New York (“SDNY”) (TreeHouse Foods, Inc. et al. v. Green Mountain Coffee Roasters, Inc. et al.). The TreeHouse complaint asserted claims under the federal antitrust laws and various state laws, contending that Keurig had monopolized alleged markets for single serve coffee brewers and single serve coffee pods. The TreeHouse complaint sought treble monetary damages, declaratory relief, injunctive relief and attorneys’ fees. In the months that followed, a number of additional actions, including claims from another coffee manufacturer (JBR, Inc.), as well as putative class actions on behalf of direct and indirect purchasers of Keurig’s products, were filed in various federal district courts, asserting claims and seeking relief substantially similar to the claims asserted and relief sought in the TreeHouse complaint. Additional similar actions were filed by individual direct purchasers (including McLane Company, Inc., BJ’s Wholesale Club, Inc., Winn-Dixie Stores Inc. and Bi-Lo Holding LLC) in 2019 and in 2021. All of these actions were transferred to the SDNY for coordinated pre-trial proceedings (In re: Keurig Green Mountain Single-Serve Coffee Antitrust Litigation) (the “Multidistrict Antitrust Litigation”).

In July 2020, Keurig reached an agreement with one of the plaintiff groups in the Multidistrict Antitrust Litigation, the putative indirect purchaser class, to settle the claims asserted for $31 million. The settlement class consisted of individuals and entities in the United States that purchased, from persons other than Keurig and not for purposes of resale, Keurig manufactured or licensed single serve beverage portion packs during the applicable class period (beginning in September 2010 for most states). The settlement was approved and paid, and the indirect purchasers’ claims have been dismissed.

Discovery in all remaining matters pending in the Multidistrict Antitrust Litigation is concluded, with the plaintiffs collectively claiming more than $5 billion of monetary damages. Keurig strongly disputes the merits of the claims and the calculation of damages. As a result, Keurig has fully briefed summary judgment motions that, if successful, would end the cases entirely. Keurig has also fully briefed other significant motions, including challenges to the validity of plaintiffs’ damages calculations. Keurig is also pursuing its opposition to direct purchaser plaintiffs’ motion for class certification. Certain of Keurig’s motions and opposition have been pending in the SDNY since 2021, with others pending since 2023.

Keurig intends to continue vigorously defending the remaining lawsuits. At this time, the Company is unable to predict the outcome of these lawsuits, the potential loss or range of loss, if any, associated with the resolution of these lawsuits or any potential effect they may have on the Company or its operations. Accordingly, the Company has not accrued for a loss contingency. Additionally, as the timelines in these cases may be beyond the Company’s control, KDP can provide no assurance as to whether or when there will be material developments in these matters.

ENVIRONMENTAL, HEALTH, AND SAFETY MATTERS

The Company operates many manufacturing, bottling, and distribution facilities. In these and other aspects of the Company's business, it is subject to a variety of federal, state, and local environmental, health, and safety laws and regulations. The Company maintains environmental, health, and safety policies and a quality environmental, health, and safety program designed to ensure compliance with applicable laws and regulations. However, the nature of the Company's business exposes it to the risk of claims with respect to environmental, health, and safety matters, and there can be no assurance that material costs or liabilities will not be incurred in connection with such claims.

The federal Comprehensive Environmental Response, Compensation and Liability Act of 1980, also known as the Superfund law, as well as similar state laws, generally impose joint and several liability for cleanup and enforcement costs on current and former owners and operators of a site without regard to fault or the legality of the original conduct. The Company was notified by the Environmental Protection Agency that it is a potentially responsible party for study and cleanup costs at a Superfund site in New Jersey and in Michigan. Investigation and remediation costs are yet to be determined, therefore no reasonable estimate exists on which to base a loss accrual. The Company participates in a study for this site with other potentially responsible parties.

PRODUCT WARRANTIES

KDP offers a one year warranty on all Keurig brewing systems it sells. KDP provides for the estimated cost of product warranties, primarily using historical information and current repair or replacement costs, at the time product revenue is recognized. Product warranties are included in accrued expenses in the accompanying Consolidated Balance Sheets.

(in millions)Accrued Product Warranties
Balance as of December 31, 2021$13
Accruals for warranties issued23
Settlements(23)
Balance as of December 31, 202213
Accruals for warranties issued17
Settlements(19)
Balance as of December 31, 2023$11