Bitfarms Ltd
For the period ended Dec 31, 2024. Filed Apr 1, 2025.
View on SEC.govAbout this filing
The yearly report of certain Canadian companies, filed under a joint US and Canadian system. It is the main yearly account these companies give US investors, largely as filed in Canada.
FY2024 · Filed Apr 1, 2025
Use the contents to explore the available documents and sections.
Contents
EX-99.1 · Paraguay
Paraguay
The Company operates a total of two Data Centers with an aggregate power capacity of 80 MW located in the city of Villarrica, Paraguay. Refer to Section 5.4*- FUTURE GROWTH PLANS - PARAGUAY EXPANSION*of this AIF.
There are no material restrictions in Paraguay on the business of operating a data center or conducting the business of the Company as described herein, and as of the date ofthis AIF, the Company has not received any material notices or statements from regulatory authorities in Paraguay that would negatively impact its operations in Paraguay. The Company is not relying on any registrations, exemptions, or “no action” letters to conduct its business in Paraguay.
In April 2024, a group of Paraguay’s Senators initially proposed a 180-day blanket ban on cryptocurrency Mining due to concerns over power theft of and disruptions to the electricity supply. However, the Senate issued a statement in support of the legal cryptocurrency Mining industry arguing that selling excess energy to Bitcoin miners unlocks substantial revenue streams and bolsters Paraguay’s economy, acknowledging that the proposed ban would not effectively address illegal Mining activities. The Senate held a public hearing on April 23, 2024 to debate the merits and drawbacks of Bitcoin Mining in the country. Lawmakers acknowledged the potential issues caused by illegal Mining operations disrupting the power supply, but also recognized the potential economic benefits of embracing licensed Mining.
Following these discussions, several significant developments occurred. On June 26, 2024, Congress in Paraguay sanctioned a bill, which was later promulgated as Law No. 7300. This law increases penalties for illegal use of electricity, particularly targeting unauthorized cryptocurrency Mining. Penalties range from fines to imprisonment up to 10 years, with provisions for equipment confiscation.
53 | Page
Secondly, also on June 26, 2024, ANDE issued a decree implementing an abrupt increase in tariffs for the cryptocurrency Mining industry. The decree increased the electricity tariffs from 6% to 16%, a 10%-point increase, across various voltage categories, effective July 1, 2024. The effective rate increase on the voltage level the Company uses was approximately 13.6%.
The text of this filing, as the company filed it with the SEC, without its images or exhibits. This is not investment advice.