BTDR$6.02+13.3%Stored close · as of Nov 6, 2026
See the whole filing, with its images and exhibits

EX-99.1 · Colocation AI Data Center:

Colocation AI Data Center:

●Bitdeer recently acquired 200 acres near existing 563 MW Rockdale facility to support AI/HPC infrastructure development. Outright ownership provides the long-term site control required to develop and finance AI/HPC data center infrastructure. Bitdeer believes its Rockdale site, with its existing large-load interconnection and established transmission infrastructure, is well positioned to receive additional power allocations over the coming years.
●Bitdeer announced a 16-Year AI/HPC Data Center Lease for its Tydal, Norway Campus, representing approximately $4.7 billion of total contract value over the initial base term, with the potential to reach a total contract value of approximately $8.0 billion if the tenant exercises its one-time 8-year lease extension.
●Tydal, Norway AI Data Center expected to be among Norway’s largest and most efficient AI data centers upon completion. With a PUE of approximately 1.1 and running on 100% renewable energy, it sets a compelling standard for data center performance, at scale.
ContentsView on SEC.gov

The text of this filing, as the company filed it with the SEC, without its images or exhibits. This is not investment advice.