Skip to main content

Bit Digital, Inc

For the period ended Jun 30, 2025. Filed Aug 14, 2025.

View on SEC.gov

About this filing

A company's report for each of its first three quarters. The financial statements are not audited. It shows how the business has moved since the last annual report, and what management says changed.

Jun 30, 2025 · Filed Aug 14, 2025

BTBT$0.73+3.9%Stored close · as of Nov 6, 2026

What changed in Management’s Discussion and Analysis?

Read the current filing

Previous report: 10-Q

Period ended 2025-03-31; filed 2025-05-15.

0001213900-25-044155

Item 2. Management’s Discussion and Analysis of Financial Condition and Results of Operations

Current report: 10-Q

Period ended 2025-06-30; filed 2025-08-14.

0001213900-25-076608

Item 2. Management’s Discussion and Analysis of Financial Condition and Results of Operations

The baseline is this issuer’s latest earlier reporting period of the same form that was filed before the current report. A previous 10-Q is a different quarter, not a year-over-year comparison. Amendments are excluded.

Compared 228 previous paragraphs and 293 current paragraphs.

106 unchanged; 98 reworded; 58 added; 24 removed; 0 previous and 31 current paragraphs rearranged.

Tables are not compared: 13 previous and 21 current tables excluded. Dates, whitespace, punctuation and numbering changes are ignored; changes to financial figures remain significant.

A changed paragraph is not evidence that risk increased or decreased. An unchanged paragraph does not establish that risk stayed the same.

Added paragraphs (58)

Current report

We believe we are a leading provider of artificial intelligence (“AI”) infrastructure solutions. We own high-performance computing (“HPC”) data centers and provide cloud-based HPC graphics processing units (“GPU”) services, which we term cloud services, for customers such as AI application and machine learning (“ML”) developers (the “HPC Business”). Our Tier-3 data centers provide hosting and colocation services. Our cloud services support generative AI workstreams, especially training and inference.

Current report

On July 30, 2025, we entered into a Contribution Agreement with WhiteFiber, pursuant to which we agreed to contribute our HPC business through the transfer of 100% of the capital shares of our cloud services subsidiary, WhiteFiber AI, Inc. and its wholly-owned subsidiaries WhiteFiber HPC, Inc., WhiteFiber Canada, Inc., WhiteFiber Japan G.K. and WhiteFiber Iceland, ehf, to WhiteFiber, upon the effectiveness of WhiteFiber’s registration statement on Form S-1 in connection with WhiteFiber’s initial public offering. For more information, see Note 21.Subsequent Events in our Notes to Unaudited Condensed Consolidated Financial Statements included elsewhere herein.

Current report

On June 18, 2025, the Company entered into a definitive credit agreement (the “Facility”) with the Royal Bank of Canada (“RBC”). The Facility provides for an aggregate of up to approximately CAD $60 million (approximately USD $43.8 million) of financing. The proceeds are to be used primarily to refinance the buildout of Tier-3 AI data center at 7300 Trans Canada Highway, Pointe-Claire, Quebec (“MTL-2”) as well as USD $5.8 million of revolving term financing (the “Revolver”). The Facility is non-recourse to the Company. The Company entered into a three-year USD $18.5 million non-revolving lease facility to finance equipment costs and building improvements to build out the site. The lease facility provides for straight-line amortization of six years and capital moratorium of six months after disbursement is complete. RBC may cancel any unutilized portion of the facility after March 31, 2026. The interest rate is fixed based on the rental rate determined by RBC for the three-year term of the lease.

Current report

As part of the Facility, the Company entered into a three-year USD $19.6 million non-revolving real estate term loan facility. The purpose of this facility is to refinance the Company’s purchase of MTL-2. The interest rate of the real estate term loan facility will be determined at the time of borrowing, or a floating interest rate ranging from RBP plus 0.75% to CORRA (“Canadian Overnight Repo Rate Average”) plus 250 bps. Payment of principal and interest is due 30 days after drawdown and is repayable in full on the last day of the three-year term.

Current report

The Revolver is being provided by RBC by way of Letters of Credit and Letters of Guaranty with fees to be determined on a transaction by transaction basis. This facility will be available for the 36 month term subject to the issuance of the EDC (Export and Development Canada) Performance Security Guaranty in the amount of USD $5.8 million and other related supporting documents. The Company agreed to certain financial covenants included maintaining on a combined basis between MTL-1 and MTL-2: fixed charge coverage of not less than 1.20:1 and a ratio of Net Funded Debt to EBITDA of not greater than 4.25:1 and decreasing to 3.50:1 from December 31, 2027.

Current report

In June of 2025, the Company announced that it had initiated a strategic transition to become a pure play ETH staking and treasury company. In connection with the transition, the Company intends to convert its BTC holdings into ETH over time and has commenced a strategic alternatives process for its bitcoin mining operations, which is expected to result in a sale or wind-down, with any net proceeds to be re-deployed into ETH.

Current report

During the second quarter of 2025, the Company received an additional 1,720 miners, which were deployed in July 2025.

Current report

For the three months ended June 30, 2025, we received 68.2 bitcoins from the Foundry mining pool. As of June 30, 2025, our maximum hash rate was at an aggregate of 2.7 EH/s for our bitcoin miners. For the three months ended June 30, 2025, we recognized revenue of $6.6 million from bitcoin mining services.

Current report

For the three months ended June 30, 2025, we earned 166.8 ETH in native staking. For the three months ended June 30, 2025, we recognized revenues of $365,332 from native staking.

Current report

For the three months ended June 30, 2024, we earned 109.4 ETH in native staking. For the three months ended June 30, 2024, we recognized revenues of $373,812 from native staking.

Current report

For the three months ended June 30, 2025, GPU servers lease expenses were relatively consistent with the same period in 2024, with a slight decrease of $0.1 million, or 2%.

Current report

For the three months ended June 30, 2025, electricity costs totaled $0.3 million. We had no electricity costs for the three months ended June 30, 2024 as we acquired Enovum in the fourth quarter of 2024, which provides colocation services.

Current report

Wage expenses. These expenses represent the salaries and benefits of data center employees involved in the operation of our facilities.

Current report

For the three months ended June 30, 2025, wage expenses totaled $0.2 million. We had no wage expenses for the three months ended June 30, 2024 as we acquired Enovum in the fourth quarter of 2024, which provides colocation services.

Current report

For the three months ended June 30, 2025, our general and administrative expenses, totaling $19.7 million, were primarily comprised of professional and consulting expenses of $7.9 million, shared-based compensation expenses of $6.9 million, salary and bonus expenses of $1.8 million, marketing expenses of $0.6 million, travel expenses of $0.3 million, and directors and officers insurance expenses of $0.2 million.

Current report

The Company enters in contracts with mining pool operators to provide computing power to digital asset mining pools. Providing computing power for digital asset transaction verification services is an output of the Company’s ordinary activities. The provision of such computing power is the only performance obligation in the Company’s contracts with mining pool operators.

Current report

For the six months ended June 30, 2024, we received 654.9 bitcoins from the Foundry mining pool. As of June 30, 2024, our maximum hash rate was at an aggregate of 4.3 EH/s for our bitcoin miners. For the six months ended June 30, 2024, we recognized revenue of $38.0 million from bitcoin mining services.

Current report

Our revenues from digital asset mining services decreased by $23.6 million, or 62.1%, to $14.4 million for the six months ended June 30, 2025 from $38.0 million for the six months ended June 30, 2024. The decrease was primarily due to a decrease of 503.4 bitcoins generated from our mining business and partially offset by a higher average BTC price for the six months ended June 30, 2025, compared to the same period in 2024.

Current report

Our revenues from ETH native staking increased by $230,918, or 33.2%, to $925,973 for the six months ended June 30, 2025 from $695,055 for the six months ended June 30, 2024. The increase was primarily due to an increase of 157.3 ETH earned from staking services partially offset by a decrease in the average price of ETH for the six months ended June 30, 2025 compared to the six months ended June 30, 2024.

Current report

For the six months ended June 30, 2025 and 2024, the cost of revenue from cloud services was comprised of the following:

Current report

For the six months ended June 30, 2025, electricity costs increased by $0.9 million, or 417%, compared to the electricity costs incurred for the six months ended June 30, 2024. The increase primarily resulted from an increase in the number of deployed GPU servers.

Current report

For the six months ended June 30, 2025, datacenter lease expenses increased by $1.3 million, or 102%, compared to the datacenter lease expenses incurred for the six months ended June 30, 2024. The increase primarily resulted from two additional datacenter leases entered into after the second quarter of 2024.

Current report

In the fourth quarter of 2024, we acquired Enovum which provides colocation services. For the six months ended June 30, 2025 and 2024, the cost of revenue from colocation services was comprised of the following:

Current report

For the six months ended June 30, 2025, electricity costs totaled $0.5 million. We had no electricity costs for the six months ended June 30, 2024 as we acquired Enovum in the fourth quarter of 2024, which provides colocation services.

Current report

For the six months ended June 30, 2025, data center lease expenses totaled $0.3 million. We had no data center lease expenses for the six months ended June 30, 2024 as we acquired Enovum in the fourth quarter of 2024, which provides colocation services.

Current report

Wage expenses. These expenses represent the salaries and benefits of data center employees involved in the operation of our facilities.

Current report

For the six months ended June 30, 2025, wage expenses totaled $0.2 million. We had no wage expenses for the six months ended June 30, 2024 as we acquired Enovum in the fourth quarter of 2024, which provides colocation services.

Current report

For the six months ended June 30, 2025, electricity costs decreased by $6.7 million, or 44%, compared to the electricity costs incurred for the six months ended June 30, 2024. The decrease primarily resulted from a decrease in the number of deployed miners.

Showing the first 40 of 58 passages. Open the source sections for the rest.

Removed paragraphs (24)

Previous report

We have entered into a five-year colocation agreement with Cerebras Systems (“Cerebras”), a leading AI hardware innovator. Cerebras is launching six new data center sites in North America and chose WhiteFiber to be its partner for its first Canadian data center. Under the agreement, the Company will provide the client 5 MW (IT load) of built-to suit data center infrastructure for a period of five years. The contract is expected to be fulfilled at MTL-3, or another data center within our proprietary development pipeline.

Previous report

On October 23, 2023, Bit Digital announced that it had commenced AI operations by signing a binding term sheet with a customer (the “Initial Customer”) to support the customer’s GPU workloads. Under the agreement, as amended, we will supply this customer with a total of 2,048 GPUs for the respective three-year periods, amounting to total targeted revenue of approximately $150 million, or approximately $50 million on an annualized basis.

Previous report

We expect to continue to opportunistically invest in miners to increase our hash rate capacity.

Previous report

For the three months ended March 31, 2025 and 2024, electricity costs totaled $0.2 million and $nil, respectively.

Previous report

We expect a proportionate increase in the cost of revenue as we continue to focus on the expansion and upgrade of our miner fleet.

Previous report

Goodwill represents the excess of the purchase price over the fair value of the net assets acquired in relation of in Enovum Acquisition. Refer to Note 14.Goodwill And Intangible Assets for further information. As of March 31, 2025 and December 31, 2024, the Company recorded goodwill in the amount of $19.2 million and $19.4 million, respectively.

Previous report

Intangible assets pertain to customer relationships acquired in connection with the acquisition of Enovum. Refer to Note 14.Goodwill and Intangible Assets for further information. As of March 31, 2025 and December 31, 2024, the total balance of intangible assets was $12.8 million and $13.0 million, respectively.

Previous report

Under the Company’s Purchase Agreement with Ionic Ventures LLC, the Company had the right, but not the obligation, to sell to Ionic up to $22 million of registered Ordinary Shares.

Previous report

In August and September 2023, the Company sold an aggregate of 781,602 ordinary shares in connection with the at-the-market offering. The Company received net proceeds of $1.9 million, net of offering costs.

Previous report

In the fourth quarter of 2023, the Company sold an aggregate of 13,962,424 ordinary shares in connection with the at-the-market offering. The Company received net proceeds of $43.3 million, net of offering costs.

Previous report

In the first quarter of 2024, the Company sold an aggregate of 12,871,934 ordinary shares in connection with the at-the-market offering. The Company received net proceeds of $38.7 million, net of offering costs.

Previous report

In the second quarter of 2024, the Company sold an aggregate of 16,237,292 ordinary shares in connection with the at-the-market offering. The Company received net proceeds of $41.6 million, net of offering costs.

Previous report

In the third quarter of 2024, the Company sold an aggregate of 14,025,827 ordinary shares in connection with the at-the-market offering. The Company received net proceeds of $51.4 million, net of offering costs.

Previous report

In the fourth quarter of 2024, the Company sold an aggregate of 24,111,575 ordinary shares in connection with the at-the-market offering. The Company received net proceeds of $111.1 million, net of offering costs.

Previous report

In November 2023, as amended on December 12, 2023, the Company finalized a service agreement to supply its initial cloud services customer with services over a three-year period. On January 10, 2024, the Company announced it had increased the size of its contract for up to an aggregate of 2,048 GPUs worth more than $50 million of annualized revenues to the Company. On January 23, 2024 the Company announced that its WhiteFiber AI business commenced generating revenue.

Previous report

We expect to also generate ongoing revenues from the production of digital assets, primarily bitcoin. Our ability to liquidate digital assets at future values will be evaluated from time to time to generate cash for operations. Generating digital assets, for example, with spot market values which exceed our production and other costs, will determine our ability to report profit margins related to such mining operations. Furthermore, regardless of our ability to generate revenue from our high performance computing business, or our digital asset business, we may need to raise additional capital in the form of equity or debt to fund our operations and pursue our business strategy, including purchases in order to fund our high performance computing business.

Previous report

Certain statements, other than purely historical information, including estimates, projections, statements relating to our business plans, objectives, and expected operating results, and the assumptions upon which those statements are based, are “forward-looking statements” within the meaning of the Private Securities Litigation Reform Act of 1995, Section 27A of the Securities Act of 1933 and Section 21E of the Securities Exchange Act of 1934. These forward-looking statements generally are identified by the words “believes,” “project,” “expects,” “anticipates,” “estimates,” “intends,” “strategy,” “plan,” “may,” “will,” “would,” “will be,” “will continue,” “will likely result,” and similar expressions.

Previous report

We intend such forward-looking statements to be covered by the safe-harbor provisions for forward-looking statements and are including this statement for purposes of complying with those safe-harbor provisions. Forward-looking statements are based on current expectations and assumptions that are subject to risks and uncertainties which may cause actual results to differ materially from the forward-looking statements. Our ability to predict results or the actual effect of future plans or strategies is inherently uncertain. In particular, information included under “Risk Factors,” “Management’s Discussion and Analysis of Financial Condition and Results of Operations” and other sections of this Report contain forward-looking statements. Where, in any forward-looking statement, an expectation or belief as to future results or events is expressed, such expectation or belief is based on the current plans and expectations of Bit Digital’s management and expressed in good faith and believed to have a reasonable basis, but there can be no assurance that the expectation or belief will result or be achieved or accomplished. Whether any such forward-looking statements are in fact achieved will depend on future events, some of which are beyond Bit Digital’s control. Except as may be required by law, Bit Digital undertakes no obligation to modify or revise any forward-looking statements to reflect new information, events or circumstances occurring after the date of this Report. Comparisons of results for current and any prior periods are not intended to express any future trends, or indications of future performance, unless expressed as such, and should only be viewed as historical data.

Previous report

Factors which could have a material adverse effect on our operations and future prospects on a consolidated basis include but are not limited to: changes in economic conditions, legislative/regulatory changes, availability of capital, interest rates, competition, and generally accepted accounting principles. These risks and uncertainties should also be considered in evaluating forward-looking statements and undue reliance should not be placed on such statements. We undertake no obligation to update or revise publicly any forward-looking statements, whether as a result of new information, future events or otherwise. Further information concerning our business, including additional factors that could materially affect our financial results, is included herein and in our other filings with the SEC.
Reworded paragraphs (98)

Previous wording

The following discussion should be read in conjunction with our interim Condensed Consolidated Financial Statements and the related notes and other financial information appearing elsewhere in this report as well as Management’s Discussion and Analysis of Financial Condition and Results of Operations included in our Form 10-K for the year ended December 31, 2024 (“Form 10-K”) and this Quarterly Report on Form 10-Q for the quarter ended March 31, 2025.

Current wording

The following discussion should be read in conjunction with our interim Condensed Consolidated Financial Statements and the related notes and other financial information appearing elsewhere in this Quarterly Report on Form 10-Q for the period ended June 30, 2025 as well as Management’s Discussion and Analysis of Financial Condition and Results of Operations included in our Form 10-K for the year ended December 31, 2024 (“Form 10-K”).

Previous wording

Bit Digital, Inc. or the “Company”, is a global platform for high performance computing (“HPC”) infrastructure and digital asset business with headquarters in New York City.

Current wording

Bit Digital, Inc. or the “Company”, is a global platform for high performance computing (“HPC”) business including cloud services and HPC data center services and digital asset business, including Etherum (ETH) staking business, with headquarters in New York City. On June 25, 2025, the Company announced that it has initiated a strategic transition to become a pure play Ethereum staking and treasury company. The Company began accumulating ETH and operating staking infrastructure in 2022 and has steadily increased its holdings since that time.

Previous wording

We design, develop, and operate data centers, through which we offer our hosting and colocation services. Our data centers meet the requirements of the Tier-3 standard, including N+1 redundancy architecture, concurrent maintainability, uninterruptible power supply, advanced and highly reliable cooling systems, strict monitoring and management systems, SOC2 Type 2, differentiated software supporting AI workloads, high density and robust bandwidth, and infrastructure to support AI workloads. We acquired Enovum Data Centers Corp (“Enovum”) on October 11, 2024. The transaction included the lease to MTL-1, a fully operational and fully leased to customers 4 MW Tier-3 datacenter headquartered in Montreal, Canada. MTL-1 is currently hosting over 5,000 GPUs, including NVIDIA H200s and H100s, on behalf of 14 customers across a variety of end markets.

Current wording

We design, develop, and operate data centers, through which we offer our hosting and colocation services. Our operational data centers meet the requirements of the Tier-3 standard, including N+1 redundancy architecture, concurrent maintainability, uninterruptible power supply, advanced and highly reliable cooling systems, strict monitoring and management systems, SOC 2 Type 2, differentiated software supporting AI workloads, high density and robust bandwidth, and infrastructure to support AI workloads.

Previous wording

On December 27, 2024, we acquired the real estate and building for a build-to-suit 5 MW (gross) Tier-3 data center (“MTL-2”) expansion project near Montreal, Canada. MTL-2, a 160,000 square foot site that was previously used as an encapsulation manufacturing facility, is located in Pointe-Claire, QC. We initially funded the purchase of CAD $33.5 million (approximately USD $23.3) million with cash on hand and are in the process of securing mortgage financing for both the site acquisition and subsequent infrastructure capex. We expect to invest approximately USD $19.3 million to develop the site to Tier-3 standards with an initial gross load of 5 MW. The site is expected to be completed and operational by the end of the third quarter of 2025.

Current wording

On December 27, 2024, we acquired the real estate and building for a build-to-suit 5 MW (gross) Tier-3 data center (“MTL-2”) expansion project near Montreal, Canada which we refer to as MTL-2. MTL-2 is a 160,000 square foot site that was previously used as an encapsulation manufacturing facility, is located in Pointe-Claire, Quebec. We initially funded the purchase of CAD $33.5 million (approximately USD $23.3) million with cash on hand. We expect to invest approximately USD $23.6 million to develop the site to Tier-3 standards with an initial load of 5 MW (gross). MTL-2 is expected to be completed and operational in the fourth quarter of 2025, with a one-month delay before it begins to generate revenue.

Previous wording

On April 10, 2025, we entered into a lease for a new data center site in Saint-Jerome, Quebec, a suburb of Montreal, MTL-3, which is subject to the lessor consummating the acquisition of the property and our receipt of the necessary permits. The facility spans approximately 202,000 square feet on 7.7 acres and is being developed to support current contracted capacity, with future expansion potential subject to utility approvals. The transaction was executed under a lease-to-own structure, which includes a fixed-price purchase option of CAD $24,240,00 (approximately USD $17,300,000) exercisable within 12 months. The lease term is 20 years, with two 5-year extension options, subject to our completion of the acquisition of the property and the receipt of all required permits. The facility is being retrofitted to Tier-3 standards, with development costs expected to total approximately USD $40,000,000, and a targeted go-live date of late third quarter of 2025.

Current wording

On April 11, 2025, we entered into a lease for a new data center site in Saint-Jerome, Quebec, a suburb of Montreal, MTL-3. The MTL-3 facility spans approximately 202,000 square feet on 7.7 acres and is being developed to as a 7 MW (gross) Tier-3 data center. It will support current contracted capacity, with Cerebras (5 MW IT Load), with future expansion potential subject to utility approvals. The transaction was executed under a lease-to-own structure, which includes a fixed-price purchase option of CAD $24.2 million (approximately USD $17.3 million) exercisable by December 2025. The lease term is 20 years, with two 5-year extensions at the Company’s option. Subject to our receipt of all required permits, the facility is being retrofitted to Tier-3 standards, with development costs expected to total approximately USD $41 million, and is expected to be completed and operational in the fourth quarter of 2025, with a one-month delay before we expect to begin to generate revenue.

Previous wording

On April 10, 2025, we entered into a real estate purchase and sale agreement (the “Purchase Agreement”) with Unifi Manufacturing, Inc. (“UMI”). Pursuant to the Purchase Agreement we agreed to purchase from UMI, an industrial/manufacturing building together with the underlying land (“NC-1”) located in Madison, North Carolina, as well as certain machinery and equipment located thereon, for a cash purchase price of $53.2 million (the “Purchase Price”). An earnest money deposit of $2.25 million was deposited in escrow pursuant to the terms of the Purchase Agreement, of which $1.25 million is non-refundable to us. The closing of the transaction contemplated by the Purchase Agreement is subject to various closing conditions of which there can be no assurance and is currently expected to occur on or about May 19, 2025.

Current wording

On May 20, 2025 (the “Closing Date”), we completed the purchase of a former industrial/manufacturing building from Unifi Manufacturing, Inc. (“UMI”). Pursuant to the Purchase Agreement we agreed to purchase from UMI, an industrial/manufacturing building together with the underlying land (“NC-1”) located in Madison, North Carolina, as well as certain machinery and equipment located thereon for a cash purchase price of $45 million. The purchase price will increase by (i) $8 million, if Duke Energy actually provides, or provides an Electric Services Agreement providing for, at least 99 MW (gross) within two years of the Closing Date or (ii) $5 million, if Duke Energy actually provides, or provides an Electric Services Agreement providing for, at least 99 MW (gross) more than two years but less than three years after the Closing Date. Additionally, the purchase price will increase by an additional $200,000 per MW over 99 MW (gross) up to a maximum of $5 million if at least 99 MW (gross) are actually delivered, or Duke Energy provides an Electric Services Agreement for the provision of at least 99 MW (gross), within four years of the Closing Date. Separately, the Company entered into a Capacity Agreement with Duke Energy pursuant to which Duke Energy agreed to use commercially reasonable efforts to achieve 24 MW (gross) of service to the Property by September 1, 2025, 40 MW (gross) by April 1, 2026 and 99 MW (gross) within four years of May 16, 2025. Management believes based upon its review of the site and a Duke Energy preliminary transmission study, that the Property may receive and support up to 200 MW (gross) of total electrical supply over an extended period of time, subject to infrastructure upgrades, such as developing new substations and other conditions.

Previous wording

We provide specialized cloud services to support generative AI workstreams, especially training and inference, emphasizing cost-effective utility and tailor-made solutions for each client. We are an authorized NVIDIA Preferred Partner through the NVIDIA Partner Network (“NPN”), an authorized partner with SuperMicro Computer Inc.®, an authorized Communications Service Provider (“CSP”) with Dell (through Dell’s exclusive distributor in Iceland, Advania), an official partnership with Hewlett Packard Enterprise and a commercial relationship with Quanta Computer Inc. (“QCT”). We are proud to be among the first service providers to offer H200, B200, and GB200 servers.

Current wording

We provide specialized cloud services to support generative AI workstreams, especially training and inference, emphasizing cost-effective utility and tailor-made solutions for each client. We are an authorized NVIDIA Preferred Partner through the NVIDIA Partner Network (“NPN”), an authorized partner with SuperMicro Computer Inc.®, an authorized Communications Service Provider (“CSP”) with Dell (through Dell’s exclusive distributor in Iceland, Advania), an official partnership with Hewlett Packard Enterprise and a commercial relationship with Quanta Computer Inc. (“QCT”). Based on Management’s knowledge of the industry, we are proud to be among the first service providers to offer H200, B200, and GB200 servers. We provide a high-standard service lease with an Uptime percentage > 99.5%.

Previous wording

We leverage a global network of data centers for hosting capacity for our GPU business in many instances by partnering with third-party data center providers in locations across Europe, Canada, and the U.S. Our initial data center partnership through which we lease capacity is at Blönduós Campus, Iceland, offering a world-class operations team with certified technicians and reliable engineers. The facility has 45kW rack density and 6 MW (gross) total capacity. We have executed contracts for 5.5 MW at the data center. The center’s energy source is 100% renewable energy, mainly from Blanda Hydro PowerStation, the winner of an IHA Blue Planet Award in 2017.

Current wording

We expect to leverage a global network of data centers for hosting capacity for our GPU business, in many instances, by negotiating with third-party providers to seamlessly integrate our cloud services at data centers across key regions in Europe, North America and Asia. Our initial data center partnership through which we lease capacity is at Blönduós Campus, Iceland, offering a world-class operations team with certified technicians and reliable engineers. The facility has 45kW rack density and 6 MW (gross) total capacity. We have executed contracts for 5.5 MW at the data center. The center’s energy source is 100% renewable energy, mainly from Blanda Hydro PowerStation, the winner of an IHA Blue Planet Award in 2017.

Previous wording

On December 12, 2023, we finalized a Master Services and Lease Agreement (“MSA”), as amended, with our Initial Customer for the provision of cloud services from a total of 2,048 GPUs over a three-year period. To finance this operation, we entered into a sale-leaseback agreement with a third party, selling 96 AI servers (equivalent to 768 GPUs) and leasing them back for three years. The total contract value with the Initial Customer for the aggregated 2,048 GPUs was estimated to be worth more than $50 million of annualized revenue. On January 22, 2024, approximately 192 servers (equivalent to 1,536 GPUs) were deployed at a specialized data center and began generating revenue, and subsequently on February 2, 2024, approximately an additional 64 servers (equivalent to 512 GPUs) also started to generate revenue.

Current wording

On October 23, 2023, Bit Digital announced that it had commenced AI operations by signing a binding term sheet with a customer (the “Initial Customer”) to support the customer’s GPU workloads. On December 12, 2023, we finalized a Master Services and Lease Agreement (“MSA”), as amended, with our Initial Customer for the provision of cloud services from a total of 2,048 GPUs over a three-year period. To finance this operation, we entered into a sale-leaseback agreement with a third party, selling 96 AI servers (equivalent to 768 GPUs) and leasing them back for three years. The total contract value with the Initial Customer for the aggregated 2,048 GPUs was estimated to be worth more than $50 million of annualized revenue. On January 22, 2024, approximately 192 servers (equivalent to 1,536 GPUs) were deployed at a specialized data center and began generating revenue, and subsequently on February 2, 2024, approximately an additional 64 servers (equivalent to 512 GPUs) also started to generate revenue.

Previous wording

In January 2025, the Company entered into a new agreement to supply its first customer for an additional 464 GPUs for a period of eighteen months. This new agreement replaces the prior agreement whereby the Company was to provide the customer with an incremental 2,048 H100 GPUs. The contract represents approximately $15 million of annualized revenue and features a two-month prepayment from the customer.

Current wording

In January 2025, the Company entered into a new agreement to supply its Initial Customer with an additional 464 GPUs for a period of eighteen months. This new agreement replaces the prior agreement whereby the Company was to provide the customer with an incremental 2,048 H100 GPUs. The contract represents approximately $15 million of annualized revenue and features a two-month prepayment from the customer. The customer has elected to defer the commencement date until August 20, 2025, which is the latest allowable date under the agreement.

Previous wording

On October 9, 2024, we executed a Master Service Agreement (the “MSA”) with Boosteroid Inc. (“Boosteroid”), a global cloud gaming provider. Following execution of a binding term sheet with Boosteroid on August 19, 2024, we finalized initial orders of 489 GPUs, projected to generate approximately $7.9 million in contracted value in the aggregate through November 2029. The GPUs have been delivered to respective data centers across the U.S. and Europe and began earning fees in November 2024. The MSA provides Boosteroid with the option to expand in increments of 100 servers, up to 50,000 servers, representing a potential contract value of approximately $700 million over the five-year term assuming Boosteroid utilizes the GPUs and services at full capacity for the duration of the contract. Expansion depends upon the internal development roadmap of Boosteroid, Boosteroid has full discretion to decide when and the quantity to pursue separate source orders (for GPU servers) under the MSA. Additional orders for 701 GPUs were executed in March 2025, representing approximately $10.3 million in contracted value over a five year term.

Current wording

In August 2024, we executed a binding term sheet with Boosteroid Inc. (“Boosteroid”), a global cloud gaming provider pursuant to which, we finalized initial orders of 489 GPUs, projected to generate approximately $7.9 million in contracted value in the aggregate through November 2029. The GPUs were delivered to respective data centers across the U.S. and Europe and began earning fees in November 2024. On October 9, 2024, we executed a Master Services and Lease Agreement (the “MSA”) with Boosteroid, pursuant to which Boosteroid may, from time to time, lease certain equipment, including GPUs, from the Company upon delivery of a purchase order. The MSA provides the general terms and conditions for such equipment leases. Pursuant to the MSA, we are granted a right of first refusal with respect to the next 5,000 servers that Boosteroid leases during the term of the MSA. The MSA provides Boosteroid with the option to expand in increments of 100 servers, up to 50,000 servers, representing a potential contract value of approximately $700 million over the five-year term assuming Boosteroid utilizes the GPUs and services at full capacity for the duration of the contract. Expansion depends upon the internal development roadmap of Boosteroid, Boosteroid has full discretion to decide when and the quantity to pursue separate source orders (for GPU servers) under the MSA. In the third quarter of 2025, the Company finalized additional purchase orders for 302, 120, and 279 GPUs, totaling approximately $10.4 million in contracted value over a five-year term.

Previous wording

On November 6, 2024, we entered into a Master Services Agreement (“MSA”) with a minimum purchase commitment of 16 GPUs, along with an associated purchase order, from a new customer. The purchase order provides for services utilizing a total of 16 H200 GPUs over a minimum of a six (6) month period, representing total revenue of approximately $320,000 for the term. The deployment commenced and revenue generation began on November 7, 2024, using the Company’s existing inventory of H200 GPUs.

Current wording

On November 6, 2024, we entered into a Master Services Agreement (“MSA”) with a minimum purchase commitment of 16 GPUs, along with an associated purchase order, from a new customer. The purchase order provides for services utilizing a total of 16 H200 GPUs over a minimum of a six month period, representing total contracted value of approximately $160,000 for the term. The deployment commenced on November 7, 2024, using the Company’s existing inventory of H200 GPUs. The service under the purchase order concluded in May 2025. Between May and August 2025, the Company signed four additional agreements on a month-to-month basis for a total of 64 H200 GPUs.

Previous wording

On November 14, 2024, we entered into a Terms of Supply and Service Level Agreement (together, the “Agreement”) and an Order Form with a new customer. The order form provides for services utilizing a total of 64 H200 GPUs on a month-to-month basis, which either party may terminate upon at least 14 days’ written notice prior to any renewal date. It represents annual revenue of approximately $1.2 million. The deployment commenced and revenue generation began on November 15, 2024, using the Company’s existing inventory of H200 GPUs.

Current wording

On November 14, 2024, we entered into a Terms of Supply and Service Level Agreement (together, the “Agreement”) and an Order Form with a new customer. The order form provides for services utilizing a total of 64 H200 GPUs on a month-to-month basis, which either party may terminate upon at least 14 days’ written notice prior to any renewal date. It represents annual revenue of approximately $1.2 million. The deployment commenced and revenue generation began on November 15, 2024, using the Company’s existing inventory of H200 GPUs. The service under the purchase order concluded in December 2024.

Previous wording

On December 30, 2024, we entered into a Master Services Agreement (“MSA”) with a minimum purchase commitment of 32 GPUs, along with an associated purchase order, from a new customer, an AI Compute Fund managed by DNA Holdings Venture Inc.(“DNA Fund”). The purchase order provides for services utilizing a total of 576 H200 GPUs over a twenty-five month period, terminable by either party upon at least 90 days’ written notice prior to any renewal date. It represents an aggregate revenue opportunity of approximately $20.2 million. Concurrently, we placed a purchase order for 130 H200 servers for approximately $30 million. The deployment commenced in February 2025.

Current wording

On December 30, 2024, we entered into a Master Services Agreement (“MSA”) with a minimum purchase commitment of 32 GPUs, along with an associated purchase order, from a new customer, an AI Compute Fund managed by DNA Holdings Venture Inc. (“DNA Fund”). The purchase order provides for services utilizing a total of 576 H200 GPUs over a twenty-five month period and terminable by either party upon at least 90 days’ written notice prior to any renewal date. It represents an aggregate revenue opportunity of approximately $20.2 million. Concurrently, we placed a purchase order for 130 H200 servers for approximately $30 million. The deployment commenced in February 2025.

Previous wording

In April 2025, the Company signed two additional cloud services agreements with DNA Fund. The first agreement, commencing in early May, includes 104 NVIDIA H200 GPUs under a 23-month term. The second, commencing mid-May, includes 512 H200 GPUs under a 24-month term. With these additions, DNA Fund’s total contracted deployment increased to 1,192 GPUs. Combined, the agreements represent approximately $20.8 million of annualized revenue.

Current wording

In April 2025, the Company signed two additional cloud services agreements with DNA Fund. The first agreement includes 104 NVIDIA H200 GPUs under a 23-month term and was deployed in May 2025. The second agreement includes 512 H200 GPUs under a 24-month term and was deployed in July 2025. With these additions, DNA Fund’s total contracted deployment increased to 1,192 GPUs. Combined, the agreements represent approximately $20.8 million of annualized revenue.

Previous wording

On January 6, 2025, we entered into a Master Services Agreement (“MSA”) with a minimum purchase commitment of 32 GPUs, along with an associated purchase order, from a new customer. The purchase order provides for services utilizing a total of 32 H200 GPUs over a minimum of six (6) month period, representing total revenue of approximately $300,000 for the term. The deployment commenced and revenue generation began on January 8, 2025, using the Company’s existing inventory of H200 GPUs.

Current wording

On January 6, 2025, we entered into a Master Services Agreement (“MSA”) with a minimum purchase commitment of 32 GPUs, along with an associated purchase order, from a new customer. The purchase order provided for services utilizing a total of 32 H200 GPUs over a minimum of six month period, representing total revenue of approximately $300,000 for the term. The deployment commenced and revenue generation began on January 8, 2025, using the Company’s existing inventory of H200 GPUs. The service under the purchase order concluded in April 2025 following a change in the customer’s ownership, and the customer paid the remaining contract value as an early termination penalty.

Previous wording

In January 2025, we entered into a Master Services Agreement (“MSA”), along with two associated purchase orders, from a new customer. The purchase orders provide for services utilizing a total of 24 H200 GPUs over a minimum twelve (12) month period, representing total revenue of approximately $450,000 for the term. The deployment commenced and revenue generation began on January 27, 2025, using the Company’s existing inventory of H200 GPUs.

Current wording

In January 2025, we entered into a Master Services Agreement (“MSA”), along with two associated purchase orders, from a new customer. The purchase orders provide for services utilizing a total of 24 H200 GPUs over a minimum twelve (12) month period, representing total revenue of approximately $450,000 for the term. The deployment commenced and revenue generation began on January 27, 2025, using the Company’s existing inventory of H200 GPUs. The service under the purchase order concluded in March 2025 after the customer ceased operations.

Previous wording

On January 30, 2025, we entered into a Master Services Agreement (“MSA”) with a minimum purchase commitment of 40 GPUs, along with an associated purchase order, from a new customer. The purchase orders provide for services utilizing a total of 40 H200 GPUs over a minimum of twelve (12) month period, representing total revenue of approximately $750,000 for the term. The deployment commenced and revenue generation began on January 24, 2025, using the Company’s existing inventory of H200 GPUs.

Current wording

On January 30, 2025, we entered into a Master Services Agreement (“MSA”) with a minimum purchase commitment of 40 GPUs, along with an associated purchase order, from a new customer. The purchase orders provide for services utilizing a total of 40 H200 GPUs over a minimum of 12 month period, representing total revenue of approximately $750,000 for the term. The deployment commenced and revenue generation began on January 24, 2025, using the Company’s existing inventory of H200 GPUs. Between April and July 2025, the Company signed four additional agreements on a month-to-month basis for a total of 184 H200 GPUs including one purchase order for 32 GPUs that was terminated in August 2025.

Previous wording

We have signed service agreements with third-party hosting partners in North America and Iceland. These partners operate specialized mining data centers, where they install and operate the miners and provide IT consulting, maintenance, and repair work on site for us. Our mining facilities in New York are maintained by Digihost Technologies Inc. (“Digihost”). Our mining facilities in Texas are maintained by Dory Creek, LLC, a subsidiary of Bitdeer Technologies Group (“Bitdeer”) and A.R.T. Digital Holdings Corp (“KaboomRacks”). Soluna Computing, Inc and DVSL ComputeCo, LLC (collectively “Soluna”) maintained our mining facilities in Kentucky and Texas. Our mining facility in Iceland is maintained by GreenBlocks ehf, an Icelandic private limited company (“GreenBlocks”). We have relocated our miners from our mining facility in Canada maintained by Blockbreakers Inc. (“Blockbreakers”) to Soluna and Coinmint after our service agreement expired in November 2024. From time to time, the Company may change partnerships with hosting facilities to recalibrate its bitcoin mining operations. These terminations are strategic, targeting reduced operational costs, enhanced energy efficiency for a smaller carbon footprint, increased flexibility in operational control, and minimized geopolitical risks. While a short-term decrease in mining output might occur, we expect these changes to yield long-term operational improvements.

Current wording

We have signed service agreements with third-party hosting partners in North America and Iceland. These partners operate specialized mining data centers, where they install and operate the miners and provide IT consulting, maintenance, and repair work on site for us. Our mining facilities in New York are maintained by Digihost Technologies Inc. (“Digihost”). Our mining facilities in Texas are maintained by Dory Creek, LLC, a subsidiary of Bitdeer Technologies Group (“Bitdeer”) and A.R.T. Digital Holdings Corp (“KaboomRacks”). Soluna Computing, Inc and DVSL ComputeCo, LLC (collectively “Soluna”) maintained our mining facilities in Kentucky and Texas. Our mining facility in Iceland is maintained by GreenBlocks ehf, an Icelandic private limited company (“GreenBlocks”). We have relocated our miners from our mining facility in Canada maintained by Blockbreakers Inc. (“Blockbreakers”) to Soluna and Coinmint after our service agreement expired in November 2024.

Previous wording

As of March 31, 2025, the Company’s active hash rate totals approximately 1.5 EH/s, with operations in North America and Iceland.

Current wording

As of June 30, 2025, the Company’s active hash rate totals approximately 1.2 EH/s, with operations in North America and Iceland.

Previous wording

During the three months ended March 31, 2025, our hosting partners continued to prepare sites to deliver our contracted hosting capacity, bringing additional power online for our miners.

Current wording

During the three and six months ended June 30, 2025, our hosting partners continued to prepare sites to deliver our contracted hosting capacity, bringing additional power online for our miners.

Previous wording

The Company’s subsidiary, Bit Digital Canada, Inc., entered into a Mining Services Agreement effective September 1, 2022, for Blockbreakers, Inc. to provide five (5) MW of incremental hosting capacity at its facility in Canada. The facility utilizes an energy source that is primarily hydroelectric.

Current wording

The Company’s subsidiary, Bit Digital Canada, Inc., entered into a Mining Services Agreement effective September 1, 2022, for Blockbreakers, Inc. to provide five MW of incremental hosting capacity at its facility in Canada. The facility utilizes an energy source that is primarily hydroelectric.

Previous wording

On May 8, 2023, the Company entered into a Master Mining Services Agreement with Blockbreakers, pursuant to which Blockbreakers agreed to provide the Company with four (4) MW of additional mining capacity at its hosting facility in Canada. The agreement is for two (2) years automatically renewable for additional one (1) year terms unless either party gives at least sixty (60) days’ advance written notice. The performance fee is 15% of the net profit. Additionally, Bit Digital has secured a side letter agreement with Blockbreakers, granting the Company the right of first refusal for any future mining hosting services offered by Blockbreakers in Canada. This agreement brought the Company’s total contracted hosting capacity with Blockbreakers to approximately 9 MW. Our service agreement with Blockbreakers expired in November 2024. A portion of the miners were transferred to other hosting facilities, and the inefficient units were sold.

Current wording

On May 8, 2023, the Company entered into a Master Mining Services Agreement with Blockbreakers, pursuant to which Blockbreakers agreed to provide the Company with four (4) MW of additional mining capacity at its hosting facility in Canada. The agreement is for two (2) years automatically renewable for additional one (1) year terms unless either party gives at least 60 days’ advance written notice. The performance fee is 15% of the net profit. Additionally, Bit Digital has secured a side letter agreement with Blockbreakers, granting the Company the right of first refusal for any future mining hosting services offered by Blockbreakers in Canada. This agreement brought the Company’s total contracted hosting capacity with Blockbreakers to approximately 9 MW. Our service agreement with Blockbreakers expired in November 2024. A portion of the miners were transferred to other hosting facilities, and the inefficient units were sold.

Previous wording

On June 7, 2022, we entered into a Master Mining Services Agreement (the “MMSA”) with Coinmint LLC, pursuant to which Coinmint will provide the required mining colocation services for a one-year period automatically renewing for three-month periods unless earlier terminated. The Company paid Coinmint electricity costs, plus operating costs required to operate the Company’s mining equipment, as well as a performance fee equal to 27.5% of the net profit, subject to a ten percent (10%) reduction if Coinmint fails to provide uptime of ninety-eight (98%) percent or better for any period. We were not privy to the emissions rate at the Coinmint facility or at any other hosting facility. However, the Coinmint facility operated in an upstate New York region that reportedly utilized power that is 99% emissions-free, as determined based on the 2023 Load & Capacity Data Report published by the New York Independent System Operator, Inc. (“NYISO”).

Current wording

On June 7, 2022, we entered into a Master Mining Services Agreement (the “MMSA”) with Coinmint LLC, pursuant to which Coinmint will provide the required mining colocation services for a one-year period automatically renewing for three-month periods unless earlier terminated. The Company paid Coinmint electricity costs, plus operating costs required to operate the Company’s mining equipment, as well as a performance fee equal to 27.5% of the net profit, subject to a 10% reduction if Coinmint fails to provide uptime of 98% or better for any period. We were not privy to the emissions rate at the Coinmint facility or at any other hosting facility. However, the Coinmint facility operated in an upstate New York region that reportedly utilized power that is 99% emissions-free, as determined based on the 2023 Load & Capacity Data Report published by the New York Independent System Operator, Inc. (“NYISO”).

Previous wording

On April 5, 2023, the Company entered into a letter agreement and MMSA Amendment with Coinmint pursuant to which Coinmint agreed to provide the Company with up to ten (10) MW of additional mining capacity to energize the Company’s mining equipment at Coinmint’s hosting facility in Plattsburgh, New York. The agreement was for two (2) years automatically renewing for three (3) months unless terminated by either party on at least ninety (90) days prior written notice. The performance fees under this letter agreement range from 30% to 33% of the net profit. This agreement brought the Company’s total contracted hosting capacity with Coinmint to approximately 30 MW at this facility.

Current wording

On April 5, 2023, the Company entered into a letter agreement and MMSA Amendment with Coinmint pursuant to which Coinmint agreed to provide the Company with up to ten (10) MW of additional mining capacity to energize the Company’s mining equipment at Coinmint’s hosting facility in Plattsburgh, New York. The agreement was for two years automatically renewing for three (3) months unless terminated by either party on at least ninety (90) days prior written notice. The performance fees under this letter agreement range from 30% to 33% of the net profit. This agreement brought the Company’s total contracted hosting capacity with Coinmint to approximately 30 MW at this facility.

Previous wording

On April 27, 2023, the Company entered into a letter agreement and MMSA Amendment with Coinmint pursuant to which Coinmint agreed to provide the Company with up to ten (10) MW of additional mining capacity to energize the Company’s mining equipment at Coinmint’s hosting facility in Massena, New York. The agreement was for one (1) year automatically renewing for three (3) months unless terminated by either party on at least ninety (90) days prior written notice. The performance fees under this letter agreement are 33% of the net profit. This new agreement brought the Company’s total contracted hosting capacity with Coinmint to approximately 40 MW.

Current wording

On April 27, 2023, the Company entered into a letter agreement and MMSA Amendment with Coinmint pursuant to which Coinmint agreed to provide the Company with up to 10 MW of additional mining capacity to energize the Company’s mining equipment at Coinmint’s hosting facility in Massena, New York. The agreement was for one year automatically renewing for three (3) months unless terminated by either party on at least 90 days prior written notice. The performance fees under this letter agreement are 33% of the net profit. This new agreement brought the Company’s total contracted hosting capacity with Coinmint to approximately 40 MW.

Previous wording

On January 26, 2024, the Company entered into a letter agreement and MMSA Amendment with Coinmint pursuant to which Coinmint agreed to provide the Company with up to six (6) MW of additional mining capacity to energize the Company’s mining equipment at Coinmint’s hosting facility in Massena, New York. The agreement was for one (1) year automatically renewing for three (3) months unless terminated by either party on at least ninety (90) days prior written notice. The performance fees under this letter agreement are 28% of the net profit. This agreement brought the Company’s total contracted hosting capacity with Coinmint to approximately 46 MW.

Current wording

On January 26, 2024, the Company entered into a letter agreement and MMSA Amendment with Coinmint pursuant to which Coinmint agreed to provide the Company with up to six MW of additional mining capacity to energize the Company’s mining equipment at Coinmint’s hosting facility in Massena, New York. The agreement was for one year automatically renewing for three months unless terminated by either party on at least 90 days prior written notice. The performance fees under this letter agreement are 28% of the net profit. This agreement brought the Company’s total contracted hosting capacity with Coinmint to approximately 46 MW.

Previous wording

In June 2021, we entered into a strategic co-mining agreement with Digihost Technologies in North America. Pursuant to the terms of the agreement, Digihost provides certain premises to Bit Digital for the purpose of the operation and storage of a twenty (20) MW bitcoin mining system to be delivered by Bit Digital. Digihost provides services to maintain the premises for a term of two (2) years. Digihost shall also be entitled to 20% of the net profit generated by the miners.

Current wording

In June 2021, we entered into a strategic co-mining agreement with Digihost Technologies in North America. Pursuant to the terms of the agreement, Digihost provides certain premises to Bit Digital for the purpose of the operation and storage of a 20 MW bitcoin mining system to be delivered by Bit Digital. Digihost provides services to maintain the premises for a term of two years. Digihost shall also be entitled to 20% of the net profit generated by the miners.

Previous wording

In April 2023, we renewed the co-mining agreement with Digihost, previously executed in June 2021. Pursuant to the terms of the new agreement, Digihost provides certain premises to Bit Digital for the purpose of the operation and storage of an up to twenty (20) MW bitcoin mining system to be delivered by Bit Digital. Digihost also provides services to maintain the premises for a term of two (2) years, automatically renewing for a period of one (1) year. Digihost shall also be entitled to 30% of the net profit generated by the miners. As of March 31, 2025, Digihost provided approximately 6.0 MW of capacity for our miners at their facility.

Current wording

In April 2023, we renewed the co-mining agreement with Digihost, previously executed in June 2021. Pursuant to the terms of the new agreement, Digihost provides certain premises to Bit Digital for the purpose of the operation and storage of an up to 20 MW bitcoin mining system to be delivered by Bit Digital. Digihost also provides services to maintain the premises for a term of two years, automatically renewing for a period of one (1) year. Digihost shall also be entitled to 30% of the net profit generated by the miners. As of June 30, 2025, Digihost provided approximately 6.0 MW of capacity for our miners at their facility.

Previous wording

On May 9, 2023, the Company entered into a Computation Capacity Services Agreement (the “Services Agreement”) with GreenBlocks. Pursuant to the Agreement, GreenBlocks will provide computational capacity services and other necessary ancillary services, such as operation, management, and maintenance, at the facility in Iceland for a term of two (2) years. GreenBlocks will own and operate the miners financed through the Loan Agreement for the purpose of providing computational capacity of up to 8.25 MW. The Company will pay power costs of five cents ($0.05) per kilowatt hour, a pod fee of $22,000 per pod per month, and a depreciation fee equal to 1/36 of the facility size per month. The performance fees under this agreement are 20% of the net profit. The Company submitted to Greenblocks a deposit in the amount of $1,052,100, which was exclusively for the purpose of paying the landlord of the facility for hosting space.

Current wording

On May 9, 2023, the Company entered into a Computation Capacity Services Agreement (the “Services Agreement”) with GreenBlocks. Pursuant to the Agreement, GreenBlocks will provide computational capacity services and other necessary ancillary services, such as operation, management, and maintenance, at the facility in Iceland for a term of two years. GreenBlocks will own and operate the miners financed through the Loan Agreement for the purpose of providing computational capacity of up to 8.25 MW. The Company will pay power costs of $0.05 per kilowatt hour, a pod fee of $22,000 per pod per month, and a depreciation fee equal to 1/36 of the facility size per month. The performance fees under this agreement are 20% of the net profit. The Company submitted to Greenblocks a deposit in the amount of $1,052,100, which was exclusively for the purpose of paying the landlord of the facility for hosting space.

Previous wording

In October 2023, we entered into a strategic co-location agreement with Soluna Computing, Inc. for a term of one (1) year automatically renewing on a month-to-month basis unless terminated by either party. Pursuant to the terms of the agreement, Soluna provided certain required mining colocation services at their hosting facility in Murray, Kentucky to the Company for the purpose of the operation and storage of up to 4.4 MW bitcoin mining system to be delivered by Bit Digital. Soluna was also entitled to 42.5% of the net profit generated by the miners. This agreement expired at the end of October 2024.

Current wording

In October 2023, we entered into a strategic co-location agreement with Soluna Computing, Inc. for a term of one year automatically renewing on a month-to-month basis unless terminated by either party. Pursuant to the terms of the agreement, Soluna provided certain required mining colocation services at their hosting facility in Murray, Kentucky to the Company for the purpose of the operation and storage of up to 4.4 MW bitcoin mining system to be delivered by Bit Digital. Soluna was also entitled to 42.5% of the net profit generated by the miners. This agreement expired at the end of October 2024.

Previous wording

In October 2024, we entered into a co-location agreement with Soluna SW, Inc. to continue our business relationship. Under this agreement, Soluna provides certain required mining colocation services to the Company at their hosting facility in Murray, Kentucky for the purpose of the operation and storage of bitcoin mining system to be delivered by the Company up to 6.6 MW (3.3 MW for terms of nine (9) months and 3.3 MW for terms of one (1) year), automatically renewing on a month-to-month basis unless terminated by either party. Soluna shall also be entitled to 35% of the net profit generated by the miners.

Current wording

In October 2024, we entered into a co-location agreement with Soluna SW, Inc. to continue our business relationship. Under this agreement, Soluna provides certain required mining colocation services to the Company at their hosting facility in Murray, Kentucky for the purpose of the operation and storage of bitcoin mining system to be delivered by the Company up to 6.6 MW (3.3 MW for terms of nine months and 3.3 MW for terms of one (1) year), automatically renewing on a month-to-month basis unless terminated by either party. Soluna shall also be entitled to 35% of the net profit generated by the miners.

Previous wording

In December 2024, we entered into two additional co-location agreements with Soluna DVSL ComputerCo, LLC. pursuant to which Soluna agreed to provide the Company with up to 11 MW (5.5 MW and 5.5 MW, respectively) at their hosting facility in Silverton, Texas. Both agreements are for one (1) year automatically renewing on a month-to-month basis unless terminated by either party on at least sixty (60) days prior written notice. Soluna shall also be entitled to 35% and 27.5%, respectively, of the net profit generated by the miners. These new agreements bring the Company’s total contracted hosting capacity with Soluna to approximately 17.6 MW. As of March 31, 2025, Soluna provided approximately 15.8 MW of capacity for our miners at their facility.

Current wording

In December 2024, we entered into two additional co-location agreements with Soluna DVSL ComputerCo, LLC. pursuant to which Soluna agreed to provide the Company with up to 11 MW (5.5 MW and 5.5 MW, respectively) at their hosting facility in Silverton, Texas. Both agreements are for one (1) year automatically renewing on a month-to-month basis unless terminated by either party on at least 60 days prior written notice. Soluna shall also be entitled to 35% and 27.5%, respectively, of the net profit generated by the miners. These new agreements bring the Company’s total contracted hosting capacity with Soluna to approximately 17.6 MW. As of June 30, 2025, Soluna provided approximately 15.8 MW of capacity for our miners at their facility.

Previous wording

In November 2023, we entered into a hosting services agreement, which was amended on March 7, 2024, with Dory Creek, LLC, a subsidiary of Bitdeer Technologies Group (“Bitdeer”), for a term of one (1) year automatically renewing on an annual basis unless terminated by either party by giving a 30-day prior notice to the other Party in writing. Pursuant to the terms of the agreement, Bitdeer provides maintenance and operation services to Bit Digital to support 17.5 MW of capacity. Bitdeer shall also be entitled to 30% of the net profit generated by the miners. Bit Digital shall have the first right, but not obligation, to accept services for any extra capacity under the terms of this Agreement. As of March 31, 2025, Bitdeer provided approximately 15.5 MW of capacity for our miners at their facility.

Current wording

In November 2023, we entered into a hosting services agreement, which was amended on March 7, 2024, with Dory Creek, LLC, a subsidiary of Bitdeer Technologies Group (“Bitdeer”), for a term of one year automatically renewing on an annual basis unless terminated by either party by giving a 30-day prior notice to the other Party in writing. Pursuant to the terms of the agreement, Bitdeer provides maintenance and operation services to the Company to support 17.5 MW of capacity. Bitdeer shall also be entitled to 30% of the net profit generated by the miners. the Company shall have the first right, but not obligation, to accept services for any extra capacity under the terms of this Agreement. As of June 30, 2025, Bitdeer provided approximately 15.5 MW of capacity for our miners at their facility.

Previous wording

In February 2025, we entered into two hosting services agreements with A.R.T. Digital Holdings Corp (“KaboomRacks”) for terms of nine (9) months and three (3) years automatically renewing on an annual basis unless terminated by either party. Pursuant to the terms of the agreements, KaboomRacks provides maintenance and operation services to Bit Digital to support 6 MW and 13 MW of capacity. KaboomRacks shall also be entitled to between 19.75% and 40% of the net profit generated by the miners. As of March 31, 2025, KaboomRacks provided approximately 8.5 MW of capacity for our miners at their facility.

Current wording

In February 2025, we entered into two hosting services agreements with A.R.T. Digital Holdings Corp (“KaboomRacks”) for terms of nine (9) months and three years automatically renewing on an annual basis unless terminated by either party. Pursuant to the terms of the agreements, KaboomRacks provides maintenance and operation services to Bit Digital to support 6 MW and 13 MW of capacity. On July 1, 2025, we entered into the first amendment to the hosting service agreement for 13 MW of capacity. The amendment modified the existing agreement, identifying the two facilities that will provide maintenance and operations service to Bit Digital to support 5 MW and 8 MW of capacity. KaboomRacks shall also be entitled to respective 40%, 14.75% and 22.5% of the net profit generated by the miners. As of June 30, 2025, KaboomRacks provided approximately 4.5 MW of capacity for our miners at their facility.

Previous wording

In May 2022, our hosting partner Blockfusion advised us that the substation at its Niagara Falls, New York facility was damaged by an explosion and fire, and power was cut off to approximately 2,515 of the Company’s bitcoin miners and approximately 710 ETH miners that had been operating at the site immediately prior to the incident. The explosion and fire are believed to have been caused by faulty equipment owned by the power utility. Blockfusion and the Company have entered into a common interest agreement to jointly pursue any claims evolving from the explosion and fire. Prior to the incident, our facility with Blockfusion in Niagara Falls, provided approximately 9.4 MW to power our miners. Power was restored to the facility in September 2022. However, we received a notice dated October 4, 2022 (the “Notice”), from the City of Niagara Falls, which ordered the cease and desist from any cryptocurrency mining or related operations at the facility until such time as Blockfusion complies with Section 1303.2.8 of the City of Niagara Falls Zoning Ordinance (the “Ordinance”), in addition to all other City ordinances and codes. Blockfusion has advised us that the Ordinance came into effect on October 1, 2022, following the expiration of a related moratorium on September 30, 2022. Blockfusion has further advised that it has submitted applications for new permits based on the Ordinance’s new standards and that the permits may take several months to process. Pursuant to the Mining Services Agreement between Bit Digital and Blockfusion dated August 25, 2021, Blockfusion represents, warrants and covenants that it “possesses, and will maintain, all licenses, registrations, authorizations and approvals required by any governmental agency, regulatory authority or other party necessary for it to operate its business and engage in the business relating to its provision of the Services.” On October 5, 2022, Bit Digital further advised Blockfusion that it expects it to comply with the directives of the Notice. Our service agreement with Blockfusion ended in September 2023. On June 3, 2024, the Company filed suit in Delaware Superior Court against Blockfusion alleging claims for breach of contract, conversion, and related claims in connection with, among other things, certain deposits and advances paid to Blockfusion, the return of which is owed to the Company. The Company is seeking in excess of $4.3 million. On October 22, 2024, Blockfusion denied the Company’s claims and brought reciprocal breach of contract and related counterclaims. Blockfusion is seeking at least $158,000 in damages. A bench trial has been scheduled for June 29, 2026. Refer to Note 19.Contingencies for further details.

Current wording

In May 2022, our hosting partner Blockfusion advised us that the substation at its Niagara Falls, New York facility was damaged by an explosion and fire, and power was cut off to approximately 2,515 of the Company’s bitcoin miners and approximately 710 ETH miners that had been operating at the site immediately prior to the incident. The explosion and fire are believed to have been caused by faulty equipment owned by the power utility. Blockfusion and the Company have entered into a common interest agreement to jointly pursue any claims evolving from the explosion and fire. Prior to the incident, our facility with Blockfusion in Niagara Falls, provided approximately 9.4 MW to power our miners. Power was restored to the facility in September 2022. However, we received a notice dated October 4, 2022 (the “Notice”), from the City of Niagara Falls, which ordered the cease and desist from any cryptocurrency mining or related operations at the facility until such time as Blockfusion complies with Section 1303.2.8 of the City of Niagara Falls Zoning Ordinance (the “Ordinance”), in addition to all other City ordinances and codes. Blockfusion has advised us that the Ordinance came into effect on October 1, 2022, following the expiration of a related moratorium on September 30, 2022. Blockfusion has further advised that it has submitted applications for new permits based on the Ordinance’s new standards and that the permits may take several months to process. Pursuant to the Mining Services Agreement between Bit Digital and Blockfusion dated August 25, 2021, Blockfusion represents, warrants and covenants that it “possesses, and will maintain, all licenses, registrations, authorizations and approvals required by any governmental agency, regulatory authority or other party necessary for it to operate its business and engage in the business relating to its provision of the Services.” On October 5, 2022, Bit Digital further advised Blockfusion that it expects it to comply with the directives of the Notice. Our service agreement with Blockfusion ended in September 2023. On June 3, 2024, the Company filed suit in Delaware Superior Court against Blockfusion alleging claims for breach of contract, conversion, and related claims in connection with, among other things, certain deposits and advances paid to Blockfusion, the return of which is owed to the Company. The Company is seeking in excess of $4.3 million. On October 22, 2024, Blockfusion denied the Company’s claims and brought reciprocal breach of contract and related counterclaims. Following limited discovery, the court entered a stipulation and order on June 18, 2025, amending the Case Management Order to extend multiple discovery deadlines and vacate the previously scheduled trial date. On August 1, 2025, the Company moved for leave to file a Second Amended Complaint, which adds claims for fraud and related causes of action arising out of Blockfusion’s, conduct both at the inception of and during the parties…

Excerpt shortened here; the source contains the full paragraph.

Previous wording

On December 23, 2024, we entered into an agreement with an unaffiliated seller of bitcoin mining computers, from whom we acquired 4,300 S21+ miners. As of the date of this report, 500 miners were delivered.

Current wording

On December 23, 2024, we entered into an agreement with an unaffiliated seller of bitcoin mining computers, from whom we acquired 4,300 S21+ miners. As of the date of this report, 2,630 miners were delivered.

Previous wording

For the three months ended March 31, 2025, the Company disposed of approximately 4,828 bitcoin miners.

Current wording

For the three and six months ended June 30, 2025, the Company disposed of nil and 4,828 bitcoin miners. In July 2025, the Company disposed of 2,972 bitcoin miners.

Previous wording

As of March 31, 2025, we had 20,854 miners owned or operating (in Iceland) for bitcoin mining with a total maximum hash rate of 2.4 EH/s.

Current wording

As of June 30, 2025, we had 22,574 miners owned or operating (in Iceland) for bitcoin mining with a total maximum hash rate of 2.7 EH/s.

Previous wording

From the inception of our bitcoin mining business in February 2020 to March 31, 2025, we earned an aggregate of 7,363.4 bitcoins.

Current wording

From the inception of our bitcoin mining business in February 2020 to June 30, 2025, we earned an aggregate of 7,431.6 bitcoins.

Showing the first 40 of 98 pairs. Open the source sections for the rest.

Rearranged current paragraphs (31)

Current report — wording carried from elsewhere

We acquired Enovum Data Centers Corp (“Enovum”) on October 11, 2024. The transaction included the lease to MTL-1, a fully operational and fully leased to customers 4 MW (gross) Tier-3 datacenter headquartered in Montreal, Canada.

Current report — wording carried from elsewhere

From time to time, the Company may change partnerships with hosting facilities to recalibrate its bitcoin mining operations. These terminations are strategic, targeting reduced operational costs, enhanced energy efficiency for a smaller carbon footprint, increased flexibility in operational control, and minimized geopolitical risks. While a short-term decrease in mining output might occur, we expect these changes to yield long-term operational improvements.

Current report — wording carried from elsewhere

The following table summarizes the results of our operations during the six months ended June 30, 2025 and 2024, respectively, and provides information regarding the dollar increase or (decrease) during the period.

Current report — wording carried from elsewhere

We generate revenues from cloud services, colocation services, digital asset mining, and ETH staking businesses.

Current report — wording carried from elsewhere

In the fourth quarter of 2023, we initiated WhiteFiber, a new business line to provide cloud services to support generative AI workstreams. The Company commenced the cloud services in January 2024.

Current report — wording carried from elsewhere

Our revenues from cloud services increased by $10.9 million, or 52.9%, to $31.4 million for the six months ended June 30, 2025 from $20.6 million for the six months ended June 30, 2024. The increase was primarily due to an increase in deployed GPU servers for the six months ended June 30, 2025 and the $1.3 million service credit issued to the customer as compensation for decreased utilization during the initial deployment period, which included testing and optimization phases, in the first quarter of 2024.

Current report — wording carried from elsewhere

Our revenue from colocation services was $3.4 million for the six months ended June 30, 2025. We had no revenue from colocation services for the six months ended June 30, 2024. In the fourth quarter of 2024, we acquired Enovum which provides customers with physical space, power, and cooling within the data center facility.

Current report — wording carried from elsewhere

During the fourth quarter of 2022, we commenced ETH staking business, in both native staking and liquid staking.

Current report — wording carried from elsewhere

For the ETH native staking business, we previously partnered with Blockdaemon, Marsprotocol and MarsLand. Currently, we stake ETH with Figment, using network-based smart contracts, on a node for the purpose of validating transactions and adding blocks to the network. Through these contracts, the Company stakes ETH on nodes for the purpose of validating transactions and adding blocks to the Ethereum blockchain network. The Company is able to withdraw staked ETH under contracted staking since April 12, 2023 when the announced Shanghai upgrade was completed. In exchange for staking the ETH and validating transactions on blockchain networks, the Company is entitled to block rewards and transaction fees for successfully validating or adding a block to the blockchain. These rewards are received by the Company directly from the Ethereum network and are calculated approximately based on the proportion of the Company’s stake to the total ETH staked by all validators.

Current report — wording carried from elsewhere

In the fourth quarter of 2023, the Company terminated the native staking activities and reclaimed all staked Ethereum with Blockdaemon. Our native staking operations with Marsprotocol commenced in the first quarter of 2023 and concluded in July 2023. After ceasing operations with Marsprotocol, we initiated our native staking operations with MarsLand in August 2023. In the first quarter of 2024, we concluded our operations with MarsLand and initiated our native staking operations with Figment. As of December 31, 2024, all of our native staking operations are with Figment.

Current report — wording carried from elsewhere

For the liquid staking business, the Company has deployed ETH into Portara protocol (formerly known as Harbour) supported by liquid staking solution provider under the consortium of Blockdaemon and Stakewise, and Liquid Collective protocol supported by Coinbase. By staking, we receive receipt tokens for the ETH staked which could be redeemed to ETH or can be traded or collateralized elsewhere, at any time. In addition, we receive rETH-h for rewards earned from Portara protocol. With the introduction of staked ETH withdrawals in April 2023, we have reassessed our Ethereum network staking approaches, weighing the advantages of traditional staking against liquid staking solutions. The withdrawal feature in native staking, coupled with yields that are on par with those of liquid staking, has encouraged us to expand our collaborations with other service providers in this domain. As a result, we terminated all liquid staking activities with StakeWise in the third quarter of 2023, reclaiming all staked Ethereum along with the accumulated rewards. In the first quarter of 2024, we ceased our liquid staking activities with Liquid Collective protocol and reclaimed all our staked Ethereum. Since the first quarter of 2024, the Company has no liquid staking activities. In July 2025, we resumed liquid staking through the Liquid Collective protocol with 5,120 ETH. This approach provides flexibility to engage in both staking and restaking through a broader range of strategies and platforms.

Current report — wording carried from elsewhere

In the first quarter of 2024, the Company has restaked 3,008 ETH into EigenLayer, a protocol built on Ethereum that enables restaking of the already-staked ETH, through Figment. To mitigate potential risks, we restake our ETH without delegating to any operator and the Company received 33,568 EigenLayer in the fourth quarter of 2024 from this restaking activity. As of the date of this report, the reward earned in 2025 from this restaking activity is not significant.

Current report — wording carried from elsewhere

We incur cost of revenue from digital asset mining, cloud services, colocation services, and ETH staking businesses.

Current report — wording carried from elsewhere

The Company’s cost of revenue consists primarily of direct production costs associated with its core operations, excluding depreciation and amortization, which are separately stated in the Company’s consolidated statements of operations. Specifically, these costs consist of:

Current report — wording carried from elsewhere

Electricity costs. These expenses were incurred by the data center for the high performance computing equipment and were closely correlated with the number of deployed GPU servers.

Current report — wording carried from elsewhere

Datacenter lease expenses. We entered into datacenter lease agreements for fixed monthly recurring costs.

Current report — wording carried from elsewhere

GPU servers lease expenses. We entered into a GPU servers lease agreement to support our cloud services. The lease payment depends on the usage of the GPU servers.

Current report — wording carried from elsewhere

Electricity costs*.* These expenses were closely correlated with the number of deployed servers hosted by the data center.

Current report — wording carried from elsewhere

Lease expenses. These expenses were incurred by the data center for lease agreement for a fixed monthly recurring cost.

Current report — wording carried from elsewhere

Cost of revenue - digital asset mining

Current report — wording carried from elsewhere

For the six months ended June 30, 2025 and 2024, the cost of revenue from digital asset mining was comprised of the following:

Current report — wording carried from elsewhere

***Electricity costs.***These expenses were incurred by mining facilities for the miners in operation and were closely correlated with the number of deployed miners.

Current report — wording carried from elsewhere

***Profit-sharing fees.***We enter into hosting agreements with certain mining facilities, which included performance fees calculated as a fixed percentage of net profit generated by the miners. We refer to these fees as profit-sharing fees.

Current report — wording carried from elsewhere

For the six months ended June 30, 2025, profit-sharing fees decreased by $4.7 million, or 68%, compared to profit-sharing fees incurred in the six months ended June 30, 2024. The decrease in profit-sharing fees was primarily due to a lower bitcoin production and partially offset by the higher average BTC price for six months ended June 30, 2025.

Current report — wording carried from elsewhere

For the six months ended June 30, 2025, cost of revenue from ETH staking business increased by $21,312, or 52%, compared to the cost of revenue incurred for the six months ended June 30, 2024. The increase was primarily driven by an increased number of staked ETH from 17,184 ETH in the six months ended June 30, 2024 to 21,568 ETH in the six months ended June 30, 2025.

Current report — wording carried from elsewhere

For the six months ended June 30, 2025 and 2024, depreciation and amortization expenses were $15.5 million and $15.2 million, respectively based on an estimated useful life of property, plant, and equipment.

Current report — wording carried from elsewhere

Effective January 1, 2025, we changed our estimate of the useful lives for our cloud service equipment from three to five years. The change was made to better reflect the expected usage patterns and economic benefits of the assets. Refer to Note 2.Summary of Significant Accounting Policies.

Current report — wording carried from elsewhere

For the six months ended June 30, 2024, a gain of $34.2 million was recognized, primarily attributable to the increases in the prices of bitcoin and ETH as of June 30, 2024.

Current report — wording carried from elsewhere

Provision for income taxes consists of federal, state and foreign income taxes. Our income tax provision for the six months ended June 30, 2025 is primarily attributable to the mix of earnings and losses in countries with differing statutory tax rates, and the valuation allowance applied to the Company’s deferred tax assets in the United States, Singapore and Hong Kong. We continue to maintain a valuation allowance against the deferred tax assets in United States, Singapore and Hong Kong as the Company does not expect those deferred tax assets are “more likely than not” to be realized in the near future, particularly due to the uncertainty on macroeconomy, politics and profitability of the business.

Current report — wording carried from elsewhere

For the six months ended June 30, 2025, our net loss was $42.8 million, representing a change of $81.0 million from a net income of $38.1 million for the six months ended June 30, 2024.

Current report — wording carried from elsewhere

On October 23, 2023, Bit Digital announced that it had commenced AI operations by signing a binding term sheet with a customer (the “Initial Customer”) to support the customer’s GPU workloads. On December 12, 2023, we finalized a Master Services and Lease Agreement (“MSA”), as amended, with our Initial Customer for the provision of cloud services from a total of 2,048 GPUs over a three-year period. To finance this operation, we entered into a sale-leaseback agreement with a third party, selling 96 AI servers (equivalent to 768 GPUs) and leasing them back for three years. The total contract value with the Initial Customer for the aggregated 2,048 GPUs was estimated to be worth more than $50 million of annualized revenue. On January 22, 2024, approximately 192 servers (equivalent to 1,536 GPUs) were deployed at a specialized data center and began generating revenue, and subsequently on February 2, 2024, approximately an additional 64 servers (equivalent to 512 GPUs) also started to generate revenue.