Skip to main content

Sigma Lithium Corp

For the period ended Dec 31, 2025. Filed Mar 30, 2026.

View on SEC.gov

About this filing

The yearly report of certain Canadian companies, filed under a joint US and Canadian system. It is the main yearly account these companies give US investors, largely as filed in Canada.

FY2025 · Filed Mar 30, 2026

Use the contents to explore the available documents and sections.

SGML$5.82+8.8%Stored close · as of Nov 6, 2026
See the whole filing, with its images and exhibits
Contents

EX-99.2 · Phase 2 Development Progress

Phase 2 Development Progress

During the three months ended December 31, 2025, Sigma Lithium’s focus remained on mine development, aiming to allow the existing pit to feed both Phase 1 and Phase 2 Greentech Processing Plants for a period of 6 months starting from the beginning of the ramp-up of Phase 2 operations.

The Phase 2 expansion remains a transformative opportunity for the Company, with expected additional production capacity of 250,000 tonnes per annum of 5% lithium oxide concentrate. Together with Phase 1, this would bring the total annual production capacity at Grota do Cirilo to 520,000 tonnes of 5% lithium oxide concentrate.

The Company continues to leverage the synergies and learnings from Phase 1 to enhance the efficiency and sustainability of Phase 2 implementation. The aim is for long lead items to be ordered in the second quarter of 2026 and construction to commence in the second half of 2026.